Specific Project Specification
Specific Project Specification
1.0 INTRODUCTION
This Specification defines the Company’s basic requirements for the Process Engineering Review
Work Package of Existing CGS 1, 3, 4 and 5 - Duri Central Gathering Station Upgrade Program, as
prepared by the ESA Contractors.
2.1 Format
(i) The package shall be delivered to Company hardcopy, indexed, hard cover bound, in English
and softcopy stored in CD 650 MB, or as further specified in the ESA Contract.
(ii) The overall format and organization shall be submitted for the Company’s review and
approval, before the work proceeds.
(i) The Contractor shall use an-approved CAD-based system to develop the package as specified
in the ESA Contract. The CAD system shall be supplemented by an integrated database containing
equipment attributes and design data intelligently linked to the P&ID graphics.
In the beginning of the services, the Contractor’s shall verify the Key Plan such as Process
Flow Diagram, Piping and Instrumentation Diagrams, Plot Plans and Single Line Diagram in this regard
shall take cognizance any requirement of this specification, and shall be accompanied by detailed
functional software and hardware specifications for, and descriptions of the system he intends to use.
Included shall be symbol conventions proposed for use in the production of all basic design drawings.
___________________________________________________________________________________________________
CGS Upgrade – Process Review Phase I Page 1 of 5
Revision: 16 August 2002
PT Caltex Pacific Indonesia
(ii) The Contractor shall prepare to arrange suitable system demonstrations for the Company’s
review and approval.
The Company’s role, and the Company’s project information input and facilities provided, are
described in ESA Contract.
(i) The scope of the Contractor’s Deliverables, shall be as listed in Table 1, and shall be subject
to pre-contractual agreement with the Company. The Contractor shall further propose a delivery
schedule for key documentation.
TABLE 1
Contractor’s Engineering Review Package (Apply for each CGS)
1.0 INTRODUCTION
2.0 COMPANY ORIGINAL PROCESS DESIGN REVIEW
3.0 CURRENT PROCESS CONDITION REVIEW AND THE RECOMMENDATIONS
4.0 PROCESS DESIGN CALCULATION AND SPECIAL STUDIES
(i) Unless furnished by the Company, the Contractor shall develop the necessary basic
engineering design basis for all conditions peculiar to the Facility site in question. These shall be
presented in the form of Basic Engineering Design Data Sheets, the format and contents of which
require the Company’s review and approval.
(i) The Contractor’s introductory statement to the Engineering Review Package shall include an
executive summary of the basic design parameters and rationale, and the production and performance
objectives for the overall facility.
(ii) Also included shall be a dissertation on the alternative cases studied by the Contractor, and
the final design assumptions used by the Contractor. Special Studies of substantial relevance shall also
be referenced, and discussed if necessary. A bibliography of key references shall be provided.
The Contractor shall produce an overall Block Flow Diagram for each CGS, the primary function
of which is to schematically show process units’ functionality, and interconnections with key off-plot
facilities. Similar drawings shall be prepared for utilities and services.
(i) Based on information developed for individual process units and other producing and
consuming facilities, the Contractor shall complete overall balances. As a minimum, balances
summarized shall be:
Overall mass balances, under selected operating modes.
Solid wastes.
Any other materials, as required by the process.
(ii) In addition, balances shall also be provided for the maximum case in which the peak demand will
occur, or any other critical or peculiar design case. Where appropriate, e.g. for crude oil, the overall
material management and priorities of supply shall be described, and reflected in the facility design.
The Process Engineering Review package of each CGS shall include the following elements, where
applicable to the specified process.
4.1 Introduction
(i) This shall be a narrative, which traces the principal streams of each unit, through the Flow
Diagram, describing and defining the process scheme, during normal operations, startup, shutdown,
specific emergency conditions which have an impact on design decisions, and alternative operations.
Special design features of each process shall also be highlighted.
(ii) In addition, the following subjects, at minimum, shall also be described in sufficient detail to
give a clear understanding of the process, its limitations and its flexibility:
Chemical changes and changes in state; internal arrangement of columns and vessels
Surge volume considerations
Intentional hydraulic overcapacity
Liquid residence times
Battery limit conditions
___________________________________________________________________________________________________
CGS Upgrade – Process Review Phase I Page 3 of 5
Revision: 16 August 2002
PT Caltex Pacific Indonesia
Hazards peculiar to the process, including those hazards associated with equipment entry for
inspection and repair
Process Flow and Control Diagrams, complete with heat and material balances, shall be produced
for each design case. All physical data will be in Company-specified or approved units of
measurement.
In a tabulation at the bottom of each flow sheet, the information below shall be shown for each
numbered stream.
Hydraulic sizing calculations for all process fluid circuits shall be documented.
(i) P&IDs shall consist of a complete issue of such diagrams produced generally in accordance
with and as specifically required by Process Engineering Review Work Package. As a minimum,
however, preliminary line sizes and piping specification allocations shall be included.
(ii) P&IDs shall be subject to examination as part of the overall facility HAZOP reviews, as
specified or agreed by the Company. Similarly, P&IDs shall also be subject to examination as part of the
Environmental Impact Assessment, and the requirements Pollution Source Control and Waste Reduction.
(iii) The Contractor shall ensure that specifications for detail design also incorporate:
the need for sufficient instrumentation/test connections for performance testing of equipment,
sufficient piping, valves and flanges for safe startup and shutdown of process units segments of
utility systems, offsite and receiving/shipping systems,
___________________________________________________________________________________________________
CGS Upgrade – Process Review Phase I Page 4 of 5
Revision: 16 August 2002
PT Caltex Pacific Indonesia
sufficient primary instrumentation for total data reconciliation and Advanced Control and Facility
Information systems.
5.1 Schedule
1. Contractor to provide expected time line for work with proposal. We will consider the schedule in
our evaluation and selection of the Contractor.
2. Work should be complete by no later than 15-Oct-02
5.2 Cost
1. Per the terms of the Engineering Service Agreement, Contractor shall submit a reimbursable price
for the work described herein with a “not to exceed” limit for the overall total of the work. In
addition to the unit rate price, Contractor shall submit a total estimate for completing all the
deliverables described above. We will consider the cost in our evaluation and selection of the
Contractor. We will evaluate Contractor performance based on overall capability to meet or beat
this estimate.
2. Costs should be identified on a “per CGS” basis.
3. Contractor shall also submit a unit rate for any additional work that may be necessary that is not
included herein.
For this specific project, addition to ESA contract requirements, please add some requirements
that need to be submitted by contractors in their bid proposal as follow:
1. Service Execution Plan (SEP). Contractor shall submit the SEP to company, including but not
limited to project organization, project schedule, detail description of service activities, based on
scope of work given by Company, and Curriculum Vitae (CV) of proposed Contractor project
team.
2. Detail information for Key Personnel. These services call Senior Process Engineers as one of
Key Personnel. Contractor shall submit the detail CV, list of experiences including his role and
responsibility, and any related information.
Failure to complete the requirement in its entirety will result in DISQUALIFICATION of applicant.