Project Report: Construction of 7-Storey Office Building

The document provides a progress report for the construction of a 7-story office building in Quezon City owned by Grand Decimal Realty. The project is currently on schedule, with construction starting in January 2021 and an adjusted completion date of September 28, 2021. As of August 16, 2021, various areas of the building including the elevator, lobby, floors, basement, and commercial units are ready for turnover by the end of August or early September.

Uploaded by

Kristhel Tabones
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views6 pages

Project Report: Construction of 7-Storey Office Building

The document provides a progress report for the construction of a 7-story office building in Quezon City owned by Grand Decimal Realty. The project is currently on schedule, with construction starting in January 2021 and an adjusted completion date of September 28, 2021. As of August 16, 2021, various areas of the building including the elevator, lobby, floors, basement, and commercial units are ready for turnover by the end of August or early September.

Uploaded by

Kristhel Tabones
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT REPORT

CONSTRUCTION OF 7-STOREY
OFFICE BUILDING
Owner: GRAND DECIMAL REALTY

Project Location:
COMMONWEALTH, QUEZON CITY

Date: SEP 06, 2021


EXECUTIVE SUMMARY
Progress Report

• PROJECT TEAM:

Owner – Grand Decimal Realty


General Contractor– Qualis Forti Construction and Development Corp.
Project Engineer - Engr. Arvin Buensuceso

• PROJECT STATUS:

Construction Start Date – January 6, 2021


Original Target Completion Date – September 8, 2021
Adjusted Target Completion Date – September 28, 2021*
*Due to adjustment of Foundation Pouring Date

Projected Accomplishment: 0%
Actual Accomplishment: 0%
Original Project Duration: 0 Working Days
Extended Project Duration: 0 Working Days
Previous Actual Accomplishment 0%
Punch list Works as of August 16, 2021

Description Status Estimated End Date


1.0 For turn-over of  Fully operational
Elevator  Waiting for Aug 31, 2021
2.0 For Turn-over of Lobby, Ready for Turn over/Interior Aug 31, 2021
2nd floor & 3rd floor Renovations

3.0 For Turn-over of 4 th flr, Ready for Turn-over Aug. 23, 2021
5th flr, 6th floor 7th flr
4.0 For Turn-over of Ready for Turn-over
Basement & Roofdeck
Sept 06, 2021
5.0 For Turn-over of Ready for Turn-over
Commercial Units at ground Sept 07, 2021
floor