PROJECT REPORT
CONSTRUCTION OF 7-STOREY
OFFICE BUILDING
Owner: GRAND DECIMAL REALTY
Project Location:
COMMONWEALTH, QUEZON CITY
Date: SEP 06, 2021
EXECUTIVE SUMMARY
Progress Report
• PROJECT TEAM:
Owner – Grand Decimal Realty
General Contractor– Qualis Forti Construction and Development Corp.
Project Engineer - Engr. Arvin Buensuceso
• PROJECT STATUS:
Construction Start Date – January 6, 2021
Original Target Completion Date – September 8, 2021
Adjusted Target Completion Date – September 28, 2021*
*Due to adjustment of Foundation Pouring Date
Projected Accomplishment: 0%
Actual Accomplishment: 0%
Original Project Duration: 0 Working Days
Extended Project Duration: 0 Working Days
Previous Actual Accomplishment 0%
Punch list Works as of August 16, 2021
Description Status Estimated End Date
1.0 For turn-over of Fully operational
Elevator Waiting for Aug 31, 2021
2.0 For Turn-over of Lobby, Ready for Turn over/Interior Aug 31, 2021
2nd floor & 3rd floor Renovations
3.0 For Turn-over of 4 th flr, Ready for Turn-over Aug. 23, 2021
5th flr, 6th floor 7th flr
4.0 For Turn-over of Ready for Turn-over
Basement & Roofdeck
Sept 06, 2021
5.0 For Turn-over of Ready for Turn-over
Commercial Units at ground Sept 07, 2021
floor
PROGRESS PHOTOS