3. Assembling project team and assigning their responsibilities are done during
which phase of a project management?
(A) Initiation
(B) Planning
(C) Execution
(D) Closure
2. A process that involves continuously improving and detailing a plan as more detail
become available is termed as
(A) project analysis
(B) project enhancing
(C) progressive deliberation
(D) progressive elaboration
6. If any one factor of a project changes, _____ other factor(s) is/are likely to be
affected.
(A) all
(B) one
(C) at least one
(D) at most one
7. Business Value =
(A) Tangible Elements
(B) Intangible Elements
(C) Tangible Elements – Intangible Elements
(D) Tangible Elements + Intangible Elements
12. A horizontal bar chart that shows project tasks against a calendar is called
(A) milestone
(B) goal
(C) Gantt chart
(D) PERT chart
13. The statistical tool that depicts a project’s tasks and the relationships between
those tasks is known as
(A) milestone
(B) goal
(C) Gantt chart
(D) PERT chart