Prefunctional Test Checklist-12 - Vav
Prefunctional Test Checklist-12 - Vav
Components included:
Associated Checklists:
1. Submittal / Approvals
Submittal. The above equipment and systems integral to them are complete and ready
for functional testing. The checklist items are complete and have been checked off only
by parties having direct knowledge of the event, as marked below, respective to each
responsible contractor. This prefunctional checklist is submitted for approval, subject to
an attached list of outstanding items yet to be completed. A Statement of Correction will
be submitted upon completion of any outstanding areas. None of the outstanding items
preclude safe and reliable functional tests being performed. ___ List attached.
Prefunctional checklist items are to be completed as part of startup & initial checkout,
preparatory to functional testing.
This checklist does not take the place of the manufacturer’s recommended
checkout and startup procedures or report.
Contractors assigned responsibility for sections of the checklist shall be
responsible to see that checklist items by their subcontractors are completed and
checked off.
3. Model Verification
Item Specified Submitted Installed
Manufacturer
Model
Serial Number
Capacity (CFM)
Max CFM
Min CFM
Fan hp
Fan voltage/phase
Electric Heat (kw)
4. Installation Checks
b. Heating Coil
i. Electric heat used: Yes / No
ii. Coil installed and wired: N/A / Yes / No
iii. Coil is clean: N/A / Yes / No
vii. Panel devices labeled and wiring tagged per drawings: N/A / Yes / No
viii. I/O devices labeled and wiring tagged per drawings: N/A / Yes / No
ix. Digital inputs and outputs operational: N/A / Yes / No
x. All electric connections tight: N/A / Yes / No
xi. Pneumatic tubing installed without air leakage: Yes / No
xii. Proper grounding installed for components and unit: N/A / Yes / No
xiii. Safeties in place and operable: N/A / Yes / No
xiv. Control system interlocks hooked up and functional: N/A / Yes / No
xv. All control devices, pneumatic tubing and wiring complete: Yes / No
e. Final
i. VAV box damper open: Yes / No
ii. Safeties and safe operating ranges for this equipment have been reviewed
and accepted: Yes / No
iii. Sequence of Operation adequately show all information: Yes / No
All field-installed temperature, [relative humidity], [CO], [CO 2] and pressure sensors and
gages, and all actuators (dampers and valves) on this piece of equipment shall be
calibrated. Sensors installed in the unit at the factory with calibration certification
provided need not be field calibrated.
All test instruments have had a certified calibration within the last 12 months:
Y/N______.
All sensors are calibrated within required tolerances ___ YES ___ NO
-- END OF CHECKLIST--
VARIABLE AIR VOLUME BOXES
03/02 15997-12- OF 4 D:\DOCS\DIV1\03-02\15997-12.DOC