Proposal for On-Site Curb Casting

The contractor requests approval to cast curbstone on site using a curbing machine instead of using precast concrete curbstone as specified. This is because using precast curbstone would hamper progress in meeting the target completion date before the rainy season for pavement work on section 5 of the Bole Ring Road RBT to Meskel Sq. Project. Casting curbstone on site would enable completion of pavement work within the expected time frame while using the same concrete volume as specified. Approval of this proposal is requested to avoid delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
287 views2 pages

Proposal for On-Site Curb Casting

The contractor requests approval to cast curbstone on site using a curbing machine instead of using precast concrete curbstone as specified. This is because using precast curbstone would hamper progress in meeting the target completion date before the rainy season for pavement work on section 5 of the Bole Ring Road RBT to Meskel Sq. Project. Casting curbstone on site would enable completion of pavement work within the expected time frame while using the same concrete volume as specified. Approval of this proposal is requested to avoid delays.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 2

RB CRBC ADDIS ENGINEERING P.L.

C
c=.›`.u=.c= ›Ç=e ›=”Í=’]”Ó %L.¾}.¾ÓM TIu`
Ref No: CRBC/BM/ 163/12 Dates: May 24,
2012

TO: Engineer Zewde Eskinder and Co. PLC


Addis Ababa
Attention: Ato Gizachew Herco, Resident Engineer
Ref: Bole Ring Road RBT to Meskel Sq. Project.
Subject: Type A Curb Stone
Dear Sirs,
As you are well aware, the construction of the pavement work for section 5
is advancing to meet the target of completion up to asphalt level before the
starting of the coming rainy season.
To do so, the contractor is endeavoring to speed up the work so far and
currently sub base placing is undergoing.
Regarding Type A curbstone, the boq states to use precast concrete curb
which requires adequate time for production and eventually hamper the
progress in meeting the target.
Hence, we propose to cast the curb at the site using our curbing machine
which extremely enables us to proceed and complete the pavement work
within the expected time.
Please note, the concrete volume of the curb stone indicated in the boq is
almost equal to the proposed one.
Therefore, we request your due consideration and approval to continue as
per our proposal.
Thanking you in advance for your cooperation, we remain.
Sincerely yours

Wang Yang
General Manager

Encl: Curbstone detail drawing (1 Page)


Cc:

P.O.Box: 2509 Tel: 00251-4-391971 Fax: 00251-4-392468


Address: Kebele 10, Woreda Akaki Kaliti Sub-City, Addis Ababa, Ethiopia
Project manager, peng Huan

P.O.Box: 2509 Tel: 00251-4-391971 Fax: 00251-4-392468


Address: Kebele 10, Woreda Akaki Kaliti Sub-City, Addis Ababa, Ethiopia