Risk Assessment for GEM Residences

The risk assessment form summarizes the activities, hazards, risks and controls for the construction of the GEM RESIDENCES project. The activities include site preparation, formwork installation, lifting of formworks, and survey and clearing. Hazards include working at heights, improper access, unstable working platforms, protruding objects, falling materials and objects. Risks range from minor to serious injuries or fatalities. Current controls include inspections, PPE, safe access equipment and competent riggers. Additional controls recommended are daily pre-task meetings, close monitoring by supervisors, and restricting other works during lifting activities to further lower risks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
86 views3 pages

Risk Assessment for GEM Residences

The risk assessment form summarizes the activities, hazards, risks and controls for the construction of the GEM RESIDENCES project. The activities include site preparation, formwork installation, lifting of formworks, and survey and clearing. Hazards include working at heights, improper access, unstable working platforms, protruding objects, falling materials and objects. Risks range from minor to serious injuries or fatalities. Current controls include inspections, PPE, safe access equipment and competent riggers. Additional controls recommended are daily pre-task meetings, close monitoring by supervisors, and restricting other works during lifting activities to further lower risks.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

RISK ASSESSMENT FORM

Project: GEM RESIDENCES


Location: E. RODRIGUEZ AVE. C5, PASIG CITY
Risk Residual
Sequence of Operational Control
SI Activity Hazard Risk Current Controls Rating Additional Controls Risk Rating
Steps Action By
S L R S L R
- Working at - Ensure access ladder - Conduct daily Pre 1 1 1 Low
1. Site heights and working platform task meeting and Operation
Installati Preparatio Serious to was inspected with discuss the activity.
on of n/ - Improper fatal injury of green tag “Safe for - Site Engineer /
formwor Mobilizati access/Unstabl person falling Use” Foreman must
ks 4 1 4
on of e working from height. - Ensure all personnel closely monitor the
personnel platform involved are wearing activity.
at site. Slip, Trip, Fall fall arrest equipment
hazard (FBH) while working
at height.
- Protruding - Ensure protruding - Conduct daily Pre 1 1 1 Low
objects objects are protected task meeting and
- Working at Minor to with rebar caps. discuss the activity. Foreman
height Serious injury - FBH must be worn - Site Engineer /
Survey - Poor of personnel at all times while Foreman must
and housekeeping at site. working at height. closely monitor the
Clearing - Falling of - Conduct activity.
the area. materials from housekeeping
height. - Ensure no other 4 1 4
- Tower Crane works are allowed to
lifting activities. commence overhead
or below on the same
area.
- Ensure everyone
are informed while
lifting activities on
progress.
- Unsecured - Prior to lift, The 5 1 5 - Conduct daily Pre 2 1 2 Low
lifting eye of Competent rigger task meeting and
the form work must inspect the discuss the activity. Tower
BBPI-OP-HSE-F01 BETONBAU PHIL., INC. Salcedo Building, Severina Avenue, Severina Subdivision
Revision: 1 KM 18 South Superhighway, Parañaque City - 1700, Philippines
Tel: +632 8243321/ 8243593; Fax: +632 8245366/ 8210120;
Page 1 of 3
E-mail: [email protected]/ www.betonbauphilinc.com
RISK ASSESSMENT FORM

Project: GEM RESIDENCES


Location: E. RODRIGUEZ AVE. C5, PASIG CITY
Risk Residual
Sequence of Operational Control
SI Activity Hazard Risk Current Controls Rating Additional Controls Risk Rating
Steps Action By
S L R S L R
(loosen or lifting eye for any lose - Site Engineer / Crane
lacking safety Physical l , damage, or lacking Foreman must Operator
bolts,) injury or of bolts . Unsecured closely monitor the and Rigger
Lifting of damage to lifting eye of the activity.
Formwork property formworks must be
s secured first prior to
lift the formwork.
- Damaged
form works. - Ensure formworks
Physical are in good condition
- Lifting injury for the stability during
Activity installation.
- Ensure no other
Physical l personnel are allowed
- Falling of load injury or to work under the
from height damage to suspended load.
property - Only competent
riggers are allowed to
assist critical lifting
operation
- Ensure lifting hook
are secured and
properly attached the
load safely.
- Tag lines must be
attached to safely
control the
movement of the
load .
5 1 5 - Conduct daily Pre Tower 1 1 1 Low
BBPI-OP-HSE-F01 BETONBAU PHIL., INC. Salcedo Building, Severina Avenue, Severina Subdivision
Revision: 1 KM 18 South Superhighway, Parañaque City - 1700, Philippines
Tel: +632 8243321/ 8243593; Fax: +632 8245366/ 8210120;
Page 2 of 3
E-mail: [email protected]/ www.betonbauphilinc.com
RISK ASSESSMENT FORM

Project: GEM RESIDENCES


Location: E. RODRIGUEZ AVE. C5, PASIG CITY
Risk Residual
Sequence of Operational Control
SI Activity Hazard Risk Current Controls Rating Additional Controls Risk Rating
Steps Action By
S L R S L R
Weather Falling of - No lifting is allowed task meeting and Crane
condition load from above maximum wind discuss the activity. Operator
(Strong wind) height velocity level. of 20 - Site Engineer / and Rigger
resulting to kph Foreman must
physical closely monitor the
injury or activity.
property
damage.

Risk Matrix Severity / Impact


General Information
1 2 3 4 5

Assessment Completed By: Ariel G. Dolera


1 1 2 3 4 5
Likelihood of Harm /
Job Title: Safety Practitioner
Environmental Damage 2 2 4 6 8 10
Assessment Date:
May 19, 2021
Review Date: 3 3 6 9 12 15

4 4 8 12 16 20

5 5 10 15 20 25

Key S = Severity 15 to 25 High


L = Likelihood 8 to 12 Medium High
Rating = S X L 4 to 6 Medium Low
2 to 3 Low
1 Insignificant

BBPI-OP-HSE-F01 BETONBAU PHIL., INC. Salcedo Building, Severina Avenue, Severina Subdivision
Revision: 1 KM 18 South Superhighway, Parañaque City - 1700, Philippines
Tel: +632 8243321/ 8243593; Fax: +632 8245366/ 8210120;
Page 3 of 3
E-mail: [email protected]/ www.betonbauphilinc.com