Appendix 2 Split of Work Scope: Power Generation A Engine System

The document outlines the split of work scope between EPGL/MAN and the Client for a power generation project. It includes two main sections - Power Generation and Generating Set. For Power Generation, EPGL/MAN will supply and install engine systems, tools, and workshop equipment. For Generating Set, EPGL/MAN will supply flex couplings, pipe adapters, ducting, alternators and auxiliary systems while the Client will install these items.

Uploaded by

mithuruet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
108 views16 pages

Appendix 2 Split of Work Scope: Power Generation A Engine System

The document outlines the split of work scope between EPGL/MAN and the Client for a power generation project. It includes two main sections - Power Generation and Generating Set. For Power Generation, EPGL/MAN will supply and install engine systems, tools, and workshop equipment. For Generating Set, EPGL/MAN will supply flex couplings, pipe adapters, ducting, alternators and auxiliary systems while the Client will install these items.

Uploaded by

mithuruet
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 16

APPENDIX 2

SPLIT OF WORK SCOPE

SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  POWER GENERATION          
A Engine System          
Engine 18V48/60TS mounted on a steel foundation
  6 Nos x x    
frame
  SaCoSone Interface cabinet 1 per engine x x    
  SaCoSone Auxiliary Cabinet 1 per engine x x    
  Turbocharger control unit 1 per engine x x    
  Tools          
  Engine Tools          
  Set of standard and special tools for the engine 1 lot x      
  Crank web deflection measuring device 1 lot x      
  Electric valve cone grinder 1 lot x      
  Electric valve seat grinder 1 lot x      
  Electronic firing pressure gauge 1 lot x      
  Assembly and reversing device for cylinder heads 1 lot x      
  Set of tools for turbocharger 1 lot x      
  Plant Tools          
  Tools for nozzle cooling water unit 1 lot x      
  Mobile strainer cleaning unit for automatic filter 1 lot x      
Workshop equipment/ tools 1 lot per
  x
(equivalent to USD 250000) plant
B Generating Set          
  Coupling Arrangement          
  Flexible coupling 1 lot x x    
  Flywheel cover 1 lot x x    
  Engine Seating          
  Foundation frame seating 1 lot x x    
  Pipe Adapters          
  Flexible pipe connections for the engine 1 lot x x    
  Rubber expansion joint for intake air duct 1 lot x x    
  Adapter for exhaust gas duct 1 lot x x    
  Low Pressure Turbo Charger Ducts          
  Intake air ducting 1 lot x x    
  Exhaust gas ducting 1 lot x x    

Appendix 2 - Split of Work Scope Page 1 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Steel support for free-standing turbocharger 1 lot x x    


  Alternator          
  Three phase synchronous alternator 1 per engine x x    
  Automatic voltage regulator (AVR) 1 per engine x x    
  Alternator Seating          
  Grouting material for alternator seating 1 per engine x x    
  Auxiliary Systems, Engine Related          
  Lube Oil Service System
  Lube oil module 1 per engine x x    
  Lube oil replenishing and flow rate measuring device 1 per engine x x    
  Lube oil separator module 1 per engine x x    
  Oil mist eliminator 1 per engine x x    
  HT Cooling Water Service System          
  Cooling-down pump, free-standing 1 per engine x x    
  HT cooling water temperature regulating valve 1 per engine x x    
Resistance thermometer for HT cooling water, loose
  1 per engine x x    
supply
  Cooling water expansion tank 1 per engine x x    
  Low Temperature Cooling Water System          
LT Cooling water temperature control valve 1 per engine x x
  Charge air temperature control valve 2 per engine x x    
  Resistance thermometer for charge air temperature 2 per engine x x    
  Two Circuit Radiator Cooling System          
  Two-circuit radiator cooler 1 per engine x x    
  Fuel Oil Service System          
  Fuel oil booster module 1 per engine x x    
  Combustion Air System          
  Intake air filter unit 1 per engine x x    
  Intake air duct upstream turbocharger 1 lot x x    
  Engine Exhaust Gas System          
  Expansion joint for exhaust gas duct lot x x    
  Exhaust gas duct inside power house lot x x    
  Insulation          
  Insulation material for exhaust gas duct inside PH lot x x    
C Auxiliary systems, plant related          
  Lube Oil Supply System          
  Lube oil supply pump 2 Set x x    
  Lube oil transfer pump 1 Set x x    
  HT Cooling Water Supply System          

Appendix 2 - Split of Work Scope Page 2 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

Preheater set for cooling water 1 per engine x x    


 
  Main Water Supply System          
  Cooling water collecting tank 1 Set x x    
  Replenishing pump module 1 Set x x    
  Water treatment plant 1 Lot x x    
  Fuel Injection Nozzle Cooling System          
  Nozzle cooling water module 1 per engine x x    
  Fuel System, plant related          
  Leakage oil module 2 Set x x    
  Fuel Oil Treatment and Supply Unit          
  HFO transfer pump (1W+1SB) module 1 Set x x    
  Heavy fuel oil separator (2 x 50%) module 1 Set x x    
  Heavy fuel oil separator module (stand-by, 1 x 50%) 1 Set x x    
  Heavy fuel oil supply pump (1W+1SB) module 1 Set x x    
  Set of Diesel oil supply pumps (1W+1SB) module 1 Set x x    
  Heavy fuel oil filter module 1 Set x x    
  Diesel oil duplex filter 1 Set x x    
  Heavy fuel oil pressure limiting valve 1 Nos x x    
  Diesel oil pressure limiting valve 1 Nos x x    
  Starting Air System          
  Starting air receiver 4 Set x x    
  Automatic draining equipment for start air receiver 4 Set x x    
Compressor module (30 bar) with electric motor (3 x
  1 Set x x    
50%)
Startup Air Blower 1 per engine x x
  Control Air System          
  Control air receiver 1 Set x x    
Control air buffer receiver 1 set x x
  Control air compressor (1W+1SB) 2 Set x x    
Control air adsorption dryer 1 Set x x
  Ventilation & Air Conditioning          
  Genset hall ventilation - dry type 1 Lot x x    
  Compressor Room ventilation 1 Lot x x    
  Aux. MCC room ventilation system 1 Lot x x    
  Switchgear room ventilation 1 Lot x x    
  Air conditioners for control room 1 Lot x x    
  Exhaust Gas System          
  Exhaust Gas Silencer          

Appendix 2 - Split of Work Scope Page 3 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Exhaust gas silencer 1 per engine  x  x    


  Exhaust Gas Duct          
  Exhaust gas ducts 1 Lot x x    
  Exhaust gas duct elbows 1 Lot x x    
  Expansion joints 1 Lot x x    
  Exhaust Gas Stack          
  Exhaust gas stacks 1 Lot x x    
  Aviation warning lights 1 Lot x x    
  Piping Material          
  Piping Material For Power Plant          
  Pipes for power plant 1 Lot x x    
  Fittings for power plant 1 Lot x x    
  Valves for power plant 1 Lot x x    
  Pipe supports for power plant 1 Lot x x    
  Bolt sets and gaskets 1 Lot x x    
  Insulation Material For Pipes          
  Pipe insulation for power plant 1 Lot x x    
D Electrical Auxiliary Systems          
  Electro - Control Package:-          
  Genset control panel (GCP_NG) 1 Lot x  x     
  Common control panel (CCP) 1 Lot x  x     
  Boiler Control Panel (BCP) 1 Lot x x    
  Operation and monitoring system 1 Lot x x    
  SaCoS-System          
  "SaCoS-EDS" engine diagnosis system 1 Lot x x    
Connecting cables; EDS-Databox/SaCoS-EDS-
  1 Lot x x    
Hardware
  Paralleling With The Grid          
  Grid Control Cabinet for paralleling with the grid 3 per plant x x    
  - Protection 1 per cabinet x x    
  - Synchronizing 1 per cabinet x x    
  Main Switchgear (MV) :-          
  Generator breaker 1 per engine x x    
  Feeder breaker for Outgoing 3 per plant x x    
Feeder breaker for auxiliary - Transformer with Bus bar
  3 per plant x x    
measuring cubicle
  Turbine breaker 1 per plant x x    
  Bus Coupler 2 per plant x x    
             

Appendix 2 - Split of Work Scope Page 4 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  NGR panel with isolator 1 per engine x x    


  MV cable from alternator terminal box to NGR panel Lot x x    
  MV cable from generator to generator breaker Lot x x    
MV cable from feeder breaker to substation or power
  Lot x x    
distribution
MV cable from Station Transformer feeder breaker to
  Lot x x    
Station Transformer
  Cable trays for the cables Lot x x    
  Station Service System :-          
Auxiliary Transformer - Three Phase Oil immerge, Two
  3 per plant x x    
Windings, Outdoor Type & Off Load Tap Changer
3 Phase & Neutral, 415 V power supply up to station
  1 per plant x x    
low voltage distribution Panel for power Plant.
Station low voltage distribution Panel (415 V) with
  3 per plant x x    
incomers for power Distribution for Power Plant.
MCC (CAPP) for the Pump House equipment’s
  1 per plant x x    
supplied by engine manufacturer.
MCC (EAP) for the Engine Auxiliary equipments
  1 per engine x x    
supplied by engine manufacturer.
MCC (ERP) for the Radiator equipments supplied by
  1 per engine x x    
engine manufacturer.
MCC (CAP) for the engine manufacturer's common
           
supplied equipment.
PCC for the Engines Manufacturer's Supplied
  1 per plant x x    
Equipment
  MCC for the equipments supplied by EPGL Lot x x    
  LV Power, Control and Signal Cables Lot x x    
  Cable trays for the cables. Lot x x    
  AC Distribution Panel (ACDP) Lot x x    
  Boiler Auxiliary Panel (BAP) Lot x x    
  DC System (24V DC) :- B1 Cabinet for Engine          
1 set per
  Batteries x x    
plant
  Battery charger 2 per plant x x    
  DC distribution board 1 per plant x x    
DC System (110 V DC) :- For Balance of Plant &
           
switch yard
  Batteries 1 per plant x x    
  Battery charger 2 per plant x x    
  DC distribution board 1 per plant x x    
  DC emergency lighting for control panel 1 per plant x x    
  Earthing System :-          

Appendix 2 - Split of Work Scope Page 5 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

Earthing below ground upto raisers and earthing


  Lot x x    
network
Earthing above ground from raisers and earthing
  Lot x x    
network
11/132 KV Switchgear, Equipment And
           
Transformers
  132 KV Switchgear for Plant          
  132 KV Switchgear Equipment Lot x x    
  132 KV Circuit breaker [3 phase trip, Live Tank type] Lot x x    
  132 KV Current Transformers Lot x x    
  132 KV Voltage Transformers Lot x x    
  132 KV Lightning Arresters. Lot x x    
  132 KV Isolators Lot x x    
Steel structures for supporting the switchgear,
  Lot x x    
equipment, posts and beams and gantry structures.
Suspension/post insulator string sets, tension insulator
  string sets and station post supporting insulator set with Lot x x    
necessary hardware
  Shield wire connectors and necessary hardware Lot x x    
132 KV Interconnection with necessary hardware as
  1 Lot x x
per PGCB requirements (Radial/LILO).
             
  Step-Up Transformers And Associated Equipment          
  Three phase step-up transformers 3 Nos x x    
Control And Protection System including -unit control
panels, central control panel & desks, synchronizing
  panel, protection panels, -11kv switchgear control Lot x x    
desk,-auxiliary power supply panel,132 kV control and
protection panel.
  Emergency Power System          
  Emergency DG Set 1 per Plant x x    
  Telemetering & Communication System          
  Communication links for the power grid SCADA system lot x x
Remote Terminal Unit(RTU) and Load dispatch control
  lot x x
interface equipment
             
E.1 Co- Generation System          
E.1.1 Exhaust Gas Boiler 1 per engine x x    
Structural operating platform with handrails &
  1 per boiler x x    
ladders/railing at operating level.
Gas bypass damper 1 per boiler x x
  Boiler Accessories 1 per boiler x x    
  Boiler Mountings and Fittings 1 per boiler x x    

Appendix 2 - Split of Work Scope Page 6 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Boiler Instruments, Controls And Safeties 1 per boiler x x    


  Completely Prewired Control Panel 1 per boiler x x    
 
Pipes, valves, clamps and fittings 1 Lot x x    

  Pipe supports to system equipment 1 Lot x x    


  Cables/Cables trays/Lugs/Glands 1 Lot x x    
HP Feed Water Pumps 1 Set x x
LP Feed Water Pumps 1 Set x x
Chemical Dosing unit 1 Set x x
HP Deaerator 1 No x x
LP Deaerator/ Feed Water Tank 1 No x x
Non condensed gas removal/ Air Vents 1 Lot x x
E.1.2 Steam Turbine Generator          
  AC generator 1 set x x    
  Generator protection (relay) panel 1 set x x    
  Metering, Synchronizing 1 set x x    
  AVR cum Excitation panel 1 set x x    
Lightning arrestor, Surge capacitor and Potential
  1 set x x    
transformer (LA, SC & PT) panel
  Turbine Control Panel 1 set x x    
  Turbine Gauge Panel 1 set x x    
  MCC for Turbine Auxiliary 1 set x x    
  Neutral Grounding Transformer for Turbine Generator 1 set x x    
Overhead Crane 1 set x x
Cooling Tower 1 set x x
Water Cooled Condenser 1 set x x
Chemical Dosing unit for Cooling Tower 1 set x x
Steam Turbine Bypass system 1 set x x
Condensate Extraction Pump (2 x 100%) 1 set x x
E.1.3 Oil Fired Boiler 1 per plant x x
Structural operating platform with hand rails &
  1 set x x    
ladders/railing at operating level
  Boiler Accessories 1 Set x x    
  Boiler Mountings and Fittings 1 Set x x    
  Boiler Instruments, Controls And Safeties 1 Set x x    
  Completely Prewired Control Panel 1 Set x x    
  Pipes, valves, clamps and fittings Lot x x    
  Pipe supports to system equipment Lot x x    
  Cables/Cables trays/Lugs/Glands Lot x x    
F Tank Farm          

Appendix 2 - Split of Work Scope Page 7 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

F.1 Tanks Inside Tank Farm          


Diesel oil storage tank, 200 m^3 1 per plant x x    
  HFO storage tank, 5000 m^3 2 per plant x x    
  HFO Service Tank, 500 m^3 2 per plant x x    
  HFO Settling/Buffer Tank, 750 m^3 2 per plant x x    
  Lube oil storage tank, 55 m^3 1 per plant x x    
  Lube oil maintenance tank, 55 m^3 1 per plant x x    
  Used LO tank, 55 m^3 1 per plant x x    
  Oily Water Tank, 55 m^3 1 per plant x x    
  Sludge Tank, 100 m^3 2 per plant x x    
 F.2 Water Tanks          
Firefighting water tank (as per NFPA) 1 per plant x x    
  Raw water storage tank (500 m^3) 1 per plant x x    
DM water tank (200 m^3) 1 per plant x x
F.3  Piping Material In Tank Farm          
Pipes in tank farm 1 lot x x    
  Fittings for pipes in tank farm 1 lot x x    
  Armatures for pipes in tank farm 1 lot x x    
  Pipe supports inside tank farm 1 lot x x    
  Bolt sets and gaskets in tank farm 1 lot x x    
F.4  Insulation Material For Tank Farm          
Insulation material for tank farm piping 1 lot x x    
 F.5 Unloading and Discharge Systems          
Unloading Pumps          
Heavy fuel oil unloading pumps, 50 m^3/hr 2 sets x x    
  Diesel oil unloading pumps, 50 m^3/hr 2 sets x x    
  Lube oil unloading pump 2 sets x x    
Sludge Discharge pump 1 set x x
  Piping material for unloading and discharge system 1 lot x x    
F.6 Fuel Truck Static Weigh Bridge (30 TON) 1 Lot x x    
  Retrofit All Steel Deck (Mono / Dual /Multi) 1 Lot x x    
  Load Cells Compression Type IP68 1 Lot x x    
  Steel Mounting (Base) of Load Cells 1 Lot x x    
  Pad Plates / Grouting Parts 1 Lot x x    
  Digital Weigh Indicator with RS 232 - C output 1 Lot x x    
F.7 Insulation for pipes 1 Lot  x   x    
G Plant Service And Protection Systems          
  Fire Fighting System 1 lot x x    
  Power House Crane          

Appendix 2 - Split of Work Scope Page 8 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Power house crane (EOT) 1 set x x    


  Lifting Devices          
 
  Monorail hoist inside fuel treatment house 1 set x x  

H CIVIL          
H1 Power Plant Buildings and Utilities          
  Engine Hall          
  Engine hall sub structure and brick walls 1 lot x x    
  Engine hall prefab super structure 1 lot x x    
Turbine Hall
Turbine hall sub structure and brick walls 1 lot x x
Turbine hall prefab super structure 1 lot x x
  Electrical / Control Building          
  Control Building sub structure and brick walls 1 lot x x    
  Control Building prefab super structure 1 lot x x    
  Fuel Treatment Plant Building          
  FTP sub structure and brick walls 1 lot x x    
  FTP prefab super structure 1 lot x x    
  Exhaust Chimney          
  Sub structure 1 lot x x    
  Prefab (steel) super structure 1 lot x x    
  Radiators Support Structure          
  Sub structure 1 lot x x    
  Prefab (steel) super structure 1 lot x x    
H2 Other Power Plant Buildings          
  Pump House          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure 1 lot x x    
  Oil Unloading Area          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure(if any) 1 lot x x    
  Day Tank Containment Area          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure (if any) 1 lot x x    
  Fuel Storage Containment Area          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure (if any) 1 lot x x    
  Water Treatment And Fire Fighting 1        

Appendix 2 - Split of Work Scope Page 9 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Sub structure and brick/concrete works 1 lot x x    


  Prefab super structure 1 lot x x    
  ONE STORY OFFICE BUILDING          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure 1 lot x x    
  WORKSHOP & STORE          
  Sub structure and brick/concrete works 1 lot x x    
  Prefab super structure 1 lot x x    
Cleaning bay 1 lot x x
  TWO STORY DORMETORY          
  Sub structure and brick/concrete works 1 lot x
  Prefab super structure 1 lot x
ONE STORY DRIVERS SHED  
Sub structure and brick/concrete works 1 lot x x
Prefab super structure 1 lot x x
H3 Auxiliary Structures          
  Cooling System Structures 1 x x    
  Supporting Structures          
  Substructures exhaust gas stack 1 x x    
  Substructures exhaust gas pipes 1 x x    
  Substructures exhaust gas boilers 1 x x    
  Substructures heat recovery building / container 1 x x    
  Substructures pipe bridge 1 x x    
  Substructures pipe stair 1 x x    
  Substructures pipe supports 1 x x    
Superstructures charge air filter and ventilation unit
  1 x x    
platform
  Oil / Water Collecting And Separating Structures          
Substructures oily water collection and separating
  1 x x    
structures
H4 Others (Roads, drains etc.)          
  Roads, drains etc. Sub Structure 1 lot x x    
  Roads, drains etc. Super Structure 1 lot x x    
  Auxiliary Transformer Areas 1 x x    
H5 Pre-Phase Work          
  Soil investigation 1 x      
  Topographical survey 1 x      
  Staking - level control, measurements 1 x      
  Environmental study / modeling 1     x  

Appendix 2 - Split of Work Scope Page 10 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

H6 Site Works          
  Site Preparation          
  Site clearing 1 x      
  Removal of contaminated material 1 x      
  Top soil removal (if required) 1 x      
  Site levelling - cutting and filling 1 x      
  Site excavation 1 x      
  Site filling (after takeover) 1 x      
  Soil improvement 1 x      
  Underground Network        
  Drainage system 1 x      
  Earthing network 1 x      
  Landscaping          
  Landscaping 1 x x    
  Paving And Surfacing          
  Access road 1 x x
  Internal Roads 1 x x    
  Gravel areas and office vehicle Parking areas 1 x x    
  Site Accessories          
  Fence/Boundary Wall 1 x x    
H7 Shelters And Other Structures          
  Substructures and Superstructures 1 x x    
H8 Others          
  Land Handover 1     x  
  Generator Base Foundation 1 x x    
  Chimney Foundation 1 x x    
  Lighting pole foundation 1 x x    
  Cable Trench 1 x x    
  Pipe Pedestal 1 x x    
  Substation 1 x x    
I Engineering And Documentation        
I1 Engineering        
  Soil investigation Job x      
  Conceptual engineering- Respective Job x      
  Basic engineering -Respective Job x      
  Development of power plant layout Job x      
Tank farm area details engineering including tank
  Job x      
design, fabrication drawing (Respective Scope)

Appendix 2 - Split of Work Scope Page 11 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

Chimney details engineering including fabrication


  Job x      
drawing
Pipe Module design engineering for HT , LT , LO
  Job x       
system equipment’s supplied by Engine Supplier
  Civil information drawings-Respective Job x      
Detailed civil engineering of power plant as per
  Job x    
construction & supply scope
  Detailed engineering - Engine Supplier's equipment Job  x      
  Detailed engineering - EPGL Supplied equipment Job x      
  Detailed engineering - Client Supplied equipment Job x     
I2 Commercial Operation Documents (respective)        
  Station manuals in English (set) 1 x      
  - As hard copy 1 x      
  - On digital media 1 x      
             
J Project Management Services          
  Project Management          
Execution plan for power plant project (respective
  1 x   x  
scope)
  Time management (respective scope) 1 x   x  
  Project kick off meeting 1 x   x  
  Project quality management plan 1 x   x  
  Inspection and test plan 1 x   x  
  Procurement management (respective scope) 1 x   x  
  Document control (respective scope) 1 x   x  

K Temporary Installation And Arrangements          


  Utilities      
Telephone, telefax and internet connection to site
  1 x x x x
(respective)
  Electricity source and hook up, main electrical panel 1 x x
  Electricity consumption during construction 1 x      
  Water source and hook up 1  x x  
  Water consumption during construction 1 x      
  Waste Management During Construction      
  Dust control 1 x      
  Sewage collection 1 x      
  Waste disposal 1 x      
  Hazardous waste disposal 1 x      
  Security      

Appendix 2 - Split of Work Scope Page 12 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Temporary fencing 1 x    
  General security and site access control 1 x    
  Security of supplied equipment 1 x    
  Safety      
  General safety and fire protection 1 x    
Safety for Engine Supplier personnel and Engine
  1 x    
Supplier contractors
L Commissioning          
L1 Commissioning Advisory Service          
  Mechanical commissioning advisor, 170 man days Lot x       
  Electrical commissioning advisor, 160 man days Lot x       
Engine automation commissioning advisor, 12 man
  Lot x       
days
  Plant automation commissioning advisor, 6 man days Lot  x      
  Pre-Commissioning          
  Pre-commissioning (respective scope) 1 x    
L2 Testing Procedures        
  Workshop Tests        
  Engine test according to standard program 1 x      
  Third party inspectors (if required) 1     x  
  Customer Witness Workshop Test        
  Allowance 1     x  
  Travel 1     x  
  Accommodation 1     x  
  Local transportation 1     x  
Commissioning Management For Respective Scope
L3          
Of Supply
  Commissioning planning 1 x   x  
  Commissioning organization and resourcing 1 x      
  Health, Safety and Environment during commissioning 1 x      
  Commissioning coordination and meetings 1 x   x  
Commissioning time management, controls and
  1 x      
progress reporting
  Commissioning and performance test documentation 1 x      
L4 Initial Fillings          
  Erection - for Engine & Engine Equipments 1 x      
  Flushing consumables (except fuel) 1 x      
  Lubricants (Engine & Turbine) and Fuel oil 1   x  
  First fill of coolant conditioner 1 x    

Appendix 2 - Split of Work Scope Page 13 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  DM Water required for engine HT/LT circuit 1 x      


Chemicals 1 x
  Fuel for Engine, Boiler commissioning 1     x  
L5 Load Banks And First Service          
  Load banks for testing purposes (if required) 1     x  
First running in service (including running in filter
  1  x    
change)
             
M Training          
  Training At Site          
Power plant operation and maintenance course (4
  1 x      
week)
  Power plant electrification course on site (2 weeks) 1 x      
             
N General          
N1 Site Facility During Construction :-          
Adequate storage facility at site suitable for the
  Job x    
equipment
  Site security/guarding Job x    
  Free & unrestricted access to the power plant site Job   x  
  Approach road from highway to power plant site Job x    
Jetty/ pontoon/ any other fuel offloading facility (if
  Job   x  
required)
  Temporary water supply. Job x    
  Office for EPC site personnel Job x      
  Office facility for engine manufacturer personnel Job x      
Lodging and boarding for engine supplier's project team
  Job x      
/ supervisors as required
  Construction supervision/ management Job x      
Fuel Quality & Composition Tests/Ambient Air
N2 Job x     
Quality Test/ Water Quality Analysis
N3 Environmental control measures as per EIA 1 lot x     
N4 Sound Attenuation measures based on ESIA report 1 lot x x 
N5 Temporary Construction Power          
Construction of 11KV transmission line up to power
  Job x x
plant site
Required construction power transformer & other
  Job x x
equipment is like HT LT panel at plant site.
  Approval for construction power Job     x  
  Monthly Bill Job x      
  Rental equipment for construction power Job x x    

Appendix 2 - Split of Work Scope Page 14 of 16


SupplyEPGL/ MAN

InstallationEPGL

SupplyClient

InstallationClient
Quantity
Section

Items

  Diesel & consumable for rental equipment Job x x    


             
O Shipping and Logistics          
Sea shipment for engine supplier's imported equipment-
  Lot  x      
CFR Chittagong / Mongla Port
  Custom clearance for imported equipment Lot     x  
  Port charges & all applicable duties, CnF charges etc. Lot  x    
  Inland transportation to site engine supplier's equipment Lot x      
Inspection during unloading of equipment at
  Lot x      
site(respective scope)
  Equipment inspection at site (respective scope) Lot x      
  Security of parts & equipment at site Lot x    
  Storage of parts & equipment at site Lot x      
  Securing of road permits / rights of way Lot   x  
  Permits / deposit / rental on containers Lot x    
             
P Taxes, duties and customs          
Bangladesh customs and import duty, vat, taxes, levies
  Lot     x  
and other taxes for permanent materials of the project
Securing of all import licenses & exemption
  Lot     x  
documentation
  Customs clearance and forwarding at port of entry Lot x
Imported Items LC Fees x
Imported Items LC related Bank Charges x
Intentionally Left Blank
  Intentionally Left Blank          
Q Insurance          
Marine & Cargo Insurance Lot x
Delay start-up Insurance Lot x
Contractors all risk Lot x
3rd party liability Insurance Lot x
Workers compensation & employers liability Lot x
             
R Permits          
  Approvals and permits, building / civil works Lot     x  
  Approvals and permits, mechanical Lot     x  
  Approvals and permits, electrical Lot     x  
  Approvals and permits, fire safety /explosives Lot     x  
  Approvals and permits, environmental / health Lot     x  
  Approvals and permits, occupancy Lot     x  

Appendix 2 - Split of Work Scope Page 15 of 16


Appendix 2 - Split of Work Scope Page 16 of 16