Relay Coordination Calculations and Time Current Curves
Relay Coordination Calculations and Time Current Curves
ABSTRACT- Protection system equipment is non-profit producing part of any power system. It is
considered idle during normal operational period but has its implications on reliability of whole power
network during system exigencies. Protection system mal-operation & failure to operate, both involve
increase in equipment damaging, operating personnel/general public safety issues and also possibly long
disturbances in maintaining continuity of supply. Properly timed and selective operations of protective
relays ensure isolation of only faulty portion of system from healthy one. In this paper load flow analysis &
short circuit studies are carried out using modern simulation tool for a typical 132 kV to 11 kV distribution
network of GEPCO. Over current & earth fault (O/C-E/F) relay settings are calculated manually and its co-
ordination with upstream and downstream relays is visualized by TCC curve view feature of using
manufacturer’s rely models.
KEY WORDS: Over current protection, star view, relay co-ordination, Earth fault settings, TCC
1- INTRODUCTION: Section (4) gives a brief review of star view
feature 0f Modern power System Simulation
Power system protection is a systematic
softwares.
knowledge, skillfulness and art of applying
relays, fuses or both to provide maximum Section (5) contains the case study of a GEPCO
sensitivity to faults and abnormal operating system from 132 kV substations to a typical end
conditions but to avoid their operations under user.
all permissible and tolerable conditions [1]. Over Section (6) contains the power system
current protection of power system equipments protection data and equipment settings and at
is one of the oldest and mostly used protection the last load flow report of the whole system is
techniques known protection Engineers upto
date. As the impedance of power system during
short circuit fault is always less than the
impedance during normal operation therefore
current through the equipment during fault
condition is always greater than during normal
operation. This many fold increase in current
from normal level can help in detection of fault
and isolation of faulty portion of system. To
cope with the possible saturation of CTs on
heavy fault currents, relay and circuit breaker
failure, a parallel backup protection system
enhances the system reliability. As the time slot
for decision to operate or not to operate for
2- POWER SYSTEM FAULTS:
protection system is very narrow therefore
proper coordination between primary and back Faults which an electrical power system will face
protection is considered as pre-requisite for are given below in Figure-2.
protection system designing.
Short Circuit Faults:
Paper layout plan is as given below:
When current through a network takes a shorter
Section (2) contains the description of possible
faults and faults discrimination techniques.
Section (3) describes the important relay terms
& settings/calculations formulae.
route than intended one then system is said to over current (O/C) relays as shown in figure-4.
undergo a short circuit fault. This relay operates when mismatch between the
different phase currents exceeds a preset limit.
Open Circuit Faults:
Operating current of earth fault (E/F) relay is the
When usual route of current is broken by vector sum of three phase currents.
opening of jumpers or conductors then system is
said to undergo an open circuit fault. However
all the open circuit faults sooner or later became
short circuit faults.
phase faults than delta connected CTs and Fault Discrimination Methods:
provision of residual over current protection due
Three basic approaches are in practice for fault
to availability of zero sequence currents [2].
Ideally three over current relays should be discrimination namely:
connected across three CTs and due to non
i. Discrimination by time
availability of neutral CT, an earth fault relay is
connected across the earth and start point of ii. Discrimination by current
iii. Discrimination by both time and current operating time is achieved for the portion of
network near the source and relatively larger
time for the portion near to the load. IEC, IEEE
Discrimination by Time: ANSI and other have devised their own typical
characteristic curves as shown in figure-8 below
In this method the relay closest to the load will
trip faster and to source will trip later according 3- RELAY SETTINGS AND CO-ORDINATION:
to time grading. Every relay behind the other When current through any phase exceeds a
will take a little bit greater time depending upon predetermined value then relay detects it as a
the coordination time interval (CTI).As we know fault and one or more of its output contacts
that fault current increases when moving
towards source due to decreasing impedance
therefore the that portion of network which has
faces the highest fault current will trip at the last
as shown in fig-6. It is evident that tripping time
increases with increasing fault current value
which is the major drawback of this coordination
method.
TMS = Relay
tolerance and
0.12 s 0.12 s 0.17 s 0.17 s
*Actual operating time is calculated using TMS at the settings error
maximum value i.e. 1.
Total CTI 0.30 s 0.20 s 0.35 s 0.25 s
Instantaneous settings:
Table 3
Current value at which relay will operate
without any intentional time delay. Its value *E/M = Electromechanical
must be greater than transient surge values of CTI = tCB + tRelay-Overtravel + tTolerance.+setting error
the system to avoid unnecessary tripping.
4- ETAP & DIgSILENT.
Operating time of relay:
ETAP & DIgSILENT are widely used tools, having
In GEPCO, IEC characteristic curves are usually in advanced features. Both may helps in carrying
use for grading purpose. Formula of IEC load flow studies to determine the continuous
curve(s)* is given by current ratings of fuses and CT ratios whereas
the short circuit study is carried to determine
the fault level at each bus for proper relay
settings/operation in case of fault and star view
Where α and β values are dependent upon the is a way of presenting one line diagram and its
type of curve used. Details are given in Table-2. associated curves/diagrams on graphical
*IEC curves are applicable to PSM<=20 only. interface. Star TCC view display the device
Slope of Curve α Β
characteristics view on an adjustable time versus
current frame. It has dynamic display allowing
Normal Inverse 0.02 0.14 the manufacturer’s device models, curves along
Very Inverse 1.00 13.5 with setting range which enables user to set the
device behavior according to need as shown in
Extremely inverse 2.00 80.0
figure-8.
Long Time inverse 1.00 120.0
Table 2 [5]
1-LINE- 492 35.02 600/5 N/A 800 N/A 90 31.79 600/5 N/A 800 N/A DT
R
2-T/F- 126 14.63 200/5 100 600 0.26 100 13.89 200/5 *524 600 0.26 IEC-SI
HV-R
6-GD- 392 5.78 400/5 12.7 200 0.07 40 3.62 400/5 43.9 200 0.8 IEC-SI
O/G-R
11-MES-
IN1&2- IEC-SI
R1&2 264 5.05 400/5 16.5 160 0.07 40 2.86 400/5 51.5 160 0.06
13-MES- 160 3.46 200/5 18.7 100 0.04 20 1.91 200/5 56.7 100 0.04 IEC-SI
O/G-
R11
14-MES- 80 3.89 100/5 42 100 0.04 50 2.25 100/5 134 100 0.04 IEC-SI
O/G-
R14
15-MES- 280 3.26 400/5 10.1 140 0.05 200 2.29 400/5 58.8 140 0.05 IEC-SI
IN22-R
16-MES- 160 3.3 200/5 17.8 100 0.04 100 1.88 200/5 55.8 100 0.04 IEC-SI
O/G2-
R1
18- 80 3.53 100/5 38.1 100 0.04 50 2.02 100/5 120 100 0.04 IEC-SI
MES-
O/G2-
R2
19- 40 3.5 50/5 75.6 100 0.04 25 2.01 50/5 28.7 100 0.04 IEC-SI
MES-
O/G2-
R3
Table 4
*Relays studied here are limited by manufacturer to minimum TMS of 0.05 only.
*When PSM is greater than 20 then 20 is used for time calculation.