EDOC-Testing and Commissioning of MV
EDOC-Testing and Commissioning of MV
Table of Contents:
1. Small Wiring And Connection Of LV Cables
2. Filling With Insulation Medium
3. Earthing of Switchgears
4. Final Inspection
1. Final Inspection of Indoor Switchgear
2. Common for Both Indoor and Outdoor Switchgear
5. Testing and Commissioning
1. Visual Inspection Check
2. Mechanical Check
3. Electrical Check
4. Operational Check
5. Insulation Resistance Check
6. High Voltage Check
6. Final Commissioning / Load Testing
7. Dos & Don’ts
It must be ensured that the ratings of CTs with meters, relays, etc. are
matching. The auxiliary wiring should be neatly supported, and loose wires
should be avoided as they may interfere with other devices. Refer to the
schematic and wiring diagram and connect the required cables of auxiliary
supply controls, metering and protection. Always use proper glands and lugs.
During the process of ensuring that the joints are oil-tight for the oil
circuit breakers, the joint faces, gaskets and the operator’s hands should
be dean before and during the assembly. Jointing material should be applied
as directed and the bolts tightened up evenly not more than half-a-turn at a
time and finally pulled up as tight as possible.
Similarly for air blast switchgear or switchgear having pneumatically
operated mechanism, due care and attention should be given to joints in
piping with air at pressure. Tests should be conducted to check for air
leakage after installation in order to ensure correctness of such joints.
3. Earthing of Switchgears
Earthing points provided in switchgear are to be connected with the station
earth bar/earth grid. Measurements of earth impedance are made to ensure
that no dangerous voltages can arise due to fault currents flowing in the
earth conductors.
4. Final Inspection
After the switchgear erection has been completed, a final inspection is made
covering various aspects of both indoor and outdoor switchgears. The details
of this inspection are discussed below.
• Check that the serial number of the base frame and mechanism
housing are the same.
• Check that the nuts of foundation bolts are fully tightened and that the
spring washers are used.
• Check the tightness of the entire hardware of poles, structure,
mechanism, etc.
• Check that porcelains, etc. are free from any damage.
• Check the levelling of the base frame and poles.
• Check that all settings marked with a red paint line are undisturbed and
properly locked with nuts and spring washer.
• Check that all pins are locked with circlips.
• Ensure that the gaskets for doors and covers are in good condition and
pasted in proper places.
• Check that cabling and earthing connections are properly made.
• Ensure that porcelains are dean and the mechanism parts duly
lubricated.
• Check that the breaker does not operate manually or electrically if the
key of the mechanical interlock (if any) is removed.
Visual inspection check of a medium voltage switchgear (photo credit: Colombara Romeo)
• Check the wiring with the relevant scheme and wiring diagrams. Check
the insulation resistance with a 500 V megger.
• Check that the control, indication and auxiliary leads are connected to
the respective terminal blocks.
• Ensure the availability of AC and DC supplies.
• Charge the dosing spring by motor. The charging time should not
exceed 15 seconds.
If the tinning is more than 15 seconds, check the voltage. If voltage is
OK, then check the linkage and gear movement for free movement. At
the end of the spring charging operation, the motor supply is
automatically cut off by the limit switch.
• Electrically close/open the circuit breaker through push buttons/control
switch from the local panel.
• Check the contact resistance between the upper and lower terminal
pads with breaker/ interrupter closed under spring force. The value
should be less than the manufacturer’s recommendation.
• Check the insulation resistance across breaker open terminals and
between lower terminal to earth with 2.5/5 kV megger. The value
should not be less than 10,000 mega-ohms or as recommended by
the manufacturer.
• Check the opening and closing of breaker/interrupter with remote
control.
Similarly for the pneumatic mechanism, the maximum and minimum pressure should be
used, and the breaker should operate satisfactorily under any of these conditions.
Closing and tripping of the circuit breaker by local control and remote
For any reading that shows considerably lower values than these, investigation should be
carried out to trace the source of the low readings. The drying out method of improving
insulation resistance may be followed.
Irrespective of whichever method is employed for drying out, the general principle is to
apply heat continuously for a considerable time so as to drive out any moisture, which may
have become entrapped.
Primary Injection Testing Of Protection System For Wiring Errors Between VTs / CTs and
Relays (photo credit: Varitel Proyectos e Ingeniería SAS)
The application of high voltage to switchgear is not universal but may be conducted. It is
preferable that such tests be carried out with AC supply. Voltage should be applied in
accordance with the values specified in the relevant standards for a particular system
voltage. The frames and secondary windings of all current transformers and voltage
transformers included in the test should be earthed.
These tests should be carried out on each phase in tandem with the remaining phases
earthed and all units racked in service position and the breaker dosed.
The insulation resistance test should be carried out before as well as after the high voltage
test to ensure that there has been no reduction in value. If the second reading is lower, each
separate component should be tested to find out where the lower figure has occurred.
The following precautions should be observed when conducting the high voltage test:
• During the test, one terminal of the testing transformer is connected to earth and to
the frame of the circuit breaker.
• The test should be commenced at a voltage of more than one-third the test voltage.
• The voltage should be increased from its initial value as rapidly as is consistent with
its value being indicated by the measuring instrument.
The full test voltage should then be maintained for the appropriate duration as the
case may be and then reduced to its initial value and switched off.
• While conducting the high voltage test, the manufacturer’s instructions should be
followed. The HV test on auxiliary and control circuit should be carried out by
looping together all the wires and applying 2000 V AC for one minute. All current
transformer and voltage transformer earth connections should be removed for this
test, and should be replaced immediately thereafter.
If the test blocks are available or the relays have test plug connections, it may be
worthwhile to carry out a final check to see that the CT polarity is correct and that the
instrumentation is giving correct reading. A typical pre-commissioning checklist is shown
below for an outdoor circuit breaker.
Carry out a final check to see that the CT polarity is correct