Đề Thi PSM I - Đề 1
Đề Thi PSM I - Đề 1
2 . Which of the following best describes the way a Product Owner can order the items in the Product Backlog?
A . Based on size; larger items at the top
B . Based on value; more valuable items at the top
C . Based on risk; safer items at the top
D . Based on size; smaller items at the top
3 . True or false? The Sprint Goal and the Sprint Backlog are the outputs of the Sprint Planning meeting.
A . FALSE
B . TRUE
9 . True or false? The Developers can have a Team Leader to improve communications and collaboration.
A . TRUE
B . FALSE
10 . There's a Scrum project that is supposed to have two releases: one in the middle and the other at the end of the project.
Which of the following statements is correct about this project?
A . Having releasable Increments depends on the preference of the operations'.
B . Increments that are created before each release should be releasable.
C . Increments are created for investigation and adaptation; they don't have to be releasable.
D . All increments should be releasable.
11 . True or false? It's up to the self-managing team to decide which Scrum events are needed in the project.
A . FALSE
B . TRUE
13 . True or false? Daily Scrums are held at the same time and place every day.
A . TRUE
B . FALSE
16 . Which statement explains the benefit of having tests in the Definition of Done?
A . Increases transparency of the Increments.
B . It makes it easier for the Scrum Master to measure performance and report progress.
C . It makes reporting easier for the Project Manager.
18 . True or false? Items at the top of the Product Backlog are, on average, smaller than those at the bottom.
A . FALSE
B . TRUE
19 . The Product Owner is not collaborating with the Developers during the Sprint. What would you do as the Scrum Master?
A . Talk to the functional manager of the Product Owner.
B . Coach the Product Owner to understand why collaboration is important in Scrum and how it can affect the value of the
product.
C . Nominate someone else as the proxy Product Owner.
D . Cancel the Sprint and start training the Product Owner.
20 . True or false? The Product Owner should have a complete Product Backlog before the first Sprint can start.
A . FALSE
B . TRUE
25 . The Developers are ready to start the first Sprint, but the Product Backlog is not yet ready. What should the Product Owner
do?
A . Let the Sprint begin, but only with the goal of completing the Product Backlog.
B . Ask the Developers to help you refine the Product Backlog instead of starting the first
C . Let the team start the first Sprint, and continue refining the Product Backlog.
26 . True or false? At least one high-priority process improvement item should exist in each Sprint Backlog.
A . FALSE
B . TRUE
34 . True or false? When multiple teams are working on a product, they should select work from the same Product Backlog.
A . TRUE
B . FALSE
35 . What happens if we forecast that some of the work defined in the Sprint Backlog won't be done by the end of the Sprint?
A . Review the work with the Product Owner to see if any adjustments are required, and keep working.
B . Extend the duration of the Sprint, to be able to deliver everything.
C . The remaining items will be moved to the next Sprint Backlog.
D . Continue to the next Sprint without a Sprint Review meeting and finish those items in the next Sprint.
36 . At the end of the Sprint, all items are Done except for one that is almost Done. What should be done with this item?
A . Consider the complete part of the item in velocity calculation and then create a new item in the Product Backlog for the
remaining work.
B . Demonstrate it in the Sprint Review meeting, if the item is presentable in its current state.
C . It can be added to the Increment if the user acceptance tests are done.
D . Move it back to the Product Backlog.
37 . True or false? The Sprint Backlog stays fixed after Sprint Planning.
A . TRUE
B . FALSE
38 . True or false? Each item in the Sprint Backlog is owned by one or a pair of Developers.
A . TRUE
B . FALSE
40 . What is the main reason for the Scrum Master to be at the Daily Scrum?
A . To tell Developers what to do
B . The Developers have asked the Scrum Master to facilitate their Daily Scrum
C . To participate as a Scrum Team member
D . To get a report on progress of the Sprint
41 . Which THREE Scrum values are demonstrated by focusing on the most valuable items first?
A . Cross-functionality
B . Trust
C . Courage
D . Focus
E . Respect
42 . Which of the following best describe the questions that are addressed in the Sprint Planning meeting? (Select multiple
choices)
A . Who will do what we have decided to do in this Sprint?
B . Why are we going to do this Sprint?
C . How are we going to do what we have decided to do in the Sprint?
D . What went wrong in the last Sprint and what can we do about it?
E . What was the feedback and how should we adapt the Product Backlog?
F . What are we going to do during the Sprint?
44 . How is the Product Backlog impacted by changes in the environment in which the product will be used?
A . The Product Backlog should be kept high-level enough to tolerate such changes.
B . It evolves to reflect the changes.
C . The old, baselined Product Backlog would be saved, and a new one would be created for
D . There's no effect on the Product Backlog.
47 . True or false? When multiple teams are working on the same product, there should be one common Definition of Done that
they all follow.
A . FALSE
B . TRUE
49 . Which of the following may be done when the team becomes mature enough during the project?
A . They may not need Sprint Retrospectives anymore.
B . Their velocity may increase.
C . They can release every Sprint.
D . They won't need timeboxed events anymore.
54 . True or false? It's generally better to have shorter Sprints when the project is riskier.
A . TRUE
B . FALSE
57 . Which TWO statements are correct about the number of Product Owners when there are three products being developed
using Scrum?
A . There can be a different Product Owner for each product.
B . There should be only one Product Owner.
C . Each product should have a separate Product Owner.
D . There can be a single Product Owner for all products.
59 . True or false? The Product Backlog is baselined before the first Sprint
A . TRUE
B . FALSE
61 . True or false? The Product Owner can delegate some of their responsibilities to the Developers.
A . FALSE
B . TRUE
63 . Which of the following is the LEAST productive way for the Scrum Master to improve the Developers' communications
with the Product Owner?
A . Teach them how to communicate effectively.
B . Monitor their communication performance.
C . Suggest effective communication tools and techniques to the Product Owner.
D . Act as a go-between for them.
66 . True or false? The Scrum Master shouldn't allow the Developers to start working without having the tasks identified and
assigned.
A . TRUE
B . FALSE
67 . True or false? Sprint Review is a meeting for receiving customer's formal acceptance.
A . TRUE
B . FALSE
68 . Which THREE of the following actions may a Scrum Master take in starting up a project?
A . Ask the Developers to discuss and identify the way they are going to develop the product.
B . Ask the development managers to introduce their departments and capabilities.
C . Ask the team to work together and prepare a complete Product Backlog.
D . Ensure that a bonus system is in place for the top performance of individuals.
E . Ask the Developers to introduce themselves to each other and describe their skills and background.
F . Ask the Product Owner to explain the project, its business need, history, goals, and context.
69 . What should the Developers do when they have trouble delivering an item because they don't understand it?
A . Move the item back to the Product Backlog.
B . Complete as much of the item as possible, and use it in the Sprint Review meeting to create a better understanding of what is
needed.
C . Defer the item to the next Sprint.
D . Collaborate with the Product Owner to see what's possible and desirable.
70 . Which of the following has the most to do with capturing and using lessons learned?
A . Sprint Planning
B . Sprint Retrospective
C . Product Backlog refinement
D . Sprint Review
71 . Which of the following is a valid service from a Scrum Master to a Product Owner?
A . Help the Product Owner order the Product Backlog items in order to maximize value.
B . Help the Product Owner find techniques for managing the Product Backlog.
C . Act as the middleman between the Product Owner and the Developers, as requested or required.
D . Act as a proxy when the Product Owner is not available to the team.
74 . True or false? Only Product Backlog items that are "Ready" can be selected for the Sprint Backlog.
A . TRUE
B . FALSE
78 . Which are the THREE classical questions of Daily Scrums, if you decide to go through them?
A . What problems did I have yesterday?
B . What impediments are in my way or in the way of the team?
C . What work did I do yesterday to help the team achieve its goal?
D . How many hours did I spend on the project yesterday?
E . What is the progress of the Sprint?
F . What work am I going to do today to help the team achieve its goal?