SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Fencing Types I - V Installation Inspection SAIC-M-1002 18-May-05 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
Fencing passing over an underground grounding grid or under overhead
SAES-M-006
1 230 kV powerlines shall have galvanized chain-link fabric and hardware,
Sec. 4.5
regardless of location.
Concrete fencing anchors shall be continuous (from fence post
SAES-M-006
2 foundation to fence post foundation) concrete shall be 150 mm wide and
Sec. 4.6
extend down 300 mm from grade. (SASD AC-036680, Sht 1)
Reinforcing for the fencing anchors shall be 1-13mm diameter bar
running at a depth of 150 mm down the center line of the anchor and a
second stirrup bar 100 mm down the center line with 150 mm bent SAES-M-006
3
sections project in 50 mm above the top of concrete 300 mm from the Sec. 4.6
centers of posts and at 600 mm centers between the posts.
(SASD AC-036680, Sht 1)
All posts shall extend 900 mm into concrete footings as measured from
the ground surface. Where solid rock is encountered, posts shall extend
SAES-M-006
4 600 mm into concrete footings. Special Gate Posts over 170mm O.D.
Sec. 5.2.1
shall extend 1220mm into concrete foundations.
(SASD AC-036680, Sht 1, Note 1)
SAES-M-006
5 Footings for all posts shall extend 100 mm below the end of the post.
Sec. 5.2.2
The Post/Foundation interface shall be 13mm minimum larger diameter
hole than the Posts used extending 125mm below the top of concrete; SAES-M-006
6
Non-shink grout shall be used to fill the void. Sec. 5.2.3
(SASD AC-036680, Sht. 1, Notes 3 & 4).
The Post or Brace shall be wire brushed or lightly sanded and coated
with one coat of APCS-113 or APCS-22 extending 25mm above the SAES-M-006
7
concrete to 125mm below the top of concrete. Sec. 5.2.3
(SASD AC-036680, Sht. 1, Note 2)
If pre-cast fence post footings are used, backfill shall be compacted to SAES-M-006
8
meet or exceed the existing soil density. Sec. 5.2.4
SAES-M-006
9 All line posts shall be equally spaced at intervals of not more than 3 m.
Sec. 5.2.5
All posts except brace posts shall be installed in a vertical position, SAES-M-006
10
plumb and in line. Sec. 5.2.6
Terminal posts (Corner, End, Gate or Tension) shall be installed at the
beginning and end and at a maximum of 90 m intervals of fence fabric SAES-M-006
11
and at changes in vertical and horizontal alignments exceeding 22½° Sec. 5.2.7
deflection angle.
All posts shall be equipped with moisture excluding top caps or extension SAES-M-006
12
arms. Sec. 5.2.8
Page 1 of 2
SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - August 2004)
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Fencing Types I - V Installation Inspection SAIC-M-1002 18-May-05 Civil
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
The top rail (41 mm O.D. pipe) for Saudi Aramco Security Fencing Type I
SAES-M-006
13 and Saudi Aramco Type II Fencing shall be continuous except over drive
Sec. 5.3
gates; One expansion coupling shall be used for every 30 m of rail.
Brace posts shall be attached to all Saudi Aramco Security Fencing Type
I and Saudi Aramco Type II line posts at a point 1500 mm above ground
level and extend downward toward the inside of the fence at 45° in a SAES-M-006
14
vertical plane which is perpendicular to the plane of the fence. For Types Sec. 5.4
III, IV, and V Fencing, brace posts shall be installed on line posts at 90 m
centers of fencing runs.
The fencing fabric for Saudi Aramco Security Fencing Type I and Saudi
SAES-M-006
15 Aramco Type II Fencing shall be attached to top rails by means of tie
Sec. 5.5.1
wires spaced at intervals not exceeding 600 mm.
The fencing fabric shall be attached to the tension wire by means of tie
wires spaced at intervals not exceeding 300 mm. The tension wire shall SAES-M-006
16
be attached to the line posts by tie wire wrapped around the post and Sec. 5.5.2
secured to the tension wire by 3 complete turns on each side of the post.
The fencing fabric shall be attached to all line posts by means of tie wire SAES-M-006
17
spaced at intervals not exceeding 350 mm along each post. Sec. 5.5.2
Except on Type V Fencing, barbed wire shall be held in the extension
arm slots by means of lock wire. Holding the barbed wire in the slots by SAES-M-006
18
means of the tension in the wire is not permitted. Barbed wire, where Sec. 5.6
required, shall be extended over walk gates.
Tension wire shall be secured to terminal posts by means of a winding SAES-M-006
19
bracket. Sec. 5.7
Each brace assembly shall consist of one top and one intermediate
compression member both of 41 mm O.D. pipe and one adjustable
diagonal tension rod of at least 10 mm diameter. For Saudi Aramco SAES-M-006
20
Security Type I Fencing and Type II Fencing, the top rail is the top Sec. 5.8.1
compression member and shall be one piece without couplings in the
bracing panel.
Gate and end posts shall be braced to the nearest line post with one SAES-M-006
21
complete brace assembly. Sec. 5.8.2
Corner and tension posts shall be braced to the two nearest line posts SAES-M-006
22
with one complete brace assembly to each line post. Sec. 5.8.3
REMARKS:
REFERENCE DOCUMENTS:
1- SAES-M-006 -- Saudi Aramco Security and General Purpose Fencing, 30 November 2003
2- AC-036680 -- Saudi Aramco Security and General Fencing Footings Details, 03 March 1997
Contractor / Third-Party Saudi Aramco
Construction Representative* PMT Representative
Work is Complete and Ready for Inspection: T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
QC Inspector PID Representative
Performed Inspection Work / Rework May Proceed T&I Witnessed QC Record Reviewed Work Verified
Name, Initials and Date: Name, Initials and Date:
QC Supervisor Proponent and Others
Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
Name, Organization,
Name, Sign and Date:
Initials and Date:
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED
Page 2 of 2