SPMT Bridge Construction B-XX-XXX, Item SPV.0105.xx.: A Description A.1 General
SPMT Bridge Construction B-XX-XXX, Item SPV.0105.xx.: A Description A.1 General
A Description
A.1 General
This work consists of preparing the Bridge Staging Area and Travel Path, constructing
temporary supports to allow for the construction of the bridge superstructure of Enter
Structure Number in the Bridge Staging Area, transporting the bridge superstructure to its
final location, and placing it on the substructure units using Self Propelled Modular
Transporters (SPMTs).
It is mandatory to transport Enter Structure Number to its final location on the substructure
units using Self Propelled Modular Transporters (SPMTs). Other methods of moving the
bridge superstructure to its final location shall not be permitted.
Perform the Work per the applicable provisions of the current WisDOT Standard
Specifications for Highway and Structure Construction.
A.2 Definitions
The following definitions apply to these special provisions.
The Heavy Lifter’s supervisor in charge of this work shall have a minimum of five years of
experience as a Heavy Lifter, which includes previous SPMT bridge move experience.
The Heavy Lifter’s SPMT operator shall have a minimum of five years of experience as a
Heavy Lifter operator.
A.4 Submittals
A.4.1 Heavy Lifter’s Qualifications
Submit the following information and data to the Engineer for approval at least 14 days prior
to the Preconstruction Meeting:
Proof that the Heavy Lifter qualifications have been met including a list of similar
projects completed within the last five years with names and phone numbers of owner’s
representatives who can verify the Heavy Lifter’s participation in those projects.
Name and experience record of the Heavy Lifter supervisor in charge of the bridge
moves.
Name and experience record of the Heavy Lifter SPMT operator.
Electronically submit the Working Drawings and associated design computations as PDFs to
the Engineer for acceptance by the Bureau of Structures, Structures Design Section. Allow
the following time period in the construction schedule: 14 calendar days after the first receipt
of plans by the Structures Design Section for a complete initial review of the design and
plans submittal, and an additional 14 calendar days for any necessary revisions and/or
corrections.
The Department will return Working Drawings (electronically) from this submittal, and any
subsequent submittals, to the contractor, either indicating acceptance or marked with required
revisions and/or corrections. Provide the engineer copies of Working Drawings to be used in
fabrication and construction.
Electronically submit the Bridge Move Document and associated design computations as
PDFs to the Engineer for acceptance by the Bureau of Structures, Structures Design Section.
Allow the following time period in the construction schedule: 14 calendar days after the first
receipt of plans by the Structures Design Section for a complete initial review of the design
and plans submittal, and an additional 14 calendar days for any necessary revisions and/or
corrections.
The Department will return the Bridge Move Document (electronically) from this submittal,
and any subsequent submittals, to the contractor, either indicating acceptance or marked with
required revisions and/or corrections. Provide the engineer copies of Working Drawings to
be used in fabrication and construction.
Submit the Elevation Control Surveys for Temporary Supports and Superstructure
Monitoring Records to the Engineer.
B Materials
Breaker Run shall conform to standard spec 311.2.
Concrete Barrier Temporary Precast Delivered and Concrete Barrier Temporary Precast
Installed shall conform to standard spec 603.2.
Shims, if required under the bearings, shall conform to standard spec 506.2. All shims shall
be steel and be the same size or larger than the bearing pads they are supporting. Submit shim
details to the Engineer for review and approval.
Non-shrink grout, if required under the bearings, shall be structural, quick-setting, rapid
strength gain, high-bond strength grout per to standard spec 506.3.30. Grout shall not contain
calcium chloride or admixture containing calcium chloride or other ingredient in sufficient
quantity to cause corrosion to steel reinforcement. Mix grout just prior to use according to the
manufacturer’s instructions.
All other materials required to complete this bid item shall conform to the Standard
Specifications and shall be included in the bid item “SPMT Bridge Construction Enter
Structure Number”. Use of non-standard materials shall be submitted to the Engineer for
approval.
C Construction
C.1 Bridge Staging Area (BSA)
Identify the location of the Bridge Staging Area Describe Location as shown on the plans.
The Contractor shall be responsible for all work items and materials necessary to prepare the
bridge staging area including clearing and grubbing, excavation, drainage, drainage
structures, fill, grades, and the soil support for all equipment, SPMTs, materials, and
temporary supports.
Restoration of the Bridge Staging Area shall be included with roadway bid items.
Conduct a geotechnical investigation of the BSA site to determine sub-surface conditions and
any required ground improvements or soft soil mitigation necessary for bridge construction
or transporting the bridge to the final site. The geotechnical investigation shall be
summarized in a report and submitted with the BSA working drawings.
The soil substrate for the BSA, under the shadow of the bridge superstructure and SPMT
assembly, shall withstand a minimum allowable bearing pressure of 1500 psf or as required
for the specific equipment and loads to be transported. The Geotechnical Report shall verify
that this minimum allowable bearing pressure is satisfactory and that more bearing capacity
is not required. Ground improvements or soft soil mitigation necessary to achieve the
necessary bearing capacity shall be included in the bid item “SPMT Bridge Construction
Enter Structure Number”.
Where the soil substrate cannot meet the minimum allowable bearing pressure, timber mats
or steel plates may be used to achieve the minimum allowable bearing pressure.
Existing soil borings in some of the areas of the BSAs are shown on the plans. The
Contractor shall determine if more soil borings are required.
Clearing and grubbing of the BSA shall conform to standard spec 201.
Excavate the BSA as necessary. Excavation shall conform to standard spec 205 and as
modified in this special provision.
The BSA Working Drawings shall include erosion control and shall conform to the erosion
control plan included in the roadway drawings. Erosion control shall conform to standard
spec 628.
Identify and address any geometric constraints including those affecting construction
activities such as concrete placement and girder erection in the BSA.
Determine any utility conflicts and resolve prior to the construction of the BSA. Refer to the
Utilities section of these special provisions for a list of known utilities within the project area.
Provide BSA Working Drawings that include a layout and grading plan, all ground
improvements, soft soil mitigation, erosion control, utility protection, and identify such items
as sheeting, haul roadways, materials to be stored on the site, temporary structures, and
temporary storm runoff control. See Section A.4.2 of this special provision for submittal
requirements.
Design the temporary supports for a minimum lateral load equal to ten percent of the dead
load. Apply the lateral load at the elevation of the bearing seats.
Provide weekly elevation control surveys, including top of footing if exposed and temporary
bearing seat elevations, to monitor settlement. Provide additional surveys when temporary
supports are complete and immediately before girders are erected, and before the deck is
placed. Provide the surveys until the superstructure is placed in its final location.
Temporary support beam seat elevations shall match the relative vertical elevations at the
bridge substructures within a tolerance of 0.01 feet. Submit to the Engineer an elevation
correction plan for review and approval if the tolerance is not met.
Remove temporary supports after bridge move unless otherwise directed by the Engineer.
Provide Temporary Supports Working Drawings that include plans and design calculations
for temporary supports. See Section A.4.2 of this special provision for submittal
requirements.
Provide Travel Path Working Drawings that include plans, geotechnical engineering
calculations for allowable soil loads along the Travel Path, and site specific methods to
provide utility protection along the entire length of the Travel Path. Also provide calculations
which show that the twist limits will not be exceeded on the Travel Path. See Section A.4.2
of this special provision for submittal requirements.
Protect all infrastructure crossed. Loaded SPMTs shall not cross over any bridge.
Remove concrete barrier in the median as necessary to gain access to the final bridge site
prior to moving the bridge. Removing Concrete Barrier shall conform to standard spec 204.
Verify that adequate horizontal and vertical clearances exist to safely move the bridge.
Design the Travel Path to limit twisting of the superstructure to the values shown on the
plans.
Determine any utility conflicts on the Travel Path and resolve prior to moving the bridge.
Refer to the Utilities section of these special provisions for a list of known utilities within the
project area.
Return the Travel Path to its preconstruction condition unless otherwise directed by the
Engineer. Travel Path restoration shall be described in the Bridge Move Document.
C.4 Utilities
The SPMT lifting system shall include the SPMTs, their blocking which provides the
interface between the SPMT platform and the bridge superstructure, and any other devices or
apparatus used to tie the SPMTs together and to move bridge superstructure(s). Provide a
description of backup equipment in the Contingency Plan section of the Bridge Move
Document for review and approval by the Engineer.
Provide an SPMT system to lift bridge(s) from temporary supports and move bridge(s) to
their final location. Design the SPMT lifting system to lift the bridge(s) at the support points
shown on the plans. Any variation in support point locations from the locations shown on the
plans shall require approval by the Engineer.
With approval by the engineer, SPMT support points may relocated, without supporting
calculations addressing the changes in internal bridge stresses and bridge deflections,
provided each of the following conditions are met:
The revised support conditions are closer to the ends of the girder than the assumed
values shown on the plans.
The revised support conditions are placed at an equal distance from each end of the girder
(symmetric support).
The revised support locations provide a single line of support at each SPMT unit, as
shown on the plans.
Provide calculations for any changes in the locations of the lift points that do not meet the
requirements above. Any changes to the superstructure design and construction as a result of
lifting point relocation shall be the responsibility of the contractor. The Contractor shall make
all design changes prior to the girder fabrication. Variations to the SPMT support locations
which do not meet the above criteria shall be supported by calculations prepared and sealed
by a professional engineer registered in the State of Wisconsin, demonstrating that the
imposed stresses and deflections in the bridge, due to the revised support conditions, fall
within the allowable limits shown on the plans. Any design changes required to mitigate the
stresses or deflections shall be included with the submittal, as well as an analysis of the
allowable twist limits for the new support locations.
While lifting and transporting superstructure on SPMT’s do not translate, or tilt the spans.
The lifting system shall provide wheel pressures equal to or less than those designated by the
Geotechnical Engineer. Provide lifting system with 24 inch stroke to fully lift a bridge,
traverse the Travel Path to the final bridge location, and place it within the allowable limits.
Calculate the anticipated lateral forces during the move including but not limited to braking,
turning, vertical grades and wind loads. Provide a system to transfer these loads to the SPMT
system. The bridge superstructure has been designed to resist xx kips, or xx % vertical
weight, or xx kips/ft, or xx ft/s2 deceleration of lateral force internally. If any of the above
forces will develop a greater lateral force, provide calculations and additional bracing if
required for the superstructure. Develop a complete Travel Path Working Plan/Drawing
from temporary supports to final bridge location within the physical Project and SPMT
equipment constraints.
Provide SPMT Lifting System Working Drawings, including plans and supporting
calculations with the Bridge Move Document. Include cut sheets for the SPMT units which
demonstrate their capabilities. Provide a lifting system that possesses steering capacity
allowing for movement forward, backward, transversely, at any angle, and in a carousel
motion about any point. Provide a system that will provide uniform support to all girders.
Provide plans and calculations with the Bridge Move Document for any additional systems
required or used to move the structure including blocking, shoring, and carrier beams. Make
a list of preparatory work necessary for moving personnel, SPMT equipment, supplies, and
additional equipment used to move bridges and incidentals to the site before beginning work
and include it in the Bridge Move Document.
Verify that the SPMT units have adequate stroke to lift the bridge off the temporary supports
and traverse the travel path within the twist limits specified on the plans. Calculations for
lifting stresses and deflections, if required, shall be included in the Bridge Move Document.
See Section A.4.2 and A.4.3 of this special provision for submittal requirements.
Shims may be used, if required, to correct discrepancies in the seat elevations at the
substructures.
Non-shrink grout may be used, if required, to correct discrepancies in the seat elevations at
the substructures.
Compare the actual stroke required to lift the bridge to the value shown on the plans, which
will indicate deflection.
After removing or minimizing the twist, measure and record the reference elevations again
and calculate the change in deflection profile of the bridge. Verify that the deflection change
agrees with the predicted values shown on the plans, within the specified tolerance. If the
deflection change exceeds the specified tolerance on the plans, consult with the Engineer.
Retain a permanent record of the elevations taken before and just after the lift for reference.
After the span is set in the final position, measure the elevations of the reference points and
check that they agree with the relative elevations just prior to lifting the bridge in the staging
area, within a tolerance of 0.25”. If the elevations exceed the specified tolerance, consult with
the Engineer.
Halt operations immediately if deflection or twist exceeds the allowable limits shown on the
plans. Return the superstructure to temporary supports if necessary, and consult with the
Engineer.
Provide a Superstructure Monitoring Plan and Working Drawings. See Section A.4.2 of this
special provision for submittal schedule.
Provide all monitoring records to the Engineer according to Section A.4.3 of this special
provision.
Prepare Bridge Move Schedule that conforms to the plans and specifications.
Identify key contacts for decisions during the bridge move. Establish authority and a
communication tree for immediate issue resolution during the move.
Describe special traffic control required during bridge move that conforms to the plans and
specifications.
Describe all utility conflicts with the bridge move and how the conflicts shall be resolved.
See section C.5 for SPMT Lifting Drawings and Design Calculations.
Submit the Preliminary and Final Bridge Move Document per Section A.4.3 of this special
provision. Update these plans and confirm they are complete prior to the final walk through
pre-move safety meeting.
Immediately prior to moving the bridge, conduct a final walk through pre-move meeting with
all Contractor, Heavy Lifter, and WisDOT project level leaders at the bridge site for the
bridge move. Verify that all items identified in the Bridge Move Document have been
completed. Walk the travel path to verify surfaces have been prepared adequately, all utility
protection is in place, slopes have been adequately supported, and verify all work has been
completed for the move.
Do not move the superstructure until all concrete in the superstructure is verified to have
reached the specified ultimate strength, as shown on the plans.
Engage the SPMT lifting system and slowly lift the bridge superstructures from their
temporary supports. Ensure that all bearing locations are lifted off their supports
simultaneously. Check the loading of the SPMT hydraulic system against anticipated loading
as defined on the working drawings. Consult with the Engineer prior to moving the bridge.
During the bridge move, continuously monitor the bridge superstructures according to the
Superstructure Monitoring Plan in section C.7. If limits are exceeded during the move, stop
the move to make necessary adjustments to the SPMT system.
The loaded SPMT units shall travel at no faster than a walking pace of approximately 3 miles
per hour when transporting the bridge superstructure.
Refer to the contingency plan for required response and resolution for issues that arise during
the move. Deliver superstructures to their final location according to the limits described in
Section C.11 “Post Move Inspection”.
Conduct a check of the profile and confirm that bridges are within a tolerance of 0.50” at
their final location. A unit price reduction will apply if the bridge is not within tolerance, per
Section E.2 of this special provision.
Repair all cracks visible during dry weather conditions. Fill all cracks less than 0.040 inches
in width with low viscosity crack sealer per standard spec 502.3.13. Fill all cracks within 14
days of final superstructure placement on the substructures.
Fill cracks greater than or equal to 0.040 inches in width according to the specifications for
Epoxy Injection Crack Repair, contained with the Special Provisions. Repair work shall only
be allowed for cracks that do not compromise the integrity of the design or the fitness of use
as determined by the Engineer. All proposed repair work shall be approved by the Engineer.
A unit price reduction will apply for cracks greater than 0.040”, per Section E.2 of this
special provision.
The Department will provide the survey results and the detailed remedial work and/or shim
thicknesses and locations needed.
The Department will perform a Post Move Inspection within two (2) days of bridge move
and after temporary supports attached to superstructure have been completely removed.
See Section E.2 for unit price reductions which will be applied when the bridge
superstructure is placed out of the allowable tolerances, as stated in this special provision.
D Measurement
The department will measure SPMT Bridge Construction B-XX-XXX as a single complete
unit of work at the locations shown on the plans.
E Payment
E.1 General
The department will pay for the measured quantity at the contract unit price under the
following bid item:
ITEM NUMBER DESCRIPTION UNIT
SPV.0105.xx SPMT Bridge Construction B-XX-XXX LS
Payment for SPMT Bridge Construction B-XX-XXX is full compensation for providing all
Working Drawings, Documents, Meetings, and other submittals or requirements described in
the special provision; for identifying the location of the Bridge Staging Area as shown on the
plans; designing and preparing the Bridge Staging Area for temporary works; for producing
the Geotechnical Report and any additional soil borings other than those shown on the plans
as required by the Contractor; designing, delivering, furnishing, and constructing temporary
supports for bridge superstructure construction; correction plans and remedial action for
temporary support elevations and settlements outside of tolerances; identifying, designing,
and preparing the bridge Travel Path; resolving all potential Travel Path impacts including
clearances, utilities, barrier removal, etc.; restoring Travel Path to pre-construction condition;
determining SPMT capabilities and developing a Bridge Move Document within these
capabilities; evaluating anticipated stresses and deformations to the bridge superstructure due
to transport if the SPMT support locations do not meet the requirements as described in this
special provision; monitoring and recording bridge superstructure deflection and twist before
and during the move; preparing a Bridge Move Document and conducting a final pre-move
walk through; moving the bridge superstructure to its final location; repairing cracks and
damage identified in the Post Move Inspection; removing concrete median barrier, Concrete
Barrier Temporary Precast Delivered and Concrete Barrier Temporary Precast Installed,
Clearing and Grubbing, Excavation, Select Crushed Material, Breaker Run, Backfill Granular
(Grade 2), Concrete Stone #1, timber mats, steel plates, shims, non-shrink grout, and epoxy
for crack injection.
All necessary materials and construction required to complete this bid item or installed for the
convenience of the contractor’s operations shall be included in the bid item “SPMT Bridge
Construction Enter Structure Number”.
The original unit price for the bid item “SPMT Bridge Construction Enter Structure Number”
shall be adjusted as follows:
The unit price pay reductions apply to each specified item, up to a maximum reduction of 20%
of the original unit bid price.