Project Change Process
Project Change Process
Approvals
Review History
Distribution
Table of Contents
Approvals ......................................................................................................................................................i
Review History..............................................................................................................................................i
Document Change Record ..........................................................................................................................i
Distribution ...................................................................................................................................................i
Table of Contents ........................................................................................................................................ii
1.0 Document Purpose.........................................................................................................................1
2.0 Related Documents ........................................................................................................................1
3.0 Purpose and Objectives ................................................................................................................1
4.0 Scope ...............................................................................................................................................1
5.0 Policy ...............................................................................................................................................1
6.0 Procedures......................................................................................................................................2
6.1 Identify Change Request .................................................................................................................. 2
6.2 Validate Change Request ................................................................................................................. 2
6.3 Analyze Impact ................................................................................................................................. 2
6.4 Control Change Request .................................................................................................................. 3
6.5 Action Change Request .................................................................................................................... 3
6.6 Close Change Request..................................................................................................................... 3
6.7 Change Management Process Diagram ........................................................................................... 4
Appendix A: Forms and Templates ...........................................................................................................5
Manual Change Request Form ....................................................................................................................... 6
Manual Change Request Log.......................................................................................................................... 7
The purpose of this document is to provide project managers with the standard process for
managing changes on ITMB projects.
Automated Project Items Control using PVCS Tracker, describes the process for recording and
tracking risks, issues, change requests and quality control items using PVCS Tracker.
The purpose of change management procedures is to manage change requests so that approved
changes will be controlled, ensuring the project remains on schedule, within budget and provides
agreed deliverables.
4.0 Scope
The Change Management Process is the mechanism used to initiate, record, assess, approve
and resolve project changes.
Project changes are needed when it is deemed necessary to change the scope, time or cost of
one or more previously approved project deliverables. Most changes will affect the budget and/or
schedule of the project.
5.0 Policy
The use of the formal change management procedure will be required when any changes are
discovered or requested which impact previously reviewed, approved and published project
deliverables.
The PSO supports the change management process. The role of the PSO in the change
management process is determined, with the project manager, once the project is approved.
The documentation and tracking of all change requests will be managed using the defined
procedure and facilitated by the use of PSO templates or PVCS Tracker.
• Decisions to analyze and decisions to proceed with changes will be made by the
ITMB Client Manager and the Project Manager if they do not impact scope,
budget or schedule.
• Changes which do impact scope, budget or schedule will be forwarded to the
Steering Committee for review.
• The Steering Committee may decide that Executive Sponsor approval and review
is required before making a decision.
6.0 Procedures
The overall flow of the change request process is presented on the following page.
Record issue
Identify issue
PM or Lead
PM or Lead
Present Analysis
Update change
to Project
request with
Manager
target date
Change Analyst
Place on Steering
Steering
Committee
approval Yes
agenda
required?
PM
Executive
approval
required?
No Yes
Forward to
Executive Sponsor
PM
Update change
Proceed with
request with
change?
control decision
No
Yes
Negotiate and
Update plans and
execute contract
work plan
changes
Confirm updates
Execute and Close Change
and file Change
monitor work plan Request
Request
PM PM
Impact Assessment (describe the scope and impact of the change, continue on next page, if necessary)
Schedule:
ID Title Status Priority Submit Date Submitter Target Date Assigned Close Date Owner Estimated Actual Cost Description Notes
To: Cost
1
2
3
4
5