Piping Check List
CLX02 - Pipework
Module :
Dwg / PID :
Task Location : User Group :
Estimated Time (MH) : Expended Time (MH) :
Sub-system :
1 Check that all of the materiel conforms to the specifications.
2 Check the pipework installation conforms to specifications, drawings and P&ID's.
3 Check that the pipework and valves are undamaged. Also check the ancillaries and any other components.
Check the installation of all pipe-supports are as per specifications and drawings. Also springs have shipping-stops fitted and
4
the piping sits on its supports.
5 Check the location of the pipe anchors.
6 Check the alignment of the pipe guides.
7 Check the check-valves operate freely before they are installed into position.
8 Check that the flow direction of the valves is in the correct sense/direction.
9 After the installation of a valve check that it operates freely.
10 Check the valves are correctly lubricated and they have the correct spindle packing.
11 Check there is a suitable access, both to operate and to maintain valves.
12 Check that the pipework does not in any way load and stress the equipment it is serving.
13 Check the pipe flanges are mounted square to each other. Also the bolting and gaskets are correct.
14 Check that all the bolts and fasteners are suitably lubricated.
15 Check the painting, the insulation and the heat tracing as per specifications.
16 Check the equipment has been bonded as per drawings and specifications.
17 Check for the correct tagging, labelling and colour coding of pipework and equipment.
18 Check that all golden welds (final tie-ins without hydrotest) have been performed as per procedure.
19 Produce a set of marked-up drawings in accordance with the installation.
20 Produce a defects list for issue in the Punch List.
NA Not Applicable X Checked & not accepted O Checked & accepted
Remarks :
Prepared By, Approved By,
defined
Signature
Name
Date
Icaps : Data entered by: Date :