5.2.2.
9 RISK ASSESSMENT
Task / Process
Revision: 000
Assessed:
LAYDOWN DRILL PIPES (DP)
Date: January 2021 Location: RIG G80
Operation: Assessment Team: TP, D, FM, RA
HAZARD INITIAL RISK CONTROL MEASURES RESIDUAL RISK
Hazard Description List all Current and Planned Control Measures, taking into Account all
and Worst Case Loss Contributing and Escalating Factors
Likelihood
Likelihood
Risk Level
Risk Level
Consequences with Category/
Severity
Severity
no Prevention or
Activity Mitigation Measures in Population Current and Planned Prevention Current and Planned Mitigation
Steps Place Affected Measures to reduce Likelihood Measures to reduce Severity
All pipe racks - No pre job safety - Personnel - Ovoid as much as touch directly tubular with
to be pinned meeting - Equipment your hands / feet - PPE
to catwalk & - Pipe rolls out of catwalk - Don’t try to stop tubular rolling with your feet - Conduct pre-job meeting
together end
Acceptable (-4)o
Undesirable (-6)
can crush leg/ foot - Cheater bar to roll pipe
Possible (3)
Serious (-2)
Serious (-2)
to end of each
Unlikely (2)
- Pinch point hazards - Stopper on catwalk prevent pipe to roll out of
pipe rack & - Roustabout trips & falls catwalk
intermediate when rolling pipe on
stopper to rack
separate pipe - Roustabout stuck
between tubular rolling
free in pipe rack.
Forklift ready - Wrong number of DP - Personnel - D to make list of pipe to be laid out make a copy - Mechanical Lifting
to remove DP laid out, mistake in tally. for the rig floor, copy for deck crew to tick out - Monitor well at all time
Air winch - No swivel or worn out as pipe is being laid out.
operator lower one cable pigtailed, 3- - Everyone is accountable to check if there is no
the pipe down part shackle not mistake when laying out pipe.
Catastrophic (-4)
Intolerable (-16)
Acceptable (-4)
to catwalk secured can cause
Serious (-2)
Unlikely (2)
Likely (4)
with single serious injury.
joint - No well monitoring, kick
Driller prepare
trip sheet &
record trip
tank level as
pipe is being
laid out
Driller pulls - Pinch point hazard - Personnel - Use only painted green handles only (on tong & - Use proper PPE
out first single - Hand injuries - Equipment slip)
joint -
Undesirable (-6)
Acceptable (-4)
Floorman set
Possible (3)
Serious (-2)
Serious (-2)
Unlikely (2)
slips, latch
tong/ iron
Roughneck
break & spin
out
connection
Driller pick up - Floorman standing - Personnel - Stay clear when elevators are at rotary level,
DP & lower in between rotary & joint think about where you could be trapped - Fatigue management training
mousehole, in mousehole
Undesirable (-6)
Acceptable (-4)
Possible (3)
Serious (-2)
Serious (-2)
crew open
Unlikely (2)
elevator &
Driller pick up
& latch on
next joint in
rotary
Floorman - Floorman pulls joint can - Personnel - Never pull joint
latch single slip and fall - Always put it with your feet clear Manual Handling
joint elevator/ -
Undesirable (-6)
Hand / foot injury
Acceptable (-4)
Possible (3)
Serious (-2)
Serious (-2)
lifting cap |&
Unlikely (2)
push joint out
to v-door to
layout joint to
catwalk
Roustabout - Roustabout pull pipe by - Personnel
roll DP out of walking backward, can - Always push pipe - Manual Handling
catwalk, one trip and fall
Acceptable (-3)
Acceptable (-2)
Possible (3)
at each end
Unlikely (2)
Light (-1)
Light (-1)
pushing onto
pipe rack
D to update - Mistake in tally - Personnel - Stop the job at crew change, do the pre job
tally, Rig Sup - Repetitive job, crew - Equipment meeting - Fatigue management training
Catastrophic (-4)
to update new change, people loose - Wait till all crew complete the job.
Intolerable (-16)
Acceptable (-4)
Serious (-2)
tally
Unlikely (2)
attention - Double check the tally sheet by Driller and TP.
Likely (4)
- Mousehole and v-door - Close mousehole and v-door gate.
not closed. - Authority to stop the job if any unsafe act/
condition is noticed.
NOTES: EQUIPMENT CHECKLIST: PPE CHECKLIST:
1) Be accountable to do the job safely. 1) Crane 1) Coveralls
2) Lifting cap / Single joint elevator 2) Gloves
3) Safety Boots
4) Hard hat
5) Safety glasses