Use Gasket Factor in Calculation
Use Gasket Factor in Calculation
Friedrich Schoeckle
AMTEC Advanced Measurements Hoher Steg 13
Lauffen 74348 Lauffen / N.
Germany Germany
ABSTRACT INTRODUCTION
A flange calculation has to fullfill three major tasks. First the GKN I is a nuclear power plant that was built in the early 1970s;
prestress value for assembly has to be determined. Then a tightness the plant is in operation since 1976. Using the steam generator
proof and a stress analysis have to be performed for every relevant handhole flanged joints of this PWR power plant as an example, the
state of operation. For reliable calculation results it is necessary that development in gasket factors in conjunction with flange calculation
all parts of the assembly (i.e. flanges, bolts and gasket) are regarded. methods are summarized and some "lessons learned" are extracted.
Using the example of a flanged joint of a steam generator of a In the first years of operation already, there were a few minor
nuclear power plant, the European development in gasket calculation troubles with leakage of handhole and manhole junctions of the
in recent years and the necessary gasket factors are summarized in steam generators. Fig. 1 gives an overview over the steam generator
this paper. Some general conclusions are drawn. and the handhole and manhole locations. Minor troubles in this case
The use of gasket factors plays an essential role in calculations for means small leakages, i.e. corrosion effects or some drops of water
flanged joints. Only if realistic gasket factors for the selected gasket near gasketed joints, especially after pressure tests. But as the leaks
of the joint (that have to be determined in tests explicitly) are used, were only small, the attempts to solve this problem did not get high
above tasks of the calculations can be met. In Europe realistic gasket priority.
factors for use in calculations are standardized in prEN 13555 and in Finally, in 1986 there was a major leakage at a handhole closure of
Germany in DIN 28090. one steam generator. The leakage caused a forced outage of the plant
Within the European standardization tasks there are two procedures for repair purposes, i.e. a time and thus money consuming procedure.
for the calculation of flanged joints, actually. One is based on the Additionally the autorized inspectors and the licencing authorities
ASME-code (incorporated in prEN 13445), the second one uses a became involved, thus it was necessary to provide a solution of the
limit load theory (prEN 1591). Whereas the ASME-procedure is only problem with adequate paperwork.
useful for formal stress analysis purposes, the EN 1591 procedure Fig. 2 shows the original version of the handhole construction,
provides the tools for stress analysis and tightness analysis (including Fig. 3 gives details about the gasket. 12 bolts (size M27) are used to
the output of a prestress value). The gasket factors that are necessary tighten this flange closure construction of nominal diameter
for this calculation are defined in prEN 13555. DN 200 mm. The gasket consists of a steel plate (outer diameter
In Germany there is another procedure incorporated in the 244 mm, thickness 7 mm) with kamm-profile; there is a 0.5 mm
standards for nuclear power plants (KTA 3201.2/KTA 3211.2); this silver topping on each side of the kamm-profile.
procedure is based on the German prestandard DIN E 2505. Stress Until that event mounting was done using torque wrenches; the
analysis and tightness analysis is possible with this procedure, if necessary torque was derived from design data; the calculations and
appropriate gasket factors (prEN 13555) are used. their results will be discussed in the next chapter. From the state of
Of course, FE-calculations are commonly used for more complex knowledge at that time, inaccurate mounting was assumed to be the
designs, too. Similar to the analytic calculation procedures, the use of reason for the leakage. Therefore the first goal was to optimize the
realistic gasket factors is essential in these calculations.
1
2000 ASME PVP Conference, Seattle
steam nozzle
mounting procedure itself and as a second goal to provide training to
the mounting staff.
An optimal mounting can be achieved using hydraulic tensioners in
combination with a control of elongation of the bolts; therefore this
method was selected. It was necessary to modify the bolt design for
this purpose, Fig. 4. The new bolts have an additional tensioning manhole
thread at the free end and – for elongation measurement purposes - a
rod in their center. With a special hydraulic tensioning device it is
possible to prestress all bolts of the junction at the same time and
with the elongation measurement the force in the bolts can be
monitored during the entire prestress process (bolt elongation vs. feedwater
nozzle
force is calibrated). Principle schemes of the methods are shown in
Fig. 5 and Fig. 6
The selected mounting procedure has some significant advantages:
(a) All bolts are prestressed at the same time (one integrated ring of
12 tensioners). This results in a reliable prestress level and a small
scatterband of the bolt forces. With the verification of the forces by
elongation measurements the results are even better.
(b) The time necessary for prestressing of a joint with the hydraulic
tensioners in combination with the elongation mesurement (special
snap-on design of the transducers) is comparable to the time
necessary with torque wrenches (special tightening sequence in
several load steps). But it is not necessary for the mounting staff to handhole
stay near the joint; especially the loading procedure can be
supervised from a distance. Thus the radiation exposure of the
mounting staff could be reduced significantly.
(c) It is no problem to provide a prestressing protocol to the
authorized inspectors.
Parallel to the modifications to the tightening process, new
calculations were performed to verify the necessary prestress value of
the bolts and to demonstrate that the junction design is (still) in Fig. 1 : steam generator of GKN I
accordance with the standards (KTA 3201.2). The calculation will be
discussed in more detail in the chapter below.
O 370
The new tightening procedure was successful. In the following O 295
years there were no more leaks at these joints – until 1998. Corrosion
effects at the outer shell of a handhole near the gasket demonstrated,
that there was a (very small) leak, again. This time, mounting could
not be blamed because the responsible staff was able to prove the
correct mounting procedure with a protocol.
Finally, it was found that the metallic gasket plates were the reason
for the leakage. The plates showed tolerances in dimensions; the
thickness of the plate at the kamm-profile varied up to +/-0.25 mm
along the circumference whereas a tolerance of +/-0.1 mm was the
25
limit. O 43
2
completely. This was verified in full scale leak rate tests that were
performed similar to the gasket testing procedure as outlined in
7
prEN 13555. The test rig is shown in Fig. 7. Gasket stress was M27 O 200
controlled using bolts equipped with strain gages, the leak rates were O 204
O 244
measured using the pressure decay method.
85
The resulting leak rates vs. gasket stress are given in Fig. 8. The
R
rate curve, see below) has a value of 65 MPa for the gasket with the
low tolerance wheras it is 10 MPa higher with the gasket with higher
tolerances. The unloading part of the leakage rate curve shows the
same behaviour, i.e. the curve of the gasket with the bad tolerances is
shifted to higher gasket stresses.
As a consequence of this event, the quality control procedures for
the parts of the flanged joints were modified. Meanwhile only
gaskets with low dimension tolerances are in the warehouse. Fig. 2 : handhole junction - old version (dimensions in mm)
2
2000 ASME PVP Conference, Seattle
tension nut
“X” “Y” O 190
O 204
O 244
F force form
F hydraulic
,5
R1 tensioner
7
nut
0,5
0,5
4
4°
5
O 244
closure
Detail “Y”
1 gasket
R
1
4°
5 O 190
O 204
flange
Fig. 3 : gasket for the handhole junction (dimensions in mm)
O 370
O 295
Fig. 5 : hydraulic prestressing (schematic plot)
25
O 43
2
O 30
47
7
M27 O 200
O 204
O 244
85
R
42
unloaded loaded
F = 0 F = 0
∆ l F
∆l = 0 ∆l = 0
3
2000 ASME PVP Conference, Seattle
difference pressure
transducer
temperature pressure
transducer transducer
reference volume
closure
Fig. 7 : test rig for leak rate measurements (pressure decay method)
gasket plate with kamm-profile (di: 204mm do: 244 mm)- silver topping thickness 0.5mm
full line: tolerance in plate thickness 0.12 mm / dotted line: tolerance in plate thickness 0.24 mm
100
10
p = 80 bar
leak rate in mg/m/s
0.1
0.01
0.001
0.0001
0 20 40 60 80 100
4
2000 ASME PVP Conference, Seattle
5
2000 ASME PVP Conference, Seattle
6
2000 ASME PVP Conference, Seattle