Time Working Sheet MT. Gas Barito

This document is a certificate of work detailing work done on the assembly job of a CPP and EVK2R-330 for a ship. It provides dates and times engineers T/S worked from September 22nd to October 21st, including dismantling components, machining parts, installing new bearings and seals, testing, and adjusting the CPP and seals before traveling back.

Uploaded by

Rudialvandy Rudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views3 pages

Time Working Sheet MT. Gas Barito

This document is a certificate of work detailing work done on the assembly job of a CPP and EVK2R-330 for a ship. It provides dates and times engineers T/S worked from September 22nd to October 21st, including dismantling components, machining parts, installing new bearings and seals, testing, and adjusting the CPP and seals before traveling back.

Uploaded by

Rudialvandy Rudi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

CERTIFICATE OF WORKING

Ship’s
PT. DINAMIKA MT.GAS
ENERGI MENTAYA
MARITIM Kind of Work
Name ASSEMBLING JOB
Order by PT. USAHA GAS ELPINDO Size of Seal CPP AND EVK2R-330
Order No 4500002269-R1 Place PT. STEADFAST MARINE
Working
Engineers TATSUMI/SUTRISNO
Fee

Working Time

Date Day Time Hrs Engineer Kind Of Work


22 Sept 2020 Tue 14:00-18:00 4 T/S Traveled from Jakarta to Pontianak

23 Sept 2020 Wed 08:30-17:00 7.5 T/S Meeting with superintendent Mr. Rudi for work procedure
Removed plate
Removed bolts coupling
Pushed tail shaft to propeller side
Dismantled bolts of stopper Piston
Removed Indicator
Dismantled Piston Rod

24 Sept 2020 Thu 08:30-17:00 7.5 T/S Removed Nut coupling


Pump out coupling
Removed Tail shaft
Transfer Tail shaft to work shop
Cleaned cement on bolt of 2 half of after cover
Removed bolts

25 Sept 2020 Fri 08:30- 17:00 7.5 T/S Dismantled 2 half of after cover
Dismantled Propeller blade
Removed push rod
Measurement Tail shaft found heavy wear on shaft sleeve
Measurement Shaft bearing found heavy wear and some
rubber was worn out
Discussed to renew shaft bearing and Machine Tail shaft sleeve

26 Sept 2020 Sat 08:30- 12:00 3.5 T/S Dismantled Joint of tail shaft and after Cover
Preparing for class inspection
Explained How to remove rubber bearing and machine of shaft
continue
27 Sept 2020 Sun 15:00-19:00 4 T/S Flight back to Jakarta

04 Oct 2020 Sun 14:00-18:00 4 T/S Flight from Jakarta to Pontianak

05 Oct 2020 Mon 08:30-17:00 7.5 T/S Removed and Assembled OD Box
Renewed O ring for OD Box
Cleaned Intermediate shaft
Attended supervisor for machining shaft sleeve

06 Oct 2020 Tue 08:30-17:00 7.5 T/S Installed Hose of OD Box


Installed Intermediate shaft
Continue Attended supervisor for machining shaft sleeve

07 Oct 2020 Wed 08:30-17:00 7.5 T/S Finishing of machining shaft sleeve at work shop

08 Oct 2020 Thu 08:30-17:00 7.5 T/S Transfer Tail shaft to work shop
Installed 2 haft to Tail shaft and tighten the bolts
Installed push rod

09 Oct 2020 Fri 08:30-17:00 7.5 S Assembled CPP blade


Assembled 2 haft aft Cover

10 Oct 2020 Sat 08:30-16:00 6.5 S Air tested


Filled grease

12 Oct 2020 Mon 08:30-17:00 7.5 S Attended supervisor machining for Shaft bearing ( Thordon )
Fwd bearing as requested by owner

13 Oct 2020 Tue 08:30-17:00 7.5 S Continue Attended supervisor machining Thordon FWD
Measurement Fwd bearing
Installed Fwd bearing to the Vessel
Attended supervisor machining Aft bearing ( inner side)

14 Oct 2020 Wed 08:30-17:00 7.5 S Measurement Aft bearing Inner side
Installed Aft bearing inner side
Continue supervisor machining Aft bearing out side

15 Oct 2020 Thu 08:30-17:00 7.5 S Continue supervisor machining Aft bearing out side
Measurement Aft bearing out side
Installed Aft bearing out side
continue

16 Oct 2020 Fri 08:30-17:00 7.5 S Continue supervisor machining Teflon

17 Oct 2020 Sat 08:30-12:00 3.5 S Continue supervisor machining Teflon

19 Oct 2020 Mon 08:30 -17:30 8 S Installed Stern tube to bull head
Installed coupling and pump in
Tighten Coupling Nut
Tighten Stopper ring

20 Oct 2020 Tue 08:30-18;00 8.5 S Installed Piston


Installed Piston’s cylinder
Connected Piston rod
Installed Indicator
Joint coupling to Intermediate shaft
Set stern tube EVK seal
Tested CPP moving blade
Adjusted Indicator ring

21 Oct 2020 Wed 16:00-20:00 4 S Traveled back to Jakarta

Signature of order Date; 19-9-2020