CERTIFICATE OF WORKING
Ship’s
PT. DINAMIKA MT.GAS
ENERGI MENTAYA
MARITIM Kind of Work
Name ASSEMBLING JOB
Order by PT. USAHA GAS ELPINDO Size of Seal CPP AND EVK2R-330
Order No 4500002269-R1 Place PT. STEADFAST MARINE
Working
Engineers TATSUMI/SUTRISNO
Fee
Working Time
Date Day Time Hrs Engineer Kind Of Work
22 Sept 2020 Tue 14:00-18:00 4 T/S Traveled from Jakarta to Pontianak
23 Sept 2020 Wed 08:30-17:00 7.5 T/S Meeting with superintendent Mr. Rudi for work procedure
Removed plate
Removed bolts coupling
Pushed tail shaft to propeller side
Dismantled bolts of stopper Piston
Removed Indicator
Dismantled Piston Rod
24 Sept 2020 Thu 08:30-17:00 7.5 T/S Removed Nut coupling
Pump out coupling
Removed Tail shaft
Transfer Tail shaft to work shop
Cleaned cement on bolt of 2 half of after cover
Removed bolts
25 Sept 2020 Fri 08:30- 17:00 7.5 T/S Dismantled 2 half of after cover
Dismantled Propeller blade
Removed push rod
Measurement Tail shaft found heavy wear on shaft sleeve
Measurement Shaft bearing found heavy wear and some
rubber was worn out
Discussed to renew shaft bearing and Machine Tail shaft sleeve
26 Sept 2020 Sat 08:30- 12:00 3.5 T/S Dismantled Joint of tail shaft and after Cover
Preparing for class inspection
Explained How to remove rubber bearing and machine of shaft
continue
27 Sept 2020 Sun 15:00-19:00 4 T/S Flight back to Jakarta
04 Oct 2020 Sun 14:00-18:00 4 T/S Flight from Jakarta to Pontianak
05 Oct 2020 Mon 08:30-17:00 7.5 T/S Removed and Assembled OD Box
Renewed O ring for OD Box
Cleaned Intermediate shaft
Attended supervisor for machining shaft sleeve
06 Oct 2020 Tue 08:30-17:00 7.5 T/S Installed Hose of OD Box
Installed Intermediate shaft
Continue Attended supervisor for machining shaft sleeve
07 Oct 2020 Wed 08:30-17:00 7.5 T/S Finishing of machining shaft sleeve at work shop
08 Oct 2020 Thu 08:30-17:00 7.5 T/S Transfer Tail shaft to work shop
Installed 2 haft to Tail shaft and tighten the bolts
Installed push rod
09 Oct 2020 Fri 08:30-17:00 7.5 S Assembled CPP blade
Assembled 2 haft aft Cover
10 Oct 2020 Sat 08:30-16:00 6.5 S Air tested
Filled grease
12 Oct 2020 Mon 08:30-17:00 7.5 S Attended supervisor machining for Shaft bearing ( Thordon )
Fwd bearing as requested by owner
13 Oct 2020 Tue 08:30-17:00 7.5 S Continue Attended supervisor machining Thordon FWD
Measurement Fwd bearing
Installed Fwd bearing to the Vessel
Attended supervisor machining Aft bearing ( inner side)
14 Oct 2020 Wed 08:30-17:00 7.5 S Measurement Aft bearing Inner side
Installed Aft bearing inner side
Continue supervisor machining Aft bearing out side
15 Oct 2020 Thu 08:30-17:00 7.5 S Continue supervisor machining Aft bearing out side
Measurement Aft bearing out side
Installed Aft bearing out side
continue
16 Oct 2020 Fri 08:30-17:00 7.5 S Continue supervisor machining Teflon
17 Oct 2020 Sat 08:30-12:00 3.5 S Continue supervisor machining Teflon
19 Oct 2020 Mon 08:30 -17:30 8 S Installed Stern tube to bull head
Installed coupling and pump in
Tighten Coupling Nut
Tighten Stopper ring
20 Oct 2020 Tue 08:30-18;00 8.5 S Installed Piston
Installed Piston’s cylinder
Connected Piston rod
Installed Indicator
Joint coupling to Intermediate shaft
Set stern tube EVK seal
Tested CPP moving blade
Adjusted Indicator ring
21 Oct 2020 Wed 16:00-20:00 4 S Traveled back to Jakarta
Signature of order Date; 19-9-2020
__________________________ _________________________