Presentation’s Content
Introduction to AMI System
Analysis of billing in PESCO through AMI
Targets and Plans of BOD PESCO
AMR Meter Replacement Mechanism
Introduction to COSMOS
Mute Meter reading updating on COSMOS
Contact details of PESCO AMI Cell
Peshawar Electric Supply
Company
What is AMI?
Advanced Metering Infrastructure (AMI) is an integrated system of smart
meters, communication networks and data management systems that
enables two way communication and control of load management
between the utilities and the end consumers.
Automated/Advance Metering
IP Cloud
Infrastructure
SDO Operation
M&T Lab
PESCO PITC NOC
Revenue Office @ @
SE/DCM PESHAWAR WAPDA House
XEN
Commercial Directorate
- Company H/Q
VPN
Billing Interface Industrial
Industrial
Commercial
Commercial
TELCO NOC
Residential
Residential
Tube well Tube well
SYSTEM ARCHITECTURE
Analysis of Billing via AMR Meters in
April, 2021
➢ Total consumers billed via AMR meters= 12006
➢ PESCO Total Active Consumers= 3123929
➢ Percentage of Total Consumers= 0.33%
Analysis of Billing via AMR Meters in
April, 2021
.
➢ Total Assessment/billing via
AMR meters= Rs. 5914 M
(four billion, seven hundred six million, eighty-six thousand, three
hundred fifteen only)
➢ PESCO Total
Assessment/billing in all
batches= Rs. 13484 M
(eleven billion three hundred eighteen million one hundred seven
thousand seven hundred thirty-three)
➢ Percentage of Total
Assessment= 43.85 %
Analysis of Billing via AMR Meters in
April, 2021
➢ Total Units assessed via
AMR meters= 250 (M) KWH
(one hundred ninety-nine million four hundred fifty-three
thousand one hundred nineteen)
➢ PESCO Total Units in all
batches= 717 (M) KWH
(six hundred seventy-nine million one hundred thousand six
hundred twenty-six)
➢ Percentage of Total Units
billed via AMR Meters=
34.86 %
Analysis of Billing via AMR Meters
in April, 2021
BOD PESCO Targets for Non AMR meters to be converted to AMR meters up to Dec 2021
26214 3-
Load above Load 10KW Mute Meters New
phase Total
25 KW to 25 KW of C3 Project Connecetions
WC
Circle code Circle CT Opr WC CT Opr WC CT Opr WC WC WC CT Opr WC
261 Peshawar 196 107 49 2993 237 449 1425 482 4974
262 Khyber 221 173 22 3538 221 552 1476 13000 464 18739
263 Mardan 347 31 19 1486 46 70 325 412 1912
264 Hazara-I 283 383 10 1343 110 283 230 403 2239
265 Swat 685 205 125 2311 108 296 415 918 3227
266 Bannu 239 282 81 3884 112 999 950 432 6115
267 Hazara-II 83 91 4 681 28 60 1525 115 2357
268 Swabi 239 37 11 1227 47 75 680 297 2019
PESCO 2293 1309 321 17463 909 2784 7026 13000 3523 41582
Circle Wise AMR 3-Phase Whole Current Meters Received to M&T for Configuration of Sim Dated:28-07-2021
Received Data
Meters Data not
by Received
Meters to be Meters Received Sims Inserted & Received for
Circle Progressive concern for
Replaced Allocated in M&T Configured addition on
field addition
Today MDM
office on MDM
Peshawar 5642 700 6 491 491 491 233 258
Khyber 5426 650 0 634 634 634 252 382
Mardan 2193 200 0 196 196 196 138 58
Hazara-I 1879 350 0 344 344 344 237 107
Swat 3205 350 0 294 294 294 107 187
Bannu 5330 540 0 539 539 539 229 310
Hazara-II 1024 210 0 210 210 210 210 0
Swabi 1761 200 0 188 188 188 147 41
Total 26460 3200 6 2896 2896 2896 1553 1343
Circle Wise AMR CT Operated Meters Received to M&T for Configuration of Sim
Dated:28-07-2021
Data
Meters Installed Receive Data not
Sims Received by
Meters to Received Progressi / d for Received for
Circle Inserted & concern field
be Replaced in M&T ve Replace additio addition on
Configured office
Today d on site n on MDM
MDM
Peshawar 400 10 196 196 196 14 11 3
Khyber 450 53 149 114 64 12 12 0
Mardan 250 0 114 110 21 10 6 4
Hazara-I 450 2 23 23 23 23 0 23
Swat 350 0 241 241 241 52 34 18
Bannu 450 17 222 222 222 28 0 28
Hazara-II 190 0 13 13 13 13 0 13
Swabi 260 0 142 132 132 11 11 0
Total 2800 82 1100 1051 912 163 74 89
Procurement of AMR meters in PESCO
Already Procured 6000
LOI Issued 30000
WC Accurate 25000
CT Operated KBK 2500
CT Operated Creative 2500
Draw AMR meter from
AMR Meters Store through SR
Installation
Mechanism Insert the SIM from M&T
Replace/ Install the
meter at site as per SOP
Intimate the data to AMI Process the MCO/ SCO
Cell through Circle for billing as per SOP
Data is updated on MCO/SCO is processed
COSMOS on IBS for billing
Online billing is
Conducted
Vendor Prefix
Whole Current CT Operated
Accurate 2998 2999
Creative 3298 3299
KBK 3798 3799
MicroTech 3698 3699
URL
[Link]
Credentials
Type Code User Password
PESCO: 26
Circle: 26100,26200………26X00 se.26X,ddt.26X, dcm.26X 22334455
Division: 2611,2612………..26XX xen.26XX,ro.26XX 22334455
Subdivision: 26165………..26XXX sdo.26XXX 22334455
Menu Bar
LAYOUT OF USER INTERFACE Search Bar
“DISCO/
Utility
Hierarchy” Reporting
Customer & Meter Info Load Profile & Billing Data
CUSTOMER PANE – FILTERS
Icons
Communication reports
Billing reports
Individual actions
Daily read
Instant read
Load profile
Monthly Billing
Communication History
Events/Alarms
Mute Meter Reading Updating on COSMOS
Mute Meter Reading Updating on COSMOS
Mute Meter Reading Updating on COSMOS
Mute Meter Reading Updating on COSMOS
Mute Meter Reading Updating on COSMOS
Contact Details of PESCO AMI Cell
Room # 343, PESCO HQ Peshawar
Gmail address:- pescoami@[Link] Phone :- 091-9223002
Mr. Inam Akber (Focal Person BOD PESCO)
Deputy Manager Commercial AMI Cell
Cell # 03309971641
email:- [Link]@[Link]
Mr. Muhammad Jibreel
Deputy Manager (Metering & Testing) AMI Cell
Cell # 03444426444
email:- [Link]@[Link]
Mr. Naveed Akber
Assistant Manager AMI Cell
Cell # 03339411640
email:- [Link]@[Link]
Thanks