Specs
Specs
SPECIFICATIONS
Part 1 of 3 (Divisions 01 to 13)
END OF SECTION
END OF SECTION
END OF SECTION
PART 1 GENERAL
1.01 SUMMARY
A. Section Includes:
1. Decorative metal wall panels at interior openings.
2. Steel framing and supports for countertops.
3. Steel framing and supports for mechanical and electrical equipment.
4. Metal ladders.
5. Ladder safety cages.
6. Metal downspout boots.
7. Loose bearing and levelling plates for applications where they are not specified in
other Sections.
B. Products furnished, but not installed, under this Section:
1. Loose steel lintels.
2. Anchor bolts, steel pipe sleeves, slotted-channel inserts, and wedge-type inserts
indicated to be cast into concrete or built into unit masonry.
3. Steel weld plates and angles for casting into concrete for applications where they are
not specified in other Sections.
C. Related Sections:
1. Division 03 Section "Cast-in-Place Concrete" for installing anchor bolts, steel pipe
sleeves, slotted-channel inserts, wedge-type inserts, and other items cast into
concrete.
2. Division 04 Section "Unit Masonry" for installing loose lintels, anchor bolts, and other
items built into unit masonry.
3. Division 05 Section "Structural Steel Framing."
4. Division 05 Section "Pipe and Tube Railings."
5. Division 05 Section "Decorative Metal Railings."
1.02 PERFORMANCE REQUIREMENTS
A. Delegated Design: Design ladders, including comprehensive engineering analysis by a
qualified professional engineer, using performance requirements and design criteria
indicated.
B. Structural Performance of Alternating Tread Devices: Alternating tread devices shall
withstand the effects of loads and stresses within limits and under conditions specified in
ICC's International Building Code.
1.03 SUBMITTALS
A. Product Data: For the following:
1. Nonslip aggregates and nonslip-aggregate surface finishes.
2. Prefabricated building columns.
3. Metal nosings and treads.
4. Paint products.
5. Grout.
B. Samples for Verification: For each type and finish of extruded nosing and tread.
C. Delegated-Design Submittal: For installed products indicated to comply with performance
requirements and design criteria, including analysis data signed and sealed by the qualified
professional engineer responsible for their preparation.
D. Qualification Data: For qualified professional engineer.
E. Mill Certificates: Signed by manufacturers of stainless-steel certifying that products
furnished comply with requirements.
F. Welding certificates.
G. Paint Compatibility Certificates: From manufacturers of topcoats applied over shop primers
certifying that shop primers are compatible with topcoats.
1.04 QUALITY ASSURANCE
A. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M,
"Structural Welding Code - Steel."
1009DF / MISHRIFAH VILLA 05 5000 - 1 METAL FABRICATIONS
1.05 PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of walls and other construction contiguous with
metal fabrications by field measurements before fabrication.
1.06 COORDINATION
A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with
paint and coating manufacturers' written recommendations to ensure that shop primers and
topcoats are compatible with one another.
B. Coordinate installation of anchorages and steel weld plates and angles for casting into
concrete. Furnish setting drawings, templates, and directions for installing anchorages,
including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to
be embedded in concrete or masonry. Deliver such items to Project site in time for
installation.
PART 2 PRODUCTS
2.01 METALS, GENERAL
A. Metal Surfaces, General: Provide materials with smooth, flat surfaces unless otherwise
indicated. For metal fabrications exposed to view in the completed Work, provide materials
without seam marks, roller marks, rolled trade names, or blemishes.
2.02 FERROUS METALS
A. Steel Plates, Shapes, and Bars: ASTM A 36/A 36M.
B. Stainless-Steel Sheet, Strip, and Plate: ASTM A 240/A 240M or ASTM A 666, Type 316L.
C. Stainless-Steel Bars and Shapes: ASTM A 276, Type 316L.
D. Rolled-Steel Floor Plate: ASTM A 786/A 786M, rolled from plate complying with ASTM A
36/A 36M or ASTM A 283/A 283M, Grade C or D.
E. Rolled-Stainless-Steel Floor Plate: ASTM A 793.
F. Abrasive-Surface Floor Plate: Steel plate with abrasive granules rolled into surface or with
abrasive material metallically bonded to steel.
G. Steel Tubing: ASTM A 500, cold-formed steel tubing.
H. Steel Pipe: ASTM A 53/A 53M, standard weight (Schedule 40) unless otherwise indicated.
I. Cast Iron: Either grey iron, ASTM A 48/A 48M, or malleable iron, ASTM A 47/A 47M,
unless otherwise indicated.
2.03 NONFERROUS METALS
A. Aluminium Plate and Sheet: ASTM B 209M, Alloy 6061-T6.
B. Aluminium Extrusions: ASTM B 221M, Alloy 6063-T6.
C. Aluminium-Alloy Rolled Tread Plate: ASTM B 632/B 632M, Alloy 6061-T6.
D. Aluminium Castings: ASTM B 26/B 26M, Alloy 443.0-F.
2.04 FASTENERS
A. General: Unless otherwise indicated, provide Type 316 stainless-steel fasteners for exterior
use and zinc-plated fasteners with coating complying with ASTM B 633 or ASTM F 1941M,
Class Fe/Zn 5, at exterior walls. Select fasteners for type, grade, and class required.
1. Provide stainless-steel fasteners for fastening aluminium.
2. Provide stainless-steel fasteners for fastening stainless steel.
B. Steel Bolts and Nuts: Regular hexagon-head bolts, ASTM F 568M, Property Class 4.6);
with hex nuts, ASTM A 563M; and, where indicated, flat washers.
C. Stainless-Steel Bolts and Nuts: Regular hexagon-head annealed stainless-steel bolts,
ASTM F 738M; with hex nuts, ASTM F 836M; and, where indicated, flat washers; Alloy
Group 2 (A4).
D. Anchor Bolts: ASTM F 1554, Grade 36, of dimensions indicated; with nuts, ASTM A 563;
and, where indicated, flat washers.
1. Hot-dip galvanize or provide mechanically deposited, zinc coating where item being
fastened is indicated to be galvanized.
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Requirements:
1.2 DEFINITIONS
A. Railings: Guards, handrails, and similar devices used for protection of occupants at open-sided
floor areas and for pedestrian guidance and support, visual separation, or wall protection.
A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint
and coating manufacturers' written instructions to ensure that shop primers and topcoats are
compatible.
B. Coordinate installation of anchorages for railings. Furnish setting drawings, templates, and
directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items
with integral anchors, that are to be embedded in concrete or masonry. Deliver items to Project
site in time for installation.
1.4 SUBMITTALS
C. Samples for Initial Selection: For products involving selection of color, texture, or
design, including mechanical finishes.
1. Sections of each distinctly different linear railing member, including handrails, top rails,
posts, and balusters.
A. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate
aesthetic effects, and to set quality standards for fabrication and installation.
1. Build mockups for each form and finish of railing consisting of two posts, top rail, infill
area, and anchorage system components that are full height and are not less than 600
mm in length.
2. Subject to compliance with requirements, approved mockups may become part of the
completed Work if undisturbed at time of Substantial Completion.
1. Build laboratory mockups at testing agency facility; use personnel, materials, and
methods of construction that will be used at Project site.
2. Test railings according to ASTM E 894 and ASTM E 935.
3. Notify Architect seven days in advance of the dates and times when laboratory mockups
will be tested.
A. Field Measurements: Verify actual locations of walls and other construction contiguous with
railings by field measurements before fabrication and indicate measurements on Shop
Drawings.
PART 2 - PRODUCTS
A. Source Limitations: Obtain each type of railing from single source from single manufacturer.
1. Do not modify intended aesthetic effects, as judged solely by Architect, except with
Architect's approval. If modifications are proposed, submit comprehensive explanatory
data to Architect for review.
C. Product Options: Drawings indicate size, profiles, and dimensional requirements of railings and
are based on the specific system indicated. See Section 016000 "Product Requirements."
1. Do not modify intended aesthetic effects, as judged solely by Architect, except with
Architect's approval. If modifications are proposed, submit comprehensive explanatory
data to Architect for review.
1. Aluminum: The lesser of minimum yield strength divided by 1.65 or minimum ultimate
tensile strength divided by 1.95.
2. Copper Alloys: 60 percent of minimum yield strength.
3. Stainless Steel: 60 percent of minimum yield strength.
4. Steel: 72 percent of minimum yield strength.
5. Glass: 25 percent of mean modulus of rupture (50 percent probability of breakage), as
listed in "Mechanical Properties" in AAMA's Aluminum Curtain Wall Series No. 12,
"Structural Properties of Glass."
2. Infill of Guards:
3. Glass-Supported Railings: Support each section of top rail by a minimum of three glass
panels or by other means so top rail will remain in place if any one panel fails.
D. Thermal Movements: Allow for thermal movements from ambient and surface temperature
changes acting on exterior railings by preventing buckling, opening of joints, overstressing of
components, failure of connections, and other detrimental effects.
A. Metal Surfaces, General: Provide materials with smooth surfaces, without seam marks, roller
marks, rolled trade names, stains, discolorations, or blemishes.
B. Brackets, Flanges, and Anchors: Same metal and finish as supported rails unless otherwise
indicated.
2.4 ALUMINUM
A. Aluminum, General: Provide alloy and temper recommended by aluminum producer and finisher
for type of use and finish indicated, and with strength and durability properties for each
aluminum form required not less than that of alloy and temper designated below.
B. Extruded Bars and Shapes, Including Extruded Tubing: ASTM B 221M, Alloy 6063-T5/T52.
C. Extruded Structural Pipe and Round Tubing: ASTM B 429/B 429M, Alloy 6063-T6.
A. Copper and Copper Alloys, General: Provide alloys indicated and with temper to suit application
and forming methods, but with strength and stiffness not less than Temper H01 (quarter hard)
for plate, sheet, strip, and bars and Temper H55 (light drawn) for tube and pipe.
B. Extruded Shapes, Bronze: ASTM B 455, Alloy UNS C38500 (architectural bronze).
D. Extruded Shapes, Nickel Silver: ASTM B 249/B 249M, Alloy UNS C79600.
E. Seamless Pipe, Bronze: ASTM B 43, Alloy UNS C23000 (red brass, 85 percent copper).
F. Seamless Tube, Bronze: ASTM B 135M, Alloy UNS C23000 (red brass, 85 percent copper).
G. Seamless Tube, Brass: ASTM B 135M, Alloy UNS C26000 (cartridge brass, 70 percent
copper).
H. Seamless Tube, Copper: ASTM B 75/B 75M, Alloy UNS C12200 (phosphorous deoxidized, high
residual phosphorous copper).
I. Castings, Bronze: Composition bronze castings complying with ASTM B 62, Alloy UNS C83600
(85-5-5-5 or No. 1 composition commercial red brass) or sand castings complying with
ASTM B 584, Alloy UNS C86500 (No. 1 manganese bronze)].
J. Castings, Brass: Sand castings complying with ASTM B 584, Alloy UNS C85200 (high-copper
yellow brass).
L. Castings, Nickel Silver: ASTM B 584, Alloy UNS C97300 (12 percent leaded nickel silver).
M. Plate, Sheet, Strip, and Bars; Bronze: ASTM B 36/B 36M, Alloy UNS C28000 (muntz metal, 60
percent copper).
N. Plate, Sheet, Strip, and Bars; Brass: ASTM B 36/B 36M, Alloy UNS C26000 (cartridge brass, 70
percent copper).
O. Plate, Sheet, Strip, and Bars; Copper: ASTM B 152/B 152M, Alloy UNS C11000 (electrolytic
tough pitch copper) or Alloy UNS C12200 (phosphorous deoxidized, high-residual phosphorous
copper).
D. Sheet, Strip, Plate, and Flat Bar: ASTM A 666 or ASTM A 240/A 240M, Type 316.
B. Bars: Hot-rolled, carbon steel complying with ASTM A 29/A 29M, Grade 1010.
A. Safety Glazing: Glazing shall comply with 16 CFR 1201, Category II.
B. Tempered Glass: ASTM C 1048, Kind FT (fully tempered), Condition A (uncoated), Type 1
(transparent flat glass), Quality-Q3. Provide products that have been tested for surface and
edge compression according to ASTM C 1048 and for impact strength according to
16 CFR 1201 for Category II materials.
C. Laminated Glass: ASTM C 1172, Condition A (uncoated), Type I (transparent flat glass),
Quality-Q3 with two plies of glass and polyvinyl butyral interlayer not less than 1.52 mm thick.
D. Ceramic-Coated Glass: Heat-treated float glass, Condition C; with ceramic enamel applied by
silk-screened process; complying with Specification No. 95-1-31 in GANA's "Engineering
Standards Manual" and with other requirements specified.
E. Safety Glazing Labeling: Permanently mark glass with certification label of the SGCC or another
certification agency acceptable to authorities having jurisdiction or manufacturer. Label shall
indicate manufacturer's name, type of glass, thickness, and safety glazing standard with which
glass complies.
F. Plastic Structural Glazing: Uncoated, transparent, monolithic acrylic sheet complying with
ASTM D 4802, Category A-1 or A-2 (cell cast or continuous cast), Finish 1 (smooth or polished),
and as follows:
G. Glazing Cement and Accessories for Structural Glazing: Glazing cement, setting blocks, shims,
and related accessories as recommended or supplied by railing manufacturer for installing
structural glazing in metal subrails.
1. Glazing Cement: Nonshrinking organic cement designed for curing by passing an electric
current through metal subrail holding glass panel, as standard with manufacturer.
2.9 FASTENERS
B. Fasteners for Anchoring to Other Construction: Select fasteners of type, grade, and class
required to produce connections suitable for anchoring railings to other types of construction
indicated and capable of withstanding design loads.
C. Provide concealed fasteners for interconnecting railing components and for attaching railings to
other work unless exposed fasteners are the standard fastening method for railings indicated.
D. Post-Installed Anchors: Fastener systems with working capacity greater than or equal to the
design load, according to an evaluation report acceptable to authorities having jurisdiction,
based on ICC-ES AC193 or ICC-ES AC308.
1. Material for Interior Locations: Carbon-steel components zinc plated to comply with
ASTM B 633 or ASTM F 1941M, Class Fe/Zn 5, unless otherwise indicated.
2. Material for Exterior Locations and Where Stainless Steel Is Indicated: Alloy Group 2
(A4) stainless-steel bolts, ASTM F 738M, and nuts, ASTM F 836M.
A. Wood Rails: Clear, straight-grained hardwood rails secured to recessed metal subrail.
1. Species: Walnut.
2. Finish: Manufacturer's standard.
3. Staining: As selected by Architect from manufacturer's full range.
4. Profile: As indicated.
B. Wood Rails: Hardwood rails complying with Section 064300 "Wood Stairs and Railings."
C. Lacquer for Copper Alloys: Clear acrylic lacquer specially developed for coating copper-alloy
products.
D. Universal Shop Primer: Fast-curing, lead- and chromate-free, universal modified-alkyd primer
complying with MPI#79.
E. Bituminous Paint: Cold-applied asphalt emulsion complying with ASTM D 1187/D 1187M.
2.11 FABRICATION
A. General: Fabricate railings to comply with requirements indicated for design, dimensions,
member sizes and spacing, details, finish, and anchorage[, but not less than that required to
support structural loads.
B. Assemble railings in the shop to greatest extent possible to minimize field splicing and
assembly. Disassemble units only as necessary for shipping and handling limitations. Clearly
mark units for reassembly and coordinated installation. Use connections that maintain structural
value of joined pieces.
C. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius
of approximately 1 mm unless otherwise indicated. Remove sharp or rough areas on exposed
surfaces.
D. Form work true to line and level with accurate angles and surfaces.
E. Fabricate connections that will be exposed to weather in a manner to exclude water. Provide
weep holes where water may accumulate. Locate weep holes in inconspicuous locations.
F. Cut, reinforce, drill, and tap as indicated to receive finish hardware, screws, and similar items.
G. Mechanical Connections: Connect members with concealed mechanical fasteners and fittings.
Fabricate members and fittings to produce flush, smooth, rigid, hairline joints.
1. Fabricate splice joints for field connection using an epoxy structural adhesive if this is
manufacturer's standard splicing method.
I. Bend members in jigs to produce uniform curvature for each configuration required; maintain
cross section of member throughout entire bend without buckling, twisting, cracking, or
otherwise deforming exposed surfaces of components.
J. Close exposed ends of hollow railing members with prefabricated end fittings.
K. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges, miscellaneous fittings,
and anchors to interconnect railing members to other work where indicated.
1. At brackets and fittings fastened to plaster or gypsum board partitions, provide crush-
resistant fillers, or other means to transfer loads through wall finishes to structural
supports and to prevent bracket or fitting rotation and crushing of substrate.
M. For railing posts set in concrete, provide stainless-steel sleeves not less than 150 mm long with
inside dimensions not less than 13 mm greater than outside dimensions of post, with metal
plate forming bottom closure.
A. General: Fabricate to sizes and shapes required; provide for proper edge clearance and bite on
glazing panels.
1. Clean-cut or flat-grind edges at butt-glazed sealant joints to produce square edges with
slight chamfers at junctions of edges and faces.
2. Grind smooth exposed edges, including those at open joints, to produce square edges
with slight chamfers at junctions of edges and faces.
B. Structural Glass Balusters: Factory-bond glass to aluminum base and top-rail channels in railing
manufacturer's plant using glazing cement to comply with manufacturer's written
specifications, unless field glazing is standard with manufacturer.
C. Structural Balusters: Provide laminated, tempered glass panels[ for both straight and curved
sections.
D. Structural Balusters: Provide thermoformed, curved, plastic glazing panels for curved sections
and laminated, tempered glass panels for straight sections.
E. Infill Panels: Provide laminated, tempered glass panels[ for both straight and curved sections].
B. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-
half of the range of approved Samples. Variations in appearance of other components are
acceptable if they are within the range of approved Samples and are assembled or installed to
minimize contrast.
C. Provide exposed fasteners with finish matching appearance, including color and texture, of
railings.
A. Mechanical Finish: AA-M3x; sand top rails, handrails, and intermediate rails in one direction
only, parallel to length of railing, with 120- and 320-grit abrasive. After installation, polish railings
with No. 0 steel wool immersed in paste wax, then rub to a luster with a soft dry cloth.
B. Clear Anodic Finish: AAMA 611, [AA-M12C22A41, Class I, 0.018 mm] [AA-M12C22A31,
Class II, 0.010 mm] or thicker.
D. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum dry film thickness of
0.04 mm. Comply with coating manufacturer's written instructions for cleaning, conversion
coating, and applying and baking finish.
E. High-Performance Organic Finish: Two-coat fluoropolymer finish complying with AAMA 2605
and containing not less than 70 percent PVDF resin by weight in color coat. Prepare, pretreat,
and apply coating to exposed metal surfaces to comply with coating and resin manufacturers'
written instructions.
A. Finish designations for copper alloys comply with the system for designating copper-alloy finish
systems defined in NAAMM's "Metal Finishes Manual for Architectural and Metal Products."
C. Hand-Rubbed Finish: M31-M34 (Mechanical Finish: directionally textured, fine satin; Mechanical
Finish: directionally textured, hand rubbed).
F. Buffed Finish, Lacquered: M21-O6x (Mechanical Finish: buffed, smooth specular; Coating:
clear, organic, air dried, as specified below).
1. Clear, Organic Coating: Lacquer specified for copper alloys, applied by air spray in two
coats per manufacturer's written instructions, with interim drying, to a total thickness of
0.025 mm.
1. Clear, Organic Coating: Lacquer specified for copper alloys, applied by air spray in two
coats per manufacturer's written instructions, with interim drying, to a total thickness of
0.025 mm.
1. Clear, Organic Coating: Lacquer specified for copper alloys, applied by air spray in two
coats per manufacturer's written instructions, with interim drying, to a total thickness of
0.025 mm.
1. Clear, Organic Coating: Lacquer specified for copper alloys, applied by air spray in two
coats per manufacturer's written instructions, with interim drying, to a total thickness of
0.025 mm.
A. Surface Preparation: Remove tool and die marks and stretch lines, or blend into finish.
B. Polished Finishes: Grind and polish surfaces to produce uniform finish, free of cross scratches.
G. When polishing is completed, passivate and rinse surfaces. Remove embedded foreign matter
and leave surfaces chemically clean.
PART 3 - EXECUTION
B. Perform cutting, drilling, and fitting required for installing railings. Set railings accurately in
location, alignment, and elevation; measured from established lines and levels and free of rack.
1. Do not weld, cut, or abrade surfaces of railing components that have been coated or
finished after fabrication and that are intended for field connection by mechanical or other
means without further cutting or fitting.
2. Set posts plumb within a tolerance of 2 mm in 1 m.
3. Align rails so variations from level for horizontal members and variations from parallel
with rake of steps and ramps for sloping members do not exceed 5 mm in 3 m.
C. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals
and other materials from direct contact with incompatible materials.
1. Coat concealed surfaces of aluminum and copper alloys that will be in contact with grout,
concrete, masonry, wood, or dissimilar metals, with a heavy coat of bituminous paint.
A. Nonwelded Connections: Use mechanical or adhesive joints for permanently connecting railing
components. Use wood blocks and padding to prevent damage to railing members and fittings.
Seal recessed holes of exposed locking screws using plastic cement filler colored to match
finish of railings.
B. Expansion Joints: Install expansion joints at locations indicated but not farther apart than
required to accommodate thermal movement. Provide slip-joint internal sleeve extending 50
mm beyond joint on either side, fasten internal sleeve securely to one side, and locate joint
within 150 mm of post.
A. Use steel pipe sleeves preset and anchored into concrete for installing posts. After posts have
been inserted into sleeves, fill annular space between post and sleeve with nonshrink,
nonmetallic grout or anchoring cement, mixed and placed to comply with anchoring material
manufacturer's written instructions.
B. Form or core-drill holes not less than 125 mm deep and 20 mm larger than OD of post for
installing posts in concrete. Clean holes of loose material, insert posts, and fill annular space
between post and concrete with nonshrink, nonmetallic grout or anchoring cement, mixed and
placed to comply with anchoring material manufacturer's written instructions.
C. Cover anchorage joint with flange of same metal as post, welded to post after placing anchoring
material] [attached to post with set screws.
D. Leave anchorage joint exposed with 3-mm buildup, sloped away from post.
E. Anchor posts to metal surfaces with flanges, angle type, or floor type as required by conditions,
connected to posts and to metal supporting members as follows:
1. For aluminum railings, attach posts as indicated using fittings designed and engineered
for this purpose.
2. For copper-alloy railings, attach posts as indicated using fittings designed and
engineered for this purpose.
3. For stainless-steel railings, weld flanges to posts and bolt to metal-supporting surfaces.
F. Install removable railing sections, where indicated, in slip-fit metal sockets cast in concrete.
1. Attach base channel to building structure, then insert and connect factory-fabricated and -
assembled glass panels if glass was bonded to base and top-rail channels in factory.
2. Attach base channel to building structure, then insert glass into base channel and bond
with glazing cement unless glass was bonded to base and top-rail channels in factory.
1. Adjust spacing of glass panels so gaps between panels are equal before securing in
position.
2. Erect glass railings under direct supervision of manufacturer's authorized technical
personnel.
C. Post-Supported Glass Railings: Install assembly to comply with railing manufacturer's written
instructions and with requirements in other Part 3 articles. Erect posts and other metal railing
components, then set factory-cut glass panels. Do not cut, drill, or alter glass panels in field.
Protect edges from damage.
A. Testing Agency: Owner will engage a qualified testing agency to perform tests and inspections
and to prepare test reports. Payment for these services will be made from the testing and
inspecting allowance, as authorized by Change Orders.
B. Extent and Testing Methodology: Testing agency will randomly select completed railing
assemblies for testing that are representative of different railing designs and conditions in the
completed Work. Test railings according to ASTM E 894 and ASTM E 935 for compliance with
performance requirements.
C. Remove and replace railings where test results indicate that they do not comply with specified
requirements unless they can be repaired in a manner satisfactory to Architect and comply with
specified requirements.
3.6 CLEANING
A. Clean aluminum and stainless steel by washing thoroughly with water and soap, rinsing with
clean water, and wiping dry.
B. Clean copper alloys according to metal finisher's written instructions in a manner that leaves an
undamaged and uniform finish matching approved Sample.
C. Clean and polish glass as recommended in writing by manufacturer. Wash both exposed
surfaces in each area of Project not more than four days before date scheduled for inspections
that establish date of Substantial Completion.
D. Clean wood rails by wiping with a damp cloth and then wiping dry.
3.7 PROTECTION
A. Protect finishes of railings from damage during construction period with temporary protective
coverings approved by railing manufacturer. Remove protective coverings at time of Substantial
Completion.
END OF SECTION
END OF SECTION
PART 2 PRODUCTS
2.01 APPLICATIONS
A. Insulation Under Concrete Slabs: Extruded polystyrene (XPS) board.
B. Insulation at Perimeter of Foundation: Extruded polystyrene (XPS) board.
C. Insulation Inside Masonry Cavity Walls: Extruded polystyrene (XPS) carbon black board.
D. Insulation Inside Prefabricated Wall Panels: Extruded polystyrene (XPS) board.
E. Insulation Over Metal Stud Framed Walls, Continuous: Extruded polystyrene (XPS) carbon
black board.
F. Insulation on Inside of Framed Walls with Exposed Facer Providing Interior Finish: Glass-fiber-
reinforced polyisocyanurate with exposed facers.
G. Insulation on Inside of Concrete and Masonry Exterior Walls: Glass fiber board.
H. Insulation in Metal Framed Walls: Batt insulation with integral vapor retarder.
I. Insulation in Wood Framed Walls: Batt insulation with separate vapor retarder.
J. Insulation in Wood Framed Ceiling Structure: Batt insulation with separate vapor retarder.
K. Insulation Above Lay-In Acoustical Ceilings: Batt insulation with no vapor retarder.
L. Insulation Over Roof Deck: Extruded polystyrene (XPS) board.
2.02 FOAM BOARD INSULATION MATERIALS
A. Expanded Polystyrene (EPS) Board Insulation: Complies with ASTM C578.
1. Flame Spread Index (FSI): Class A - 0 to 25, when tested in accordance with ASTM E84.
2. Smoke Developed Index (SDI): 450 or less, when tested in accordance with ASTM E84.
3. Complies with fire resistance requirements indicated on drawings as part of an exterior
non-load-bearing exterior wall assembly when tested in accordance with NFPA 285.
4. Board Size: 1220 mm by 2440 mm.
5. Board Thickness: As indicated on drawings
6. Board Edges: Square.
7. Type and Compressive Resistance: Type XI, 5 psi (35 kPa), minimum.
F. Expanded Graphite Polystyrene (GPS) Board Insulation: Complying with ASTM C578, Type I.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that substrate, adjacent materials, and insulation materials are dry and that substrates
are ready to receive insulation.
B. Verify substrate surfaces are flat, free of honeycomb, fins, irregularities, or materials or
substances that may impede adhesive bond.
3.02 BOARD INSTALLATION AT FOUNDATION PERIMETER
A. Adhere a 152 mm wide strip of polyethylene sheet over construction, control, and expansion
joints with double beads of adhesive each side of joint.
1. Tape seal joints.
2. Extend sheet full height of joint.
B. Apply adhesive to back of boards:
1. Three continuous beads per board length.
2. Full bed 3.2 mm thick.
C. Install boards horizontally on foundation perimeter.
1. Place boards to maximize adhesive contact.
2. Install in running bond pattern.
3. Butt edges and ends tightly to adjacent boards and to protrusions.
D. Extend boards over expansion joints, unbonded to foundation on one side of joint.
E. Cut and fit insulation tightly to protrusions or interruptions to the insulation plane.
F. Immediately following application of board insulation, place protective boards over exposed
insulation surfaces.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Requirements:
1. Section <Insert Section number> "<Insert Section title>" for roofing membrane, roof
thermal insulation, aggregate or roof-paver ballast, and roofing system warranty.
2. Section 129300 "Site Furnishings" for exterior unit planters.
1.2 DEFINITIONS
A. Captured Water: Water that is retained in the drainage layer of a vegetated roof assembly after
new water additions have ceased and that cannot escape the roof except through evaporation
or plant transpiration.
D. Plant; Plants; Plant Material: Vegetation in general, including trees, shrubs, vines, ground
covers, ornamental grasses, bulbs, corms, tubers, or herbaceous vegetation.
E. Growing Medium: Manufactured, lightweight soil mixture that promotes good growing conditions
for specific varieties of plants.
C. Samples for Verification: For each of the following components of vegetated roof assembly:
C. Product Test Reports: For complete analysis of each growing medium, for tests performed by
manufacturer and witnessed by a qualified testing agency or by a qualified testing agency.
A. Maintenance Data: For vegetated roof assembly and plants, including a recommended
maintenance plan with procedures for inspection and care during a calendar year. Submit
before start of required warranty and maintenance periods.
B. Continuing Maintenance Proposal: From vegetated roof assembly Installer approved by roofing-
membrane manufacturer to Owner, in the form of a standard one-year maintenance agreement,
starting on date initial maintenance service is concluded. State services, obligations, conditions,
and terms for agreement period and for future renewal options.
B. Bulk Materials:
1. Do not dump or store bulk materials on or near structures, utilities, walkways and
pavements, or existing roof areas or plants.
2. Provide erosion-control measures to prevent erosion or displacement of bulk materials,
discharge of debris-bearing water runoff, and airborne dust reaching adjacent properties,
water conveyance systems, or walkways.
3. Accompany each delivery of bulk materials with product certificates.
C. Handle and store materials, and place equipment in a manner to avoid overloading roof
structure or damaging roofing membrane.
A. Weather Limitations: Proceed with planting only when existing and forecasted weather
conditions permit planting to be performed when optimum results may be obtained. Apply
products during favorable weather conditions according to manufacturer's written instructions
and warranty requirements.
1.9 WARRANTY
A. Special Warranty for Vegetated Roof Assembly: Installer agrees to repair or replace
components of vegetated roof assembly that fail in materials or workmanship within specified
warranty period.
1. Failures include, but are not limited to, ponding water or prolonged wetness of growing
medium caused as a result of failure of the assembly to properly drain.
2. Warranty Period: Five years from date of Substantial Completion.
B. Special Warranty for Plant Growth: Installer agrees to repair or replace plantings and
accessories that fail in materials, workmanship, or growth within specified warranty period.
1. Foliage Cover: Planted materials shall grow to achieve and maintain at least 80 percent
foliage cover over planting area commencing 24 months after planting, through the
duration of this warranty.
a. Immediately remove dead plants and replace unless required to plant in the
succeeding planting season.
b. Replace plants that are more than 25 percent dead or in an unhealthy condition at
end of warranty period.
c. A limit of one replacement of each plant will be required except for losses or
replacements due to failure to comply with requirements.
5. Provide extended warranty for period equal to original warranty period, for replaced plant
material.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain vegetated roof assembly components from single source from single
manufacturer.
B. Drainage Panels: Assembly manufacturer's standard drainage board formed from geotextile-
faced, molded-plastic sheet with a geotextile face and "cups" of the molded sheet facing upward
like small reservoirs to retain water while allowing excess water to drain away below the board
or geotextile-faced, entangled plastic-filament core.
C. Root Barrier: Vegetated roof assembly manufacturer's standard plastic sheet manufactured
from [recycled] polyethylene or polypropylene plastic; formulated to resist root growth and
bacteria.
a. Minimum: 4 percent.
b. Maximum: 10 percent.
6. Chemical Properties:
B. Custom Growing Medium: Manufactured soil mixture for plants indicated on Drawings and that
complies with the following:
A. Lime: ASTM C 602, Class T or Class O agricultural liming material containing a minimum of 80
percent calcium carbonate equivalent.
B. Sulfur: Granular, biodegradable, and containing a minimum of 90 percent elemental sulfur, with
a minimum of 99 percent passing through 3.35-mm sieve and a maximum of 10 percent
passing through 0.425-mm sieve.
C. Iron Sulfate: Granulated ferrous sulfate containing a minimum of 20 percent iron and 10 percent
sulfur.
E. Agricultural Gypsum: Minimum 90 percent calcium sulfate, finely ground with 90 percent
passing through 0.30-mm sieve.
A. Walkway Pavers: Concrete & stone pavers specified in Section 321400 "Unit Paving."
C. Setting Bed: Aggregate setting-bed material specified in Section 321400 "Unit Paving."
D. Separation Geotextile: Woven geotextile fabric, manufactured for separation applications, made
from polyolefins or polyesters; as recommended by vegetated roof assembly manufacturer.
2.8 ACCESSORIES
B. Access Boxes: Manufacturer's standard stainless-steel or aluminum boxes with removable, rigid
covers for accessing drains, valves, and switches beneath the finish elevation of growing
medium; secure each cover with four noncorrosive screws.
1. Size: As shown on Drawings for each location.
3.1 EXAMINATION
A. Examine each area to receive vegetated roof assembly for compliance with requirements for
installation tolerances and other conditions affecting performance.
1. Verify that roof insulation over roofing membrane is in place, secure, and flush along all
seams.
2. Verify that perimeter and other flashings are in place and secure along entire lengths
where they will be covered by vegetated roof assembly.
1. Verify that no foreign or deleterious material or liquid, such as paint, paint washout,
concrete slurry, concrete layers or chunks, cement, plaster, oils, gasoline, diesel fuel,
paint thinner, turpentine, tar, roofing compound, or acid has been deposited in growing
medium within a planting area.
2. If growing medium is contaminated by foreign or deleterious material or liquid, remove
growing medium and contamination and replace with new growing medium.
A. Protection Course: Cover roofing system with protection board with butted and fully taped joints
before roofing system is subject to vegetated roof assembly installation work.
C. Sloped Roofs: Install erosion-control fabric and anti-slip devices for slopes steeper than 1/2 inch
per 12 inches (1:24) according to manufacturer's written instructions.
D. Small Plant Stabilization: Install erosion-control fabric over planting area to secure small plants
according to manufacturer's written instructions.
E. Geofoam Fill: Install geofoam-fill blocks in as few layers as possible with abutting edges and
ends and with the long dimension of each block placed at right angles to blocks in each
subsequent layer. Offset joints of blocks in successive layers.
1. Install geofoam connectors at each layer, without damaging roofing system, to resist
horizontal displacement of geofoam and according to geofoam-fill manufacturer's written
instructions.
2. Cover geofoam fill with separation geotextile before placing overlying growing medium.
F. Access Boxes: Install access box at each drain, valve, and switch and at locations shown on
Drawings. Install top of boxes level with [beneath 25 mm above the finish elevation of growing
medium.
3.3 PLANTING
B. Do not place growing medium or plants during frozen, wet, or muddy conditions.
D. Uniformly moisten an excessively dry growing medium that is too dusty or unworkable.
E. Preplanted Vegetative Mat: Install in full contact with growing medium and secure in position.
F. Site Planting: Plant vegetated roofs according to requirements specified in Section 329300
"Plants" except as otherwise indicated on Drawings and required by vegetated roof assembly
manufacturer's written instructions. Perform digging carefully to prevent damaging roofing
system below the vegetated roof assembly.
G. Seeding Grasses: Sow seed at a total rate of 2.3 to 3.6 kg/92.9 sq. m.
H. Meadow Grasses and Wildflowers: Sow seed at a total rate of 170 g/92.9 sq. m.
I. Plugging: Plant plugs in holes or furrows, spaced 300 mm apart in both directions.
J. Individual Plant Planting: Set out and space plants other than grasses and wildflowers 225 mm
part [as indicated on Drawings in even rows with triangular spacing.
B. Setting Bed: Install setting bed according to paver manufacturer's written instructions.
C. Install paver supports according to pedestal manufacturer's written instructions. Adjust for final
level and slope with shims.
D. Loosely set walkway pavers, maintaining a uniform joint width. Tightly seat pavers against
spacers to eliminate lateral movement or drift of paving assembly. Align joint patterns parallel in
each direction.
E. Tolerances: Do not exceed1.6-mm unit-to-unit offset from flush (lippage) nor 3 mm in 600 mm
and 6 mm in 3 m from level, or indicated slope, for finished surface of paving.
A. Install soil retainer where indicated according to manufacturer's written instructions. Secure with
adhesive.
1. Flood Testing: Flood test each deck area for leaks, according to procedures in
ASTM D 5957, after completing and protecting roofing membrane but before placing
overlaying construction. Install temporary containment assemblies, plug or dam drains,
and flood with potable water.
a. Testing agency shall test each deck area indicated for testing on Drawings for
leaks using an electronic leak-detection method that locates discontinuities in the
roofing membrane.
b. Testing agency shall perform tests on abutting or overlapping smaller areas as
necessary to cover entire test area.
c. Testing agency shall create a conductive electronic field over the area of roofing to
be tested and electronically determine locations of discontinuities or leaks, if any,
in the roofing.
d. Testing agency shall provide survey report indicating locations of discontinuities if
any.
3. Proceed with installation of vegetated roof assembly only after unsatisfactory conditions
have been corrected.
3.7 PROTECTION
A. Protect vegetated roof assemblies from damage, including growing-medium contamination, due
to operations of other contractors and trades. Repair or replace damaged vegetated roof
assemblies.
END OF SECTION
END OF SECTION
END OF SECTION
PART 1 GENERAL
1.1 SUMMARY
A. Section Includes:
B. Related Requirements:
1. Section 054000 "Cold-Formed Metal Framing" for exterior and interior load-bearing and
exterior non-load-bearing wall studs; floor joists; roof rafters and ceiling joists; and roof
trusses.
A. Product Certificates: For each type of code-compliance certification for studs and tracks.
B. Evaluation Reports: For post-installed anchors and power-actuated fasteners, from ICC-ES or
other qualified testing agency acceptable to authorities having jurisdiction.
PART 2 - PRODUCTS
B. Horizontal Deflection: For wall assemblies, limited 1/360 of the wall height based on horizontal
loading of 480 Pa.
A. Framing Members, General: Comply with ASTM C 754 for conditions indicated.
1. Steel Sheet Components: Comply with ASTM C 645 requirements for metal unless
otherwise indicated.
2. Protective Coating: Coating with equivalent corrosion resistance of ASTM A 653/A 653M,
Z120, hot-dip galvanized unless otherwise indicated.
B. Studs and Tracks: ASTM C 645. Use either steel studs and tracks or embossed steel studs and
tracks.
2. Embossed Steel Studs and Tracks: Roll-formed and embossed with surface deformations
to stiffen the framing members so that they are structurally equivalent to conventional
ASTM C 645 steel studs and tracks.
a. Minimum Base-Metal Thickness: As required by horizontal deflection performance
requirements.
b. Depth: As indicated on Drawings.
1. Clip System: Clips designed for use in head-of-wall deflection conditions that provide a
positive attachment of studs to tracks while allowing 76-mm minimum vertical
movement.
D. Firestop Tracks: Top track manufactured to allow partition heads to expand and contract with
movement of structure while maintaining continuity of fire-resistance-rated assembly indicated;
in thickness not less than indicated for studs and in width to accommodate depth of studs.
E. Flat Strap and Backing Plate: Steel sheet for blocking and bracing in length and width indicated.
1. Minimum Base-Metal Thickness: As indicated on Drawings.
F. Cold-Rolled Channel Bridging: Steel, 1.367-mm minimum base-metal thickness, with minimum
13-mm wide flanges.
1. Depth: As indicated on Drawings.
2. Clip Angle: Not less than 38 by 38 mm, 1.72-mm thick, galvanized steel.
H. Resilient Furring Channels: 13-mm deep, steel sheet members designed to reduce sound
transmission.
1. Configuration: Asymmetrical or hat shaped.
I. Cold-Rolled Furring Channels: 1.34-mm uncoated-steel thickness, with minimum 13-mm wide
flanges.
J. Z-Shaped Furring: With slotted or nonslotted web, face flange of 32 mm, wall attachment
flange of 22 mm, minimum uncoated-metal thickness of 0.455 mm, and depth required to fit
insulation thickness indicated.
A. Tie Wire: ASTM A 641/A 641M, Class 1 zinc coating, soft temper, 1.59-mm diameter wire, or
double strand of 1.21-mm diameter wire.
C. Wire Hangers: ASTM A 641/A 641M, Class 1 zinc coating, soft temper, 4.12 mm in diameter.
G. Grid Suspension System for Gypsum Board Ceilings: ASTM C 645, direct-hung system
composed of main beams and cross-furring members that interlock.
A. General: Provide auxiliary materials that comply with referenced installation standards.
1. Fasteners for Steel Framing: Of type, material, size, corrosion resistance, holding power,
and other properties required to fasten steel members to substrates.
1. Asphalt-Saturated Organic Felt: ASTM D 226/D 226M, Type I (No. 15 asphalt felt),
nonperforated.
2. Foam Gasket: Adhesive-backed, closed-cell vinyl foam strips that allow fastener
penetration without foam displacement, 3.2 mm thick, in width to suit steel stud size.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and substrates, with Installer present, and including welded hollow-metal
frames, cast-in anchors, and structural framing, for compliance with requirements and other
conditions affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
1. Furnish concrete inserts and other devices indicated to other trades for installation in
advance of time needed for coordination and construction.
1. Before sprayed fire-resistive materials are applied, attach offset anchor plates or ceiling
tracks to surfaces indicated to receive sprayed fire-resistive materials. Where offset
1. Gypsum Plaster Assemblies: Also comply with requirements in ASTM C 841 that apply to
framing installation.
2. Portland Cement Plaster Assemblies: Also comply with requirements in ASTM C 1063
that apply to framing installation.
3. Gypsum Veneer Plaster Assemblies: Also comply with requirements in ASTM C 844 that
apply to framing installation.
4. Gypsum Board Assemblies: Also comply with requirements in ASTM C 840 that apply to
framing installation.
B. Install framing and accessories plumb, square, and true to line, with connections securely
fastened.
C. Install supplementary framing, and blocking to support fixtures, equipment services, heavy trim,
grab bars, toilet accessories, furnishings, or similar construction.
E. Do not bridge building control and expansion joints with non-load-bearing steel framing
members. Frame both sides of joints independently.
A. Install framing system components according to spacings indicated, but not greater than
spacings required by referenced installation standards for assembly types.
B. Where studs are installed directly against exterior masonry walls or dissimilar metals at exterior
walls, install isolation strip between studs and exterior wall.
D. Install tracks at floors and overhead supports. Extend framing full height to structural supports
or substrates above suspended ceilings except where partitions are indicated to terminate at
suspended ceilings. Continue framing around ducts that penetrate partitions above ceiling.
3. Other Framed Openings: Frame openings other than door openings the same as
required for door openings unless otherwise indicated. Install framing below sills of
openings to match framing required above door heads.
4. Fire-Resistance-Rated Partitions: Install framing to comply with fire-resistance-rated
assembly indicated and support closures and to make partitions continuous from floor to
underside of solid structure.
a. Bend track to uniform curve and locate straight lengths so they are tangent to arcs.
b. Begin and end each arc with a stud, and space intermediate studs equally along
arcs. On straight lengths of no fewer than two studs at ends of arcs, place studs
(150 mm o.c.
E. Direct Furring:
1. Erect insulation, specified in Section 072100 "Thermal Insulation," vertically and hold in
place with Z-shaped furring members spaced 610 mm o.c.
2. Except at exterior corners, securely attach narrow flanges of furring members to wall with
concrete stub nails, screws designed for masonry attachment, or powder-driven fasteners
spaced 610 mm o.c.
3. At exterior corners, attach wide flange of furring members to wall with short flange
extending beyond corner; on adjacent wall surface, screw-attach short flange of furring
channel to web of attached channel. At interior corners, space second member no more
than 305 mm from corner and cut insulation to fit.
G. Installation Tolerance: Install each framing member so fastening surfaces vary not more than 3
mm from the plane formed by faces of adjacent framing.
A. Install suspension system components according to spacings indicated, but not greater than
spacings required by referenced installation standards for assembly types.
B. Isolate suspension systems from building structure where they abut or are penetrated by
building structure to prevent transfer of loading imposed by structural movement.
1. Install hangers plumb and free from contact with insulation or other objects within ceiling
plenum that are not part of supporting structural or suspension system.
a. Splay hangers only where required to miss obstructions and offset resulting
horizontal forces by bracing, countersplaying, or other equally effective means.
2. Where width of ducts and other construction within ceiling plenum produces hanger
spacings that interfere with locations of hangers required to support standard suspension
system members, install supplemental suspension members and hangers in the form of
trapezes or equivalent devices.
3. Wire Hangers: Secure by looping and wire tying, either directly to structures or to inserts,
eye screws, or other devices and fasteners that are secure and appropriate for substrate,
and in a manner that will not cause hangers to deteriorate or otherwise fail.
4. Flat Hangers: Secure to structure, including intermediate framing members, by attaching
to inserts, eye screws, or other devices and fasteners that are secure and appropriate for
structure and hanger, and in a manner that will not cause hangers to deteriorate or
otherwise fail.
5. Do not attach hangers to steel roof deck.
6. Do not attach hangers to permanent metal forms. Furnish cast-in-place hanger inserts
that extend through forms.
7. Do not attach hangers to rolled-in hanger tabs of composite steel floor deck.
8. Do not connect or suspend steel framing from ducts, pipes, or conduit.
E. Seismic Bracing: Sway-brace suspension systems with hangers used for support.
F. Grid Suspension Systems: Attach perimeter wall track or angle where grid suspension systems
meet vertical surfaces. Mechanically join main beam and cross-furring members to each other
and butt-cut to fit into wall track.
G. Installation Tolerances: Install suspension systems that are level to within 3 mm in 3.6 m
<Insert dimensions> measured lengthwise on each member that will receive finishes and
transversely between parallel members that will receive finishes.
END OF SECTION
1009DF / MISHRIFAH VILLA 09 2216 - 7 NON-STRUCTURAL METAL
FRAMING
SECTION 09 2400
CEMENT PLASTERING
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Cement plastering.
1.02 RELATED REQUIREMENTS
A. Section 07 2500 - Weather Barriers.
B. Section 09 2116 - Gypsum Board Assemblies: Metal stud framing and furring for plaster.
C. Section 09 2236 - Lath: Lath, furring, beads, screeds, and joint accessories for plaster base.
1.03 REFERENCE STANDARDS
A. ASTM C91/C91M - Standard Specification for Masonry Cement; 2012.
B. ASTM C150/C150M - Standard Specification for Portland Cement; 2017.
C. ASTM C206 - Standard Specification for Finishing Hydrated Lime; 2014.
D. ASTM C207 - Standard Specification for Hydrated Lime for Masonry Purposes; 2006
(Reapproved 2011).
E. ASTM C897 - Standard Specification for Aggregate for Job-Mixed Portland Cement-Based
Plasters; 2015.
F. ASTM C926 - Standard Specification for Application of Portland Cement-Based Plaster; 2019a,
with Editorial Revision.
G. ASTM C1328/C1328M - Standard Specification for Plastic (Stucco) Cement; 2012.
H. ASTM E119 - Standard Test Methods for Fire Tests of Building Construction and Materials;
2019.
I. ICC (IBC) - International Building Code; Most Recent Edition Adopted by Authority Having
Jurisdiction, Including All Applicable Amendments and Supplements.
J. ICC (IRC) - International Residential Code for One- and Two-Family Dwellings; Most Recent
Edition Adopted by Authority Having Jurisdiction, Including All Applicable Amendments and
Supplements.
K. NTMA (SPECS) - NTMA Terrazzo Specifications; Current Edition.
L. UL (DIR) - Online Certifications Directory; Current Edition.
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittals procedures.
B. Product Data: Provide data on plaster materials and trim accessories.
C. Evaluation Service Reports: Show compliance with specified requirements.
D. Installer's Qualification Statement.
1.05 QUALITY ASSURANCE
A. Installer Qualifications: Company specializing in performing the work of this section with
minimum three years documented experience.
B. Copies of Documents at Project Site: Maintain at the project site a copy of each referenced
document that prescribes execution requirements.
1.06 MOCK-UP
A. Mock-Up Panel: Construct a 1200 mm wide by 2400 mm high sample panel of plaster work at
the jobsite demonstrating installation procedures, finish texture, and color. Show each phase of
installation including framing and reinforcement.
PART 2 PRODUCTS
2.01 PAINTS AND FINISHES - GENERAL
A. Paints and Finishes: Ready mixed, unless intended to be a field-catalyzed paint.
1. Provide paints and finishes of a soft paste consistency, capable of being readily and
uniformly dispersed to a homogeneous coating, with good flow and brushing properties,
and capable of drying or curing free of streaks or sags.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that surfaces are ready to receive work as instructed by the product manufacturer.
B. Examine surfaces scheduled to be finished prior to commencement of work. Report any
condition that may potentially effect proper application.
C. Test shop-applied primer for compatibility with subsequent cover materials.
D. Measure moisture content of surfaces using an electronic moisture meter. Do not apply
finishes unless moisture content of surfaces are below the following maximums:
1. Gypsum Wallboard: 12 percent.
2. Plaster and Stucco: 12 percent.
3. Masonry, Concrete, and Concrete Masonry Units: 12 percent.
4. Interior Wood: 15 percent, measured in accordance with ASTM D4442.
5. Concrete Floors and Traffic Surfaces: 8 percent.
3.02 PREPARATION
A. Clean surfaces thoroughly and correct defects prior to application.
B. Prepare surfaces using the methods recommended by the manufacturer for achieving the best
result for the substrate under the project conditions.
C. Remove or mask surface appurtenances, including electrical plates, hardware, light fixture trim,
escutcheons, and fittings, prior to preparing surfaces or finishing.
D. Seal surfaces that might cause bleed through or staining of topcoat.
E. Concrete:
F. Masonry:
G. Concrete Floors and Traffic Surfaces: Remove contamination, acid etch, and rinse floors with
clear water. Verify required acid-alkali balance is achieved. Allow to dry.
H. Gypsum Board: Fill minor defects with filler compound. Spot prime defects after repair.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Private-use bathroom accessories.
2. Warm-air dryers.
3. Underlavatory guards.
B. Related Requirements:
1.2 COORDINATION
A. Coordinate accessory locations with other work to prevent interference with clearances required
for access by people with disabilities, and for proper installation, adjustment, operation,
cleaning, and servicing of accessories.
B. Deliver inserts and anchoring devices set into concrete or masonry as required to prevent
delaying the Work.
B. Samples: Full size, for each exposed product and for each finish specified.
1. Approved full-size Samples will be returned and may be used in the Work.
C. Product Schedule: Indicating types, quantities, sizes, and installation locations by room of each
accessory required.
1.6 WARRANTY
A. Manufacturer's Special Warranty for Mirrors: Manufacturer agrees to repair or replace mirrors
that fail in materials or workmanship within specified warranty period.
1. Failures include, but are not limited to, visible silver spoilage defects.
2. Warranty Period: 15 years from date of Substantial Completion.
PART 2 - PRODUCTS
A. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,
by a qualified testing agency, and marked for intended location and application.
A. Source Limitations: Obtain private-use bathroom accessories from single source from single
manufacturer.
D. Soap Dish:
1. Description:
2. Mounting: Recessed.
3. Material and Finish: Solid brass, polished.
E. Medicine Cabinet:
G. Robe Hook
1. Description: Double-prong unit.
2. Material and Finish: Solid brass, polished.
I. Towel Bar:
1. Description: 19-mm round tube with circular end brackets.
2. Mounting: Flanges with concealed fasteners.
3. Length: 762 mm.
4. Material and Finish: Stainless steel, No. 4 finish (satin).
J. Towel Pin:
1. Description: Projecting minimum of 127 mm from wall surface.
2. Material and Finish: Stainless steel, No. 7 finish (polished)
K. Towel Ring:
1. Description: Pin projecting approximately 63 mm from wall with oval ring.
2. Pin Material and Finish: Solid brass, polished.
3. Ring Material and Finish: Matching pin
L. Towel Shelf:
1. Description: Surface-mounted, guest-towel shelf with four 9-mm diameter stainless-steel
tubes mounted in support arms.
M. Towel Rack:
N. Retractable Clothesline:
1. Description: Surface-mounted rectangular housing with minimum 1829-mm long,
retractable, spring-actuated, synthetic clothesline and remote retention bracket.
2. Material and Finish Stainless steel, No. 7 finish (polished).
A. Source Limitations: Obtain warm-air dryers from single source from single manufacturer.
B. Warm-Air Dryer:
1. Description: Standard-speed, warm-air hand dryer.
2. Mounting: Surface mounted, with low-profile design.
3. Operation: Electronic-sensor activated with timed power cut-off switch.
A. Underlavatory Guard:
1. Description: Insulating pipe covering for supply and drain piping assemblies that prevents
direct contact with and burns from piping; allow service access without removing
coverings.
2. Material and Finish: Antimicrobial, molded plastic, white.
2.6 MATERIALS
A. Stainless Steel: ASTM A 666, Type 304, 0.8-mm minimum nominal thickness unless otherwise
indicated.
B. Brass: ASTM B 19, flat products; ASTM B 16/B 16M, rods, shapes, forgings, and flat products
with finished edges; or ASTM B 30, castings.
C. Steel Sheet: ASTM A 1008/A 1008M, Designation CS (cold rolled, commercial steel), 0.9-mm
minimum nominal thickness.
D. Galvanized-Steel Sheet: ASTM A 653/A 653M, with Z180 hot-dip zinc coating.
E. Galvanized-Steel Mounting Devices: ASTM A 153/A 153M, hot-dip galvanized after fabrication.
F. Fasteners: Screws, bolts, and other devices of same material as accessory unit and tamper-
and-theft resistant where exposed, and of galvanized steel where concealed.
H. Mirrors: ASTM C 1503, Mirror Glazing Quality, clear-glass mirrors, nominal 6.0 mm thick.
2.7 FABRICATION
A. General: Fabricate units with tight seams and joints, and exposed edges rolled. Hang doors and
access panels with full-length, continuous hinges. Equip units for concealed anchorage and with
corrosion-resistant backing plates.
B. Keys: Provide universal keys for internal access to accessories for servicing and resupplying.
Provide minimum of six keys to Owner's representative.
PART 3 - EXECUTION
3.1 INSTALLATION
B. Grab Bars: Install to withstand a downward load of at least 1112 N, when tested according to
ASTM F 446.
A. Adjust accessories for unencumbered, smooth operation. Replace damaged or defective items.
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Seating.
2. Tables.
3. Trash receptacles.
4. Planters.
B. Related Requirements:
1. Division 03 Section "Cast-in-Place Concrete" for installing anchor bolts cast in concrete
footings.
2. Division 31 Section "Earth Moving" for excavation for installing concrete footings.
B. Samples: For each exposed product and for each color and texture specified.
C. Samples for Verification: For each type of exposed finish, not less than 152-mm long linear
components and 102-mm square sheet components.
D. Product Schedule: For site furnishings. Use same designations indicated on Drawings.
A. Furnish extra materials that match products installed and that are packaged with protective
covering for storage and identified with labels describing contents.
1. Bench Replacement Planks: No fewer than two full-size units for each size indicated.
2. Trash Receptacle Inner Containers: Five full-size units for each size indicated, but no
fewer than two units.
3. Anchors: Manufacturers standard.
PART 2 - PRODUCTS
2.1 SEATING AND TABLES See the table at the end of the Evaluations for a list of manufacturers'
products. Use this table in combination with manufacturers' catalogs or product data to insert
series, type, model, and designations of other characteristics.
1. Material:
a. Wood: Teak; formed into evenly spaced parallel slats.
a. Straight shape.
b. Closed shape indicated around a planter.
C. Table Top:
1. Material:
a. Wood: Teak; formed into evenly spaced parallel slats.
b. Planks: Evenly spaced, parallel.
c. Sheet: Solid.
C. Trash Receptacles:
1. Receptacle Shape and Form: As indicated; with opening for depositing trash in lid or top.
2. Lids and Tops: Matching facing panels secured by cable or chain, hinged, swiveled, or
permanently secured.
2.3 PLANTERS
1. Finish: Smooth.
2.4 MATERIALS
A.Aluminum: Alloy and temper recommended by aluminum producer and finisher for type of use
and finish indicated; free of surface blemishes and complying with the following:
1009DF / MISHRIFAH VILLA 12 9300 - 4 SITE FURNISHING
1. Rolled or Cold-Finished Bars, Rods, and Wire: ASTM B 211 (ASTM B 211M).
2. Extruded Bars, Rods, Wire, Profiles, and Tubes: ASTM B 221 (ASTM B 221M).
3. Structural Pipe and Tube: ASTM B 429/B 429M.
4. Sheet and Plate: ASTM B 209 (ASTM B 209M).
5. Castings: ASTM B 26/B 26M.
B. Steel and Iron: Free of surface blemishes and complying with the following:
C. Stainless Steel: Free of surface blemishes and complying with the following:
D. Wood: Surfaced smooth on four sides with eased edges; kiln dried, free of knots, solid stock of
species indicated.
2. Certified Wood: Fabricate site furnishings with components produced from wood
obtained from forests certified by an FSC-accredited certification body to comply with
FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship."
3. Finish: Manufacturer's standard transparent wood preservative treatment and sealer.
F. Plastic: Color impregnated, color and UV-light stabilized, and mold resistant.
J. Galvanizing: Where indicated for steel and iron components, provide the following protective
zinc coating applied to components after fabrication:
2.6 FABRICATION
A. Metal Components: Form to required shapes and sizes with true, consistent curves, lines, and
angles. Separate metals from dissimilar materials to prevent electrolytic action.
B. Welded Connections: Weld connections continuously. Weld solid members with full-length,
full-penetration welds and hollow members with full-circumference welds. At exposed
connections, finish surfaces smooth and blended so no roughness or unevenness shows after
finishing and welded surface matches contours of adjoining surfaces.
1009DF / MISHRIFAH VILLA 12 9300 - 6 SITE FURNISHING
C. Pipes and Tubes: Form simple and compound curves by bending members in jigs to produce
uniform curvature for each repetitive configuration required; maintain cylindrical cross section of
member throughout entire bend without buckling, twisting, cracking, or otherwise deforming
exposed surfaces of handrail and railing components.
E. Exposed Surfaces: Polished, sanded, or otherwise finished; all surfaces smooth, free of burrs,
barbs, splinters, and sharpness; all edges and ends rolled, rounded, or capped.
F. Factory Assembly: Assemble components in the factory to greatest extent possible to minimize
field assembly. Clearly mark units for assembly in the field.
A. Appearance of Finished Work: Noticeable variations in same piece are not acceptable.
Variations in appearance of adjoining components are acceptable if they are within the range of
approved Samples and are assembled or installed to minimize contrast.
A. Surface Preparation: Remove tool and die marks and stretch lines, or blend into finish.
B. Polished Finishes: Grind and polish surfaces to produce uniform finish, free of cross scratches.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for
correct and level finished grade, mounting surfaces, installation tolerances, and other conditions
affecting performance of the Work.
B. Proceed with installation only after unsatisfactory conditions have been corrected.
A. Comply with manufacturer's written installation instructions unless more stringent requirements
are indicated. Complete field assembly of site furnishings where required.
B. Unless otherwise indicated, install site furnishings after landscaping and paving have been
completed.
C. Install site furnishings level, plumb, true, and securely anchored at locations indicated on
Drawings.
D. Post Setting: Set cast-in support posts in concrete footing with smooth top, shaped to shed
water. Protect portion of posts above footing from concrete splatter. Verify that posts are set
plumb or at correct angle and are aligned and at correct height and spacing. Hold posts in
position during placement and finishing operations until concrete is sufficiently cured.
E. Posts Set into Voids in Concrete: Form or core-drill holes for installing posts in concrete to
depth recommended in writing by manufacturer of site furnishings and 19 mm larger than OD of
post. Clean holes of loose material, insert posts, and fill annular space between post and
concrete with [nonshrink, nonmetallic grout] [or] [anchoring cement], mixed and placed to
comply with anchoring material manufacturer's written instructions, with top smoothed and
shaped to shed water.
F. After posts have been inserted into sleeves, fill annular space between post and sleeve with
nonshrink, nonmetallic grout or anchoring cement, mixed and placed to comply with anchoring
material manufacturer's written instructions, with top smoothed and shaped to shed water.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Site constructed steam room enclosure and benches.
B. Steam generator and controls.
C. Light fixture and switch.
1.02 RELATED REQUIREMENTS
A. Section 07 9200 - Joint Sealants: Sealing between steam bath enclosure and adjacent
construction.
B. Section 07 9005 - Joint Sealers: Sealant placed at exterior periphery of steam room
enclosure and sealant used within the steam room enclosure construction.
C. Section 22 1005 - Plumbing Piping: Domestic water supply to steam generator and faucet.
D. Section 22 1006 - Plumbing Piping Specialties: Floor drain in steam room.
E. Section 26 2717 - Equipment Wiring: Disconnect switch.
F. Section 26 5100 - Interior Lighting: Light fixtures.
1.03 REFERENCE STANDARDS
A. ASTM C665 - Standard Specification for Mineral-Fiber Blanket Thermal Insulation for Light
Frame Construction and Manufactured Housing; 2012.
B. ASTM C1036 - Standard Specification for Flat Glass; 2011.
C. GANA (GM) - GANA Glazing Manual; 2009.
D. GANA (SM) - FGMA Sealant Manual; Glass Association of North America; 2008.
E. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority Having
Jurisdiction, Including All Applicable Amendments and Supplements.
F. PS 1 - Structural Plywood; 2009.
G. RIS (GR) - Standard Specifications for Grades of California Redwood Lumber; 2000.
H. UL (DIR) - Online Certifications Directory; current listings at database.ul.com.
I. WWPA G-5 - Western Lumber Grading Rules; 2011.
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings: Indicate room layout, equipment locations, dimensions, door and frame
assembly, details of assembly, anchors, utility rough-in locations.
1. Show field measurements of space into which sauna will be installed.
C. Product Data: Provide data on equipment, accessories, utility characteristics.
D. Samples: Submit two panels of wall finish, 1000 x 1000 mm in size, illustrating color and
texture.
E. Manufacturer's Installation Instructions: Indicate installation procedures; characteristics,
location and coordination with required utilities.
F. Operation Data: Describe recommended operation of steam generator unit.
G. Maintenance Data: Describe cleaning procedures for room finishes and maintenance
required for steam generator.
1.05 REGULATORY REQUIREMENTS
A. Conform to applicable code for enclosure construction and operating equipment.
B. Steam Generator: Conform to applicable code for UL approval .
1.06 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Correct defective Work within a five year period after Date of Substantial Completion.
C. Provide five year manufacturer warranty for steam generator.
1. Include coverage for steam generator.
1009DF / MISHRIFAH VILLA 13 2426 - 1 STEAM BATHS
PART 2 PRODUCTS
2.01 COMPONENTS
A. Wall Panels: ____ mm (____ inch) nominal thickness, total RSI value of ____ (R value of
____).
B. Wall Construction: As follows:
1. Interior Finish: 19 x 100 mm (3/4 x 4 inch) nominal tongue and groove boards.
2. Vapor Barrier: 0.25 mm (10 mil) thick.
3. Studs: 38 x 89 mm (2 x 4) nominal size.
4. Insulation: RSI of 2.1 (R value of 12).
5. Exterior Finish: 19 x 100 mm (3/4 x 4 inch) nominal tongue and groove boards.
C. Ceiling Panels: (As indicated) mm nominal thickness, total RSI value of (As indicated) (R
value of (As indicated)).
D. Ceiling Construction: As follows:
1. Interior Finish: 19 x 100 mm (3/4 x 4 inch) nominal tongue and groove boards.
2. Vapor Barrier: 0.25 mm (10 mil) thick.
3. Joists: 38 x 89 mm (2 x 4) nominal size.
4. Insulation: RSI of 3.5 (R value of 20).
5. Exterior Finish: 19 x 100 mm (3/4 x 4 inch) nominal tongue and groove boards.
E. Floor Construction: As follows:
1. Interior Finish: 19 x 100 mm (3/4 x 4 inch) nominal tongue and groove boards.
2. Vapor Barrier: 0.25 mm (10 mil) thick.
3. Joists: 38 x 89 mm (2 x 4) nominal size.
4. Insulation: RSI of 3.5 (R value of 20).
F. Door and Frame Unit: (As indicated) mm nominal thickness, wood construction RSI value of
(As indicated) (R value of (As indicated)), with (As indicated) mm size glazing, hydraulic
closer, non-metallic push/pull hardware.
G. Benches: Same wood species as interior wall finish, 19 x 63 mm (3/4 x 2 1/2 inch) board
size, set 12 mm (1/2 inch) apart, secured to framing with galvanized screws.
2.02 MATERIALS
A. Lumber (Steam Room Interior): RIS Redwood Clear Grade, S4S, tongue and groove,
maximum moisture content of 12 percent.
B. Lumber (Concealed Framing): RIS Redwood Clear Grade, S4S, maximum moisture
content of 12 percent.
C. Plywood for Sheathing and Underlayment: PS 1 Grade C-D or better; softwood, sanded,
preservative treated.
D. Batt Insulation: ASTM C665, preformed glass fiber batt; friction fit.
E. Vapor Barrier: Black polyethylene film reinforced with glass fiber square mesh, including
seaming tape with permanent adhesive.
F. Glazing: Two panes of ASTM C 1036 clear float glass, hermetically sealed insulated units
with polyurethane sealant edge seal; total unit thickness of (As indicated).
G. Fasteners: Electro galvanized steel, size and type to suit condition.
H. Concealed Reinforcement and Accessories: Steel, non-corrosive.
I. Sealant: (As indicated) specified in Section 07 9005.
J. Light Fixture: Incandescent, (As indicated) watt lamp, sealed vapor tight.
2.03 EQUIPMENT
A. Steam Generator and Accessories: Electric unit, floor mounted; (As indicated) kilowatt
rating, (As indicated) volt, (As indicated) ampere, single phase; with controls, copper piping
from unit to room outlet, shut-off valves that are readily accessible after installation, chrome
plated brass steam room outlet.
B. Timer: Mechanical type, surface mounted, sixty minute count-down type, with steam
generator shut-off at 0 minutes.
SPECIFICATIONS
Part 2 of 3 (Divisions 21 to 28)
END OF SECTION
PART 1 - GENERAL
1.1 DESCRIPTION
A. General:
1. Furnish all labor, materials, tools, equipment, and services for fire protection systems, as
indicated, in accordance with provisions of Contract Documents.
2. Completely coordinate with work of all other trades.
3. Although such work is not specifically indicated, furnish and install all supplementary or
miscellaneous items, appurtenances and devices incidental to or necessary for a sound,
secure and complete installation.
4. See Division 1, for General Requirements.
5. See Section 230500, for Basic Mechanical Requirements.
6. See Section 221006, for Pipes and Pipe Fittings.
1.2 QUALITY ASSURANCE
A. Design criteria: Provide complete fire protection systems as indicated on the drawings.
1. Where there is conflict between local authority requirements (Civil Defense) and the
drawings or specifications, requirements of local authorities shall govern.
2. Design and install entire system in accordance with indicated codes, standards and
regulation.
3. All materials and equipment shall be produced in a plant of recognized reputation and
regularly engaged in the production of pipes and/or equipment conforming to the specified
standards. A single manufacturer shall produce all the pipe of the same type supplied for
the work. Materials and equipment shall be new, of makes and kinds specified herein, or
as indicated on the Contract Drawings, without exception
4. All the work specified in this section shall be installed in accordance with the applicable
provisions of the following codes and standard:
a. Factory Mutual Laboratories (FM)
b. Underwriter's Laboratories (UL)
c. National Fire Protection Association (NFPA)
d. Calculations: Hydraulic calculations for pipe sizing by Contractor.
B. System standards:
1. Local authority (civil defense) requirements
2. NFPA 10 Standard for portable fire extinguishers.
3. NFPA 13 Standard for the installation of sprinkler systems.
4. NFPA 14 Standard for the installation of stand pipe and hose systems.
5. NFPA 20 Standard for the Installation of Centrifugal Fire Pumps
6. NFPA 24 Standard for the installation of private fire service mains and their
appurtenances.
7. NFPA 25 Inspection, testing and maintenance of water based fire protection systems.
8. NFPA 2001 Standard on Clean Agent Fire Extinguishing Systems
9. ANSI American National Standards Institute
10. ASME American Society of Mechanical Engineers
11. ASMEB1.20.1 Pipe Threads, General Purpose
12. ASME B16.3 Malleable Iron Threaded Fittings, Classes 150 and 300
13. ASME B16.5 Steel Pipe Flanges and Flanged Fittings
14. ASME B16.9 Factory-Made Wrought Steel Buttwelding Fittings
15. ASME B16.11 Forged Steel Fittings, Socket-Welding and Threaded
16. ASME B16.18 Cast Copper Alloy Solder-Joint Pressure Fittings
17. ASME B16.20 Metallic Gaskets for Pipe Flanges: Ring Joint Spiral Wound and
Jacketed
18. ASME B16.25 Buttwelding Ends
2.3 HANGERS
A. Hanger and Support Spacing
1. Use hangers with minimum vertical adjustment.
2. Where several pipes can be installed in parallel and at the same elevation, provide multiple or
trapeze hangers.
3. Support riser piping independently of connected horizontal piping.
4. Adjust hangers to obtain the slope specified in the piping section of these specifications.
5. Space hangers for pipe as follows:
PART 3 EXECUTION
3.1 GENERAL
A. Cooperate with other trades to insure adequate space for equipment and piping placement.
B. Review plans, specifications and shop drawings of other trades to coordinate work.
C. Install in strict accordance with approved shop drawings.
D. Install all piping, valves, and connections from mains to building fire protection systems.
E. Do not begin installation until local authority approval is submitted to the Engineer.
3.2 INSTALLATION OF PIPING, VALVES AND ACCESSORIES
A. Install piping as shown on drawings.
1. Where conditions of construction require piping installation at a lower elevation,
route piping to avoid interference with work of other trades.
2. Offset, crossover and otherwise route piping to install system in available space. Not
all offsets necessarily shown.
3. Pitch all branch lines, cross mains, feed mains and risers to drainage points.
4. Provide angle drain valves at all low points
5. Plugs permitted at offsets when approved by local authority.
6. Install pressure gauges at top of each standpipe riser and elsewhere as required by
local authority.
7. Install automatic air release valve at top of each riser.
8. All pipe work shall be painted after installation.
B. Provide OS & Y valve and drain valve at base of all standpipes.
3.3 FIELD QUALITY CONTROL
A. Cleaning and Inspecting: Clean and inspect fire protection systems in accordance with
Section 221005 “Pipe & Pipe fittings: After fire piping installation has been completed and
before piping is placed into service flush entire system as required to remove foreign
substances, under pressure as specified in NFPA14. Continue flushing until water is clear.
3.4 EXTRASTOCK
A. Heads: Provide for each style and temperature rating required, furnish additional
sprinkler heads, according to the regulations or NFPA-13. and as per the bill of
quantities.
END OF SECTION
PART 2 P R O D U C T S
2.1 PIPES ANDFITTINGS
A. The material of Hot and Coldwater Pipe shall be PPR- Polypropylene.
B. The pipe shall be PN20, SDR-6. The pipe shall comply with DIN 8077 / 8078, SASO 1738 /
1739.
C. The injection molded fittings shall be PN 20, SDR-6. The fitting shall comply with the DIN
16962,SASO-ISO15874-3
D. The injection molded brass reinforced fittings shall be to PN 20, SDR-6. The fitting shall comply
with the DIN 16962, SASO-ISO 15874-3
E. The pipe shall withstand to hot water 95Deg C, 6.2 bar for every restart of 5 years. Hot water 80
Deg C for every restart of 25 years
PART 3 EXECUTION
3.1 WATERSERVICE
A. Water service shall be extended from valved outlets to main at point of tie-in. All valves, meter,
truck filling point and such other components as shown shall be installed to provide a complete
water supply system.
3.2 INSTALLATION
A. See Section 23 0500- Basic Pipe and Pipe fittings for general piping installation instructions.
Refer to the drawings for further details.
3.3 FIELD QUALITY CONTROL
A. General: Do not enclose, cover, or put into operation water distribution piping system until it has
been inspected, tested and approved by the Engineer. Expose all such work for testing that has
been covered or concealed before it has been inspected, tested and approved by the Engineer.
Notify the Engineer at least 24 hours prior to the time such inspection is to be made. Prepare
inspection and test reports for the Engineer's review.
END OF SECTION
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Pipe and Pipe Fittings, Valves, Strainers.
B. Pool Equipment.
C. Circulators and Pumps.
D. Filters.
E. Surge tanks.
F. OZONE GENERATOR (IF APPLICABLE)
G. Pool Water Treatment Systems.
H. Solar Water heating system.
I. Heating boiler.
J. Shell and tube heat exchanger.
1.2 RELATED REQUIREMENTS
A. Section 13 1100 - Swimming Pool.
B. Section 22 0513 - Common Motor Requirements for Plumbing Equipment.
C. Section 26 2717 - Equipment Wiring: Electrical characteristics and wiring connections.
1.3 REFERENCE STANDARDS
A. ASME A112.19.8M - Suction Fittings for Use in Swimming Pools, Wading Pools, Spas, and
Hot Tubs; 2007.
B. ASME A112.19.17 - Manufactured Safety vacuum Release Systems (SVRS) for
Residential and Commercial Swimming Pool, Spa, Hot Tub, and Wading Pool; 2010.
C. ASME BPVC-VIII-1 - Boiler and Pressure Vessel Code, Section VIII, Division 1 - Rules for
Construction of Pressure Vessels; 2015.
D. ASTM D1785 - Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe,
Schedules 40, 80, and 120; 2015.
E. ASTM D2467 - Standard Specification for Poly(Vinyl Chloride) (PVC) Plastic Pipe Fittings,
Schedule 80; 2006.
F. ASTM D2855 - Standard Practice for Making Solvent-Cemented Joints with Poly(Vinyl
Chloride) (PVC) Pipe and Fittings; 1996 (Reapproved 2010).
G. NSF 50 - Equipment for Swimming Pools, Spas, Hot Tubs and Other Recreational Water
Facilities; 2015.
H. UL 1081 - Swimming Pool Pumps, Filters, and Chlorinators; Current Edition, Including All
Revisions.
1.4 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings
The Contractor shall prepare shop drawings of the swimming pool and equipment based up on
the designers swimming pool package and submit copies to the Owner for review before
ordering the materials, components and equipment or commence the work.
C. Compliance with DESIGNER SWIMMING POOL PACKAGE
The Contractor shall comply with all the requirements of the following swimming pool designer
(otherwise exclusively mentioned)
1.8 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirement
B. Provide five year manufacturer warranty for water heaters.
PART 2 PRODUCTS
2.1 PIPE AND FITTINGS
A. As mentioned in swimming pool design package.
B. PVC Pipe: ASTM D1785, Schedule 80.
1. Fittings: ASTM D2467, PVC.
2. Joints: ASTM D2855, solvent weld.
C. Unions for Pipe Sizes 50 mm (2 inches) and Under: PVC for plastic piping; bronze unions
for copper pipe, soldered joints.
D. Flanges for Pipe Sizes over 50 mm (2 inches): PVC for plastic piping; bronze for copper
piping.
E. Valves: PVC plastic body and ball, double lever handle, double union with socket
ends, EPDM seals, teflon seats.
F. Butterfly Valves: Iron body, bronze disc, resilient replaceable seat for service to 180
degrees F (82 degrees C) wafer style, 10 position lever handle.
2.2 POOL PUMPS
A. As mentioned in swimming pool design package.
B. NSF Listing: Provide products that are NSF listed under NSF 50.
C. Type: UL 1081, horizontal shaft, single stage, direct connected, with motor, oil
lubricated, with casing, integral hair and lint strainer, renewable wear ring, impeller,
mechanical seal.
D. Casing: Bronze, self-primary, double volute rated for 860 kPa (125 psi) working pressure,
with pipe flanges.
E. Impeller: Bronze, closed with casing wear rings.
F. Shaft: Alloy steel with integral thrust collar and stainless steel sleeve.
G. Seal: Carbon rotating against a stationary ceramic seat.
H. Strainer: Hair and lint basket built into casing with 12:1 ratio of free area to pipe inlet area,
removable cover.
I. Pump Motors: Operate at 3500 rpm unless otherwise indicated. Refer to Section 22 0513.
J. Performance:
1. Flow capacity: (As indicated on Drawings) L/s.
2. Head: (As indicated on Drawings) kPa.
K. Electrical Characteristics:
1. (As indicated on Drawings) kW.
2. (As indicated on Drawings) Volts, three phase, 60 Hz.
2.3 CLOSE COUPLED PUMPS
A. As mentioned in swimming pool design package.
B. NSF Listing: Provide products that are NSF listed under NSF 50.
C. Type: Horizontal shaft, single stage, single or double suction, direct connected, radially or
horizontally split casing, for 860 kPa (125 psi) maximum working pressure.
D. Casing: Cast iron, with suction and discharge gage ports, renewable bronze casing
wearing rings, seal flush connections, drain plug, flanged suction and discharge.
1009DF / MISHRIFAH VILLA 22 5100 - 3 SWIMMING POOL PLUMBING
SYSTEMS
E. Impellers: Bronze, fully enclosed, keyed to motor shaft extension.
F. Shaft: Stainless steel.
G. Seals: Carbon rotating against a stationary ceramic seat, maximum continuous operating
temperature of 107 C (225 F).
H. Performance: Flow capacity and head as indicated on Drawings.
1. Flow Capacity: L/s.
2. Head: kPa.
I. Electrical Characteristics: As indicated on Drawings.
1. (As indicated) kW.
2. [] volts, three phase, 60 Hz.
2.4 POOL FITTINGS AND EQUIPMENT
A. As mentioned in swimming pool design package.
B. NSF Listing: Provide products that are NSF listed under NSF 50.
C. Main Drain:
1. Grate Style: Standard.
2. Material and Size: ABS body, 225 x 225 mm (9 x 9 inch) square frame and grate, 284
cm (44 inch) square open area, PVC outlet coupling, 50 mm (2 inch) bottom
connections with plugs.
D. Frames and Grates:
1. Shape: Round.
2. Material and Size: ABS, white color with stainless steel securing screws, 200 mm (8
inch) nominal diameter, 84 cm (13 inch) square open area.
E. Suction Drain: Complying with ASME A112.19.18M, with safety vacuum release
system complying with ASME A112.19.17.
1. Bronze frame, chrome plated grille, nominal 100 x 250 mm (4 x 10 inch) size, 161 sq
cm (25 sq in) open area, for maximum 400 L/min (105 gpm) flow at 0.46 m/s (1.5 ft/s)
velocity.
F. Wall and Floor Inlets:
1. White ABS, nominal 100 mm (4 inch) diameter, with internal spinner valve disc.
G. Gutter Drain:
1. White ABS, nominal 70 x 114 mm (2.75 x 4.5 inch), 26 sq cm (4 sq in) open area.
H. Ball Inlets:
1. ABS body and ball with stainless steel screws, with 40 mm (1-1/2 inch) water inlet,
13 mm (1/2 inch) air connection, 2.6 L/s (30 gpm) nominal flowrate.
I. Skimmers:
1. NSF approved, ABS molded body, with 250 mm (10 inch) diameter cover, 200 mm (8
inch) wide hinged weir with automatic level adjustment of 140 mm (4.5 inches),
thermoplastic strainer with 2600 cu cm (160 cu in) capacity, 3.3 L/s (55 gpm) flow
rating.
J. Hair and Lint Strainer:
1. ABS molded body with basket with 12:1 ratio of free area to pipe inlet area,
removable lexan cover.
2.5 RESIDENTIAL FILTERS
A. As mentioned in swimming pool design package.
B. NSF Listing: Provide products that are NSF listed under NSF 50.
C. Filter Media: Cartridge.
D. Tank: Fiberglass reinforced tank with mounting base.
1. Maximum Working Pressure: 345 kPa (50 psi).
2. Minimum Burst Pressure: 2070 kPa (300 psi).
3. Hydrostatic Test: 518 kPa (75 psi).
E. Element Cartridge: Reinforced polyester with gasketed molded end caps.
A. A compact cartridge combined with high airflow compressors, ultra violet lump completed
with hardware and causing.
This ozone generator should be selected at rate sufficient for pool capacity. A suitable power
supply shall be supplied from swimming pool control panel ozone generator compact plant shall
be interlocked with filter pump such a way that if the filter pump are running the ozone generator
plant will function.
END OF SECTION
3.10 IDENTIFICATION
A. All equipment, except in finished rooms, shall be identified by stenciling the title of the
equipment as taken from the plans in a position that is clearly visible from the floor. The letters
shall be made with black paint and shall be not less than 50 mm high. The titles shall be short
and concise and abbreviations may not be used. In finished rooms, equipment shall be
identified by engraved nameplates.
B. No identification shall be done until all painting required under the architectural section of these
Specifications has been accomplished.
C. Identification shall be both in English and Arabic languages on the same size.
3.11 PUTTING SYSTEMS IN OPERATION "START UP"
A. At time agreed to by the Client, put all systems into satisfactory operation.
B. Operate all systems in good working order for a period as required by the Client.
END OF SECTION
PART 1 - GENERAL
1.1 SECTIONINCLUDES
A. Single phase electric motors.
B. Three phase electric motors.
1.2 RELATED REQUIREMENTS
A. Section 26 27 17 - Equipment Wiring: Electrical characteristics and wiring connections.
B. Section 26 29 13 - Enclosed Controllers.
1.3 REFERENCE STANDARDS
A. IEEE 112 - IEEE Standard Test Procedure for Polyphase Induction Motors and Generators;
Institute of Electrical and Electronic Engineers; 2004.
B. NEMA MG 1 - Motors and Generators; National Electrical Manufacturers Association; 2011.
C. NFPA 70 - National Electrical Code; National Fire Protection Association; Most Recent Edition
Adopted by Authority Having Jurisdiction, Including All Applicable Amendments and
Supplements.
1.4 SUBMITTALS
A. See Section 01 30 00 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide wiring diagrams with electrical characteristics and connection
requirements.
C. Test Reports: Indicate test results verifying nominal efficiency and power factor for three phase
motors larger than 1/2 horsepower.
D. Manufacturer's Installation Instructions: Indicate setting, mechanical connections, lubrication,
and wiring instructions.
E. Operation Data: Include instructions for safe operating procedures.
F. Maintenance Data: Include assembly drawings, bearing data including replacement sizes, and
lubrication instructions.
1.5 QUALITYASSURANCE
A. Conform to NFPA 70.
1.6 DELIVERY, STORAGE, AND HANDLING
A.Protect motors stored on site from weather and moisture by maintaining factory covers and
suitable weather-proof covering. For extended outdoor storage, remove motors from equipment
and store separately.
1.7 WARRANTY
A. See Section 01 78 00 - Closeout Submittals, for additional warranty requirements.
PART 2 - PRODUCTS
2.1 GENERAL CONSTRUCTION ANDREQUIREMENTS
A. Electrical Service: Refer to Section 26 27 17 for required electrical characteristics.
B. Construction:
1. Open drip-proof type except where specifically noted otherwise.
2. Design for continuous operation in 40 degrees C environment.
3. Design for temperature rise in accordance with NEMA MG 1 limits for insulation class,
service factor, and motor enclosure type.
C. Visible Nameplate: Indicating motor horsepower, voltage, phase, cycles, RPM, full load amps,
1009DF / MISHRIFAH VILLA ELECTRICAL REQUIREMENTS
23 0513 - 1
FOR HVAC EQUIPMENT
locked rotor amps, frame size, manufacturer's name and model number, service factor, power
factor, efficiency.
D. WiringTerminations:
1. Provide terminal lugs to match branch circuit conductor quantities, sizes, and materials
indicated. Enclose terminal lugs in terminal box sized to NFPA 70, threaded for conduit.
2. For fractional horsepower motors where connection is made directly, provide threaded
conduit connection in end frame.
2.2 APPLICATIONS
A. Exception: Motors less than 250 watts, for intermittent service may be the equipment
manufacturer's standard and need not conform to these specifications.
B. Single phase motors for shaft mounted fans, oil burners, and centrifugal pumps: Split phase
type.
C. Single phase motors for shaft mounted fans or blowers: Permanent split capacitor type.
D. Single phase motors for fans, pumps, blowers, and air compressors: Capacitor start type.
E. Single phase motors for fans, blowers, and pumps: Capacitor start, capacitor run type.
F. Motors located in exterior locations, wet air streams downstream of sprayed coil dehumidifiers,
draw through cooling towers, air cooled condensers, humidifiers, direct drive axial fans, roll
filters, explosion proof environments, and dust collection systems: Totally enclosed type.
G. Motors located in outdoors, in wet air streams downstream of sprayed coil dehumidifiers, in
draw through cooling towers, and in humidifiers: Totally enclosed weatherproof epoxy-treated
type.
H. Motors located outdoors and in draw through cooling towers: Totally enclosed weatherproof
epoxy-sealedtype.
2.3 SINGLE PHASE POWER - SPLIT PHASE MOTORS
A. Starting Torque: Less than 150 percent of full load torque.
B. Starting Current: Up to seven times full load current.
C. Breakdown Torque: Approximately 200 percent of full load torque.
D. Drip-proof Enclosure: Class A (50 degrees C temperature rise) insulation, NEMA Service
Factor, prelubricated sleeve or ball bearings.
E. Enclosed Motors: Class A (50 degrees C temperature rise) insulation, 1.0 Service Factor,
prelubricated ball bearings.
2.4 SINGLE PHASE POWER - PERMANENT-SPLIT CAPACITOR MOTORS
A. Starting Torque: Exceeding one fourth of full load torque.
B. Starting Current: Up to six times full load current.
C. Multiple Speed: Through tapped windings.
D. Open Drip-proof or Enclosed Air Over Enclosure: Class A (50 degrees C temperature rise)
insulation, minimum 1.0 Service Factor, prelubricated sleeve or ball bearings, automatic reset
overloadprotector.
2.5 SINGLE PHASE POWER - CAPACITOR START MOTORS
A. Starting Torque: Three times full load torque.
B. Starting Current: Less than five times full load current.
C. Pull-up Torque: Up to 350 percent of full load torque.
D. Breakdown Torque: Approximately 250 percent of full load torque.
E. Motors: Capacitor in series with starting winding; provide capacitor-start/capacitor-run motors
with two capacitors in parallel with run capacitor remaining in circuit at operating speeds.
F. Drip-proof Enclosure: Class A (50 degrees C temperature rise) insulation, NEMA Service
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Identification markers shall be provided on all piping & duct works including equipment & all
system components.
1.2 SUBMITTALS
A. Submit samples of all nameplates, valve tags, pile markers, duct stencils and application
sample, valve schedules, equipment schedules, etc. for review by the Engineer.
B. Submit nomenclature system for all valves, equipment, etc. for review.
C. Submit copy of all valve schedules, piping lists, and equipment list with Operating and
Maintenance Manuals.
1.3 COMPLIANCE
A. Proper identification for system and equipment where required by codes, regulations,
authority’s requirements.
PART 2 PRODUCTS
2.1 MANUFACTURER’SIDENTIFICATION
A. Manufacturer's nameplate, catalog numbers, rating identification, name or trademark shall be
permanently affixed with screws or riveted to all equipment and material furnished under this
specification.
B. Identify model number, size, capacity, electrical characteristics, serial number.
C. Leave nameplates clean, legible and with unobstructed view.
2.2 APPARATUS IDENTIFICATION
A. Equipment nameplates shall be 50 mm high, 1.5 mm thick, three layer black laminated plastic
plates with 20 mm inch high white lettering engraved through the black layer. Edges shall be
beveled.
B. Equipment identification nameplate shall be securely attached to each piece of
equipment.
C. Secure nameplate to each starter, switch, relay, transformer, etc. that controls the equipment.
D. Nameplates to bear notations corresponding to notations on operating instructions and as built
Drawings.
2.3 PIPE IDENTIFICATION
A. Provide directional arrows on circulating systems separate from and adjacent to each
identification. Identification in conformance with ANSI 13.1 Scheme of Identification of Piping
Systems (OSHA).
B. Color code all pipes & indentify with suitable identification
C. Plastic Markers: Snap-on laminated plastic protected by clear acrylic coating, “Setmark” by
Seton Name Plate Corp. or approved equal. Each marker must show accepted color-coded
background, proper color of legend in relation to background color, accepted legend letter size,
accepted marker length.
D. 50 mm letter size for pipe or insulation 75 mm or larger. 25 mm letter size for pipe or insulation
65 mm or smaller.
E. Name of contents and directional arrows shall be placed at points of entrance and exit from
mechanical room, adjacent to each valve, on each riser, at each tee fitting, at points of entrance
and exit from building, at least once in each room, and intervals no longer than 6 m on long pipe
A. Duct markers shall be stenciled on to insulation of duct with legend and flow arrow.
Letters shall be 50 mm high. Black lettering shall be on white background.
A. The contractor shall provide valve tags for all valves attached to handwheel or stem of each
control and line shutoff valve, with heavy brass "S" hook, color-coded plastic laminate or
brass identification tag. Engraved laminate tags shall be at least 25 mm in diameter with
numerals at least 3 mm thick.
B. Identify all fire service valves with above specified tags with "FIRE MAIN - DO NOT CLOSE"
with white letters on red background.
A. The contractor shall provide typewritten schedules giving numbers, service and locations, and
notations of normal position and future position of all services.
2.7 CONTROLS
A. Provide engraved plastic laminate identification plate showing function of switches and
manually operable controls, including switches furnished under another Division. Provide
point numbers on all control system components corresponding to programmed and
second drawing point numbers.
3.1 PREPARATION
A. Degrease and clean surfaces to receive adhesive for identification materials of any
materials that will prevent paint to marker adhesion. Equipment Identification
A. Equipment Identification
1. Properly identify each piece of equipment and controls pertaining thereto by
nameplates mounted on equipment and controls using round head brass machine
screws or pop rivets. Cardholders in any form not acceptable.
B. Apply with sufficient adhesive to ensure permanent adhesion and seal with clear lacquer.
C. Place warning signs on machines driven by electric motors which are controlled by fully
automatic starters.
D. Identify air handling units, fans and pumps with area served.
E. Small devices, such as inline pumps, may be identified with tags.
F. Identify control panels and major control components outside panels with plastic
nameplates.
G. Identify equipment out of view behind access doors, in unfinished rooms on the face of the
access door.
3.3 DUCTWORK IDENTIFICATION
A. Provide identification of supply air, return air, outside air, exhaust air ducts and all toilet
exhaust, general exhaust by means of stenciled lettering identifying contents and direction of
flow.
B. Ducts coming out of shaft at each floor shall be stenciled, at each junction or branch take- off,
at least once in each room where ducts are concealed, at each access panel, in equipment
rooms and at intervals not longer than 6 m. Stencil shall clearly identify duct service (S for
supply, R for return, X for exhaust), area served by branch, and arrow indicating direction of
flow.
C. Apply to clean surfaces free of dust, grease, oil or any other material which will prevent paint
adhesion.
3.4 PIPING IDENTIFICATION
A. Apply markings after all cleaning and painting of piping and insulation is completed.
B. Location for Pipe Identification:
1. Within 300 mm of each valve, fitting, thermometer or gauge (except on plumbing fixture).
2. At each branch and riser takeoff.
3. At each pipe passage through wall, floor and ceiling construction.
4. On all horizontal runs spaced 6 m maximum but not less than once in each room at
entrance and exit of each concealed space.
5. Where capped piping is provided for future connections, provide legible and durable metal
tags indicating symbol identification.
6. At wall and ceiling access panels.
7. In addition to foregoing identification for piping, identify fire protection piping with 25 mm
wide red painted band, completely encircling pipe adjacent to symbol identifications.
A. Valve Identification tags shall have the following abbreviations plus valve number.
Service Abbreviation
Domestic Cold Water DCWS
Domestic Hot Water Supply DHWS
Sprinkler Sprinkler
Irrigation Water Supply IWS
A. Where acceptable by the Engineer, provide color-coded ceiling tacks to locate coils, fire
dampers, valves, control devices, etc. or other approved label on each T-bar suspended
ceiling push-out tile. Locate in corner of panel closest to equipment.
A. Contractor shall include in the contract to procure and handover the following minimum
quantity of the spare parts as per the list and / or that recommended by the manufacturer.
These spare parts shall be brand new and similar to the equipment / material being
installed.
1. Pipe Identification
Plastic Marker: 25 Nos.
END OF SECTION
1 General
a. Execute work of this section only by skilled tradesmen regularly
employed in the manufacture and installation of sheet metal ductwork
and components listed.
b. Equipment supplied under this contract shall be new and selected
specifically for this project by manufacturers having at least five years
experience in the production of specific items or equipment supplied.
c. Regulatory Requirements.
b. Sheet Metal and Air Conditioning Contractors National Association Incorporated manuals
(SMACNA) except where details or notes on drawings indicate otherwise:
2.3 DUCTWORK
A. Duct work Material
1. All ductwork except in kitchens and laundry extract systems shall be G-90 grade
manufactured from strip mill, cold rolled sheet, continuously hot dip galvanized in
accordance with ASTM A527 or BS 2989 grade Z2.
2. All flanges and stiffeners used in the construction of galvanized mild steel ductwork shall
be galvanized steel section.
3. Where flexible ductwork is used, it shall conform to ductwork of the type manufactured in
accordance with BS 1470 aluminum strip corrugated and spirally wound with double lock
seam.
4. The length of flexible ductwork shall not exceed 1.5 m per section and shall be supported
as recommended by the manufacturer.
5. Kitchen extract ductwork shall be air and watertight welded construction manufactured
from 16 g stainless steel sheets in accordance with BS 1449 (or American equivalent), Part
1 Grade CR4 GP.
Provide access door per drawing. In any case the distance between access door
shall not exceed 30m.
6. Laundry and kitchen dishwasher extract duct work shall be welded stainless steel
construction in accordance with SMACNA standards.
A. Testing for ductwork leakage may be performed for separate sections of the system
or after the complete system is installed.
B. Testing shall be performed in accordance with SMACNA Leak Testing Criteria and
Procedures and in the following steps:
1. Pressurize ductwork section or the complete ductwork system to the design static
pressure and listen for noisy leaks.
2. Depressurize the system and reseal all the leaks thus found.
3. Pressurize the system to 1.5 times the design static pressure. The total
allowable leakage shall not exceed 1% of the total system air flow rate.
C. Balancing and adjusting of air distributing and exhausting system shall be performed
in accordance with the ASHRAE and AMCA standards.
PART 1 - GENERAL
1.1 DESCRIPTION
A. General:
1. Furnish all labour, materials, tools equipment and services for air filters in accordance with
provisions of contract documents.
2. Completely coordinate with work of other trades.
3. Although such work is not specifically indicated, furnish and install all supplementary or
miscellaneous items, appurtenances and devices incidental to or necessary for a sound,
secure and complete installation.
4. See Division 1, for General Requirements.
5. Work included
a. Panel filters.
b. High efficiency bag filters.
c. Permanent Washable Filters.
d. Sand trap louvers.
B. Related work specified elsewhere:
1. Section 238219 Fan Coil Units
2. Section 233113 Ductworks, and Duct Accessories.
3. Section 237413 Air Handling Units.
1.2 QUALITY ASSURANCE
A. Filter media shall be U/L listed, Class 1 or Class II, as approved by the Engineer.
B. Filter components assembled to form filter banks shall be products of same manufacturer.
1.3 MAINTENANCE
A. Provide spare parts in accord with section 01730 minimum 15% extra stock of each type and
size.
1.4 SUBMITTAL
A. Refer General-Basic Mechanical Requirements; 1.03 Submittals section.
PART 2 - PRODUCTS
2.1 FRAMES
A. Fabricate filter frames and supporting structures of galvanized steel or extruded aluminum with
necessary gasketing between frames and walls. Provide holding frames 1.5 mm, "T" section
construction.
2.2 PANEL FILTERS
A. Media: 50 mm thick fibrous glass blanket, factory sprayed with flameproof, non-drip, non-
volatile adhesive.
B. Holding frames: 1.50 mm minimum galvanized frame with expanded metal grid on air leaving
side and steel rod grid on air entering side, hinged with pull and retaining handles.
C. Efficiency 30% based on ASHRAE 62-76 test method.
D. Initial resistance 6 mm WG based on 2.5 M/s face velocity.
2.3 HIGH EFFICIENCY BAG FILTERS
A. Media: Reinforced glass fiber performed into series of pockets and bonded to header. Provide
approximately one square meter of media per 100 liters/second capacity.
B. Holding Frames: gauge 1.50 mm galvanized steel with sealing grooves and gaskets, locking
clips, and provision for front mounted panel prefilter and side removal of filter media.
C. Efficiency: 80-85 % average based on ASHRAE 62-76 test method.
PART 1 - GENERAL
The Air Conditioning Contractor shall supply, deliver, install, set to work and commission the systems and
equipment as detailed in this section of the specification, as shown on the Tender drawings and listed in the
Schedule at the end of this section.
The condensing unit shall have special design suitable for high ambient climatic conditions.
Project cooling shall be covered by using the Variable Refrigerant Volume VRF IV R410A systems with All
Inverter Heat Pump to provide cooling to the zones as required.
2. SYSTEM FEATURES
2.1 General
VRF system shall be control volume flow of refrigerant through the indoor units, by means of
an electronic expansion valve fitted in each indoor unit. It shall be having the following
features:
1) VRF indoor units shall be having inverter-controlled fan motors to allow the system to
accurately respond to head pressure control requirements.
2) The system must be able to vary evaporating and condensing temperatures based on
ambient temperatures and/or load to ensure optimum seasonal efficiency and comfort. Or
alternatively fix the evaporating temperature for continual very high off coil temperatures.
3) Part load conditions must be met by a combination of change of compressor speed and
change in refrigerant temperature at a suitable reaction speed which is set at the condenser
on commissioning.
4) VRF Indoor systems shall be having a minimum of 50 step inverter fan control to allow the
system to accurately respond to head pressure control requirements.
5) Inverter Scroll compressor shall respond to control frequencies from 60 to 402Hz to provide
stepless capacity control.
6) VRF outdoor unit shall having All condenser fans capable of at least 78 Pascal’s of external
static pressure.
7) The refrigerant must be distributed by the use of a refrigerant networking system (Refnet) to
ensure low pipe pressure losses as well as keeping the require pipe work installation space
and material used to a minimum compared to other parallel pipe work systems.
8) The system shall be having the ability to sustain refrigerant piping lengths of up to 165m
(equivalent piping length has to be at least 190 meters) with a level difference of 90m
between fan coil units and condensing unit, providing connection ratios are suitable. The
system shall be capable of having up to 1000m of refrigerant pipe work installed. The system
shall be capable of having up to 90m from the first refnet to the furthest indoor unit, providing
manufacturer system design guidelines are used. The elevation between the highest and
lowest indoor units must be able to be extended up to 30 meters.
9) The system must be able to adjust capacity depending on the load requirements and outside
temperature to ensure that the efficiency is optimised, and responsiveness maintained.
10) The system has to smoothly operate at ambient temperatures ranging at least from -5°CDB
to +55°CDB in cooling. The system operation must be possible outside above-mentioned
limits, unless safety devices are activated.
11) The system shall be operating with Refrigerant R410A, being a zeotropic blend constituted of
a maximum of two different refrigerants providing a maximum temperature glide of less than
0.17K to avoid fractionation problems.
1009DF / MISHRIFAH VILLA 23 6213 - 3 VRF AIR CONDITIONING SYSTEM
12) The system shall be having the capability to automatically charge the correct volume of refrigerant
during commissioning and, if automatic charging has been utilised, the system must also have the
ability to self-diagnose refrigerant containment for maintenance and service purposes. The unit shall
be capable of carrying out automatically the calculated required additional refrigerant charge
necessary to operate the system within its optimum efficiency. This cycle shall be completely
automatic and provide a warning to the service technician to indicate when charging has been
completed or the charging cylinder is empty. The refrigerant cycle shall not rely upon float valves,
level switches or weighed input of the refrigerant. The calculated refrigerant charge shall be retained
within the memory of the outdoor PCB as a reference for a refrigerant containment check which can
be carried out as required to verify the correct refrigerant charge remains within the system. The
automatic refrigerant charging and containment check facilities shall be capable of being used at any
time during the life of the system for any alterations or service operations which may be required.
13) In the event of compressor failure, the system shall be allowed emergency operation of its
other compressors in order to maintain 8 hours of interim capacity whist spares are sourced.
14) Systems containing multiple outdoor units shall sequentially cycle its start-up sequence to
ensure equalised compressor operation to extend operating life and reduce lifecycle cost.
15) In the outdoors units it is preferable to having a 7-segment decimal display, displaying
detailed error codes, stage of the start-up procedure as well as function and operating data
of the system. For the commissioning of a system and in order to properly set all necessary
data and values for the optimum operation of it, it is recommended for the starting-up the use
of special software provided by the manufacturer of the system. The establishing of the
values and the programming should be possible even offline.
16) The system shall have the capability to monitor and log data in a critical memory which shall
be store and provide 5 minutes of real time operational data prior to any system failure. This
information provides the system with “Black Box” data recording capability which can be
used by a qualified service technician to perform efficient and precise interrogation.
The equipment manufacturer must be fully certified and registered to comply in the areas of
CE, ISO9001 and ISO14001 and also must possess the BES 6001 certificate to
demonstrate responsible sourcing throughout the supply chain by proving product
stewardship against social, economic and environmental sustainability criteria. The
equipment manufacturer shall be responsible for the manufacture of the compressor,
refrigerant oil and refrigerant used within the system to maintain integrity of design and
optimise efficiency and reliability of equipment.
All equipment shall be run tested in accordance with the following procedures prior to leaving place of
manufacture:
1) A choke test carried out on the refrigerant piping to detect obstacles.
2) The pipework shall be tested to 38bar.
3) Electronic leak testing shall be carried out to ensure maximum system refrigerant containment.
4) System vacuum test to 2 Torr
5) Refrigerant test to within 0.3%
6) Electrical tests shall include flash testing at 1440V AC to ensure that current leaks above 5mA are
detected, megger test at 500V DC to ensure resistance levels are above 10 mega Ohm and earth
continuity tests.
7) The system shall be tested by a recognised 3rd party as per AHRI 1230:2010 and shall meet or exceed
relevant Local Standards like ESMA, Estidama, SASO, & MEW etc.
1- The outdoor unit must be suitable for outdoor installation. The shell/casing of the unit shall be made
of enameled stainless-steel sheet, with polyester thermal powder coating (minimum 70μ) for high
protection in environment near the seaside. The units shall be air-cooled type incorporating heat
exchanger coils manufactured from copper tubes and aluminium fins. The air-cooled heat exchanger
of the outdoor unit shall be having to having undergone appropriate treatment for protection and
long-life efficient operation against atmospheric corrosion. Specifically, the aluminium fins shall be
coated with a layer of acrylic resin and on top covered with a hydrophilic film or any other material
which shall be provide minimum 1000 hrs of Salt spray protection meeting JIS/Equivalent Standards
e to acid rain and salt corrosion. The bottom of the unit shall be having a sheet of stainless steel for
protection against oxidation.
2- The outdoor units shall be able to deliver cooling capacities ranging from 8HP (22,4kW) and up to
16HP (45,0kW) in a single shell/housing. A combination of two or three outdoor units shall be
possible in order to having systems with cooling capacity reaching 48 HP (135,0 kW). No limitations
on possible combinations shall be accepted while the most appropriate one shall be decided
primarily for operating at the best possible seasonal efficiency. Aforementioned cooling capacities
shall be clearly mentioned in the manufacturer’s official technical documentation and literature and
shall be calculated, based on the following conditions:
Indoor room air temperature: 27oCDB / 19oCWB.
Ambient air temperature: 35oCDB.
Equivalent piping length: 5,0m.
Height difference: 0m.
3- Compressors: In the outdoor unit there shall be either one or two compressors in separate shells, so
in case one fails it shall be not be necessary to replace both. The outdoor units shall be having axial
fan(s) DC inverter driven, air-cooled heat exchanger, piping, wiring and automation, factory-installed
electronic expansion valves, oil separator, accumulator at the suction side of the compressor, high &
low pressure sensors, protection thermostats, fuses, protection against overcurrent, protection for
overloading of the inverter, liquid and gas stop valves and solenoid valves, timers and all the
necessary sensors and protection equipment to ensure continuous, safe and smooth operation.
4- The outdoor unit - and consequently the whole system - shall be keep on operating even if one
compressor is turned off (emergency operation). In case of a multi-outdoor unit system it shall be
possible to isolate one module, while the rest of the system shall be continuing to operate even if
delivering reduced capacity. This ensures continuous air conditioning of the premises, until the cause
of the issue seizes to exist.
5- Outdoor units should have a specific function and appropriate devices to prevent refrigerant in liquid
phase to return to the compressor. This ensures the specified density of the oil and therefore the
adequate lubrication of the compressor. This function increases the efficiency of the system and
extends the lifespan of the compressor.
6- Compressors shall be hermetically closed scroll type with integrated motor and sound absorbing
jacket. They shall be having a DC inverter driven motor and be able to continuously change the
frequency, resulting in a change to the volumetric refrigerant flow from the compressor, in order to
accurately and fast respond to the required load. The change in frequency should be done
incrementally, but in enough steps so the change of delivered capacity can be approximated as
linear. The minimum number of capacity steps shall be no less than 100.
7- The compressors shall be equipped with the technology, providing the minimization or elimination of
1009DF / MISHRIFAH VILLA 23 6213 - 5 VRF AIR CONDITIONING SYSTEM
refrigerant backflow within the scroll structure al low load conditions, thus minimizing the losses and
improving the overall seasonal efficiency. This shall be done by means of refrigerant bypass port,
which allows high pressure refrigerant to go partially to pressure equalization chamber on the back
side of movable scroll, thus compensating the scroll compressing force loss at low load conditions.
8- The motor windings shall be specially constructed, in order to achieve the safe and smooth operation
to avoid hazards due to the continuously changing of frequency and voltage. The compressors shall
be protected by an electrical crankcase heater to prevent oil condensation at low ambient
temperatures.
9- The oil supply in the compressor shall be on the high-pressure side, ensuring optimum lubrication of
all moving parts. Therefor a separate lubrication system shall be not be required for the moving parts
of the compressor, since the oil in the center of the crankshaft shall be transported across the
surface of the rotating parts from the center to the perimeter. This optimizes the performance of the
compressor and minimizes stress and wear, extending its lifetime. The compressors’ motors shall
have a cooling system using compressed gas, to avoid sudden changes in temperature resulting in
significant stresses on winding and bearings.
10- Compressors shall be altered the rotation speed linearly and consume energy in accordance with
cooling and heating loads, ensuring operational autonomy and independent temperature control in
each room. The two DC inverter compressors shall be able to vary their speed separately controlling
the volumetric flow more accurately, with lower power consumption, resulting in higher efficiencies
at all loads and connection ratios.
11- For protecting the compressor from frequent start-stops, there shall be an appropriate timer.
12- Oil recovery system: The oil recovery from the piping network and the indoor units has to be
achieved by the use of a microprocessor. The oil shall be recovered at least once every eight hours,
via a special oil recovery function, ensuring smooth operation of compressors.
13- Fans: The fan motor(s) of the outdoor unit shall be DC inverter to further increase energy savings, to
more accurately adjust the fan speed and reduce noise. The setting of the fan speed shall be result in
precise control of system’s performance in accordance with the requirements of indoor and ambient
conditions. The DC inverter fan motors shall be automatically adjusting the rotation speed - thus the
air flow - and having at least 120 different steps. Each fan shall be separately controlled in order to
further increase the accuracy of system control.
14- The impeller shall be made of plastic and with a special configuration to achieve greater air flow with
low noise level. Outdoor units shall be having a protective cover over the fan to guard against
accidents and to avoid foreign objects entering the units. It shall be special design and construction
to minimize the external static pressure drop of the fan.
15- Fans shall be having a high external static pressure setting in order to reach at least 78 Pa. This shall
allow the installation / connection of duct(s) for greater flexibility during installation. In case of an
outdoor unit with two fans, then each fan shall be having the ability to be separately ducted.
16- System control and functions: All indoor units to be connected to a system must be independently
controlled depending on the requirements of each room. The indoor units shall be connected to the
outdoor unit via the wiring and refrigeration piping network. The wiring cables are not required to be
shielded, but the installer shall be having to ensure that it shall be not be closer than 5cm to power
cables.
17- The system’s operation must be based on pressure sensors and thermostats, which via a specially
designed integrated circuit shall be control the frequency of the compressor motor (inverter) by
1009DF / MISHRIFAH VILLA 23 6213 - 6 VRF AIR CONDITIONING SYSTEM
varying the compressor’s speed resulting in changes to the refrigerant’s volume and temperature.
The result, combined with ambient temperature and building’s load requirements, shall be always
deliver the necessary capacity while maintaining optimum efficiency.
18- The system shall be having the ability to perform capacity control from down to 9% and up to 100%
of the nominal capacity. The capacity delivered by the system should match the building’s load. This
way the system shall be consume the minimum required energy, at the highest possible efficiency.
19- The room temperature for each room must be controlled by a microprocessor, where processing of
the various parameters and the corrective settings are proportional and according to the integral -
differential method of regulation.
20- Parameters; set temperature and return air temperature for the differential control, gas and liquid
refrigerant temperatures for controlling the superheat
22- Variable Refrigerant Temperature: The system has to automatically adjust the evaporating and the
condensing temperature in order to always deliver the exact capacity for the building’s load, with the
highest possible efficiency. In parallel, it must be possible to also set a target refrigerant
temperature. This way the delivered capacity shall be ambient temperature dependent thus having
very high seasonal efficiency. In addition, it must be possible to operate the system with at least
three different set refrigerant temperatures. With higher evaporating temperatures the system shall
be able to deliver mostly or even only sensible capacity. The adjustment of the evaporating and the
condensing temperature shall be easily field set, without any optional accessories prior or after the
commissioning of the system.
23- Ambient temperature dependent variation of the refrigerant temperature – evaporating and/or
condensing is required, and results in even greater energy savings and optimal seasonal efficiencies,
as per latest directives of the European Union or equivalent local standards.
24- It should also be possible to fix the evaporating temperature at different values in order to having
the system operate with different Sensible Heat Factors. Relative humidity levels can be maintained
within the comfort zone according to international standards and guidelines.
25- Only Humidity sensor in the outdoor unit type system is not acceptable as it is shown drop in
efficiency. System supplied shall not have humidity sensors to avoid mix ups.
26- Refer to schedules for equipment details and provide computerized selection on software based on
actual pipe run for consultant approval
The fan motor shall be DC inverter motor. The unit static pressure shall be automatically adjustable from the
unit wired remote controller (service mode). Unit height Shall not exceed 250mm.
The sound pressure level of these indoor units shall in no case exceed 45 dbA at high fan speed mode when
measured 1.5m distance from the unit.
A factory installed condensate lift pump shall be provided within the unit and shall be capable of discharging
1009DF / MISHRIFAH VILLA 23 6213 - 7 VRF AIR CONDITIONING SYSTEM
above the drain outlet.
The unit casing shall be manufactured from galvanised steel plate and shall be insulated at all applicable
panels. The use of a polystyrene only construction for the outer casing will not be acceptable. Facility shall
be provided for duct connection for introduction of fresh air to the unit and branch ductwork from the unit.
The heat exchanger coils shall be manufactured from copper tubes and aluminium fins and have 2 to 3 rows
of cooling coil. It shall have electronic expansion valve to control refrigerant flow rate in response to the
load variation in the conditioned space. The expansion valve shall be controlled by an integral computerised
PID control system to maintain correct room temperature.
The return air to the unit shall be through the back of the unit as standard however shall have bottom return
option
The unit casing shall be manufactured from galvanised steel plate and shall insulated at all applicable panels.
The use of a polystyrene only construction for the outer casing will not be acceptable. Facility shall be
provided for duct connection for introduction of fresh air to the unit and branch ductwork from the unit. The
return air to the unit shall be through the back of the unit as standard.
The fan shall be of the dual suction multi blade type, statically and dynamically balanced to ensure low noise
and vibration free operation.
Return air filter and filter frame shall be field supplied by others, however shall be available as an option.
The heat exchanger coils shall be manufactured from copper tubes and aluminum fins. It shall have
electronic expansion valve to control refrigerant flow rate in response to the load variation in the
conditioned space. The expansion valve shall be controlled by an integral computerized PID control system
to maintain correct room temperature.
The condensate shall be drained from the unit using suitable tube and run directly to a main drainage point.
A drain trap shall be fitted to compensate for negative air pressure. Drain Pump shall be available as an
option.
The unit casing shall be manufactured from galvanised steel plate and shall be insulated at all applicable
panels. The use of a polystyrene only construction for the outer casing will not be acceptable. Suitable
provision shall be available for duct connection for introduction of fresh air to the unit and branch ductwork
from the unit.
The fan shall be of the dual suction multi blade type, statically and dynamically balanced to ensure low noise
and vibration free operation.
The heat exchanger coils shall be manufactured from copper tubes and aluminium fins. It shall have
electronic expansion valve to control refrigerant flow rate in response to the load variation in the
conditioned space. The expansion valve shall be controlled by an integral computerised PID control system
to maintain the designed room temperature.
A dedicated round flow decoration panel shall be provided for each unit. The decoration panel shall
incorporate the return air grille and supply air louvers.
The air filters shall be incorporated within the unit and shall be mold resistant washable resin net type.
The unit casing shall be manufactured from Heat resistant plastic resin. The casing color shall be Fresh
White.
The fan shall be of the dual suction multi blade type, statically and dynamically balanced to ensure low noise
and vibration free operation. Fan motor shall be higher efficiency DC Motor.
The return air shall be through the bottom grille while the supply air shall be through the louver situated at
the front of the unit. A facility shall be provided to automatically swing the supply air louvers or lock them at
five adjustable settings and flaps shall be able to close completely when unit is switched off.
The heat exchanger coils shall be manufactured from copper tubes and aluminum fins. It shall have
electronic expansion valve to control refrigerant flow rate in response to the load variation in the
conditioned space. The expansion valve shall be controlled by an integral computerised PID control system
to maintain correct room temperature.
The condensate shall be drained from the unit using suitable tube and run directly to a main drainage point.
The air filters shall be incorporated within the unit and shall be washable resin net type.
The unit casing shall be manufactured from heat resistant plastic. The casing colour shall be Fresh White.
The back plate and the support frames shall be manufactured from galvanised steel plate.
The fan shall be multi blade cross flow type, statically and dynamically balanced to ensure low noise and
vibration free operation.
The heat exchanger coils will be manufactured from copper tubes and aluminium fins. It shall have
electronic expansion valve to control refrigerant flow rate in response to the load variation in the
conditioned space. The expansion valve shall be controlled by an integral computerised PID control system
to maintain correct room temperature.
The condensate shall be drained from the unit using suitable tube and run directly to a main drainage point.
The air filters shall be incorporated within the unit and shall be washable resin net type. Drain pump shall be
available as an option.
Proprietary REFNET joints and headers, manufactured by VRF / VRF equipment supplier
only, shall be used throughout the installation to reduce imbalance in refrigerant flow
between indoor units. Size shall be suggested and approved by the VRF / VRF
manufacturer.
Mains Power Wiring shall be the responsibility of the Electrical Contractor who shall provide
3-phase 400V main isolators mounted on the VRF / VRF Condensing Units and a 1-phase
230V fused spur located within 1m of fan coil units. Inverter PCB shall be cooled by
Refrigerant and air-cooled PCBs are not acceptable. All solid-state components shall be
able to withstand 105 C temperature.
Controls wiring shall be the responsibility of the Air Conditioning Contractor who shall provide
system control wiring in accordance with the manufacturer’s recommendations.
Local control will be provided via remote controllers mounted within the occupied space,
providing individual start/stop, run/fail indication, set point adjustment and fault code
diagnosis. Time Clock control shall be flexible with seven independent day settings, five
actions per day of ON or OFF which can be configured in any desired pattern. The
controller shall contain an internal temperature sensor, which can be used for system
control or Fabric Protection control. Fabric protection shall be configurable with a start
temperature of between 5 – 150C and adjustable differential for the off temperature of
between 1 – 50C higher. The controller shall have the ability to be locked down without the
need of any other external adapter PCB or Centralised device to leave only the following
functions operable:
LEVEL 1 ACCESS
• All buttons operational
LEVEL 2 ACCESSES
• On/off button
• schedule timer on/off button
• Temperature adjust button
• Operation adjust button
• Fan speed button
• Air direction adjust button
LEVEL 3 ACCESSES
• On/off button
• Temperature adjust button
• Fan speed button
Intelligent Touch Manager System shall be provided with a true touch active screen with
colour Liquid Crystal Display with Icon displays to provide simple user-friendly operation:
Controller Display
On/Off selection
Set Point adjustment (Range 16-32oC)
Fan speed adjustment
Heat/cool/auto changeover mode selection
Frost protection set point
Timer settings
Holiday period settings
Priority settings for restriction of local access for start/stop, heat/cool mode and set point adjustment range
limitation
Reset ability for filter maintenance warnings
Start/stop operation, set point control, cool/heat mode selection, air volume setting, air flow
direction setting and enabling/disabling operation of the remote controllers by group, zone or
collectively.
Monitoring of operation status of the indoor units, filter change indication and error code of the
group or the zone.
Comprehensive schedule set up to start/stop the air conditioning systems. This can be set for year,
month, weekday, hour and minute. This will enable normal day-to-day time clock functions as well as
yearly holiday set up. Up to 5 settings can be configured up to 13 months in advance and allocated to
various groups/zones.
Volt free forced stop input possible such as fire shut down.
Password protection for zone, group operation and setup screen for various functions.
The controller shall have wide touch screen control colour display and can be wired by a non-polar 2-
wire transmission cable to a distance of 1 km away from the outdoor units.
Integration device will be provided to enable communication between the VRF / VRF system,
and the third party supplied BMS.
Gateway HUB
kWh-meter
BMS
DIII [F1/F2]
VRF /
VRF
Outline of Functions
The device enables interfacing between VRF / VRF system and central monitoring board.
Data of up to 256 groups of air-conditioners are controllable by the BACnet Gateway
Air conditioners are operable, and the state can be monitored from the central monitoring
board by BACnet communication.
Main Functions
The device should monitor and control air conditioners from a maximum of 256 groups, on a
unit by unit basis. Major features are listed below:
The copper tubing shall be of a suitable thickness to be capable of withstanding pressure test
as detailed in the current revision of BS/EN378.
The copper tubing shall be suitably selected with a wall thickness capable of withstanding the
system operating pressures on Refrigerant R410A, all as described within the outdoor
unit’s installation manual.
Pipework shall be supported and not secured at regular intervals not exceeding 1.5m.
Preferably to create a method of adequate support ant containment, piping should be laid
on suitably supported galvanised cable tray, insulated and held in position with plastic
coated steel banding. Due care and attention shall be taken at all times to allow pipework
to freely expand and contract naturally.
2.9 Insulation
All Refrigerant pipework to be insulated with slip-on close cell elastomeric pipe insulation, with
a fire performance rating class “O” of the 1985 Building Regulations, having a wall
thickness of not less than 13mm. After commissioning, all joints to be properly sealed to
provide and adequate seal and clearly marked for ease of identification.
Where required external insulation shall be protected with a suitable enclosure to encase the
piping, as to reduce the effects of Bird, Vermin and Environmental attack.
PART 3 EXECUTION
Pipework shall be installed by a Supplier’s Approved Installer in accordance with the current
revision of BS/EN378 and in accordance with Supplier’s Design and Installation
Instructions and the unit’s installation manual.
Brazing shall be carried out by skilled operatives, in accordance with the HVCA Code of
Practice – Brazing and Bronze Welding of Copper Pipe and Sheet.
During brazing, oxygen free nitrogen shall be passed through the pipework to displace oxygen
and ensure that oxidisation does not occur.
Appropriate refrigerant tools shall be utilised at all times. The use of hacksaw or any tool that
creates filings is prohibited.
Pipework shall remain capped at all times other than when actually being installed to prevent
the ingress of moisture and contaminants.
Condensate pipework shall be installed by the supplier’s approved Installer in accordance with
supplier’s Design and Installation Instructions and the unit’s installation manual.
The entire refrigeration system shall be pressurised with Nitrogen to 38 bar for a period of
24hours.
Leak testing shall be carried out with a calibrated electronic leak detector, or similar if the
system fails to hold pressure within testing period.
Upon completion of pressure test the pressure shall be released and vacuum pump installed
on the system to remove air and moisture from the system. The system shall be
evacuated to –101.1kPa (-758mmHg, 2 torr) and held for a period of 2 hours with the
vacuum pump switched off.
Refrigerant should be charged to the liquid pipe in its liquid state to ensure that the refrigerant
composition is assured. The refrigerant charge shall be calculated to the system
requirements and in accordance with Supplier’s Design and Installation Instruction
booklet.
END OF SECTION
PART 1 GENERAL
1.1 GENERAL
A. Supply and install as indicated in the schedule of equipment, Air Handling Units (AHUs), each
capable of the duty as mentioned in the schedule of equipment. The space available for the unit
to be physically verified at the site and dimensions of the units shall be selected to fit into the
spaces available. Where necessary the units may be built on site, subject to acceptance of the
finished units for warranty purposes by the original supplier and his local agent.
B. The units shall be double skin construction, draw-thru type comprising of various sections such as
filter section, cooling coil and fan section as per the details shown either in the drawings or
specified in the schedule of equipment.
C. Manufacturer / manufacturer’s representative should carry enough stock of spares including fans,
motors, drives, filters, hardwares (locks, hinges etc.,) locally to minimize breakdown response
time. The stock of spares shall be witnessed by Client / Consultant for necessary approval.
A. The equipment manufacturer shall strictly adhere to following standards & specification:
1. ISO 9001:2008 certification for Quality Management Systems of the manufacturing facility
required.
4. Eurovent certification.
5. Model boxes to be Eurovent certified with both Polyurethane foam and Rockwool insulation
to demonstrate the flexibility of the manufacturer meeting customer requirement.
6. Eurovent certified selection software should have the flexibility of customizing the unit
dimensions meeting the plant requirements.
7. The equipment manufacturer shall submit the mechanical performance report certified by
Eurovent for the following characteristics.
B. The thermal transmittance and thermal bridge factor shall be relaxed to T3 and TB3 respectively
for re-circulated Air Handling Units installed in conditioned plant rooms.
PART 2 PRODUCTS
A. The unit casings shall be of double skinned panels not less than 50mm thickness. Casing shall be
assembled with self- supporting modular panel elements with an integrated base frame made of
zincated steel and sections along upper sides of the units. Suitable for moist and salty outdoor
coordination of Jeddah.
B. The frame work shall be of anodized pentapost construction extruded aluminum, thermal break
construction using polyamide profiles for thermal bridging (thermal bridging using gasket not
acceptable).
C. Sheet metal thickness shall be not less than 1.0 mm thick for both inner and outer skin for panels
having polyurethane foam insulation. Alternatively, sheet metal thickness shall not be less than
1.2mm thick for both inner and outer skin for panels having rock wool insulation of 60 Kg/cu. m
density. The inner and outer skin shall be pre-painted, 270 GSM galvanized steel sheet having 7
to 9 microns of primer coat and 20 to 25 microns of polyester coat on the outer surface. For
additional protection, outer surface of the outer skin shall be provided with vinyl guard film for
scratch protection. Inside and outside of panel walls shall be completely smooth.
D. Floor panels (inner skin) shall be of checkered plate of minimum 3mm thick, galvanized steel
sheet for unit capacity of 40000 CFM and above.
E. All casing panels shall be insulated with injected CFC free polyurethane foam insulation and shall
be in accordance to Class O of ISO 1182.2 standards. The insulation density shall be 45 Kg /m³
and having thermal conductivity (K value) of 0.02 W/m K.
F. The blank offs of the units shall be made out of not less than 1.5mm, 270 GSM galvanized steel
sheet duly epoxy coated for corrosion resistance.
G. The base frame of the units shall be made out of not less than 3.0mm thick up to 10000 CFM and
4.0mm thick beyond 10000 CFM, 220 GSM galvanized steel sheet duly epoxy coated for
corrosion resistance.
H. Access doors shall be provided with special gasket and locking device. Access doors 400 mm
and larger shall be provided with hinges and handles and access doors with width smaller than
400 mm shall be removable type fitted with quick release flap turn lock with spring pressure
arrangement. Sealant between panels shall be an anti fungicide material.
I. The manufacturer shall guarantee that no condensation shall take place on the exterior of panels.
In the event that any condensation problems appear after installation, the contractor shall
undertake all remedial measures to rectify and to the satisfaction of the consultants. Any stacked
K. Units shall be factory fitted with Marine lamps for both fan and filter section with view ports.
L. Units installed outdoors shall be fitted with weather proof aluminium canopy.
A. The Air Handling Unit shall have internal vibration isolation system by mounting fan, motor and
drive assembly on spring isolators designed for 93% isolation. The fan discharge shall be
connected to the air handling unit casing through canvas connection to prevent vibration transfer.
In addition to the above the entire unit shall be mounted on additional vibration isolators.
A. Filter cells shall be of standard sizes with Aluminium Frame and shall be obtained from reputed
European manufacturer. The filters shall be sealed against the filter frame using a permanently
elastic gasket to a standard compatible with the filter efficiency.
B. Pressure drop tapings shall be integrated into the frame to allow a manometer or filter monitor to
be fitted. Filter materials shall be flame-retardant, incombustible, non-odorous and may offer no
sustenance to vermin. Each filter section has to be provided with manometer.
C. The filter material shall be pleated to provide a large effective area. Filter section should be
provided with an inspection door.
D. The contractor shall supply one set of all filters per AHU as spares for replacement after testing
and commissioning and prior to handing over of the installation.
E. Panel Filter:
1. The Panel filter material shall be synthetic media pleated to provide a large effective area
and shall be supported by a wire mesh and frame. The filter cells shall be suitable for side
withdrawal on the inspection side. The filter class shall be EU-4 as per Eurovent 4/5 or G4
as per EN 779.
F. Bag Filter:
1. Bag filter material shall be synthetic media, of standard and readily available sizes. The
filters shall be clamped against the frame using a cam locking bar. The filter class should
be EU7 as per Eurovent 4/5 or G7 as per EN 779.
2. Bag filters shall be provided for both Fresh Air Handling Units and Re-circulated Air
Handling Units.
B. Coils need to be AHRI 410 certified for “Forced-Circulation Air-Cooling and Air-Heating Coils.
C. Cooling coils shall be fabricated from ½” OD copper tubing of 0.41mm thickness expanded into
0.12mm thick Copper fins with anti corrosive coating.. Return bends shall be die formed. Headers
shall be heavy section seamless copper tubing with a copper male adaptor for the ease of piping.
All joints shall be silver brazed. Fittings shall include plugged vent and drain taps for each section.
D. Coil end plates shall be made out of minimum 1.0mm thick, stainless steel – SS 316 material.
E. The coil shall be tested to 21 bar and designed to operate at 16 bar NP. Maximum coil face
velocity shall not exceed 2.5 m/s. Droplet moisture eliminators of PVC material shall be fitted to
all fresh air handling unit cooling coils.
G. The coil shall be mounted on stainless steel – SS 316 guide rails for side withdrawal. Header
connection through the unit casing shall be sealed with plastic grommet.
H. Drainpan shall be of stainless steel – SS 316 construction and designed with all round edges
allowing complete cleaning & avoiding microbial growth as per ASHRAE 62-1999. Drainpan to be
insulated with minimum of 13 mm thick nitrile foam closed cell rubber insulation.
I. Drain pan of floor mounted units shall have dual slope to facilitate fast removal of condensate and
arrangement to be provided to slide the coil. Any stacked or double height coils shall have
separate drain pan to reduce carry over. Drain pans shall have drain connection to the service
side.
J. U Trap sizing details to be provided by the AHU manufacturer. Details of the same shall be
affixed near the drain pipe to facilitate the contractor to follow.
K. Piping
A. Fans shall be double inlet, double width, and backward curved centrifugal type with galvanized
steel casings. Fan ratings shall be based on tests and procedures performed in accordance with
AMCA publication 211 and AMCA publication 311. Further, comply with the requirements of the
AMCA certified ratings program and all fans shall bear AMCA seal confirming the same.
B. Fan make shall be Nicotra (Italy) / Kruger (Singapore) / Comefri (Italy). Country of origin
certificate from the respective chamber of commerce to be submitted.
C. Every individual fan shall be run before delivery to check bearing condition and vibration. Fan
shafts shall be mounted in taper sleeve bearings designed for continuous operation and a mean
useful life of 200,000 hours. Backward curved impeller should be coated with 60 micron epoxy
painting of high quality.
D. Fans shall be designed in accordance to the specified operating class of AMCA standard 99-
2408-69 – performance class limits for centrifugal fans. The impeller & fan shaft shall be
statically and dynamically balanced to a balancing grade of G 2.5.
E. The fan shall be connected to the outlet opening by means of an airtight flexible connection. Fans
shall not exceed a maximum outlet velocity of 12 m/sec.
F. Fan motor assembly shall be mounted on common base channel made out of extruded
aluminium channels isolated by spring isolators.
G. Fan drive shall be rated at 150% of the maximum motor power of the units and shall be fitted with
1009DF / MISHRIFAH VILLA 23 7412 - 5 AIR HANDLING UNITS
adjustable belt tension arrangement. Sheaves shall be factory painted with two coats.
H. Belt guards or screen protection door (epoxy coated) in Fan section shall be provided in
accordance with CEN Standard.
I. The fan motor shall be IE2 efficiency rated, suitable for operating at 380-415V, 3Ph, 50Hz
electrical power supply. The fan motor shall be wired to the safety isolation switch or connection
box.
J. The degree of protection shall be IP55 with mounting method B3 and Class F insulation for the
electric motors.
K. Motors make shall be AEG (Italy) / Crompton Greaves (India) / Marathon (Netherlands). Motors
of China origin not acceptable.
L. The contractor shall select power input and speed of the fan subsequent to ascertaining system
static pressure in accordance with pressure drop calculations to the approval of the engineer.
M. The fan motor shall meet the safety requirements of the CE and compatible with variable
frequency drives.
N. The motor shall be mounted on a common, torsionally rigid, hot dip galvanized steel base frame.
A. Sand trap louvers of aluminium construction duly epoxy coated with bird screen and extruded
aluminium, aerofoil construction dampers shall be provided at the intake section of the unit.
B. Fresh air dampers shall be of opposed blade louver type. Blades shall be made of extruded
aluminium, aerofoil construction and shall be rattle-free.
C. Fresh air fans and fresh air intakes shall be per the requirements mentioned in the equipment
schedule. Electrical actuator to be provided to open and close action.
2.7 SAFETYFEATURES
B. The fan access door shall be equipped with micro-switch inter locked with fan motor to enable
switching off the fan motor automatically in the event of door opening.
C. Fan and motor base shall be properly earthed from the factory.
D. All screws used for panel fixing and projecting inside the unit shall be covered with PVC caps to
avoid human injury.
A. All the major components for their make and origin, materials (type of sheet / thickness) shall be
witnessed and certified by a repute third party agency prior to dispatch.
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting performance of the Work.
B. Examine casing insulation materials and filter media before air-handling unit installation. Reject
insulation materials and filter media that are wet, moisture damaged, or mold damaged.
C. Examine roughing-in for steam, hydronic, and condensate drainage piping systems and electrical
services to verify actual locations of connections before installation.
D. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 INSTALLATION
A. Equipment Mounting: Install air-handling units on concrete bases using restrained spring
isolators. Secure units to anchor bolts installed in concrete bases. Comply with requirements
for concrete bases specified in Division 03 Section "Cast-in-Place Concrete." Comply with
requirements for vibration isolation devices specified in Division 23 Section "Vibration and
Seismic Controls for HVAC Piping and Equipment."
B. Arrange installation of units to provide access space around air-handling units for service and
maintenance.
C. Install filter-gage, static-pressure taps upstream and downstream of filters. Mount filter gages
on outside of filter housing or filter plenum in accessible position. Provide filter gages on filter
banks, installed with separate static-pressure taps upstream and downstream of filters.
3.3 CONNECTIONS
A. Comply with requirements for piping specified in other Division 23 Sections. Drawings indicate
general arrangement of piping, fittings, and specialties.
C. Connect piping to air-handling units mounted on vibration isolators with flexible connectors.
D. Connect condensate drain pans using DN 32, ASTM B 88, Type M (ASTM B 88M, Type C)
copper tubing. Extend to nearest equipment or floor drain. Construct deep trap at connection
to drain pan and install cleanouts at changes in direction.
F. Steam and Condensate Piping: Comply with applicable requirements in Division 23 Section
"Steam and Condensate Heating Piping." Install shutoff valve at steam supply connections, float
and thermostatic trap, and union or flange at each coil return connection. Install gate valve and
inlet strainer at supply connection of dry steam humidifiers, and inverted bucket steam trap to
condensate return connection.
H. Connect duct to air-handling units with flexible connections. Comply with requirements in
Division 23 Section "Air Duct Accessories."
1. Leak Test: After installation, fill water and steam coils with water, and test coils and
connections for leaks.
2. Charge refrigerant coils with refrigerant and test for leaks.
3. Fan Operational Test: After electrical circuitry has been energized, start units to confirm
proper motor rotation and unit operation.
4. HEPA-Filter Operational Test: Pressurize housing to a minimum of 3-inch wg (750 Pa) or
to designed operating pressure, whichever is higher; test housing joints, door seals, and
sealing edges of filter with soapy water to check for air leaks.
5. Test and adjust controls and safeties. Replace damaged and malfunctioning controls
and equipment.
D. Air-handling unit or components will be considered defective if unit or components do not pass
tests and inspections.
1. Energize motor; verify proper operation of motor, drive system, and fan wheel. Adjust fan
to indicated rpm.
2. Measure and record motor electrical values for voltage and amperage.
3. Manually operate dampers from fully closed to fully open position and record fan
performance.
3.6 ADJUSTING
B. Comply with requirements in Division 23 Section "Testing, Adjusting, and Balancing for HVAC"
for air-handling system testing, adjusting, and balancing.
3.7 CLEANING
A. After completing system installation and testing, adjusting, and balancing air-handling unit and
air-distribution systems and after completing startup service, clean air-handling units internally
to remove foreign material and construction dirt and dust. Clean fan wheels, cabinets,
dampers, coils, and filter housings, and install new, clean filters.
3.8 DEMONSTRATION
A. Train Owner's maintenance personnel to adjust, operate, and maintain air-handling units.
END OF SECTION
1. GENERAL
The Dehumidifiers should be high performance units designed for swimming pool applications where it
is necessary to control humidity and to prevent condensation to guarantee optimal comfort.
1. SYSTEM COMPONENTS
1.1 Frame
All units shall be made from hot-galvanised thick sheet metal, painted with polyurethane powder
enamel at 180°C to ensure the best resistance against the atmospheric agents. The frame shall be self-
supporting with removable panels. All screws and rivets are in stainless steel. The colour of the units is
RAL 7035 or similar approved by the site team.
The refrigerant gas used in these units is R410 or approved. The refrigerant circuit shall made by using
international primary brands components and according to ISO 97/23 concerning welding procedures.
All units shall be supplied with two circuits, each refrigerant circuit shall be totally independent from the
other. Any incorrect operation of one circuit should not influence the other circuit. The refrigerant
circuit shall include:
liquid line manual shut-off valve, sight glass, filter drier, thermal expansion valve with external equalizer,
Schrader valves form maintenance and control, pressure safety device (according to PED regulation).
1.3 Compressors
The compressors shall be scroll type with crankase heater and thermal overload protection by a klixon
embedded in the motor winding. The compressors shall be mounted on rubber vibration dampers and
they can be supplied with sound attenuation jacket to reduce the noise emission. The compressor
crankcase heater shall be always powered when the unit is in stand-by. The inspection on the
compressors shall be possible only through the unit front panel.
The low noise version LS shall be supplied with compressors jacket and complete acoustic insulation of
the compressor vane with high density sound absorption material.
Condensers and evaporators shall be made of copper pipes and aluminium fins. All evaporators shall be
painted with epoxy powders to prevent corrosion problem due to their use in aggressive environments.
The diameter of the copper pipes shall be 3/8" and the thickness of the aluminium fins is 0,1 mm. The
tubes shall be mechanically expanded into the aluminium fins to improve the heat exchange factor. The
geometry of these heat exchangers guarantees a low air side pressure drop and then the use of low
1.5 Fans
The fans shall be made of galvanized steel, centrifugal type, double inlet with forward curved blades.
They shall be statically and dynamically balanced and supplied complete of the safety fan guard
according to EN 294. They shall be mounted on the unit frame by interposition of rubber vibration
dampers. The electric motors shall be 4 poles (about 1500 rpm), three-phase power supply. The motors
shall be connected to the fans by pulleys and belts. The protection class of the motors is IP 54.
Air Filters shall be supplied as standard with the unit, it is made of G3 class synthetic fibre filtering media
(efficiency 85% by weight)
2. APPROVED MANUFACTURERS
The following manufacturers are approved for use. No substitutions will be permitted.
3. ANCILLARY ITEMS
The electric switch board is made according to electromagnetic compatibility norms CEE 73/23 and
89/336. The accessibility to the board is possible after removing the front panel of the unit and the OFF
positioning of the main switch. The moisture protection degree is IP55. The unit shall be having the
compressors sequence relay who disables the operation of the compressor in case the power supply
phase sequence is not the correct one. The following components are also standard installed: main
switch, magnetic-thermal switches (as a protection fans and compressors), control circuit automatic
breakers, compressor contactors, fan contactors. The terminal board is supplied with voltage free
contacts for remote ON-OFF and general alarm.
3.2 Microprocessors
A. Basic control;
It manages the following features:
B. Advanced Control
All units shall be totally pre-assembled and charged with refrigerant R410 or similar approved. The unit
shall be completely tested before the expedition. The Units shall be in accordance to the European/
American Directives and must be provided with CE branding and relative conformity certificate.
Testing, Balancing and Commissioning shall be as referred to throughout this Section, and in accordance
with Section 15950 Testing, Adjusting and Balancing.
The test rig and all necessary blanks for the purpose of sealing the ductwork under test shall be
provided, blanks shall be removed after the test has been approved for each section of the ductwork.
END OF SECTION
PART 1 GENERAL
A. All general provisions contained herein or within any other Section of the Specifications
shall be fully applicable to each and every other Section.
B. Works on all installations shall be carried out in a neat, efficient and workmanlike
manner, assuring satisfactory operation, maintenance and repair. Work shall be in
accordance with the requirements of this Specification and shall fulfill its true intent and
meaning. No deviations from this Specification and/or the Drawings shall be made
without written approval of the Engineer.
D. Unless otherwise specifically stated, the installation shall be left complete, tested and
ready for operation in all respects and fully integrated and coordinated with all other
trades.
E. The Contractor shall submit proof, if requested by the Engineer that the materials,
appliances, equipment or devices that are furnished and installed under the contract
meet the requirements of the reference standards with regard to fire and safety hazards.
A. Work under this division of the Specification shall include furnishing all labor, materials,
equipment and services to install the complete electrical system, putting into operation,
tested and commissioned as shown on the Drawings and as specified herein. The work
includes, but is not limited to, the following principal systems and equipment:
4. All kinds of electrical raceways, underground electrical services, boxes and fittings.
5. All kinds of wiring devices, dimmers, disconnect switches, starters, electric meters,
etc.
6. Interior, exterior lighting, street, flood, façade and other special lighting.
B. Electrical installations serving all mechanical plants (HVAC & Plumbing) including all LV
cabling, cable trays, disconnect switches and connections to equipment.
C. Electrical installations serving all special systems and equipment provided under other
divisions of the Specification.
1009DF / MISHRIFAH VILLA 26 0510 - 1 BASIC ELECTRICAL
REQUIREMENTS
D. All low current systems as indicated in the tender documents.
1.3 REFERENCES
A. The entire Electrical Installation shall comply with the requirements of the latest editions of
the standards from the following institutes in all respect, including current additions and/or
amendments:
A. The Medium voltage electrical power supply from Saudi Electricity Company (SEC) shall
be 3 phase, 13.8 kV Delta, 60 Hertz.
B. The Low voltage electrical power supply and distribution system shall be 3 phase, 4 wire,
60 Hertz earthed neutral system. The voltage rating shall be 400/231 Volts for
Residential Villa and Support Facilities, unless specifically shown otherwise on the
Drawings.
A. Lighting levels shall be in accordance with appropriate standards and agreed upon with the
Engineer. Low energy lighting shall be the preferred source in all areas. The Standards
manual and the standards set forth by IES and CIBSE, the following maintained
illumination levels are recommended:
B. The earthing system shall take the form of (TN-C) system for the distribution systems
and TN-S system in all buildings. The Contractor shall ensure that the installation of
earthing system complies with the requirements as given in Section 26 0526.
C. The earthing conductor (the final conductor by which the connection to the selected
means of earthing is made) shall be of copper construction.
A. Assign a local specialist supplier/designer for all low current and special systems
including earthing and lightning protection systems.
B. Specialist suppliers shall verify the design and submit shop drawings and materials
based on the requirements of the construction documents and related international
standards.
D. Suppliers shall support their submittals with catalogues and satisfactory calculations.
E. Bear the cost of any extra items found necessary to provide a properly functional system.
1.8 CO-ORDINATION
A. The Contractor shall be solely responsible for the proper co-ordination of all phases of
the work and timely delivery to the site of all equipment and materials for proper
execution of the work.
B. Visit the site and survey in detail the as-built situation of all the areas related to the
project before bidding/signing the Contract.
C. Co-ordinate the work with all or any other disciplines to ensure proper phasing and
continuity of the Works. If it becomes necessary to remake any part of these works or
that of any other discipline or trade as a result of poor or badly timed co-ordination, then
all costs associated with remaking those works shall be borne by the Contractor.
D. Co-ordinate with all supply undertakings and authorities and include for attendance along
E. Take into consideration all statutory and local requirements issued by the Saudi
Electricity Company (SEC), Local Authority, Central Government, Broadcasting
Authority, Telephone and Telecommunications Authorities along with any other
requirements to be considered for the correct and legal operation of the Electrical and
Telecommunication Installation or equipment connected to the Installation as part of this
Contract. Pay all costs due to the requirements of any authority except for connection
fees.
F. The Contractor shall be responsible for co-ordination with all Electrical and Mechanical
systems’ suppliers and shall include in his cost all the electrical requirements (even if
they were not mentioned in the BOQ or drawings) to provide a fully functional
system as specified and as recommended by the manufacturer or applicable codes.
This shall also be applicable to all ancillary systems and equipment such as Security,
Audio-Visual, BMS and all low current & special systems.
G. The Contractor shall coordinate with the SEC “Saudi Electric Company” for the
connection of the new Electrical Room to feed the Residential Villa, Support Facilities
and other future loads etc.
H. The Contractor shall be responsible in coordination with the SEC and other matters
concerning with the power supply of the construction for the new Electrical Room or
either Transformer Room to complete and functional of the system.
I. The Contractor shall prepare, process and coordinate the approval from the SEC for the
connection of power supply / Electrical tie-in Points.
A. External to buildings and in non-air conditioned spaces, all apparatus shall be rated for a
ambient temperature maximum of 55 degrees C, minimum of 0 degrees C, generally
dusty desert conditions, a maximum humidity of 100 percent RH, and an elevation of 630
meters above sea level.
B. In air conditioned buildings (Residential Villa and Support Facilities), all apparatus shall
be rated for ambient temperature of 45 degrees C maximum, minimum of 0 degrees C
and a maximum humidity of 90 percent RH.
C. When equipment is installed in direct sunlight, it shall either be shielded from direct
radiation or suitably rated for additional solar gains. Cables shall always be shielded from
direct sunlight.
D. All apparatus shall be rated for continuous service twenty four hours a day, seven days a
week throughout its normal rated life, except for necessary routine maintenance.
E. All equipment shall be rated for very harsh and corrosive environmental conditions which
persist at the project site. All buried installations shall be suitable for aggressive and salty
soil conditions.
F. All external electrical enclosure must be protected and must comply with the type test.
1.10 ACCESSIBILITY
A. All works within the project and particularly above suspended ceilings or inside vertical
shafts shall be installed so as to be accessible for operation, maintenance and repair. If
necessary, deviations from the Drawings may be made to accomplish this, but no
change shall be made without written approval from the Engineer. Locations of access
doors and panels shall be approved by the Engineer before installation work is
B. All material and equipment fixed or unfixed, shall be protected against corrosion,
deterioration and ingress of foreign matter and moisture.
C. All material and equipment shall be kept clear of the floor or ground by means of wooden
blocks and shall be protected against weather with durable waterproof wrapping and
other appropriate means.
D. The Contractor shall be liable for any loss due to delivery, storage or site security
problems.
B. All equipment installed in plant rooms and outside areas shall not be audible in occupied
areas.
C. Any vibration isolators, isolating bases, flexible connections, silencers, other acoustic
treatment or anti-vibration precautions necessary shall be included in the rates for
equipment’s.
D. Submit proof of the selected noise proofing measures to the Engineer before
commencement of work.
E. Submit to the Engineer for information the noise level generation by the plant selected so
that structural soundproofing measures can be evaluated. This means either data on the
acoustic capacity level in relation to frequency, or the sound pressure level measured at
1 meter from the plant at octave median frequencies from 63 Hz to 4000 Hz. Details of
the spatial and operational conditions shall also be given.
F. All costs of noise sound level measurements and any repeat measurements, necessary
if acoustic requirements are not met, shall be allowed for by the Contractor.
1.13 GUARDS
A. All moving parts of machinery shall be protected by strong guards to adequately protect
all personnel working on or in the vicinity of equipment. The guards shall be constructed
in such a manner that the movement of drive belts and rotation of shafts may be readily
observed without removal of the guard.
B. All 'live' parts of electrical equipment shall be protected in such a way to adequately
protect all personnel working on or in the vicinity of equipment from injury.
A. All signs and notices shall be in Arabic and English with the Arabic version being above
or to the right of the English version.
B. A schedule of all signs and notices with proposed Arabic translations shall be approved
by the Engineer prior to manufacture.
A. Mounting heights of equipment above finished floor level shall be coordinated with
architectural details and other disciplines/equipment. Any discrepancy found between
these heights and other details shall be brought to the notice of the Engineer for
clarification and final decision. Unless otherwise indicated in Drawings, mounting heights
of electrical devices shall be as follows:
B. Where accessories with varying mounting heights (e.g. light switch and socket outlet) are
shown in approximately the same location on plan, their center lines shall be aligned
vertically.
C. Where wall mounted accessories are shown adjacent to each other they shall be mounted
with their wall plates separated by 50 mm.
A. Each item of the Electrical Installation including electrical switchgear, control gear,
equipment, devices, etc. shall be fitted with a non-corrodible label clearly indicating its
function giving at least the following information:
1. Manufacturer’s name.
2. Country of origin.
3. Type/model number or code.
4. Rated voltage, current and frequency (as applicable).
5. Short circuit breaking capacity with time.
6. Compliance mark of the international standard(s).
B. Prior to final testing, confirm that all labeling is intact over the whole site and that all
cables have been fitted with circuit markers. 13800 Volt cables shall be clearly labeled
"DANGER High Voltage" every two meters of their exposed length.
C. All conductors shall have their outer covering colored to suit the phase to which they are
connected.
D. An instruction notice giving details of first aid treatment for electric shock shall be
positioned in an approved position in each switch room.
B. Where cables enter or leave the bottoms of switchboards, or pass through pipe ducts,
they shall be sealed by the use of hard wood plugs treated with vermin repellent and
surrounded by mastic sealant.
C. All spare pipe ducts shall be similarly sealed by the use of solid hard wood plugs.
D. Alternative methods of vermin sealing will be accepted, but the written comments of the
Engineer must be obtained prior to installation.
A. The whole of the works shall be carried out with care and so arranged as to minimize the
risk of fire and the extent of damage resulting from any outbreak of fire.
A. During the course of construction a situation may arise when a power outage or shut
down of an existing facility will be required to facilitate power connection of a new
installation with the existing facility in operation, or power connection between different
phases of a new construction. For such situations or any other situation which requires
power shut down of an existing facility under operation, submit a work plan for approval
to the Engineer, indicating therein the temporary arrangements he shall make to
maintain the continuity of power supply to the existing facility.
B. The activities of the work plan shall be scheduled in such a way to cause minimum
inconvenience to the users or occupants of the existing facility (e.g. shut down during
holiday or after working hours) and in proper coordination with all concerned authorities.
The work plan shall include, but not limited to the following:
C. The cost for the provision of activities and other interim arrangements for the continuity
of power supply to the existing facility during power shut down procedures shall be
deemed to be included in the total price of the tender.
A. Study the location of all existing utilities and any other facilities, and perform the Work so
as not to damage them. In the event that any of such facilities are damaged by the
Contractor, the same shall be immediately repaired by the Contractor at his cost and
responsibility.
B. In the event that the Contractor damages the existing utilities or facilities listed below, the
Contractor shall pay to the Client, in addition to the repair costs, an amount specified
below:
1. Power Cable, Control Cable: An amount equal to 100 percent of Instrument Cable
actual repair costs.
2. Telephone Cable: An amount equal to 100 percent of the actual repair costs.
3. Fresh Water Line: An amount equal to one 100 percent of the actual repair costs
4. Sewer Line: An amount equal to 100 percent of the actual repair costs.
A. Obtain the services of the major Electrical Equipment manufacturer to provide a complete
computerized study of fault current and coordination of relays, fuses, circuit breakers, and
all other protective devices. The Contractor shall coordinate with the Saudi Electricity
Company (SEC) to include protection settings and fault levels of the SEC feeders and
circuit breakers in the study.
B. The study shall include all feeders at medium voltage and low voltage system.
C. The Contractor shall obtain all data, characteristic curves and all necessary information
from all other trades in connection with his work to provide complete study for the system.
E. The short circuit and protection study shall be bound in a standard A4 size report. The final
selection and settings of all protective devices shall be based on this study. The complete
study shall be approved by the Engineer. Protective devices shall be adjusted, tested, and
calibrated in the field prior to energizing the equipment per the settings listed in the study.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Single conductor building wire.
B. Underground feeder and branch-circuit cable.
C. Metal-clad cable.
D. Power and control tray cable.
E. Manufactured wiring systems.
F. Wiring connectors.
G. Electrical tape.
H. Heat shrink tubing.
I. Wire pulling lubricant.
J. Cable ties.
K. Firestop sleeves.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
conductors and cables, including detailed information on materials, construction, ratings,
listings, and available sizes, configurations, and stranding.
C. Sustainable Design Documentation: Submit manufacturer's product data on conductor and
cable showing compliance with specified lead content requirements.
D. Manufactured Wiring System Shop Drawings: Provide plan views indicating proposed
system layout with components identified; indicate branch circuit connections.
E. Design Data: Indicate voltage drop and ampacity calculations for copper conductors.
Include proposed modifications to raceways, boxes, wiring gutters, enclosures, etc. to
accommodate substituted conductors.
F. Field Quality Control Test Reports.
G. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
H. Project Record Documents: Record actual installed circuiting arrangements. Record actual
routing for underground circuits.
PART 2 PRODUCTS
2.01 CONDUCTOR AND CABLE APPLICATIONS
A. Do not use conductors and cables for applications other than as permitted by NFPA 70 and
product listing.
B. Provide single conductor building wire installed in suitable raceway unless otherwise
indicated, permitted, or required.
2.07 ACCESSORIES
A. Electrical Tape:
1. Vinyl Color Coding Electrical Tape: Integrally colored to match color code indicated;
listed as complying with UL 510; minimum thickness of 7 mil (0.18 mm); resistant to
1009DF / MISHRIFAH VILLA 26 0519 - 4 LOW-VOLTAGE ELECTRICAL
POWER CONDUCTORS AND
CABLES
abrasion, corrosion, and sunlight; suitable for continuous temperature environment up
to 221 degrees F (105 degrees C).
2. Vinyl Insulating Electrical Tape: Complying with ASTM D3005 and listed as complying
with UL 510; minimum thickness of 7 mil (0.18 mm); resistant to abrasion, corrosion,
and sunlight; conformable for application down to 0 degrees F (-18 degrees C) and
suitable for continuous temperature environment up to 221 degrees F (105 degrees
C).
3. Rubber Splicing Electrical Tape: Ethylene Propylene Rubber (EPR) tape, complying
with ASTM D4388; minimum thickness of 30 mil (0.76 mm); suitable for continuous
temperature environment up to 194 degrees F (90 degrees C) and short-term 266
degrees F (130 degrees C) overload service.
4. Electrical Filler Tape: Rubber-based insulating moldable putty, minimum thickness of
125 mil (3.2 mm); suitable for continuous temperature environment up to 176 degrees
F (80 degrees C).
5. Varnished Cambric Electrical Tape: Cotton cambric fabric tape, with or without
adhesive, oil-primed and coated with high-grade insulating varnish; minimum
thickness of 7 mil (0.18 mm); suitable for continuous temperature environment up to
221 degrees F (105 degrees C).
6. Moisture Sealing Electrical Tape: Insulating mastic compound laminated to flexible,
all-weather vinyl backing; minimum thickness of 90 mil (2.3 mm).
B. Heat Shrink Tubing: Heavy-wall, split-resistant, with factory-applied adhesive; rated 600 V;
suitable for direct burial applications; listed as complying with UL 486D.
C. Wire Pulling Lubricant: Listed; suitable for use with the conductors or cables to be installed
and suitable for use at the installation temperature.
D. Cable Ties: Material and tensile strength rating suitable for application.
E. Sealing Systems for Roof Penetrations: Premanufactured components and accessories as
required to preserve integrity of roofing system and maintain roof warranty; suitable for
cables and roofing system to be installed; designed to accommodate existing penetrations
where applicable.
F. Firestop Sleeves: Listed; provide as required to preserve fire resistance rating of building
elements.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that interior of building has been protected from weather.
B. Verify that work likely to damage wire and cable has been completed.
C. Verify that raceways, boxes, and equipment enclosures are installed and are properly sized
to accommodate conductors and cables in accordance with NFPA 70.
D. Verify that field measurements are as indicated.
E. Verify that conditions are satisfactory for installation prior to starting work.
3.02 PREPARATION
A. Clean raceways thoroughly to remove foreign materials before installing conductors and
cables.
3.03 INSTALLATION
A. Circuiting Requirements:
1. Unless dimensioned, circuit routing indicated is diagrammatic.
2. When circuit destination is indicated without specific routing, determine exact routing
required.
3. Arrange circuiting to minimize splices.
4. Include circuit lengths required to install connected devices within 10 ft (3.0 m) of
location indicated.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Grounding and bonding requirements.
B. Conductors for grounding and bonding.
C. Connectors for grounding and bonding.
D. Ground bars.
E. Ground rod electrodes.
F. Chemically-enhanced ground electrodes.
G. Ground plate electrodes.
H. Ground enhancement material.
I. Ground access wells.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements for submittals procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
grounding and bonding system components.
C. Shop Drawings:
1. Indicate proposed arrangement for signal reference grids. Include locations of items to
be bonded and methods of connection.
D. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by product testing agency. Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
E. Field quality control test reports.
F. Project Record Documents: Record actual locations of grounding electrode system
components and connections.
PART 2 PRODUCTS
2.01 GROUNDING AND BONDING REQUIREMENTS
A. Do not use products for applications other than as permitted by NFPA 70 and product
listing.
B. Unless specifically indicated to be excluded, provide all required components, conductors,
connectors, conduit, boxes, fittings, supports, accessories, etc. as necessary for a complete
grounding and bonding system.
C. Where conductor size is not indicated, size to comply with NFPA 70 but not less than
applicable minimum size requirements specified.
D. Grounding System Resistance:
1. Achieve specified grounding system resistance under normally dry conditions unless
otherwise approved by Architect or Engineer. Precipitation within the previous 48
hours does not constitute normally dry conditions.
2. Grounding Electrode System: Not greater than 5 ohms to ground, when tested
according to IEEE 81 using "fall-of-potential" method.
3. Between Grounding Electrode System and Major Electrical Equipment Frames,
System Neutral, and Derived Neutral Points: Not greater than 0.5 ohms, when tested
using "point-to-point" methods.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that work likely to damage grounding and bonding system components has been
completed.
B. Verify that field measurements are as indicated.
C. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Ground Rod Electrodes: Unless otherwise indicated, install ground rod electrodes
vertically. Where encountered rock prohibits vertical installation, install at 45 degree angle
or bury horizontally in trench at least 30 inches (750 mm) deep in accordance with NFPA
70.
D. Make grounding and bonding connections using specified connectors.
1. Remove appropriate amount of conductor insulation for making connections without
cutting, nicking or damaging conductors. Do not remove conductor strands to facilitate
insertion into connector.
2. Remove nonconductive paint, enamel, or similar coating at threads, contact points,
and contact surfaces.
3. Exothermic Welds: Make connections using molds and weld material suitable for the
items to be connected in accordance with manufacturer's recommendations.
4. Mechanical Connectors: Secure connections according to manufacturer's
recommended torque settings.
5. Compression Connectors: Secure connections using manufacturer's recommended
tools and dies.
E. Identify grounding and bonding system components in accordance with Section 26 0553.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Support and attachment requirements and components for equipment, conduit, cable,
boxes, and other electrical work.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for channel
(strut) framing systems, non-penetrating rooftop supports, and post-installed concrete and
masonry anchors.
C. Shop Drawings: Include details for fabricated hangers and supports where materials or
methods other than those indicated are proposed for substitution.
D. Evaluation Reports: For products specified as requiring evaluation and recognition by ICC
Evaluation Service, LLC (ICC-ES), provide current ICC-ES evaluation reports upon request.
E. Installer's Qualification Statement: Include evidence of compliance with specified
requirements.
F. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by product testing agency. Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
PART 2 PRODUCTS
2.01 SUPPORT AND ATTACHMENT COMPONENTS
A. General Requirements:
1. Provide all required hangers, supports, anchors, fasteners, fittings, accessories, and
hardware as necessary for the complete installation of electrical work.
2. Provide products listed, classified, and labeled as suitable for the purpose intended,
where applicable.
3. Where support and attachment component types and sizes are not indicated, select in
accordance with manufacturer's application criteria as required for the load to be
supported. Include consideration for vibration, equipment operation, and shock loads
where applicable.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that mounting surfaces are ready to receive support and attachment components.
C. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Install anchors and fasteners in accordance with ICC Evaluation Services, LLC (ICC-ES)
evaluation report conditions of use where applicable.
D. Provide independent support from building structure. Do not provide support from piping,
ductwork, or other systems.
E. Unless specifically indicated or approved by Architect or Engineer, do not provide support
from suspended ceiling support system or ceiling grid.
F. Unless specifically indicated or approved by Architect or Engineer, do not provide support
from roof deck.
G. Do not penetrate or otherwise notch or cut structural members without approval of
Structural Engineer.
H. Provide required vibration isolation and/or seismic controls in accordance with Section 26
0548.
I. Equipment Support and Attachment:
1. Use metal fabricated supports or supports assembled from metal channel (strut) to
support equipment as required.
2. Use metal channel (strut) secured to studs to support equipment surface-mounted on
hollow stud walls when wall strength is not sufficient to resist pull-out.
3. Use metal channel (strut) to support surface-mounted equipment in wet or damp
locations to provide space between equipment and mounting surface.
4. Unless otherwise indicated, mount floor-mounted equipment on properly sized 3 inch
(80 mm) high concrete pad constructed in accordance with Section 03 3000.
5. Securely fasten floor-mounted equipment. Do not install equipment such that it relies
on its own weight for support.
J. Conduit Support and Attachment: Also comply with Section 26 0533.13.
K. Cable Tray Support and Attachment: Also comply with Section 26 0536.
L. Box Support and Attachment: Also comply with Section 26 0533.16.
M. Interior Luminaire Support and Attachment: Also comply with Section 26 5100.
N. Exterior Luminaire Support and Attachment: Also comply with Section 26 5600.
O. Preset Concrete Inserts: Use manufacturer provided closure strips to inhibit concrete
seepage during concrete pour.
P. Secure fasteners according to manufacturer's recommended torque settings.
Q. Remove temporary supports.
R. Identify independent electrical component support wires above accessible ceilings (only
where specifically indicated or permitted) with color distinguishable from ceiling support
wires in accordance with NFPA 70.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Galvanized steel rigid metal conduit (RMC).
B. Intermediate metal conduit (IMC).
C. PVC-coated galvanized steel rigid metal conduit (RMC).
D. Flexible metal conduit (FMC).
E. Liquidtight flexible metal conduit (LFMC).
F. Electrical metallic tubing (EMT).
G. Rigid polyvinyl chloride (PVC) conduit.
H. Liquidtight flexible nonmetallic conduit (LFNC).
I. Conduit fittings.
J. Accessories.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements for submittals procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for conduits
and fittings.
C. Shop Drawings:
1. Indicate proposed arrangement for conduits to be installed within structural concrete
slabs, where permitted.
2. Include proposed locations of roof penetrations and proposed methods for sealing.
PART 2 PRODUCTS
2.01 CONDUIT APPLICATIONS
A. Do not use conduit and associated fittings for applications other than as permitted by NFPA
70 and product listing.
B. Unless otherwise indicated and where not otherwise restricted, use the conduit types
indicated for the specified applications. Where more than one listed application applies,
comply with the most restrictive requirements. Where conduit type for a particular
application is not specified, use galvanized steel rigid metal conduit.
C. Underground:
1. Under Slab on Grade: Use rigid PVC conduit.
2. Exterior, Direct-Buried: Use rigid PVC conduit.
3. Where rigid polyvinyl (PVC) conduit is provided, transition to galvanized steel rigid
metal conduit where emerging from underground.
4. Where rigid polyvinyl (PVC) conduit larger than 2 inch (53 mm) trade size is provided,
use galvanized steel rigid metal conduit elbows for bends.
5. Where steel conduit is installed in direct contact with earth where soil has a resistivity
of less than 2000 ohm-centimeters or is characterized as severely corrosive based on
soils report or local experience, use corrosion protection tape to provide
supplementary corrosion protection or use PVC-coated galvanized steel rigid metal
conduit.
D. Embedded Within Concrete:
1. Within Slab on Grade (within structural slabs only where approved by Structural
Engineer): Use galvanized steel rigid metal conduit, intermediate metal conduit (IMC),
PVC-coated galvanized steel rigid metal conduit, rigid PVC conduit, or reinforced
thermosetting resin conduit (RTRC).
2. Within Slab Above Ground: Not permitted.
3. Within Slab Above Ground (within structural slabs only where approved by Structural
Engineer): Use galvanized steel rigid metal conduit, intermediate metal conduit (IMC),
PVC-coated galvanized steel rigid metal conduit, electrical metallic tubing (EMT), or
rigid PVC conduit.
4. Within Concrete Walls Above Ground: Use galvanized steel rigid metal conduit,
intermediate metal conduit (IMC), PVC-coated galvanized steel rigid metal conduit, or
rigid PVC conduit.
5. Where rigid polyvinyl (PVC) conduit is provided, transition to galvanized steel rigid
metal conduit where emerging from concrete.
6. Where electrical metallic tubing (EMT) emerges from concrete into salt air, use
corrosion protection tape to provide supplementary corrosion protection for a minimum
2.11 ACCESSORIES
A. Corrosion Protection Tape: PVC-based, minimum thickness of 20 mil (0.51 mm).
B. Conduit Joint Compound: Corrosion-resistant, electrically conductive; suitable for use with
the conduit to be installed.
C. Solvent Cement for PVC Conduit and Fittings: As recommended by manufacturer of
conduit and fittings to be installed.
D. Sealing Compound for Sealing Fittings: Listed for use with the particular fittings to be
installed.
E. Modular Seals for Conduit Penetrations: Rated for minimum of 40 psig; Suitable for the
conduits to be installed.
F. Sealing Systems for Roof Penetrations: Premanufactured components and accessories as
required to preserve integrity of roofing system and maintain roof warranty; suitable for
conduits and roofing system to be installed; designed to accommodate existing penetrations
where applicable.
G. Flashing Panels for Exterior Wall Penetrations: Premanufactured components and
accessories as required to preserve integrity of building envelope; suitable for conduits and
facade materials to be installed.
H. Firestop Sleeves: Listed; provide as required to preserve fire resistance rating of building
elements.
I. Duct Bank Spacers: Nonmetallic; designed for maintaining conduit/duct spacing for
concrete encasement in open trench installation; suitable for the conduit/duct arrangement
to be installed.
J. Bore Spacers: Nonmetallic; designed for maintaining conduit/duct spacing for installation
within casing; furnished with roller wheels to facilitate installation, openings to facilitate grout
flow, and holes for stabilization cable; suitable for the casing and conduit/duct arrangement
to be installed.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Install galvanized steel rigid metal conduit (RMC) in accordance with NECA 101.
D. Install intermediate metal conduit (IMC) in accordance with NECA 101.
E. Install PVC-coated galvanized steel rigid metal conduit (RMC) using only tools approved by
the manufacturer.
F. Install rigid polyvinyl chloride (PVC) conduit in accordance with NECA 111.
G. Install liquidtight flexible nonmetallic conduit (LFNC) in accordance with NECA 111.
H. Conduit Routing:
1. Unless dimensioned, conduit routing indicated is diagrammatic.
2. When conduit destination is indicated without specific routing, determine exact routing
required.
3. Conceal all conduits unless specifically indicated to be exposed.
4. Conduits in the following areas may be exposed, unless otherwise indicated:
a. Electrical rooms.
b. Mechanical equipment rooms.
c. With reflected ceiling area.
5. Unless otherwise approved, do not route conduits exposed:
a. Across floors.
b. Across roofs.
c. Across top of parapet walls.
d. Across building exterior surfaces.
6. Conduits installed underground or embedded in concrete may be routed in the
shortest possible manner unless otherwise indicated. Route all other conduits parallel
or perpendicular to building structure and surfaces, following surface contours where
practical.
7. Arrange conduit to maintain adequate headroom, clearances, and access.
8. Arrange conduit to provide no more than the equivalent of four 90 degree bends
between pull points.
9. Arrange conduit to provide no more than 150 feet (46 m) between pull points.
10. Route conduits above water and drain piping where possible.
11. Arrange conduit to prevent moisture traps. Provide drain fittings at low points and at
sealing fittings where moisture may collect.
12. Maintain minimum clearance of 6 inches (150 mm) between conduits and piping for
other systems.
13. Maintain minimum clearance of 12 inches (300 mm) between conduits and hot
surfaces. This includes, but is not limited to:
a. Heaters.
b. Hot water piping.
c. Flues.
14. Group parallel conduits in the same area together on a common rack.
I. Conduit Support:
1. Secure and support conduits in accordance with NFPA 70 and Section 26 0529 using
suitable supports and methods approved by the authority having jurisdiction.
3.04 CLEANING
A. Clean interior of conduits to remove moisture and foreign matter.
3.05 PROTECTION
A. Immediately after installation of conduit, use suitable manufactured plugs to provide
protection from entry of moisture and foreign material and do not remove until ready for
installation of conductors.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Outlet and device boxes up to 100 cubic inches (1,650 cu cm), including those used as
junction and pull boxes.
B. Cabinets and enclosures, including junction and pull boxes larger than 100 cubic inches
(1,650 cu cm).
C. Boxes and enclosures for integrated power, data, and audio/video.
D. Boxes for hazardous (classified) locations.
E. Floor boxes.
F. Underground boxes/enclosures.
G. Accessories.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for cabinets
and enclosures, boxes for hazardous (classified) locations, floor boxes, and underground
boxes/enclosures.
1. Underground Boxes/Enclosures: Include reports for load testing in accordance with
SCTE 77 certified by a professional engineer or an independent testing agency upon
request.
C. Samples:
1. Floor Boxes: Provide one sample(s) of each floor box proposed for substitution upon
request.
D. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
E. Project Record Documents: Record actual locations for outlet and device boxes, pull
boxes, cabinets and enclosures, floor boxes, and underground boxes/enclosures.
F. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Keys for Lockable Enclosures: Two of each different key.
PART 2 PRODUCTS
2.01 BOXES
A. General Requirements:
1. Do not use boxes and associated accessories for applications other than as permitted
by NFPA 70 and product listing.
2. Provide all boxes, fittings, supports, and accessories required for a complete raceway
system and to accommodate devices and equipment to be installed.
3. Provide products listed, classified, and labeled as suitable for the purpose intended.
4. Where box size is not indicated, size to comply with NFPA 70 but not less than
applicable minimum size requirements specified.
5. Provide grounding terminals within boxes where equipment grounding conductors
terminate.
B. Outlet and Device Boxes Up to 100 cubic inches (1,650 cu cm), Including Those Used as
Junction and Pull Boxes:
1. Use sheet-steel boxes for dry locations unless otherwise indicated or required.
2. Use cast iron boxes or cast aluminum boxes for damp or wet locations unless
otherwise indicated or required; furnish with compatible weatherproof gasketed
covers.
3. Use cast iron boxes where exposed galvanized steel rigid metal conduit or exposed
intermediate metal conduit (IMC) is used.
4. Use nonmetallic boxes where exposed rigid PVC conduit is used.
5. Use suitable concrete type boxes where flush-mounted in concrete.
6. Use suitable masonry type boxes where flush-mounted in masonry walls.
7. Use raised covers suitable for the type of wall construction and device configuration
where required.
8. Use shallow boxes where required by the type of wall construction.
9. Do not use "through-wall" boxes designed for access from both sides of wall.
10. Sheet-Steel Boxes: Comply with NEMA OS 1, and list and label as complying with UL
514A.
11. Cast Metal Boxes: Comply with NEMA FB 1, and list and label as complying with UL
514A; furnish with threaded hubs.
12. Nonmetallic Boxes: Comply with NEMA OS 2, and list and label as complying with UL
514C.
13. Boxes for Supporting Luminaires and Ceiling Fans: Listed as suitable for the type and
weight of load to be supported; furnished with fixture stud to accommodate mounting
of luminaire where required.
14. Boxes for Ganged Devices: Use multigang boxes of single-piece construction. Do not
use field-connected gangable boxes unless specifically indicated or permitted.
15. Minimum Box Size, Unless Otherwise Indicated:
16. Wall Plates: Comply with Section 26 2726.
C. Cabinets and Enclosures, Including Junction and Pull Boxes Larger Than 100 cubic inches
(1,650 cu cm):
1. Comply with NEMA 250, and list and label as complying with UL 50 and UL 50E, or UL
508A.
2. NEMA 250 Environment Type, Unless Otherwise Indicated:
3. Junction and Pull Boxes Larger Than 100 cubic inches (1,650 cu cm):
2.02 ACCESSORIES
A. Flashing Panels for Exterior Wall Penetrations: Premanufactured components and
accessories as required to preserve integrity of building envelope; suitable for boxes and
facade materials to be installed.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that mounting surfaces are ready to receive boxes.
C. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install boxes in accordance with NECA 1 (general workmanship) and, where applicable,
NECA 130, including mounting heights specified in those standards where mounting
heights are not indicated.
3.03 CLEANING
A. Clean interior of boxes to remove dirt, debris, plaster and other foreign material.
3.04 PROTECTION
A. Immediately after installation, protect boxes from entry of moisture and foreign material until
ready for installation of conductors.
END OF SECTION
PART 1 GENERAL
1.01 A. CABLE TRAYAND ACCESORIES
1.02 SECTION INCLUDES
A. Metal cable tray systems:
1. Metal ladder cable tray.
2. Metal ventilated trough cable tray.
3. Metal solid-bottom cable tray.
1.06 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for cable
tray system components and accessories. Include dimensions, materials, fabrication
details, finishes, and span/load ratings.
C. Shop Drawings: Include dimensioned plan views and sections indicating proposed cable
tray routing, required clearances, and locations and details of supports, fittings, building
element penetrations, and equipment connections.
D. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by product testing agency. Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
E. Project Record Documents: Record actual routing of cable tray and locations of supports.
PART 2 PRODUCTS
2.01 CABLE TRAY SYSTEM - GENERAL REQUIREMENTS
A. Provide new cable tray system consisting of all required components, fittings, supports,
accessories, etc. as necessary for a complete system.
B. Provide products listed, classified, and labeled as suitable for the purpose intended.
C. Do not use cable tray for applications other than as permitted by NFPA 70 and product
listing/classification.
D. Provide cable tray system and associated components suitable for use at indicated
span/load ratings under the service conditions at the installed location.
E. Unless otherwise indicated, specified span/load ratings are according to NEMA VE 1 (metal
cable tray systems) or NEMA FG 1 (fiberglass cable tray systems) with safety factor of 1.5
and working load only (no additional concentrated static load).
PART 3 EXECUTION
4.01 EXAMINATION
A. Verify that work likely to damage cable tray system has been completed.
B. Verify that field measurements are as indicated.
C. Verify that the dimensions and span/load ratings of cable tray system components are
consistent with the indicated requirements.
D. Verify that mounting surfaces are ready to receive cable tray and associated supports.
E. Verify that conditions are satisfactory for installation prior to starting work.
4.02 PREPARATION
A. Modifications to Existing Cable Tray Systems: Remove inactive or abandoned cables from
existing cable tray system.
4.03 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install cable tray in accordance with NECA 1 (general workmanship), and NEMA VE 2.
C. Unless otherwise indicated, arrange cable tray to be parallel or perpendicular to building
lines.
D. Arrange cable tray to provide required clearances and maintain cable access.
1. Minimum Clearance Above and Adjacent to Cable Tray: 12 inches (300 mm).
2. Cable Tray for Telecommunications Cables: Maintain recommended separation from
sources of EMI greater than 5 kVA in accordance with NECA/BICSI 568.
4.05 ADJUSTING
A. Adjust tightness of mechanical connections to manufacturer's recommended torque
settings.
4.06 CLEANING
A. Remove dirt and debris from cable tray.
B. Clean exposed surfaces to remove dirt, paint, or other foreign material and restore to match
original factory finish.
4.07 PROTECTION
A. Protect cable tray system from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Trench duct.
B. Service fittings.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings: Include dimensioned plan views and sections indicating system layout,
connection locations and details, insert spacing and height, and service fitting locations.
C. Product Data: Provide manufacturer's standard catalog pages and data sheets including
dimensions, materials, fabrication details, finishes, conductor and cable fill capacities,
service condition requirements, and accessories.
D. Project Record Documents: Record actual installed locations of ducts, junction boxes, and
service fittings.
E. Operation and Maintenance Data: Include instructions for locating preset inserts and
installing afterset inserts.
PART 2 PRODUCTS
2.01 DUCT SYSTEM REQUIREMENTS
A. Provide all components, fittings, supports, and accessories required for a complete duct
system.
B. Provide products listed, classified, and labeled as suitable for the purpose intended.
C. Do not use duct systems for applications other than as permitted by NFPA 70 and product
listing.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Unless otherwise indicated, arrange duct to be parallel or perpendicular to building lines.
D. Install duct supports located according to manufacturer's recommendations. Permanently
fasten duct supports to the supporting framework.
E. Provide expansion fittings with suitable bonding jumper where duct crosses structural joints
intended for expansion.
F. Make adjustments such that duct is level at the proper elevation.
1. Trench Duct: Top of cover plate assembly flush with finished floor, accounting for
flooring material and associated trim.
G. Install marker caps in each insert adjacent to junction boxes, at end of each duct run, on
both sides of permanent partitions, and on both sides of change in direction of duct. Adjust
3.04 ADJUSTING
A. Adjust duct system covers to eliminate movement and noise under normal traffic.
3.05 CLEANING
A. After concrete placement and before installation of conductors and cables, clean interior of
duct system to remove moisture and foreign matter.
B. Clean exposed surfaces to remove dirt, paint, or other foreign material and restore to match
original factory finish.
3.06 PROTECTION
A. Prior to concrete placement, do not use installed duct system as walkway or working
platform.
B. Protect installed duct system from subsequent construction operations. Do not allow
equipment or heavy traffic over the duct system without using ramps that ensure load is not
transferred to the duct.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Vibration isolation requirements.
B. Seismic control requirements.
1. Includes requirements for seismic qualification of equipment not specified in this
section.
C. Vibration-isolated equipment support bases.
D. Vibration isolators.
E. External seismic snubber assemblies.
F. Seismic restraint systems.
1.03 DEFINITIONS
A. Electrical Component: Where referenced in this section in regards to seismic controls,
applies to any portion of the electrical system subject to seismic evaluation in accordance
with applicable codes, including distributed systems (e.g. conduit, cable tray).
B. Seismic Restraint: Structural members or assemblies of members or manufactured
elements specifically designed and applied for transmitting seismic forces between
components and the seismic force-resisting system of the structure.
1.06 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Design Documents: Prepare and submit all information required for plan review and
permitting by authorities having jurisdiction, including but not limited to floor plans, details,
and calculations.
C. Product Data: Provide manufacturer's standard catalog pages and data sheets for
products, including materials, fabrication details, dimensions, and finishes.
1. Vibration Isolators: Include rated load capacities and deflections; include information
on color coding or other identification method for spring element load capacities.
2. Seismic Controls: Include seismic load capacities.
D. Shop Drawings - Vibration Isolation Systems:
1. Include dimensioned plan views and sections indicating proposed arrangement of
vibration isolators; indicate equipment weights and static deflections.
2. Vibration-Isolated Equipment Support Bases: Include base weights, including
concrete fill where applicable; indicate equipment mounting provisions.
E. Shop Drawings - Seismic Controls:
1. Include dimensioned plan views and sections indicating proposed electrical
component locations and distributed system routing, with locations and details of
gravity supports and seismic restraints and associated attachments.
2. Identify mounting conditions required for equipment seismic qualification.
3. Identify anchor manufacturer, type, minimum embedment, minimum spacing, minimum
member thickness, and minimum edge distance requirements.
4. Indicate proposed arrangement of distributed system trapeze support groupings.
5. Indicate proposed locations for distributed system flexible fittings and/or connections.
6. Indicate locations of seismic separations where applicable.
7. Include point load drawings indicating design loads transmitted to structure at each
attachment location.
F. Seismic Design Data:
1. Compile information on project-specific characteristics of actual installed electrical
components necessary for determining seismic design forces required to design
appropriate seismic controls, including but not limited to the following.
a. Component operating weight and center of gravity.
b. Component elevation in the building in relation to the roof elevation (z/h).
c. Component importance factor (Ip).
d. For distributed systems, component materials and connection methods.
e. Component amplification factor (ap) and component response modification factor
(Rp), determined in accordance with ASCE 7 tables.
PART 2 PRODUCTS
2.01 VIBRATION ISOLATION REQUIREMENTS
A. Design and provide vibration isolation systems to reduce vibration transmission to
supporting structure from vibration-producing electrical equipment and/or electrical
connections to vibration-isolated equipment.
B. Comply with applicable general recommendations of ASHRAE (HVACA), where not in
conflict with other specified requirements:
C. General Requirements:
1. Select vibration isolators to provide required static deflection.
2. Select vibration isolators for uniform deflection based on distributed operating weight
of actual installed equipment.
3. Select seismic type vibration isolators to comply with seismic design requirements,
including conditions of equipment seismic certification where applicable.
4. Select vibration isolators for outdoor equipment to comply with wind design
requirements.
5. Select vibration-isolated equipment support bases and associated vibration isolators to
provide minimum 2 inch (50 mm) operating clearance beneath base unless otherwise
indicated.
D. Equipment Isolation:
1. Transformers:
a. Specified vibration isolators are in addition to any factory-installed internal core
and coil assembly vibration isolators unless otherwise indicated.
b. Floor-Mounted Transformers, Non-Seismic Applications: Use resilent material
isolator pads, resilient material isolator mounts, or open (unhoused) spring
isolators.
c. Floor-Mounted Transformers, Seismic Applications: Use seismic type resilient
material isolator mounts or seismic type restrained spring isolators.
E. Conduit Isolation:
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as shown on the drawings.
B. Verify that mounting surfaces are ready to receive vibration isolation and/or seismic control
components and associated attachments.
C. Verify that conditions are satisfactory for installation prior to starting work.
3.03 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install products in accordance with applicable requirements of NECA 1 (general
workmanship).
3.05 ATTACHMENTS
A. Statement of special inspections.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Electrical identification requirements.
B. Identification nameplates and labels.
C. Wire and cable markers.
D. Voltage markers.
E. Underground warning tape.
F. Floor marking tape.
G. Warning signs and labels.
PART 2 PRODUCTS
2.01 IDENTIFICATION REQUIREMENTS
A. Existing Work: Unless specifically excluded, identify existing elements to remain that are
not already identified in accordance with specified requirements.
B. Identification for Equipment:
1. Use identification nameplate to identify each piece of electrical distribution and control
equipment and associated sections, compartments, and components.
a. Switchgear:
1) Identify ampere rating.
2) Identify voltage and phase.
3) Identify power source and circuit number. Include location
4) Use identification nameplate to identify main and tie devices.
5) Use identification nameplate to identify load(s) served for each branch
device. Do not identify spares and spaces.
6) See Section 26 2300 for factory-installed mimic bus.
b. Switchboards:
1) Identify ampere rating.
2) Identify voltage and phase.
3) Identify power source and circuit number. Include location.
4) Use identification nameplate to identify main overcurrent protective device.
5) Use identification nameplate to identify load(s) served for each branch
device. Do not identify spares and spaces.
c. Motor Control Centers:
1) Identify ampere rating.
2) Identify voltage and phase.
3) Identify power source and circuit number. Include location.
4) Use identification nameplate to identify main overcurrent protective device.
5) Use identification nameplate to identify load(s) served for each branch
device. Do not identify spares and spaces.
d. Panelboards:
1) Identify ampere rating.
2) Identify voltage and phase.
3) Identify power source and circuit number. Include location.
PART 3 EXECUTION
3.01 PREPARATION
A. Clean surfaces to receive adhesive products according to manufacturer's instructions.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install identification products to be plainly visible for examination, adjustment, servicing, and
maintenance. Unless otherwise indicated, locate products as follows:
1. Surface-Mounted Equipment: Enclosure front.
2. Flush-Mounted Equipment: Inside of equipment door.
3. Free-Standing Equipment: Enclosure front; also enclosure rear for equipment with
rear access.
4. Elevated Equipment: Legible from the floor or working platform.
5. Branch Devices: Adjacent to device.
6. Interior Components: Legible from the point of access.
7. Conduits: Legible from the floor.
8. Boxes: Outside face of cover.
9. Conductors and Cables: Legible from the point of access.
10. Devices: Outside face of cover.
C. Install identification products centered, level, and parallel with lines of item being identified.
D. Secure nameplates to exterior surfaces of enclosures using stainless steel screws and to
interior surfaces using self-adhesive backing or epoxy cement.
1. Do not use adhesives on exterior surfaces except where substrate cannot be
penetrated.
E. Install self-adhesive labels and markers to achieve maximum adhesion, with no bubbles or
wrinkles and edges properly sealed.
F. Install underground warning tape above buried lines with one tape per trench at 3 inches
(75 mm) below finished grade.
G. Secure rigid signs using stainless steel screws.
H. Mark all handwritten text, where permitted, to be neat and legible.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Short-circuit study.
B. Protective device coordination study.
C. Arc flash and shock risk assessment.
1. Includes arc flash hazard warning labels.
D. Criteria for the selection and adjustment of equipment and associated protective devices
not specified in this section, as determined by studies to be performed.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Study preparer's qualifications.
C. Field testing agency's qualifications.
D. Study reports, stamped or sealed and signed by study preparer.
E. Product Data: In addition to submittal requirements specified in other sections, include
manufacturer's standard catalog pages and data sheets for equipment and protective
devices indicating information relevant to studies.
1. Include characteristic time-current trip curves for protective devices.
2. Clearly indicate whether proposed short circuit current ratings are fully rated or, where
acceptable, series rated systems.
3. Include documentation of listed series ratings upon request.
4. Identify modifications made in accordance with studies that:
a. Can be made at no additional cost to Owner.
b. As submitted will involve a change to the contract sum.
F. Arc Flash Hazard Warning Label Samples: One of each type and legend specified.
G. Site-specific arc flash hazard warning labels.
H. Field quality control reports.
I. Certification that field adjustable protective devices have been set in accordance with
requirements of studies.
J. Project Record Documents: Revise studies as required to reflect as-built conditions.
1. Include hard copies with operation and maintenance data submittals.
2. Include computer software files used to prepare studies with file name(s) cross-
referenced to specific pieces of equipment and systems.
PART 2 PRODUCTS
2.01 ARC FLASH HAZARD WARNING LABELS
A. Provide warning labels complying with ANSI Z535.4 to identify arc flash hazards for each
work location analyzed by the arc flash and shock risk assessment.
1. Materials: Comply with Section 26 0553.
2. Legend: Provide custom legend in accordance with NFPA 70E based on equipment-
specific data as determined by arc flash and shock risk assessment.
a. Include orange header that reads "WARNING".
b. Include the text "Arc Flash and Shock Hazard; Appropriate PPE Required" or
approved equivalent.
c. Include the following information:
1) Arc flash boundary.
2) Available incident energy and corresponding working distance.
3) Site-specific PPE (personnel protective equipment) requirements.
4) Nominal system voltage.
5) Limited approach boundary.
6) Restricted approach boundary.
7) Equipment identification.
8) Date calculations were performed.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install arc flash warning labels in accordance with Section 26 0553.
3.04 ATTACHMENTS
A. Previous studies.
B. Existing drawings.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Electrical connections to equipment.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide wiring device manufacturer’s catalog information showing
dimensions, configurations, and construction.
C. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by product testing agency. Include instructions for storage, handling, protection,
examination, preparation, and installation of product.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that equipment is ready for electrical connection, wiring, and energization.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Programmable controllers.
B. Remote input/output units.
C. Programmer/loader unit.
1.03 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings: Indicate electrical characteristics and connection requirements, including
layout of completed assemblies, interconnecting cabling, dimensions, weights, and external
power requirements.
C. Product Data: Provide data for each component specified showing electrical characteristics
and connection requirements.
D. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, installation, and starting of product.
E. Project Record Documents: Record actual locations of controller cabinets and input and
output devices connected to system. Include interconnection wiring and cabling
information, and terminal block layouts in controller cabinets.
F. Operation Data: Include bound copies of operating and programming instructions.
G. Maintenance Data: Include card replacement, adjustments, and preventative maintenance
procedures and materials.
PART 2 PRODUCTS
2.01 PROGRAMMABLE CONTROLLER
A. Description: Programmable controller manufactured to NEMA ICS 3 Part 2.
B. Configuration:
1. Processor Unit: Include processor, power supply, random access memory and
input/output modules.
2. Remote Input/Output Unit: Include input/output modules, interface module and power
supply for system inputs and outputs.
D. Programming Instruction Set:
1. Language Characteristics: Ladder diagram.
2. Logic Operations: AND, OR, XOR, NOT.
3. Register Operations: Store, recall.
4. Arithmetic Operations: Addition, subtraction, multiplication, division, square root.
5. Process Control: Proportional-Integral-Derivative.
6. Other Functions: Timing; counter; data moving operations.
E. Processor Unit:
1. Memory Size: 16 KB.
2. Storage Registers: 48.
3. Internal Relay Equivalents: 256 retentive; 256 non-retentive.
F. Input/Output Units:
1. Remote Input Output Communications Unit: RS 232.
G. Power Supply: Input voltage of 220 volts, 60 Hz.
H. Enclosure: NEMA ICS 6; Type 12.
I. Programmer/Loader Unit: Manual graphic display type.
PART 3 EXECUTION
3.01 INSTALLATION
A. Install in accordance with manufacturer's instructions.
B. Do not install products until major construction is complete and building interior is enclosed
and heated.
C. Connect input and output devices as indicated.
3.04 MAINTENANCE
A. See Section 01 7000 - Execution and Closeout Requirements, for additional requirements
relating to maintenance service.
B. Provide a separate maintenance contract for specified maintenance service.
C. Provide manufacturer's service and maintenance of programmable controllers for one year
from Date of Substantial Completion.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Low-voltage (600V and less) arc-resistant metal-enclosed drawout switchgear and
accessories for service and distribution applications.
B. Low-voltage power circuit breakers for switchgear.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
switchgear, enclosures, overcurrent protective devices, and other installed components and
accessories.
1. Include characteristic trip curves for each type and rating of overcurrent protective
device.
2. Arc-Resistant Switchgear: Indicate IEEE C37.20.7 accessibility type, and maximum
fault current and arc duration.
C. Shop Drawings: Indicate dimensions, voltage, bus ampacities, overcurrent protective
device arrangement and sizes, short circuit current ratings, short-time current ratings,
conduit entry locations, conductor terminal information, and installed features and
accessories.
1. Include dimensioned plan and elevation views of switchgear and adjacent equipment
with all required clearances indicated.
2. Include wiring diagrams showing all factory and field connections.
3. Include documentation demonstrating selective coordination upon request.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Low-Voltage Switchgear - Other Acceptable Manufacturers:
1. ABB
2. Eaton Corporation
3. Schneider Electric; Square D
4. Alfanar; Terasaki
5. Siemens
B. Substitutions: See Section 01 6000 - Product Requirements.
C. Products other than basis of design are subject to compliance with specified requirements
and prior approval of Engineer. By using products other than basis of design, Contractor
accepts responsibility for costs associated with any necessary modifications to related work,
including any design fees.
D. Source Limitations: Furnish switchgear and associated components produced by the same
manufacturer as the other electrical distribution equipment used for this project and
obtained from a single supplier.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install switchgear in accordance with NECA 1 (general workmanship) and IEEE C37.20.1.
C. Arrange equipment to provide required clearances and maintenance access, including
accommodations for drawout circuit breakers.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Provide required seismic controls in accordance with Section 26 0548.
F. Install switchgear plumb and level.
G. Unless otherwise indicated, mount switchgear on properly sized 4 inch (100 mm) high
concrete pad constructed in accordance with Section 03 3000.
H. Provide grounding and bonding in accordance with Section 26 0526.
I. Install all field-installed devices, components, and accessories.
J. Provide fuses complying with Section 26 2813 for fused circuit breakers as indicated.
K. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
L. Set field-adjustable circuit breaker tripping function settings as determined by overcurrent
protective device coordination study performed in accordance with Section 26 0573.
M. Set field-adjustable ground fault protection pickup and time delay settings as indicated.
N. Identify switchgear in accordance with Section 26 0553.
3.04 WARRANTY
A. Submit written guarantee signed by the contractor and manufacturer for the period of one
year from the date of substantial completion. The guarantee shall cover the repair and
replacement of defective materials and workmanship as directed by the Engineer.
3.05 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
B. Adjust alignment of switchgear covers and doors.
3.06 CLEANING
A. Clean dirt and debris from switchgear enclosures and components according to
manufacturer's instructions.
B. Repair scratched or marred surfaces to match original factory finish.
3.08 PROTECTION
A. Protect installed switchgear assemblies from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Low-voltage (600 V and less) switchboards and associated accessories for service and
distribution applications.
B. Overcurrent protective devices for switchboards.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
switchboards, enclosures, overcurrent protective devices, and other installed components
and accessories.
1. Include characteristic trip curves for each type and rating of overcurrent protective
device upon request.
C. Shop Drawings: Indicate dimensions, voltage, bus ampacities, overcurrent protective
device arrangement and sizes, short circuit current ratings, conduit entry locations,
conductor terminal information, and installed features and accessories.
1. Include dimensioned plan and elevation views of switchboards and adjacent
equipment with all required clearances indicated.
2. Include wiring diagrams showing all factory and field connections.
3. Clearly indicate whether proposed short circuit current ratings are fully rated or, where
acceptable, series rated systems.
4. Include documentation of listed series ratings upon request.
5. Include documentation demonstrating selective coordination upon request.
6. Identify mounting conditions required for equipment seismic qualification.
D. Manufacturer's equipment seismic qualification certification.
E. Service Entrance Switchboards: Include documentation of Utility Company approval of
switchboard.
F. Source Quality Control Test Reports: Include reports for tests designated in NEMA PB 2 as
production (routine) tests.
G. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
H. Field Quality Control Test Reports.
I. Project Record Documents: Record actual installed locations of switchboards and final
equipment settings.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Switchboards:
1. ABB
2. Eaton Corporation
3. Schneider Electric; Square D
4. Alfanar; Terasaki
5. Siemens
B. Substitutions: See Section 01 6000 - Product Requirements.
C. Products other than basis of design are subject to compliance with specified requirements
and prior approval of Engineer. By using products other than basis of design, Contractor
accepts responsibility for costs associated with any necessary modifications to related work,
including any design fees.
D. Source Limitations: Furnish switchboards and associated components produced by the
same manufacturer as the other electrical distribution equipment used for this project and
obtained from a single supplier.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings and configurations of the switchboards and associated components
are consistent with the indicated requirements.
C. Verify that mounting surfaces are ready to receive switchboards.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install switchboards in accordance with NECA 1 (general workmanship), NECA 400, and
NEMA PB 2.1.
C. Arrange equipment to provide required clearances and maintenance access, including
accommodations for any drawout devices.
D. Where switchboard is indicated to be mounted with inaccessible side against wall, provide
minimum clearance of 1/2 inch (10 mm) between switchboard and wall.
E. Provide required support and attachment in accordance with Section 26 0529.
F. Install switchboards plumb and level.
G. Unless otherwise indicated, mount switchboards on properly sized 4 inch (100 mm) high
concrete pad constructed in accordance with Section 03 3000.
H. Provide grounding and bonding in accordance with Section 26 0526.
I. Install all field-installed devices, components, and accessories.
J. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
K. Set field-adjustable circuit breaker tripping function settings as determined by overcurrent
protective device coordination study performed in accordance with Section 26 0573.
3.04 WARRANTY
A. Submit written guarantee signed by the contractor and manufacturer for the period of one
year from the date of substantial completion. The guarantee shall cover the repair and
replacement of defective materials and workmanship as directed by the Engineer.
3.05 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
B. Adjust alignment of switchboard covers and doors.
3.06 CLEANING
A. See Section 01 7419 - Construction Waste Management and Disposal, for additional
requirements.
3.08 PROTECTION
A. Protect installed switchboards from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Power distribution panelboards.
B. Overcurrent protective devices for panelboards.
R. SASO 1611 Low voltage switchgear and control gear assemblies - Part 3: Particular
requirements for the assemblies intended to be installed in places where unskilled persons
have access for their use-distribution boards.
S. IEC 60947-1: Low Voltage Switchgear and Control Gear: Part 1: General Rules.
T. IEC 60947-2: Low Voltage Switchgear and Control Gear: Part 2: Circuit Breakers
U. IEC 60529: Degrees of protection provided by enclosure (IP Code)
V. IEC 60068-2-30: a tropicalization process must undergo for all circuit breakers.
W. IEC 61439-1/-2: Low voltage switchgear and control gear assemblies - Part 1: Conforming
assemblies
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
panelboards, enclosures, overcurrent protective devices, and other installed components
and accessories.
1. Include characteristic trip curves for each type and rating of overcurrent protective
device upon request.
C. Shop Drawings: Indicate outline and support point dimensions, voltage, main bus ampacity,
overcurrent protective device arrangement and sizes, short circuit current ratings, conduit
entry locations, conductor terminal information, and installed features and accessories.
1. Include dimensioned plan and elevation views of panelboards and adjacent equipment
with all required clearances indicated.
2. Include wiring diagrams showing all factory and field connections.
3. Clearly indicate whether proposed short circuit current ratings are fully rated or, where
acceptable, series rated systems.
4. Include documentation of listed series ratings upon request.
5. Identify mounting conditions required for equipment seismic qualification.
D. Manufacturer's equipment seismic qualification certification.
E. Source Quality Control Test Reports: Include reports for tests designated in NEMA PB 1 as
routine tests.
F. Field Quality Control Test Reports.
G. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings and configurations of the panelboards and associated components
are consistent with the indicated requirements.
C. Verify that mounting surfaces are ready to receive panelboards.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship).
B. Install products in accordance with manufacturer's instructions.
C. Install panelboards in accordance with NECA 407 and NEMA PB 1.1.
R. Trim: Fix plumb and square prior to painting. Fix trim for flush mounted cabinets flush with
wall surface finish.
S. Protection: Treat concealed surfaces of recessed cabinets with heavy field application of
waterproof compound prior to installation.
T. Mounting Heights: Top of trim 1880 mm above finished floor, unless otherwise indicated.
U. Mounting: Plumb and rigid without distortion of box. Mount recessed panel boards with
fronts uniformly flush with wall finish.
V. Circuit Directory: Create a directory to indicate installed circuit loads after balancing panel
board loads. Obtain approval before installing. Use a computer or typewriter to create
directory; handwritten directories are not acceptable.
W. Provision for Future Circuits at Flush or Surface Panel boards: Stub four empty conduits
from panel board into accessible ceiling space or space designated to be ceiling space in
the future. Stub four empty conduits into raised floor space or below slab not on grade.
3.04 CONNECTIONS
A. Install equipment-grounding connections for panel boards with ground continuity to main
Electrical ground bus.
B. Tighten electrical connectors and terminals according to manufacturer's published torque
tightening Values.
3.04 WARRANTY
A. Submit written guarantee signed by the contractor and manufacturer for the period of one
year from the date of substantial completion. The guarantee shall cover the repair and
replacement of defective materials and workmanship as directed by the Engineer.
3.05 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
B. Adjust alignment of panelboard fronts.
C. Load Balancing: For each panelboard, rearrange circuits such that the difference between
each measured steady state phase load does not exceed 20 percent and adjust circuit
directories accordingly. Maintain proper phasing for multi-wire branch circuits.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Low-voltage (600 V and less) arc-resistant NEMA motor control centers.
B. Motor control center units:
1. Feeder units.
2. Combination magnetic motor starter units.
C. Overcurrent protective devices for motor control centers and associated units, including
overload relays.
D. Motor control accessories:
1. Auxiliary contacts.
2. Pilot devices.
3. Control and timing relays.
4. Control power transformers.
5. Control terminal blocks.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for motor
control centers, enclosures, units, overcurrent protective devices, and other installed
components and accessories.
1. Include characteristic trip curves for each type and rating of overcurrent protective
device upon request.
2. Arc-Resistant Motor Control Centers: Indicate IEEE C37.20.7 accessibility type, and
maximum fault current and arc duration.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Motor Control Centers - Other Acceptable Manufacturers:
1. ABB
2. Eaton Corporation
3. Schneider Electric; Square D
4. Alfanar; Terasaki
5. Siemens
B. Products other than basis of design are subject to compliance with specified requirements
and prior approval of Engineer. By using products other than basis of design, Contractor
accepts responsibility for costs associated with any necessary modifications to related work,
including any design fees.
C. Source Limitations: Furnish motor control centers and associated components produced by
a single manufacturer and obtained from a single supplier.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install motor control centers in accordance with NECA 1 (general workmanship), NECA
402, and NEMA ICS 2.3.
C. Arrange equipment to provide required clearances and maintenance access, including
accommodations for any drawout devices.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Provide required seismic controls in accordance with Section 26 0548.
F. Install motor control centers plumb and level.
G. Unless otherwise indicated, mount motor control centers on properly sized 4 inch (100 mm)
high concrete pad constructed in accordance with Section 03 3000.
H. Provide grounding and bonding in accordance with Section 26 0526.
I. Install all field-installed devices, components, and accessories.
J. Provide fuses complying with Section 26 2813 for fusible switches as indicated.
K. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
L. Set field-adjustable motor controllers and associated components according to installed
motor requirements, in accordance with manufacturer's recommendations and NFPA 70.
M. Set field-adjustable circuit breaker tripping function settings as determined by overcurrent
protective device coordination study performed in accordance with Section 26 0573.
N. Set field-adjustable ground fault protection pickup and time delay settings as indicated.
O. Provide filler plates to cover unused spaces.
P. Identify motor control centers in accordance with Section 26 0553.
3.04 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
B. Adjust alignment of motor control center covers and doors.
3.05 CLEANING
A. Clean dirt and debris from motor control center enclosures and components according to
manufacturer's instructions.
B. Repair scratched or marred surfaces to match original factory finish.
3.07 PROTECTION
A. Protect installed motor control centers from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Equipment for Owner electricity metering:
1. Single circuit electricity meters.
2. Multi-circuit electricity meters.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for
electricity metering systems and associated components and accessories. Include ratings,
configurations, standard wiring diagrams, dimensions, service condition requirements, and
installed features.
C. Shop Drawings: Include system interconnection schematic diagrams showing all factory
and field connections. Include requirements for interface with other systems.
D. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
E. Field Quality Control Test Reports.
F. Project Record Documents: Record actual installed locations of meters and final equipment
settings.
G. Maintenance Data: Include information on replacement parts and recommended
maintenance procedures and intervals.
H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Enclosure Keys: Two of each different key.
3. See Section 26 2813 for requirements for spare fuses and spare fuse cabinets.
F. Instrument Transformers:
1. Comply with IEEE C57.13, where applicable.
2. Select suitable ratio, burden, and accuracy as required for connected devices.
3. Current Transformers: Compatible with connected meters; replace meters damaged
by connection of incompatible current transformers. Provide shorting terminal blocks
for connection of secondaries where applicable.
4. Potential Transformers: Include primary and secondary fuses with disconnecting
means.
G. Interface with Other Work:
1. Interface with electrical power monitoring system.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings and configurations of metering systems and associated components
are consistent with the indicated requirements.
C. Verify that mounting surfaces are ready to receive meters.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship).
B. Install products in accordance with manufacturer's instructions.
C. Provide required support and attachment components in accordance with Section 26 0529.
D. Provide grounding and bonding in accordance with Section 26 0526.
E. Provide fuses complying with Section 26 2813 as required.
3.04 ADJUSTING
A. Program system parameters according to requirements of Owner or by the Owner
representative Electrical Engineer.
3.05 CLEANING
A. Clean exposed surfaces to remove dirt, paint, or other foreign material and restore to match
original factory finish.
3.07 PROTECTION
A. Protect installed system components from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Wall switches.
B. Wall dimmers.
C. Fan speed controllers.
D. Receptacles.
E. Wall plates.
F. Floor box service fittings.
G. Poke-through assemblies.
H. Access floor boxes.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's catalog information showing dimensions, colors, and
configurations.
1. Wall Dimmers: Include derating information for ganged multiple devices.
2. Surge Protection Receptacles: Include surge current rating, voltage protection rating
(VPR) for each protection mode, and diagnostics information.
C. Samples: One for each type and color of device and wall plate specified.
D. Certificates for Surge Protection Receptacles: Manufacturer's documentation of listing for
compliance with UL 1449.
E. Field Quality Control Test Reports.
F. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
G. Operation and Maintenance Data:
1. Wall Dimmers: Include information on operation and setting of presets.
2. GFCI Receptacles: Include information on status indicators.
3. Surge Protection Receptacles: Include information on status indicators.
H. Project Record Documents: Record actual installed locations of wiring devices.
I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Screwdrivers for Tamper-Resistant Screws: Two for each type of screw.
3. Extra Keys for Locking Switches: Two of each type.
4. Extra Surge Protection Receptacles: Two of each type.
5. Extra Wall Plates: One of each style, size, and finish.
6. Extra Flush Floor Service Fittings: Two of each type.
7. Extra Poke-Through Core Hole Closure Plugs: Two for each core size.
PART 2 PRODUCTS
2.01 WIRING DEVICE APPLICATIONS
A. Provide wiring devices suitable for intended use and with ratings adequate for load served.
B. For single receptacles installed on an individual branch circuit, provide receptacle with
ampere rating not less than that of the branch circuit.
C. Provide weather resistant GFCI receptacles with specified weatherproof covers for
receptacles installed outdoors or in damp or wet locations.
D. Provide tamper resistant receptacles for receptacles installed in dwelling units.
E. Provide GFCI protection for receptacles installed within 6 feet (1.8 m) of sinks.
F. Provide GFCI protection for receptacles installed in kitchens and toilets or any location that
are located on the wet areas.
G. Provide GFCI protection for receptacles serving electric drinking fountains.
H. Provide isolated ground receptacles for receptacles serving computers.
I. Unless noted otherwise, do not use combination switch/receptacle devices.
J. For flush floor service fittings, use tile rings for installations in tile floors.
K. For flush floor service fittings, use carpet flanges for installations in carpeted floors.
2.06 RECEPTACLES
A. Receptacles - General Requirements: Self-grounding, complying with NEMA WD 1 and
NEMA WD 6, and listed as complying with UL 498, and where applicable, FS W-C-596;
types as indicated on the drawings.
1. Wiring Provisions: Terminal screws for side wiring or screw actuated binding clamp
for back wiring with separate ground terminal screw.
2. NEMA configurations specified are according to NEMA WD 6.
B. GFCI Receptacles:
1. GFCI Receptacles - General Requirements: Self-testing, with feed-through protection
and light to indicate ground fault tripped condition and loss of protection; listed as
complying with UL 943, class A.
a. Provide test and reset buttons of same color as device.
C. USB Charging Devices:
1. USB Charging Devices - General Requirements: Listed as complying with UL 1310.
a. Charging Capacity - Two-Port Devices: 2.1 A, minimum.
b. Charging Capacity - Four-Port Devices: 4.2 A, minimum.
2. USB Charging/Tamper Resistant Receptacle Combination Devices: Two-port (Type
A) USB charging device and receptacle, commercial specification grade, duplex, 20A,
220V, listed and labeled as tamper resistant type; rectangular decorator style.
D. Surge Protection Receptacles:
1. Surge Protection Receptacles - General Requirements: Listed and labeled as
complying with UL 1449, Type 2 or 3.
a. Energy Dissipation: Not less than 240 J per mode.
b. Protected Modes: L-N, L-G, N-G.
c. UL 1449 Voltage Protection Rating (VPR): Not more than 700 V for L-N, L-G
modes and 1200 V for N-G mode.
d. Diagnostics:
1) Visual Notification: Provide indicator light to report functional status of surge
protection.
2) Audible Notification: Provide switchable audible alarm to report that surge
protection is not functional.
2. Standard Surge Protection Receptacles: Industrial specification grade, duplex, 20A,
220V, rectangular decorator style.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that outlet boxes are installed in proper locations and at proper mounting heights and
are properly sized to accommodate devices and conductors in accordance with NFPA 70.
C. Verify that wall openings are neatly cut and will be completely covered by wall plates.
D. Verify that final surface finishes are complete, including painting.
E. Verify that floor boxes are adjusted properly.
F. Verify that branch circuit wiring installation is completed, tested, and ready for connection to
wiring devices.
G. Verify that core drilled holes for poke-through assemblies are in proper locations.
H. Verify that openings in access floor are in proper locations.
I. Verify that conditions are satisfactory for installation prior to starting work.
3.02 PREPARATION
A. Provide extension rings to bring outlet boxes flush with finished surface.
B. Clean dirt, debris, plaster, and other foreign materials from outlet boxes.
3.03 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship) and, where applicable,
NECA 130, including mounting heights specified in those standards unless otherwise
indicated.
B. Coordinate locations of outlet boxes provided under Section 26 0533.16 as required for
installation of wiring devices provided under this section.
1. Orient outlet boxes for vertical installation of wiring devices unless otherwise indicated.
2. Where multiple receptacles, wall switches, or wall dimmers are installed at the same
location and at the same mounting height, gang devices together under a common
wall plate.
3.05 ADJUSTING
A. Adjust devices and wall plates to be flush and level.
3.06 CLEANING
A. Clean exposed surfaces to remove dirt, paint, or other foreign material and restore to match
original factory finish.
END OF SECTION
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard data sheets including voltage and current
ratings, interrupting ratings, time-current curves, and current limitation curves.
1. Spare Fuse Cabinet: Include dimensions.
PART 2 PRODUCTS
2.01 FUSES
A. Provide products listed, classified, and labeled as suitable for the purpose intended.
B. Unless specifically indicated to be excluded, provide fuses for all fusible equipment as
required for a complete operating system.
C. Provide fuses of the same type, rating, and manufacturer within the same switch.
D. Comply with UL 248-1.
E. Unless otherwise indicated, provide cartridge type fuses complying with NEMA FU 1, Class
and ratings as indicated.
F. Voltage Rating: Suitable for circuit voltage.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that fuse ratings are consistent with circuit voltage and manufacturer's
recommendations and nameplate data for equipment.
B. Verify that mounting surfaces are ready to receive spare fuse cabinet.
C. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Do not install fuses until circuits are ready to be energized.
B. Install fuses with label oriented such that manufacturer, type, and size are easily read.
C. Identify spare fuse cabinet in accordance with Section 26 0553.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Enclosed circuit breakers.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for circuit
breakers, enclosures, and other installed components and accessories.
1. Include characteristic trip curves for each type and rating of circuit breaker upon
request.
C. Shop Drawings: Indicate outline and support point dimensions, voltage and current ratings,
short circuit current ratings, conduit entry locations, conductor terminal information, and
installed features and accessories.
1. Include dimensioned plan and elevation views of enclosed circuit breakers and
adjacent equipment with all required clearances indicated.
2. Include wiring diagrams showing all factory and field connections.
3. Clearly indicate whether proposed short circuit current ratings are fully rated or, where
acceptable, series rated systems.
4. Include documentation of listed series ratings upon request.
5. Identify mounting conditions required for equipment seismic qualification.
D. Manufacturer's equipment seismic qualification certification.
E. Field Quality Control Test Reports.
F. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, installation, and starting of product.
G. Project Record Documents: Record actual installed locations of enclosed circuit breakers.
H. Maintenance Data: Include information on replacement parts and recommended
maintenance procedures and intervals.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings of the enclosed circuit breakers are consistent with the indicated
requirements.
C. Verify that mounting surfaces are ready to receive enclosed circuit breakers.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Arrange equipment to provide minimum clearances in accordance with manufacturer's
instructions and NFPA 70.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Provide required seismic controls in accordance with Section 26 0548.
F. Install enclosed circuit breakers plumb.
G. Install flush-mounted enclosed circuit breakers so that trims fit completely flush to wall with
no gaps and rough opening completely covered.
H. Except where indicated to be mounted adjacent to the equipment they supply, mount
enclosed circuit breakers such that the highest position of the operating handle does not
exceed 79 inches (2000 mm) above the floor or working platform.
I. Provide grounding and bonding in accordance with Section 26 0526.
J. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
K. Set field-adjustable circuit breaker tripping function settings as determined by overcurrent
protective device coordination study performed according to Section 26 0573.
L. Set field-adjustable ground fault protection pickup and time delay settings as directed.
M. Identify enclosed circuit breakers in accordance with Section 26 0553.
3.04 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
3.05 CLEANING
A. Clean dirt and debris from circuit breaker enclosures and components according to
manufacturer's instructions.
B. Repair scratched or marred exterior surfaces to match original factory finish.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Enclosed safety switches.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. ABB
B. Eaton Corporation
C. Schneider Electric
D. Siemens Industry
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings of the enclosed switches are consistent with the indicated
requirements.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Arrange equipment to provide minimum clearances in accordance with manufacturer's
instructions and NFPA 70.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Install enclosed switches plumb.
F. Except where indicated to be mounted adjacent to the equipment they supply, mount
enclosed switches such that the highest position of the operating handle does not exceed
79 inches (2000 mm) above the floor or working platform.
G. Provide grounding and bonding in accordance with Section 26 0526.
H. Provide fuses complying with Section 26 2813 for fusible switches as indicated or as
required by equipment manufacturer's recommendations.
I. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
J. Identify enclosed switches in accordance with Section 26 0553.
3.04 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
3.05 CLEANING
A. Clean dirt and debris from switch enclosures and components according to manufacturer's
instructions.
B. Repair scratched or marred exterior surfaces to match original factory finish.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Enclosed NEMA controllers for low-voltage (600 V and less) applications:
1. Magnetic motor starters.
2. General purpose contactors.
3. Manual motor starters.
4. Motor-starting switches without overload protection.
B. Overcurrent protective devices for motor controllers, including overload relays.
C. Control accessories:
1. Auxiliary contacts.
2. Pilot devices.
3. Control and timing relays.
4. Control power transformers.
5. Control terminal blocks.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide manufacturer's standard catalog pages and data sheets for motor
controllers, enclosures, overcurrent protective devices, and other installed components and
accessories.
1. Include characteristic trip curves for each type and rating of overcurrent protective
device upon request.
C. Shop Drawings: Indicate dimensions, voltage, controller sizes, short circuit current ratings,
conduit entry locations, conductor terminal information, and installed features and
accessories.
1. Include dimensioned plan and elevation views of enclosed controllers and adjacent
equipment with all required clearances indicated.
2. Include wiring diagrams showing all factory and field connections.
3. Clearly indicate whether proposed short circuit current ratings are fully rated or, where
acceptable, series rated systems.
4. Include documentation of listed series ratings upon request.
5. Include documentation demonstrating selective coordination upon request.
6. Identify mounting conditions required for equipment seismic qualification.
D. Manufacturer's equipment seismic qualification certification.
E. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
F. Field Quality Control Test Reports.
G. Project Record Documents: Record actual installed locations of controllers and final
equipment settings.
1. Include nameplate data of actual installed motors and associated overload relay
selections and settings.
2. Motor Circuit Protectors: Include magnetic instantaneous trip settings.
H. Maintenance Data: Include information on replacement parts and recommended
maintenance procedures and intervals.
I. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Electronic Trip Circuit Breakers: Provide one portable test set.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. ABB
B. Eaton Corporation
C. Schneider Electric
D. Siemens Industry
E. Source Limitations: Furnish enclosed motor controllers and associated components
produced by a single manufacturer and obtained from a single supplier.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that ratings of enclosed controllers are consistent with the indicated requirements.
C. Verify that mounting surfaces are ready to receive enclosed controllers.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install controllers in accordance with NECA 1 (general workmanship).
C. Arrange equipment to provide minimum clearances in accordance with manufacturer's
instructions and NFPA 70.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Provide required seismic controls in accordance with Section 26 0548.
F. Install enclosed controllers plumb and level.
G. Provide grounding and bonding in accordance with Section 26 0526.
H. Install all field-installed devices, components, and accessories.
I. Provide fuses complying with Section 26 2813 for fusible switches as indicated.
J. Where accessories are not self-powered, provide control power source as indicated or as
required to complete installation.
K. Set field-adjustable controllers and associated components according to installed motor
requirements, in accordance with manufacturer's recommendations and NFPA 70.
L. Set field-adjustable circuit breaker tripping function settings as determined by overcurrent
protective device coordination study performed in accordance with Section 26 0573.
3.04 ADJUSTING
A. Adjust tightness of mechanical and electrical connections to manufacturer's recommended
torque settings.
3.05 CLEANING
A. Clean dirt and debris from controller enclosures and components according to
manufacturer's instructions.
B. Repair scratched or marred exterior surfaces to match original factory finish.
3.07 PROTECTION
A. Protect installed enclosed controllers from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Variable frequency controllers.
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide catalog sheets showing voltage, controller size, ratings and size of
switching and overcurrent protective devices, short circuit ratings, dimensions, and
enclosure details.
C. Shop Drawings: Indicate front and side views of enclosures with overall dimensions and
weights shown; conduit entrance locations and requirements; and nameplate legends.
1. Identify mounting conditions required for equipment seismic qualification.
D. Manufacturer's equipment seismic qualification certification.
E. Test Reports: Indicate field test and inspection procedures and test results.
F. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by testing agency. Include instructions for storage, handling, protection, examination,
preparation, and installation of product.
G. Manufacturer's Field Reports: Indicate start-up inspection findings.
H. Operation Data: NEMA ICS 7.1. Include instructions for starting and operating controllers,
and describe operating limits that may result in hazardous or unsafe conditions.
I. Maintenance Data: NEMA ICS 7.1. Include routine preventive maintenance schedule.
J. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Extra Air Filters: Two of each type.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Products other than basis of design are subject to compliance with specified requirements
and prior approval of Engineer. By using products other than basis of design, Contractor
accepts responsibility for costs associated with any necessary modifications to related work,
including any design fees.
B. Source Limitations: Furnish variable frequency motor controllers and associated
components produced by a single manufacturer and obtained from a single supplier.
2.02 DESCRIPTION
A. Variable Frequency Controllers: Enclosed controllers suitable for operating the indicated
loads, in compliance with requirements of NEMA ICS 7. Select unspecified features and
options in accordance with NEMA ICS 3.1.
B. Seismic Qualification: Provide variable frequency controllers and associated components
suitable for application under the seismic design criteria specified in Section 26 0548 where
required. Include certification of compliance with submittals.
C. Enclosures: NEMA 250, Type 1, suitable for equipment application in places regularly open
to the public.
2.04 COMPONENTS
A. Display: Provide integral digital display to indicate output voltage, output frequency, and
output current.
B. Status Indicators: Separate indicators for overcurrent, overvoltage, ground fault,
overtemperature, and input power ON.
C. Furnish HAND-OFF-AUTOMATIC selector switch and manual speed control.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that surface is suitable for controller installation.
B. Do not install controller until building environment can be maintained within the service
conditions required by the manufacturer.
C. Verify that field measurements are as indicated on shop drawings.
3.02 INSTALLATION
A. Install in accordance with NEMA ICS 7.1 and manufacturer's instructions.
B. Provide required support and attachment in accordance with Section 26 0529.
C. Provide required seismic controls in accordance with Section 26 0548.
D. Tighten accessible connections and mechanical fasteners after placing controller.
E. Provide fuses in fusible switches; refer to Section 26 2813 for product requirements.
F. Select and install overload heater elements in motor controllers to match installed motor
characteristics.
G. Identify variable frequency controllers in accordance with Section 26 0553.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Photovoltaic system requirements.
B. Photovoltaic modules.
C. Photovoltaic module mounting system.
D. Photovoltaic combiner boxes.
E. Photovoltaic inverters.
F. Charge controllers.
G. Monitoring system.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Design Documents: Prepare and submit all information required for plan review and
permitting by authorities having jurisdiction, including but not limited to floor plans, riser
diagrams, details, and description of operation.
1.08 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Specified warranties indicate minimum requirements. Provide additional warranties or
extended warranty periods where required to qualify for rebate and incentive programs.
C. Photovoltaic Modules:
1. Provide minimum five year manufacturer warranty covering repair or replacement due
to defective materials or workmanship.
D. Photovoltaic Module Mounting System: Provide minimum 10 year manufacturer warranty
covering repair or replacement due to defective materials or workmanship.
E. Photovoltaic Combiner Boxes: Provide minimum five year manufacturer warranty covering
repair or replacement due to defective materials or workmanship.
F. Photovoltaic Inverters: Provide minimum five year manufacturer warranty covering repair or
replacement due to defective materials or workmanship.
G. Charge Controllers: Provide minimum five year manufacturer warranty covering repair or
replacement due to defective materials or workmanship.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Source Limitations: For each type of component, furnish products produced by a single
manufacturer and obtained from a single supplier.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that ratings and configurations of system components are consistent with the
indicated requirements.
C. Verify that mounting surfaces are ready to receive system components.
D. Verify that conditions are satisfactory for installation prior to starting work.
3.02 PREPARATION
A. Use open circuiting, short circuiting, or opaque covering to disable modules, array or
portions of array prior to installation and service.
B. Roof-Mounted Arrays: Protect roof and adjacent roof-mounted items from damage.
3.03 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship).
B. Install products in accordance with manufacturer's instructions.
C. Install photovoltaic system in accordance with NECA 412.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Provide required seismic controls in accordance with Section 26 0548.
F. Mount equipment such that the highest position of any operating handle for circuit breakers
or switches does not exceed 79 inches (2000 mm) above the floor, ground, or working
platform.
G. Provide cast-in-place concrete foundations for ground-mounted arrays as required,
constructed in accordance with Section 03 3000.
H. Foundation-Mounted Poles for Pole-Mounted Arrays:
1. Provide cast-in-place concrete foundations for poles as required, constructed in
accordance with Section 03 3000.
a. Install anchor bolts plumb per template furnished by pole manufacturer.
b. Position conduits to enter pole shaft.
2. Install foundations plumb.
3. Install poles plumb, using leveling nuts or shims as required to adjust to plumb.
4. Tighten anchor bolt nuts to manufacturer's recommended torque.
5. Install non-shrink grout between pole anchor base and concrete foundation, leaving
small channel for condensation drainage.
6. Install anchor base covers or anchor bolt covers as indicated.
3.06 CLEANING
A. Clean modules using only methods recommended by manufacturer to avoid scratches and
other damage. Clean exposed surfaces on other components to remove dirt, paint, or other
foreign material and restore to match original factory finish.
3.07 COMMISSIONING
A. See Section 01 9113 - General Commissioning Requirements for commissioning
requirements.
3.09 PROTECTION
A. Protect installed products from subsequent construction operations.
3.10 MAINTENANCE
A. See Section 01 7000 - Execution and Closeout Requirements, for additional requirements
relating to maintenance service.
B. Provide to Owner, a proposal as an alternate to the base bid, a separate maintenance
contract for the service and maintenance of photovoltaic system for two years from date of
Substantial Completion, to include the work described below; Include a complete
description of preventive maintenance, systematic examination, adjustment, cleaning,
inspection, and testing, with a detailed schedule.
C. Conduct site visit at least once every six months to perform inspection, testing, and
preventive maintenance. Conduct tests similar to those made during original field quality
control testing. Submit report to Owner comparing test results with those of original tests
along with evaluations and recommendations.
D. Provide trouble call-back service upon notification by Owner:
1. Include allowance for call-back service during normal working hours at no extra cost to
Owner.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Capacitors for low voltage (600 V or less) power factor correction applications:
1. Automatic capacitor systems.
1.09 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Capacitor Assemblies: Provide minimum one year manufacturer warranty covering repair
or replacement due to defective materials or workmanship.
C. Capacitor Cells: Provide minimum five year manufacturer warranty covering repair or
replacement due to defective materials or workmanship.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Power Factor Correction Capacitors:
1. ABB
2. Eaton Corporation
3. Schneider Electric
4. Siemens
B. Source Limitations: Furnish capacitor assemblies and associated components and
accessories produced by a single manufacturer and obtained from a single supplier.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that the ratings of capacitors are consistent with the indicated requirements.
C. Verify that mounting surfaces are ready to receive capacitors.
D. Verify that conditions are satisfactory for installation prior to starting work.
E. Examine conditions under which centralized automatic power factor capacitor assemblies
are to be installed. Notify the Engineer in writing of conditions detrimental to proper
completion of the work. Do not proceed with work until unsatisfactory conditions have been
corrected.
3.02 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship).
B. Install products in accordance with manufacturer's instructions.
C. Arrange equipment to provide minimum clearances and required maintenance access.
D. Provide required support and attachment in accordance with Section 26 0529.
E. Install capacitor assemblies plumb and level.
H. Upon completion of installation of equipment and after circuitry has been energized, test
equipment to demonstrate compliance with requirements. When possible, field-correct
malfunctioning units, then retest to demonstrate compliance; otherwise remove and replace
with new equipment and retest.
I. Prior to energization of low voltage switchgear and centralized automatic power factor
capacitor assemblies:
1. Perform insulating resistance test on each pole, phase-to-phase and phase-to-earth
for (1) minute. Minimum test voltage to be 1,000 volts D.C. with a minimum resistance
of 100 megohms.
2. Check centralized automatic power factor capacitor assemblies for continuity and for
short circuits.
3. Notify the Engineer of any abnormalities.
J. After assemblies are energized, demonstrate functioning in accordance with manufacturers
requirements.
K. Submit detailed reports indicating inspection and testing results and corrective actions
taken.
3.04 CLEANING
A. Clean exposed surfaces to remove dirt, paint, or other foreign material and restore to match
original factory finish.
3.06 PROTECTION
A. Protect installed capacitors from subsequent construction operations.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Strike (air) terminals and interconnecting conductors.
B. Grounding and bonding for lightning protection.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings: Indicate location and layout of air terminals, grounding electrodes, and
bonding connections to structure and other metal objects. Include terminal, electrode, and
conductor sizes, and connection and termination details.
1. Where conductors or grounds are to be embedded or concealed in other construction,
submit shop drawings at least 30 days prior to start of construction.
2. If concrete-encased grounds are to be used and are not shown in Contract
Documents, provide sufficient data to determine concrete encasement dimensions and
location.
3. Include data on actual ground resistance determined by field measurement in
accordance with NFPA 780.
4. Include engineering analysis of equalization of potential to metal bodies within the
structure.
5. Include access panels, test holes, and disconnecting means for maintenance.
C. Product Data: Provide dimensions and materials of each component, indication of testing
agency listing, and installation instructions.
D. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
E. Installation Certification: Submit copy of certification agency's approval.
F. Operation and Maintenance Data: Provide recommended inspection and testing plan,
including recommended intervals, to achieve periodic maintenance as recommended in
NFPA 780; provide customized plan reflecting actual installation configuration with specific
installed components identified.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Lightning Protection Components:
2.03 COMPONENTS
A. All Components: Complying with applicable requirements of UL 96.
B. Strike (Air) Terminals: Copper, solid, with adhesive bases for single-ply roof installations.
C. Grounding Rods: Solid copper.
D. Ground Plate: Copper.
E. Conductors: Copper cable.
F. Connectors and Splicers: Bronze.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated on shop drawings.
B. Coordinate work with installation of roofing and exterior and interior finishes.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Surge protective devices for distribution locations.
1.06 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Include detailed component information, voltage, surge current ratings,
repetitive surge current capacity, voltage protection rating (VPR) for all protection modes,
maximum continuous operating voltage (MCOV), nominal discharge current (I-n), short
circuit current rating (SCCR), connection means including any required external overcurrent
protection, enclosure ratings, outline and support point dimensions, weight, service
condition requirements, and installed features.
C. Shop Drawings: Include wiring diagrams showing all factory and field connections with wire
and circuit breaker/fuse sizes.
D. Certificates: Manufacturer's documentation of listing for compliance with the following
standards:
1. UL 1449.
2. UL 1283 (for Type 2 SPDs).
1.10 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Manufacturer's Warranty: Provide minimum five year warranty covering repair or
replacement of surge protective devices showing evidence of failure due to defective
materials or workmanship.
C. Exclude surge protective devices from any clause limiting warranty responsibility for acts of
nature, including lightning, stated elsewhere.
PART 2 PRODUCTS
2.01 MANUFACTURERS
A. Products other than basis of design are subject to compliance with specified requirements
and prior approval of Engineer. By using products other than basis of design, Contractor
accepts responsibility for costs associated with any necessary modifications to related work,
including any design fees.
B. Source Limitations: Furnish surge protective devices produced by a single manufacturer
and obtained from a single supplier.
3.02 INSTALLATION
A. Perform work in accordance with NECA 1 (general workmanship).
B. Install products in accordance with manufacturer's instructions.
C. Arrange equipment to provide minimum clearances in accordance with manufacturer's
instructions and NFPA 70.
D. Unless indicated otherwise, connect service entrance surge protective device on load side
of service disconnect main overcurrent device.
E. Provide conductors with minimum ampacity as indicated on the drawings, as required by
NFPA 70, and not less than manufacturer's recommended minimum conductor size.
F. Install conductors between SPD and equipment terminations as short and straight as
possible, not exceeding manufacturer's recommended maximum conductor length. Breaker
locations may be reasonably rearranged in order to provide leads as short and straight as
possible. Twist conductors together to reduce inductance.
G. Do not energize SPD until bonding of neutral and ground for service entrance and
separately derived systems is complete in accordance with Section 26 0526 where
applicable. Replace SPDs damaged by improper or missing neutral-ground bond.
H. Disconnect SPD prior to performing any high potential testing. Replace SPDs damaged by
performing high potential testing with SPD connected.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Interior luminaires.
B. Ballasts and drivers.
C. LED retrofit luminaire conversion kits.
D. Accessories.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings:
1. Indicate dimensions and components for each luminaire that is not a standard product
of the manufacturer.
2. Provide photometric calculations where luminaires are proposed for substitution upon
request.
C. Product Data: Provide manufacturer's standard catalog pages and data sheets including
detailed information on luminaire construction, dimensions, ratings, finishes, mounting
requirements, listings, service conditions, photometric performance, installed accessories,
and ceiling compatibility; include model number nomenclature clearly marked with all
proposed features.
1. LED Luminaires:
a. Include estimated useful life, calculated based on IES LM-80 test data.
b. Include IES LM-79 test report upon request.
2. Lamps: Include rated life, color temperature, color rendering index (CRI), and initial
and mean lumen output.
D. Samples:
1. Provide one sample(s) of each specified luminaire where indicated.
E. Field quality control reports.
F. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, and installation of product.
G. Operation and Maintenance Data: Instructions for each product including information on
replacement parts.
H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Extra Lamps: Ten percent of total quantity installed for each type, but not less than
two of each type.
I. Project Record Documents: Record actual connections and locations of luminaires and any
associated remote components.
1.09 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Provide three year manufacturer warranty for LED luminaires, including drivers.
PART 2 PRODUCTS
2.01 LUMINAIRE TYPES
A. Furnish products as indicated in luminaire schedule included on the drawings.
2.02 LUMINAIRES
A. Provide products that comply with requirements of NFPA 70.
B. Provide products that are listed and labeled as complying with UL 1598, where applicable.
C. Provide products listed, classified, and labeled as suitable for the purpose intended.
D. Unless otherwise indicated, provide complete luminaires including lamp(s) and all sockets,
ballasts, reflectors, lenses, housings and other components required to position, energize
and protect the lamp and distribute the light.
E. Unless specifically indicated to be excluded, provide all required conduit, boxes, wiring,
connectors, hardware, supports, trims, accessories, etc. as necessary for a complete
operating system.
F. Provide products suitable to withstand normal handling, installation, and service without any
damage, distortion, corrosion, fading, discoloring, etc.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify that outlet boxes are installed in proper locations and at proper mounting heights and
are properly sized to accommodate conductors in accordance with NFPA 70.
C. Verify that suitable support frames are installed where required.
D. Verify that branch circuit wiring installation is completed, tested, and ready for connection to
luminaires.
E. Verify that conditions are satisfactory for installation prior to starting work.
3.02 PREPARATION
A. Provide extension rings to bring outlet boxes flush with finished surface.
B. Clean dirt, debris, plaster, and other foreign materials from outlet boxes.
3.03 INSTALLATION
A. Coordinate locations of outlet boxes provided under Section 26 0533.16 as required for
installation of luminaires provided under this section.
B. Perform work in accordance with NECA 1 (general workmanship).
3.05 ADJUSTING
A. Aim and position adjustable luminaires to achieve desired illumination as indicated or as
directed by Architect or Engineer. Secure locking fittings in place.
3.08 PROTECTION
A. Protect installed luminaires from subsequent construction operations.
3.09 ATTACHMENTS
A. Luminaire schedule.
B. Luminaire cut sheets.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Exterior luminaires.
B. Ballasts and Drivers
C. Lamps.
D. LED retrofit luminaire conversion kits.
E. Poles and accessories.
F. Luminaire accessories.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings:
1. Indicate dimensions and components for each luminaire that is not a standard product
of the manufacturer.
2. Provide photometric calculations where luminaires are proposed for substitution upon
request.
3. Provide structural calculations for each pole proposed for substitution.
C. Product Data: Provide manufacturer's standard catalog pages and data sheets including
detailed information on luminaire construction, dimensions, ratings, finishes, mounting
requirements, listings, service conditions, photometric performance, weight, effective
projected area (EPA), and installed accessories; include model number nomenclature
clearly marked with all proposed features.
1. LED Luminaires:
a. Include estimated useful life, calculated based on IES LM-80 test data.
b. Include IES LM-79 test report upon request.
2. Poles: Include information on maximum supported effective projected area (EPA) and
weight for the design wind speed.
D. Samples:
1. Provide one sample(s) of each specified luminaire upon request.
2. Provide one sample(s) of each luminaire proposed for substitution upon request.
3. Provide one sample of each product finish illustrating color and texture upon request.
E. Field Quality Control Reports.
1. Include test report indicating measured illumination levels.
F. Manufacturer's Installation Instructions: Indicate application conditions and limitations of
use stipulated by product testing agency. Include instructions for storage, handling,
protection, examination, preparation, installation, and starting of product.
G. Operation and Maintenance Data: Instructions for each product including information on
replacement parts.
H. Maintenance Materials: Furnish the following for Owner's use in maintenance of project.
1. See Section 01 6000 - Product Requirements, for additional provisions.
2. Extra Lamps: Ten percent of total quantity installed for each type, but not less than
two of each type.
I. Project Record Documents: Record actual connections and locations of pole foundations,
luminaires, and any pull or junction boxes.
1.08 WARRANTY
A. See Section 01 7800 - Closeout Submittals, for additional warranty requirements.
B. Provide three year manufacturer warranty for all LED luminaires, including drivers.
C. Provide three year manufacturer warranty for LED retrofit luminaire conversion kits.
PART 2 PRODUCTS
2.01 LUMINAIRE TYPES
A. Furnish products as indicated in luminaire schedule included on the drawings.
B. Substitutions: See Section 01 6000 - Product Requirements.
2.02 LUMINAIRES
A. Provide products that comply with requirements of NFPA 70.
B. Provide products that are listed and labeled as complying with UL 1598, where applicable.
C. Provide products listed, classified, and labeled as suitable for the purpose intended.
D. Unless otherwise indicated, provide complete luminaires including lamp(s) and all sockets,
ballasts, reflectors, lenses, housings and other components required to position, energize
and protect the lamp and distribute the light.
E. Unless specifically indicated to be excluded, provide all required conduit, boxes, wiring,
connectors, hardware, poles, foundations, supports, trims, accessories, etc. as necessary
for a complete operating system.
F. Provide products suitable to withstand normal handling, installation, and service without any
damage, distortion, corrosion, fading, discoloring, etc.
G. Provide luminaires listed and labeled as suitable for wet locations unless otherwise
indicated.
H. LED Luminaires:
1. Components: UL 8750 recognized or listed as applicable.
2. Tested in accordance with IES LM-79 and IES LM-80.
3. LED Estimated Useful Life: Minimum of 50,000 hours at 70 percent lumen
maintenance, calculated based on IES LM-80 test data.
3.02 PREPARATION
A. Provide extension rings to bring outlet boxes flush with finished surface.
B. Clean dirt, debris, plaster, and other foreign materials from outlet boxes.
3.03 INSTALLATION
A. Coordinate locations of outlet boxes provided under Section 26 0533.16 as required for
installation of luminaires provided under this section.
B. Perform work in accordance with NECA 1 (general workmanship).
C. Install products in accordance with manufacturer's instructions.
D. Install luminaires in accordance with NECA/IESNA 501.
E. Provide required support and attachment in accordance with Section 26 0529.
F. Install luminaires plumb and square and aligned with building lines and with adjacent
luminaires.
G. Install accessories furnished with each luminaire.
H. Bond products and metal accessories to branch circuit equipment grounding conductor.
I. Install LED lamps in each luminaire.
3.05 ADJUSTING
A. Aim and position adjustable luminaires to achieve desired illumination as indicated or as
directed by Architect. Secure locking fittings in place.
B. Luminaires with Field-Rotatable Optics: Position optics according to manufacturer's
instructions to achieve lighting distribution as indicated or as directed by Architect.
3.06 CLEANING
A. Clean surfaces according to NECA/IESNA 501 and manufacturer's instructions to remove
dirt, fingerprints, paint, or other foreign material and restore finishes to match original
factory finish.
3.08 PROTECTION
A. Protect installed luminaires from subsequent construction operations.
3.09 ATTACHMENTS
A. Luminaire schedule.
B. Luminaire cut sheets.
END OF SECTION
B. Concrete hand holes: Molded or Concrete material, with reinforced concrete structure, with a
heavy duty Ductile Iron Frame and Cover of rating grade ‘A’
1. Standard: Comply with ASTM C 857.
2. Configuration: Designed for flush burial with open bottom unless otherwise indicated.
3. Cover: Weatherproof, secured by tamper-resistant locking devices and having structural
load rating consistent with enclosure and hand hole location.
4. Cover Finish: Nonskid finish shall have a minimum coefficient of friction of 0.50.
5. Cover Legend: Molded lettering, "COMMUNICATIONS" or other custom logos and text.
6. Conduit Entrance Provisions: Conduit-terminating fittings shall mate with entering ducts
for secure, fixed installation in enclosure wall.
7. Hand holes size and size is 800mm x 800mm x 750mm (W x L x D).
C. Maintenance Hole:
1. Refer to Section 33 8126 - Communications Underground Ducts, Manholes and
Handholds for details.
2. Shall be inside dimensions 2750mm long by 1500mm wide 2000mm high unless
otherwise specified on the Drawings and Specifications. The exact manhole size and
configuration shall be submitted to client for approval.
3. The manhole hole shall be constructed of reinforced pre-cast concrete, 316.4 kg/cm2 and
designed for truck loading.
END OF SECTION
PART 1 GENERAL
1.2 REFERENCES
C. UL – Underwriters Laboratories.
1.3 SUBMITTALS
B. Conform to ISO 14025 and EN 15804 or ISO 21930 in the development of life cycle assessments
(LCA) and Type III environmental product declarations (EPD).
C. All cable and equipment shall be installed in a neat and workmanlike manner. All methods of
construction that are not specifically described or indicated in the contract documents shall be subject
to the control and approval of the Owner or Owner Representative. Equipment and materials shall
be of the quality and manufacture indicated. The equipment specified is based upon the acceptable
manufacturers listed. Where “approved equal” is stated, equipment shall be equivalent in every way
to that of the equipment specified and subject to approval.
D. Strictly adhere to all Building Industry Consulting Service International (BICSI), Electronic Industries
Alliance (EIA) and Telecommunications Industry Association (TIA) recommended installation
practices when installing communications/data cabling.
E. Material and work specified herein shall comply with the applicable requirements of:
1.5 SUBMITTALS
1. Manufacturers cut sheets, specifications and installation instructions for all products (submit
with bid).
A. Delivery: Deliver materials to site in manufacturer’s original, unopened containers and packaging,
with labels clearly identifying product name and manufacturer.
B. Storage: Store materials in clean, dry area indoors in accordance with manufacturer’s instructions.
C. Handling: Protect materials and finish during handling and installation to prevent damage.
1.6 WARRANTY
PART 2 PRODUCTS
2.1 MANUFACTURER
A. Middle Atlantic Products, Inc. Phone (973) 839-1011. Fax (973) 839-1976. Website
middleatlantic.com. E-mail [email protected].
1. Customizable 42U rack is configured to be compatible with almost all server manufacturer’s
equipment. 42U Racks feature a symmetrical frame to allow enclosures to be bayed in space-
saving layouts, including side-by-side, one in front of another, in a corner, in U or T
arrangements, all without the need for an expensive intermediate frame.
2. The 16-fold frame design allows for the integrated channel above-the-joint on the horizontal
frame section, which prevents liquid from collecting on the gasket and from penetrating the
door or side panel when opened. The frame system provides multiple internal surfaces and
points for mounting equipment and accessories. The top panel of the 42U Rack is secured with
the standard eye-bolts. Whether you require a top panel for cable entry or for ventilation, it can
be quickly replaced by loosening 4 screws. This stable, static design permits use of roof-
mounted cooling units. An integrated water/dust protection lip protects the gasket roof
configurations.
1009DF / MISHRIFAH VILLA 27 1116 - 2 LOW-PROFILE WALL-MOUNT
EQUIPMENT RACKS
3. The 42U Rack’s door system includes a four-point locking system. The door can be easily
rotated so it can be hinged from the left or right. The side panels can be screwed on, locked in
place, or hinged to provide side door access.
2.3 OPTIONS
PART 3 EXECUTION
3.1 EXAMINATION
B. Notify Architect of conditions that would adversely affect installation or subsequent use.
1009DF / MISHRIFAH VILLA 27 1116 - 3 LOW-PROFILE WALL-MOUNT
EQUIPMENT RACKS
C. Do not begin installation until unacceptable conditions are corrected.
3.2 INSTALLATION
B. Install low-profile, wall-mount equipment racks plumb, level, square, and secure.
1. Assemble relay racks according to manufacturer’s instructions. Verify that equipment mounting
rails are sized properly for rack-mount equipment before attaching the rack to the floor.
2. All racks must be attached to the floor in four places using appropriate floor mounting anchors.
When placed over a raised floor, threaded rods should pass through the raised floor tile and be
secured in the structural floor below. (Use CPI Part Number 40604-003 for concrete slab floors
or 40607-001 wood floors. Raised floor support kits are also available.)
3. Racks shall be grounded to the TGB using appropriate hardware provided by the contractor.
The ground will meet local code requirements and will be approved by the Authority Having
Jurisdiction (AHJ).
4. In seismic areas, the rack should have additional bracing as required by building codes and the
recommendations of a licensed structural engineer.
5. Ladder rack may be attached to the top of the rack to deliver cables to the rack. The rack shall
not be drilled to attach ladder rack. Use appropriate hardware from the ladder rack
manufacturer.
6. The equipment load will be evenly distributed and uniform on the rack. Place large and heavy
equipment towards the bottom of the rack. Secure all equipment to the rack with equipment
mounting screws. In seismic areas, secure equipment to shelves with additional bracing.
3.3 ADJUSTING
B. Repair minor damages to finish in accordance with manufacturer’s instructions and as approved by
Architect.
3.4 PROTECTION
A. Protect installed low-profile, wall-mount equipment racks from damage during construction.
END OF SECTION
a. Technical Information
1) Standard Requirements: Telcordia GR-771 tested
2) Application: Customer premises environments, environments
3) Mounting Type: Pole-mount, Wall-Mountable
4) Product Type: FOH Closures
5) Fiber Management: Configuration Full slack storage basket - tray stacker
6) Ground Feed through Cable Entries: 1
7) Number of Feeder Ports: 2 2 / 8 ports: 2 feeder ports and 6 drop ports
8) Number of Ports 8
9) SCF Type 8-inch canister, 28 in LID
10) Splicing Capacity 288
11) Splice Tray Stacker Configuration 0.4-in tray height (single-fiber or ribbon).
12) Dimensions: Diameter and Length 20.8 cm x 71.1 cm8.2 in x 28 in
13) Outside Diameter with Clamp 12.1 in (30 cm)
14) Weight 10 kg (22 lb)
B. CABLE MANAGEMENT
1. The Cable Management System shall be used to provide a neat and efficient means for
routing and protecting fiber and copper cables and patch cords on telecommunication
racks and enclosures. The system shall be a complete cable management system
PART 3 EXECUTION
3.1 OPTICAL FIBER TERMINATION HARDWARE
A. Fiber slack shall be neatly coiled within the fiber splice tray or enclosure. No slack loops shall
be allowed external to the fiber panel.
B. Each cable shall be individually attached to the respective fiber enclosure by mechanical
means. The cables strength member shall be securely attached the cable strain relief bracket
in the enclosure.
C. Each fiber bundle shall be stripped upon entering the splice tray and the individual fibers routed
in the splice tray.
D. Each cable shall be clearly labeled at the entrance to the splice enclosure. Cables labeled
within the bundle shall not be acceptable.
E. A maximum of 24 strands of fiber shall be spliced in each tray. All spare strands shall be
installed and stored into spare splice trays.
3.2 BACKBONE CABLE INSTALLATION
A. Backbone cables shall be installed separately from horizontal distribution cables
B. A pull cord (nylon; 1/8" minimum) shall be co-installed with all cable installed in any conduit.
C. Where cables are housed in conduits, the backbone and horizontal cables shall be installed in
separate conduits
D. Where cables are installed in an air return plenum, riser rated cable shall be installed in metallic
conduit.
E. Where backbone cables and distribution cables are installed in a cable tray or wireway,
backbone cables shall be installed first and bundled separately from the horizontal distribution
cables.
F. All backbone cables shall be securely fastened to the sidewall of the TR on each floor.
Backbone cables spanning more than three floors shall be securely attached at the top of the
cable run with a wire mesh grip and on alternating floors or as required by local codes.
G. Vertical runs of cable shall be supported to messenger strand, cable ladder, or other method to
provide proper support for the weight of the cable.
H. Large bundles of cables and/or heavy cables shall be attached using metal clamps and/or
metal banding to support the cables.
3.3 RACKS
A. Racks shall be securely attached to the concrete floor using minimum 10mm hardware or as
required by local codes.
END OF SECTION
PART 2 PRODUCTS
2.1 GENERAL
A. All materials shall meet or exceed all applicable referenced standards, federal, state and local
requirements, and conform to codes and ordinances of authorities having jurisdiction.
1. Network Router
RJ45 ports support 10/100/1000 Ethernet connections. A WAN port is active only if the
corresponding SFP port is empty. By default, the WAN1 port is set to DHCP Client.
SFP ports are hot-swappable and support 10/100/1000 fiber SFP modules. If an SFP module
is plugged in, then the SFP port is active, and the corresponding WAN port is deactivated. By
default, the SFP1 port is set to DHCP Client.
VLAN 802.1Q
Advanced QoS Per-User Rate Limiting
Guest Traffic Isolation Supported
WMM Voice, Video, Best Effort, and Background
Concurrent Clients 250+
PART 3 EXECUTION
3.1 INSTALLERS
A. Submit written proof that the following experience requirements are being met:
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of contract, including General and Supplementary Conditions,
Division 01 Specification Sections apply to this section.
B. Requirements specified in the following sections apply to this Section:
1. Section "Basic Division 16 Requirements."
2. Section "Conduit Rough-In Systems."
3. Section “Raceways”
4. Section “Cabinets and Racks”
5. Section "Structured Cabling Systems."
6. Section “Data Network Electronics”
7. Section “Real Time Location Systems”
1.2 SUMMARY
A. This Section includes Internet Protocol Television Distribution System for distribution of live and
recorded sources in high definition format including all software, hardware, licensing and
programming.
B. This Section includes requirements for video and sound system components including, but not
limited to, the following:
1. The system shall be able to deliver IP video and signaling over the Ethernet network to
enable video distribution and control throughout the whole building.
2.
The video distribution system shall be capable of distributing a digital video signal, CATV
and satellite program sources as well as locally generated program sources (e.g. DVD,
1009DF / MISHRIFAH VILLA 27 4133 - 1 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
Character Generator, video on demand, etc) to any data network output locations as
described in these specifications and shown on Drawings. The system shall provide High
Definition video and audio to these locations.
a. The initial installed distribution system shall contain componentry to distribute 140
standard and high definition television stations, additional new satellite television
stations, Hotel locally generated program sources (VCR, billboard, DVD, laser disk,
satellite), local video origination stations and digitally stored content on demand
services.
3. Refer to video distribution riser diagram on Drawings and details for general information of
the system intent and functionality.
4. Provide video servers, IP receivers to receive incoming High definition and standard
definition signals from all stations, new satellite stations, video on demand server content
and Owner provided local origination channels, to distribute the streaming channels (high
definition) on the data network.
B. Extent of Digital Video Distribution System, modulators, high definition LCD flat panel televisions
and brackets as shown on Drawings. Digital Video Distribution system shall be comprised of, but
not limited to, IP distribution equipment for two-way communication over a single data cable.
Include servers, encoders, decoders, set top boxes, cable connectors, patch cords, splices,
software and licensing. System shall utilize the data network as its transport medium. Utilizing
equipment, components and cabling as listed in these documents and as shown on Drawings.
1. The main video head end shall be server based. It shall be connected to the data network
for connectivity throughout the building.
2. The system shall be controlled locally via set top box (STB).
a. The STB shall be connected to the local monitor (LCD high definition flat panel
television), with HDMI cable. The STB shall not require a fan or be PC based.
A. The installation shall include comprehensive audio/video systems consisting of modern solid state
type equipment providing the following:
1. Distribution of IPTV content to all television locations designated with a set top box from a
centralized IPTV headend located at the ground floor in the existing part.
a. The IPTV content shall include broadcast TV channels provided by appropriate TV
channel programming providers and arranged by the owner.
b. The IPTV content shall include interactive Electronic Program Guide (EPG) if the
data is available to the region and selected TV channels.
c. The IPTV content shall include on-demand entertainment content, including movies,
concerts, fitness, health. The IPTV system shall be flexible to accommodate such
content from the Owner and other content service providers, such as the
manufacturer.
1) When on-demand entertainment content are provided by content service
providers, such service providers typically will require royalty and service fees
from the Owner.
d. The IPTV content shall include a set of customized information pages facilitating
services and/or describing facilities of the properties. These customized information
pages shall be created by the manufacturer specifically for the hotel with guided
input from the Owner and be appealing and informative to guest rooms.
1009DF / MISHRIFAH VILLA 27 4133 - 2 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
2. System shall allow staff to have time-shift viewing flexibility in watching TV programming.
a. System shall provide Network Personal Video Recorder (NPVR) capability so that
guests can record interesting TV programs and watch them at convenient and
comfortable time to them, instead of being restricted by the broadcast time.
3. System shall have comprehensive management capabilities so that Owner and the
operational staffs can have clear, complete and detail understanding of the system’s
operations.
4. System shall provide the highest available quality of content, such as High Definition TV
quality for audio and video content.
5. Provide software to allow Owner to create and customize various forms of user interface
graphics, entertainment content, and TV channel selection and setting.
1.6 SUBMITTALS
A. Shop drawings and manufacturer’s literature shall include all information necessary to confirm
that the proposed system is in complete compliance with the Specifications.
1. All items of equipment must be new, in current production and currently eligible for
maintenance coverage.
4. Scaled diagrams indicating head end equipment layout and dimensions. Include
layout of equipment in relation to room size and other new system equipment in
that room. Include rack equipment layout.
5. Wiring Diagrams detailing wiring for power, signal, and control differentiating
clearly between manufacturer-installed wiring and field-installed wiring. Identify
wiring interface to other systems.
6. Field Testing Data.
7. Record Documents:
8. Warranty information.
9. Qualifications as required herein.
A. Manufacturer's Qualifications:
1009DF / MISHRIFAH VILLA 27 4133 - 3 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
1. Firms regularly engaged in manufacture and installation of professional
audio/visual systems, components and accessories, of types, capacities and
characteristics required, whose products have been in satisfactory use in similar
service for not less than 5 years and who shall be able to refer to similar
installations rendering satisfactory service.
B. Supplier's Qualifications:
C. Installer Qualifications:
B. Handle equipment and components carefully to avoid breakages, impacts, denting and
scoring finishes. Do not install damaged equipment; replace and return damaged units to
equipment manufacturer.
1.9 COORDINATION
A. Coordinate all work to be performed with actual field and project conditions. At a minimum,
perform the following tasks prior to submitting bids or shop drawings for the project:
1. Perform field investigations to determine all necessary incidental items which will be
required for complete and proper installation of all work. Verify all items affecting the bid
price prior to bidding.
2. Perform all necessary field measurements to provide complete, accurate, and coordinated
shop drawing submittals.
3. Organize and attend all necessary coordination meetings required to assure proper
coordination and installation of all related work included in the project.
4. Coordinate will all vendors to provide the proper connectivity and interfaces for this
equipment to work in conjunction with other systems.
A. At the time of Contract execution, the A/V Contractor shall assign a Project Manager to this
Project that will be responsible for administering all correspondence between the A/V
Contractor, administering all other trades, Construction Manager, Owner and
Architect/Engineer. The Project Manager shall also be responsible for the following:
B. The project team will consist of a Project Engineer that will be responsible for all on-site
day-to-day tasks, installation, and data collection and programming at the site.
C. Kickoff Meeting – Purpose of the meeting is to introduce the project team to the Owner and
Engineer and to identify any schedule conflicts, equipment lead times, review any
previously approved substitutions, environmental and space requirements, additional
data/electrical requirements and customer responsibilities.
1. Provide a list of milestone dates to meet the installation schedule including shop
1009DF / MISHRIFAH VILLA 27 4133 - 5 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
drawing review, equipment delivery, programming review, customer review, etc.
E. Installation Review
1. Complete a review meeting with the Owner and review all the required
inputs/outputs and scenarios discussed in the design meetings and implement to
verify with all the equipment in operating condition.
1.11 WARRANTY
All equipment, software, services, and programming shall be covered by a three (3) years parts
and labor warranty from date of acceptance. Acceptance will be provided in writing by Engineer
after system is installed, programmed, and tested to the satisfaction of the Owner use if systems
are being extended and there is a current warranty on the equipment.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. All items of equipment including wire and cable shall be designed by the manufacturer
supplier to operate as a complete system and shall be accompanied by complete service
notes and drawings detailing all inter-connections.
B. Equipment shall be listed by Underwriter's Laboratories, Inc. Each major component shall
bear the manufacturer's name and catalog number.
C. Careful attention has been made to specify current production models for all equipment
listed, however due to frequent updates of equipment in this field some model numbers
may become with the same features by the time this project is built. In such cases the
nearest equivalent product discontinued by the same manufacturer shall be provided.
1. InfoValue.
2. Tangerine Global.
3. Exterity.
4. Tandberg.
5. Or approved identical.
A. Provide complete and satisfactory operating IP digital video distribution as described herein, using
materials and equipment of types, sizes, ratings, and performances as indicated. Use materials
and equipment that comply with referenced standards and manufacturer's standard design and
B. The digital video system shall integrate with the Owner's Wide Area Network (WAN)/Local Area
Network (LAN). Provide all necessary hardware/software required to connect to the data network.
Coordinate with Division 16 Section “Data Network Electronics” for connectivity and compatibility
requirements.
C. The digital video distribution system shall consist of centrally and/or remotely located multimedia
sources, file server(s), and streaming server(s) with local user control of the sources via the local
or wide area network. This system shall provide:
1. On-demand viewing of stored digital content over the television
2. Television on-screen video navigation, using graphical depiction of scheduled media,
allowing the user to have easy access to all scheduled media with a single remote control
button press.
a. Playback and control of MPEG-2, MPEG-4, windows media video files streaming to
the television
b. Ability to stream a video file to the set top box (STB).
c. Universal access to videos over the facility WAN.
d. Copyright management across the WAN. The system will allow only the maximum
number of concurrent viewers across the WAN to access each video file based on
the licensing for that specific file.
e. Ability to automatically delete expired digital video files when/if copyright license
expires.
f. Ability to add digital videos to the system at any time.
4. Unified control, at each TV location , of all remote resources and the local television or
projector from a single IR remote control or Web browser (via the local workstation), the
user can control all remote resources (play, stop, forward, reverse) and have the ability to
control the local television or projector (on/off, channel, volume, mute). When a multimedia
resource is selected, the television or projector shall automatically tune to the appropriate
channel; no user interaction is required.
D. VIEWING REQUIREMENTS
1. The proposed line up must support similar broadcast content provided by the local cable
television providers.
2. The vendor platform must provide international/foreign FTG content.
3. The platform must provide FTG video-based promotional materials. This is intended to be
a looping channel of video that can be added or subtracted as required.
4. The platform must provide that the guest can select a FTG digital music line up that.
5. The platform should allow a guest the ability to pause live TV for a maximum of 20 minutes.
6. The platform should support a customized channel lineup that can be configured for each
room based on a profile or selected input (e.g. a line up customized for a single room).
1009DF / MISHRIFAH VILLA 27 4133 - 7 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
7. The platform must have an interactive program guide listing the program schedule for the
FTG video content.
8. The platform must allow custom program data to be imported from Client Systems to
update EPG with Client Systems channel and content information.
9. The platform must provide "instant" Response Channel Changing. Instant refers to a
channel change time of less than 1.5 seconds.
10. The platform must support digital rights management as required by content provider
agreement that specifies that DRM is a condition of carriage. (i.e. DRM may not be
mandatory for all broadcast channels).
11. The platform must support passing through 708CC / 608CC closed captioning data.
12. The platform must provide 'Television Episodes' as part of its VOD content library. A
"Television Episode' is a single 30 or 60 minute episode of a full season of network
programming which was recorded as a VOD asset and available to the guest to purchase..
13. The platform must support 'Specialized' content as part of its VOD content library. A
"Specialized' asset is defined as a VOD asset which is not sourced by a major studio..
14. The platform must allow users to Pause, Stop, FF, RW All Content
15. The platform must implement trick play support using an open standard RTSP
implementation.
16. The platform must provide an interactive screen for displaying VOD asset listings
17. The platform must provide the guest with a list of VOD assets based on a category.
18. The platform shall provide the guest with a search tool to allow the guest to search available
titles for specified keywords (i.e. action, western, director, actor, title etc.).
19. The platform should support multiple audio track capabilities where a guest can select
which language the VOD asset is to be played back in. This is only applicable to VOD
assets that are encoded with multiple audio track support.
20. The platform shall support audio subtitles for VOD programs.
21. The platform shall support the feature of providing the guest with a free preview on selected
assets prior to purchase.
22. The platform shall support the feature of providing the guest with a movie trailer prior to
committing to a purchase.
23. The platform must support a digital rights management as required by content provider
agreement that specifies that DRM is a condition of carriage.
24. The platform must display studio metadata for each VOD asset
25. The platform must provide sufficient VOD servers throughout the network. VOD
concurrency of 20% and a high availability configuration to achieve 99.99% availability
minimum, with 99.99996% is preferred.
E. INTERACTIVE REQUIREMNTS
1. The application hosting platform must be scaleable to support all concurrent connections.
2. The platform proposed must support the development for new applications which can be
created and/or purchased from 3rd parties.
3. The platform must allow the guest the ability to see a user interface in their chosen
language.
4. The platform must allow the user interface language to be preset on guest registration.
5. The user interface must be based on open standards and not be proprietary to a particular
vendor. (i.e. HTML, HTTP, HTTPS, JavaScript, etc)
6. The platform must provide the means to filter particular URLs from being received by a
guest set-top box.
7. The platform must provide an interactive weather application that allows the guest to see
the weather forecast for the local geographic area and simultaneously their home area as
described by their ZIP code in PMS.
F. OPERATIONAL REQUIREMENTS
1. The platform must provide operational metrics and reports so that Owneris able to report
on and analyze throughput, success/exception ratios.
2. The platform must provide scalability features which allow for channel, user, location, and
functionality growth.
3. The platform must be remotely accessible by both Owner and vendor with appropriate
measures to ensure secure platform access.
4. The platform must ensure guest information will be secure and protected from unauthorized
use.
5. The platform must provide the ability to remotely upgrade the STB population on a
scheduled basis, en mass or individually
6. The platform must have the ability to sustain a wholesale reboot by all the set top box
population (i.e. handles a "boot storm" without undo platform failures and wait for service
restoration).
7. The platform must provide help screens, dialogue tags, drop down instructions to assist
guests with their in room experience.
8. The platform must provide the support desk with the ability to remotely restart / upgrade
any set top box.
9. The platform must provide reports of active set top box, idle set top box, and set top boxes
not responding.
10. The normal operation is to have the service on in guest rooms. The specific guest greeting
portal will be created when guest registers at the hotel so that when the guests turn their
TV on they have their welcome page on their TV and "immediate" access to their services.
11. The platform must provide all status, alarm & performance information to one central
operations center.
B. Set-top Box (STB) shall be used to convert the digital signal provided over the data network
into a signal that is connected into the TV. The STB should have the following features and
functionality:
1. VGA, HDMI output.
2. 100 MB network interface.
3. Embedded OS and browser.
4. IR remote control
5. Low profile; mount on back of TV.
a. Coordinate with mounting bracket to limit profile of bracket and Monitor.
b. Provide remote sensor for IR operation if necessary.
c. Integrate with monitor to display channel/program name on screen if STB
display is not visible to user.
6. Integrate with a LCD/Plasma Display and be capable of natively rendering HD
video at 720p and 1080i.
7. Support SD and HD content.
8. Support Dolby AC-3 audio content.
9. Keep all content in the digital domain when displaying on a LCD/Plasma display.
10. Must be able to be turned off remotely (remote network reboot).
11. Support IGMP v2 and V3.
12. Support unicast video on demand access using RTSP.
13. Capable of being controlled using an on-board RS-232 interface which is capable
of being controlled by a 3rd party serial IR automation controller.
14. FCC certification.
15. Noiseless, fan less and diskless.
16. Must solely rely on IP over Fast Ethernet for receiving all data - FTG, VOD, PPV,
applications, etc.
17. Tamper-proof form factor.
18. Allow definition of a pre-set volume limit.
19. Include audio outputs which can feed an external speaker platform.
20. Enable the ability to display a graphic over the video.
C. IPTV Set-top Box Management Server
1. Linux OS.
2. 1 GB network interface.
3. IPTV Set-top box management server (software)
1. High Definition Encoders – Shall convert analog signal to digital signal for the
purpose of storing content digitally and streaming live and stored content across
the data network. Encoders shall support the following general features:
4. Program Sources
a. Aspect Ratio: 16 x 9.
b. Resolution: 1366 x 768.
c. HD Display Standards: 480i, 480p, 720p, 1080i.
d. Contrast Ratio: 800:1.
e. Inputs: DVI-D, composite, S-Video, component, RS-232, RCA audio.
f. External speakers.
g. PIP/POP/Split Screen.
h. Wall mounted.
i. Support integration with flat panel overlay.
j. 3 year warranty.
2.5 CABLES/WIRES
A. Utilize factory-manufactured patch cords in lieu of field terminated cables and components
at rack connections and wherever possible.
C. Provide all video cabling/connectors to produce the optimal video signal available from the
source to the display as available from the equipment.
A. Identify all system components and label for simple coordination with the operating and
maintenance manuals.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine conditions for compliance with requirements and other conditions affecting the
performance of the IPTV system work.
3.2 INSTALLATION
A. General: Install system in accordance with NFPA 70 and other applicable codes. Install
equipment in accordance with manufacturer's written instructions.
B. All installation practices shall be in accordance with, but not limited to, these specifications
and drawings. Installation shall be performed in accordance with the applicable standards,
requirements and recommendations of authorities having jurisdiction.
C. If, in the opinion of the installer, an installation practice is desired or required, which is
contrary to these specifications or drawings, a written request for modification shall be
made to the Consultant. Modifications shall not commence without written approval from
the Consultant.
E. Install all equipment to industry safety and ergonomic standards and provide full
engineering and technical support throughout the installation process.
F. Wiring Methods: Install wiring in raceway except within accessible ceiling spaces, where
open cable wiring methods may be used. Use UL-listed plenum cable. Conceal wiring.
G. Impedance and Level Matching: Carefully match input and output impedances and signal
levels at signal interfaces. Provide matching networks where required.
I. Wiring Within Enclosures: Provide adequate length of conductors to allow sliding cabinet
1009DF / MISHRIFAH VILLA 27 4133 - 14 INTERNET PROTOCOL
TELEVISION DISTRIBUTION
SYSTEM
to open and rotate 90 degrees. Bundle, lace, and train the conductors to terminal points
with no excess. Provide and use lacing bars.
J. Splices, Taps, and Terminations: Make splices, taps, and terminations on numbered
terminal strips in junction, pull, and outlet boxes, terminal cabinets, and equipment
enclosures.
K. Identification of Conductors and Cables: Use color coding of conductors and apply wire
and cable marking tape to designate wires and cables so all media are identified in
coordination with system wiring diagrams.
L. Repairs: Wherever walls, ceilings, floors, or other building finishes are cut for installation,
repair, restore, and refinish to original appearance.
M. Adjust and balance all circuits as specified herein. Set all controls and software parameters
to render a fully and optimally operating systems and subsystems. All computer-controlled
functions shall require complete audio/computer/software setup, balancing, label-entry and
documentation.
O. The installer must take such precautions as are necessary to guard against
electromagnetic and electrostatic hum, to supply adequate ventilation, and to install the
equipment so as to provide maximum safety to the operator.
P. Care shall be exercised in wiring so as to avoid damage to the cables and to the equipment.
All joints and connections shall be made with rosin-core solder or with mechanical
connectors approved by the Consultant.
Q. Coordinate all programming and protocols with the data network electronics provider to
ensure proper streaming and QoS to ensure clear delivery of signal to all set top boxes.
C. Meet with Owner for detailed system design and configuration review. Meeting to explain
features, functionality and operability of system. Provide two (2) sessions.
D. Identify, initiate, coordinate and complete all required programming of all equipment for
proper and safe operation of equipment and users.
E. Utilize optimal video inputs for connection of IPTV to encoder and set-top box.
F. Properly test all equipment for proper operation and provide final adjustments as required
for optimal audio and visual performance.
G. Provide all equipment test reports, signed and certified to Owner and Engineer prior to
substantial completion.
A. Coordinate exact unit location with drawings and exact field dimensions.
C. Install all A/V patch cords, test and adjust unit per manufacturer’s recommendation.
3.5 LABELING
A. Provide labels on all cabling and patch cords identifying source, output, type to easily and
correctly indicate operation and use.
1. Engrave faceplates for A/V outlets with input type or provide factory provided (non-
removable) markings acceptable to Owner and Engineer.
C. Provide labels at all equipment controls requiring user interface or not for Owner
troubleshooting and easy identification for future re-programming or configuration.
D. Labels shall be affixed free of smudges and fingerprints within three inches of termination.
3.6 GROUNDING
A. Provide equipment grounding connections for systems. Division 16 will provide ground
conductor to signal grounding busbar per J-Std 607A.
C. Ground equipment, conductor, and cable shields to eliminate shock hazard and to minimize
to the greatest extent possible, ground loops, common mode returns, noise pickup, cross
talk, and other impairments. Measure, record, and report ground resistance.
C. The system shall be physically inspected by the Owner's representative and the
Architect/Engineer to assure that all equipment is installed in a neat and workmanlike
manner as called for in the plans and specifications.
1. All components are operational and functioning properly to the system designs
intent.
2. Perform all necessary adjustments and balancing of all signal and amplifier level
controls to insure proper operation. Ensure output levels of sources are equal.
3. The complete system is free from grounds, open and shorts except for made
grounds required by the system installation.
4. The system is free of hum or noise including but not limited to ground loops,
improper impedance matching or improper shielding.
5. Configure signal processor to perform all gating, precedence, equalization and
compression to provide optimal performance.
6. Correct all of the above and retest to demonstrate compliance where required by
Engineer.
7. All testing shall be documented. Provide a signed copy to the Owner/Engineer
verifying the system is complete, and fully functional.
8. Make observations to verify that units and controls are properly labeled and
interconnecting wires and terminals are identified.
B. The manufacturer/supplier shall set all field adjustable components to optimize the system.
Balance all signals, adjust and verify input voltages, current settings and frequency
settings.
C. Occupancy Adjustments:
1. When requested by the Architect, within one year of date of substantial completion,
provide on-site assistance in re-programming systems to suit user operation and
actual, occupied conditions.
2. Provide up to three visits for this work.
3.9 CLEANING
A. Provide cutting and patching necessary to perform work per appropriate Sections. Clean
all equipment on a day-to-day basis and final cleaning of all equipment prior to turning over
to the Owner. All necessary cleaning referred to herein shall be cleaned to the satisfaction
of the Owner's representative.
B. Equipment:
1. Blow out and dry all raceways and conduits prior to installation of cabling.
D. Final Cleaning:
A. Prepare, set up, and supervise installation of system equipment to the satisfaction of the
Owner’s Representative and requirements of manufacturer warranty.
C. Final Adjustment Upon Achieving Substantial Completion of the Work: Adjust all operable
components to ensure that they are properly installed and functioning smoothly. Replace
any component which cannot be adjusted for proper operation.
A. The installer shall provide on-the-job training by a suitably qualified instructor, to personnel
designated by the Owner, to instruct them in the operation and maintenance of the
systems. At no additional cost to the Owner, the Installer shall provide a manufacturer’s
representative for such instruction in the event the Installer does not have qualified
instructors on staff for certain sophisticated equipment. All training shall take place after
the systems are operational, but before the acceptance tests. There shall be a total of 40
hours of training on the systems included in this specification, at the discretion of the
Owner. There shall be 2 follow-up training visits after 6 months, each an 8 hour training
session for a refresher on equipment as determined by the Owner.
B. The Installer shall orally instruct and demonstrate, to personnel selected by the Owner, the
Owner’s Operating Manual and all final drawings as provided for in this Section.
D. Off-site Training - Provide the cost of tuition for six people, designated by the Owner, to
attend a service school held at the manufacturer’s location. Include transportation, meals,
etc.
A. Equipment Manuals:
B. Equipment Drawings:
1. Contractor shall provide a revised set of system wiring diagrams upon the
completion of the installation for subsequent testing of the system to show actual
cable routing, connections with other systems cable lengths values of all
equipment as installed and actual signal values as tested.
2. Utilize architectural floor plans for system layout.
C. Software:
1. Provide copies of all system programming for backup of systems and future
reworking/reconfiguration.
2. Provide all documentation to Owner on CD in PDF and Word format.
END OF SECTION
A. All items of equipment including wire and cable shall be designed by the manufacturer supplier
to operate as a complete system and shall be accompanied by complete service notes and
drawings detailing all inter-connections.
B. Equipment shall be listed by Underwriter's Laboratories, Inc. Each major component shall bear
the manufacturer's name and catalog number.
C. Careful attention has been made to specify current production models for all equipment listed,
however due to frequent updates of equipment in this field some model numbers may become
with the same features by the time this project is built. In such cases the nearest equivalent
product discontinued by the same manufacturer shall be provided.
D. Equipment manufactured by:
1. As per KACST requirements
E. The extended platform shall give real-time video (30) ips with 720p HD resolution using H.264
compression for optimized bandwidth and storage efficiency.
F. Can pan 360° endlessly and tilt between -45° to +20° with a preset accuracy of 0.02°.The
operating temperature ranges between -30 ºC to45 ºC (-22 ºF to 113 ºF).
G. The network camera shall an alarm input and relay output shall be built in for integration with
hard wired external sensors.
H. The network camera shall provide a removable, local storage medium (Mini SD) for scheduled
and event-based recording of images.
I. The network camera shall provide an accessory port for hardware expansion and two-way
audio and additional alarm inputs.
J. Color and day/night models shall be available for outdoor environments.
K. The network camera shall be capable of firmware upgrades remotely, over the network. In
addition, a built-in accessory jack shall provide hardware expansion capabilities for future
accessories such as two-way audio and hard drive.
L. The network camera shall provide auto back focus (ABF) functionality through a push button on
the camera. ABF parameters shall be configurable through a standard Web browser interface.
M. The network camera shall provide auto back focus (ABF) intervals and initiate when IR cut filter
is removed or when temperature thresholds are exceeded.
N. The network camera shall provide a service connector to assist the installer to set field of view
and focus the camera.
O. The network camera shall provide advanced low-light capabilities for color and day/night
models with sensitivity down to 0.12 Lux in color and 0.03 Lux in black-white (B-W).
P. The network camera (day/night model) shall have a removable IR cut filter mechanism for
increased sensitivity in low-light installations. The sensitivity of the IR cut filter removal shall be
configurable through a Web browser.
Q. The network camera shall support two simultaneous, configurable video streams. H.264 and
MJPEG compression formats shall be available for primary and secondary streams with
selectable Unicast and Multicast protocols. The streams shall be configurable in a variety of
frame rates, bit rates, and GOP (a group of pictures) structures.
R. The extended platform shall give real-time video (30 ips) with HD resolution using H.264
compression for optimized bandwidth and storage efficiency.
S. The network camera shall support industry standard Power over Ethernet (PoE) IEEE 802.3af
to supply power to the camera over the network. The network camera shall also offer 24 VAC
power input.
T. The network camera shall have a window blanking feature to conceal user-defined privacy
areas that cannot be viewed by an operator. The network camera shall support up to four
blanked windows. A blanked area shall appear on the screen as a solid gray window.
U. The network camera shall use a standard Web browser interface for remote administration and
configuration of camera parameters including ABF.
V. The network camera shall support standard IT protocols.
W. The network camera shall support open architecture best practices with a published API
available to third-party network video recording and management systems.
a. Abandoned Object: Detects objects placed in a defined zone and triggers an alarm if
the object remains in the zone longer than the user-defined time allows. An airport
terminal is a typical installation for this behavior. This behavior can also detect objects
left behind at an ATM, signaling possible card skimming.
b. Adaptive Motion: Detects and tracks objects that enter a scene and then triggers an
alarm when the objects enter a user-defined zone. This behavior is primarily used in
outdoor environments with light traffic to reduce the number of false alarms caused by
environmental changes.
c. Camera Sabotage: Detects contrast changes in the field of view. An alarm is triggered if
the lens is obstructed with spray paint, a cloth, or a lens cap. Any unauthorized
repositioning of the camera also triggers an alarm.
d. Directional Motion: Generates an alarm in a high traffic area when a person or object
moves in a specified direction. Typical installations for this behavior include an airport
gate or tunnel where cameras can detect objects moving in the opposite direction of the
normal flow of traffic or an individual entering through an exit door.
e. Loitering Detection: Identifies when people or vehicles remain in a defined zone longer
than the user-defined time allows. This behavior is effective in real-time notification of
suspicious behavior around ATMs, stairwells, and school grounds.
f. Object Counting: Counts the number of objects that enter a defined zone or cross a
tripwire. This behavior might be used to count the number of people at a store
entrance/exit or inside a store where the traffic is light. This behavior is based on
tracking and does not count people in a crowded setting.
g. Object Removal: Triggers an alarm if an object is removed from a defined zone. This
behavior is ideal for customers who want to detect the removal of high value objects,
such as a painting from a wall or a statue from a pedestal.
h. Stopped Vehicle: Detects vehicles stopped near a sensitive area longer than the user-
defined time allows. This behavior is ideal for airport curbside drop-offs, parking
enforcement, suspicious parking, traffic lane breakdowns, and vehicles waiting at gates.
4. Analytic Suites shall be preloaded or configuration and alarm notification when used with
its system or a third-party system that supports Analytics API.
5. Multiple behaviors can be scheduled to work during a certain time or condition.
Y. Object Video Analytics for EP High Definition Digital Network Cameras
1. Object Video (OV) intelligent video analytics technology shall be embedded in EP network
cameras, enabling rule configuration and alarm notification when using OV ready systems.
2. OV analytics shall be made available in three suites: OV Security Suite, OV Security Suite
Plus and OV Event Counting Suite. These suites shall provide a spectrum of settings to
allow use of the behaviors in a variety of applications. The technology shall help users
identify situations of interest, such as surveillance and business effectiveness analysis.
3. OV Security Suite shall include Tripwire Detection, Inside Area Detection, and Camera
Tamper Detection behaviors: Tripwire Detection shall identify objects that cross a user-
defined line drawn within the camera’s field of view; Inside Area Detection shall identify
objects entering, appearing, or moving within a user-defined area; and Camera Tamper
Detection shall detect changes in the camera field of view, including obstruction of lens
(such as by cloth, spray paint, or a lens cap cover) and unauthorized movement of the
camera.
Z. Video Streams up to 2 simultaneous streams, Live stream at 30fps and recording stream at
5fps.
AA. Accessories shall include pan-tilt motor and power supply unit for pan-tilt motor.
BB. Field equipment cabinet to house the industrial switch.
PART 3 - EXECUTION
3.01 INSTALLATION
A. All video signals from cameras in the system shall be home run to the terminating location as
indicated on the drawings. Video signal cable shall be CAT6AAA cable or equivalent. The
contractor shall ensure video signal integrity against loss or attenuation and provide clean roll
free switching. CAT6AAA cable lengths must not exceed Data network standards limitation (90-
100 meter)
B. Video and control data cable shall not be contained in any conduits with high voltage.
C. All wire shall meet code. Circuitry powering and connecting the camera units and the
monitoring equipment shall be concealed within building confines, conduit or wire troughs. No
wiring shall be left exposed and accessible to tampering or the harsh elements of the
environment. Conduit, greenfield or junction boxes will be used where necessary to conceal the
wiring. All cable utilized shall be identified with descriptive labels or keying system.
D. Final code and local requirements for all security related equipment is the responsibility of the
contractor and vendors. This includes but is not limited to National Electric Code, ANSI
A. The Aspirating Smoke Detector (ASD) shall offer various classifications to include Very
Early Warning Smoke Detection (VEWFD), Early Warning Smoke Detection (EWFD), and
Standard Smoke Detection (SFD) settings as identified per the requirements of NFPA.
B. The ASD shall be self-contained and monitored by a display featuring LEDs and/or LCD
to include a control system utilizing microprocessor-based technology with all functions
fully programmable, LED displays, alarm indications, airflow and detector faults.
C. The system shall constantly sample air from the environment. In operation, air shall be
drawn from the air sampling piping network, through a particle separator and a 30 micron
filter assembly being pulled through the detection chamber by the aspirator. The system
D. The ASD shall incorporate a dual light source technology system for the automatic
discrimination of signals from non-fire related sources, such as dust. The system shall
automatically compensate for changes in environmental conditions and the negative
effect of filter contamination.
E. The ASD shall display a series of LEDs or be visible via an interactive LCD. The ASD
shall include a Reset, Isolate, and Test functions on the front of the panel. The system
shall be configured by a programmer that is PC based via PipeIQ software.
1. Up to five threshold alarm levels (Alert, Action 1, Action 2, Fire 1, and Fire 2).
2. Test, reset, and isolate functions from remote locations.
3. Design pipe network and ability to calculate obscurations levels, transport times,
sample hole diameters, flow and pressure levels.
4. Shall allow the ability to program the detector to three different settings: day,
night, and weekend mode.
5. Acclimate mode shall automatically adjust alarm levels within user-specified
parameters to reduce nuisance alarms.
G. The program shall allow the ASD firmware to be updated in the field by system installers
and maintainers.
H. The ASD shall have the capability to connect to the building automation/management
system via Modbus Protocol utilizing a TCP server or serial connection using RS-485.
I. Provide local networking capability and monitoring through the onboard Ethernet
connection allowing for up to six email addresses. Each address shall be configured to
notify the recipient of a specific alarm level, fault level, or isolate condition.
1. Detectors shall be tested and approved to cover up to 8,000 sq. ft. / (744 sq. m).
2. Detectors shall be approved to monitor up to five alarm levels. Each level shall
be programmable and able to select desired sensitivity, ranging from 0.00029%/ft
– 6.0%/ft. UL approval compliance recognizes sensitivity ranges from
0.00029%/ft – 4.0%/ft.
3. Detectors shall report alarms and faults using fault relays or direct connection via
the SLC loop, if applicable.
4. Detectors shall include a field-replaceable filter and an internal particle separator
to reduce the amount of non-combustible materials reaching the detection
chamber.
5. The software shall provide pipe design, system configuration, and system
monitoring in a single software program. It shall store up to 18,000 events.
Events shall include smoke levels, alarm conditions, operator actions, and faults.
The date and time of each event shall be recorded.
6. The front panel of the detector shall indicate flow faults, configuration, external
monitor, time, communication, trouble, filter, isolation, voltage, and high flow
faults via dedicated LEDs or an LCD display.
1.03 SUBMITTALS
A. General
1. System shall be complete in all ways and shall include all engineering and electrical
installation, all detection and control equipment, auxiliary devices and controls, alarm
interfaces, functional testing, training, and all other operations necessary for a functional,
UL Listed, and FM Approved system.
2. Provide the services of a qualified technician to perform all system software modifications,
upgrades or changes. Response time of the technician to the site shall not exceed 4
hours.
3. Provide all hardware, software, programming tools and documentation necessary to
modify the fire alarm system on site. Modification includes addition and deletion of
devices, circuits, zones and changes to system operation and custom label changes for
devices or zones. The system structure and software shall place no limit on the type or
extent of software modifications on-site. Modification of software shall not require power-
down of the system or loss of system fire protection while modifications are being made.
B. Shop Drawings
1. Sufficient information, clearly presented, shall be included to determine compliance with
drawings and specifications.
2. Include manufacturer's name(s), model numbers, ratings, power requirements, equipment
layout, device arrangement, complete wiring point-to-point diagrams, and conduit layouts.
3. Show annunciator layout, configurations, and terminations.
4. Prepare product data and site drawings indicating the system layout, including location of
modules, detection/aspiration unit, air intake ports, flow calculations, transport times,
power requirements, and sample hole obscuration sensitivity level calculations.
5. Show method and spacing of hanger supports on aspirating tube to the building structure.
C. Manuals
1. Submit simultaneously with the shop drawings, complete operating and maintenance
manuals listing the manufacturer's name(s), including technical data sheets.
2. Wiring diagrams shall indicate internal wiring for each device and the interconnections
between the items of equipment.
3. Provide a clear and concise description of operation that gives, in detail, the information
required to properly operate the equipment and system.
D. Software Modifications
1. Provide the services of a qualified technician to perform all system software modifications,
upgrades or changes. Response time of the technician to the site shall not exceed 4
hours.
2. Provide all hardware, software, programming tools and documentation necessary to
modify the fire alarm system on site. Modification includes addition and deletion of
devices, circuits, zones and changes to system operation and custom label changes for
devices or zones. The system structure and software shall place no limit on the type or
extent of software modifications on-site. Modification of software shall not require power-
down of the system or loss of system fire protection while modifications are being made.
3. System commissioning data shall be supplied as recommended per manufacturer’s
instructions within 30 days of installation.
D. The ASD shall offer Very Early Warning Smoke Detection, Early Warning Smoke Detection,
and Standard Smoke Detection settings. The ASD shall offer a wide range of sensitivity settings
from 0.00029%/ft – 4.0%/ft. The detector shall be capable of operating in temperatures from
32°F (0°C) to 100°F (38°C). Sampled air temperatures shall range from –4°F (–20°C) to 140°F
(60°C). Operating humidity shall range from 10-95% non-condensing.
E. Installer
1. The equipment installer shall be authorized and trained by the manufacturer and shall have
the ability to design a system based on code requirements. The installer shall be capable of
providing calculations, design, and testing documents upon request.
1.05 MAINTENANCE
A. Maintenance and testing shall be on a semi-annual schedule or as required by the local AHJ. A
preventive maintenance schedule shall be provided by the contractor describing the protocol for
preventive maintenance. The schedule shall include:
1. Systematic examination, adjustment and cleaning of all detectors, manual fire alarm
stations, control panels, power supplies, relays, water flow switches and all accessories of
the fire alarm system.
2. Each circuit in the fire alarm system shall be tested semiannually.
3. Each smoke detector shall be tested in accordance with the requirements of NFPA 72
Chapter 10.
B. As part of the bid/proposal, include a quote for a maintenance contract to provide all
maintenance, tests, and repairs described below. Include also a quote for unscheduled
maintenance/repairs, including hourly rates for technicians trained on this equipment, and
response travel costs for each year of the maintenance period. Submittals that do not identify
3 DESIGN PARAMETERS
A. The ASD design shall comply with all national and local code requirements and UL and
FM approved listings. The ASD shall be designed with the following parameters:
1. NFPA Classifications:
a. SFD: Standard Fire Detection. The sample port spacing shall not exceed 900 sq. ft.
(83.7 sq. m) and shall initiate an alarm/alert in less than 120 seconds from the
furthest sample port. The detector shall be programmed to alarm at 2.0%
obscuration per foot at the sample port for Fire 1 setting.
a. Sampling of return air grills shall comply with the requirements of NFPA-76 and
manufacturer’s recommendations. The sample port spacing shall not exceed more
than 4 sq. ft. (0.37 sq. m) per return air grill. The sample ports must be aligned at
an angle between 20 to 45 degrees in the direction of the airflow. The sample pipe
shall stand-off between 2”-8” (.05 - .2 m) from the return air grill.
3. In-Duct Sampling:
a. The ASD monitoring in-duct applications shall be installed and designed based on
the manufacturer’s recommendations and verified via PipeIQ software calculations.
B. A test port shall be provided at each pipe run located at 18” above the finished floor for
under floor systems, or 5ft above the finished floor when pipe network is above the ceiling.
The test port shall be constructed using a vented end cap. Provide a decal indicating the
install date, detector zone, pipe number, test point ID, transport time and suction pressure
(Pa).
A. The ASD shall be capable of connection to an Intelligent Fire Alarm Control Panel (FACP)
via a Signaling Line Circuit (SLC) using the communications protocol native to the system,
without the use of any additional hardware. The FACP shall be capable of monitoring and
annunciating up to five smoke event thresholds on the ASD and ten trouble conditions.
Each event threshold shall be capable of being assigned a discrete type ID at the FACP,
including Aspiration Alarm, Aspiration Pre-Alarm, Aspiration Supervisory, Aspiration Non-
1. Low flow – If the device has decreased in air flow, a Fault shall be generated at a user-
settable decrease in air flow.
2. High flow – If the device has increased in air flow, a Fault shall be generated at a user-
settable increase in air flow
3. Configuration – Device configuration failure. A Fault shall be generated if a configuration
update did not transfer.
4. Sensor – If the particulate sensor is not operating properly and needs immediate
replacement, a Fault shall be generated.
5. External Monitor – If the external monitor detects an open a Fault shall be generated.
6. Time – If the internal time base needs to be updated, a Fault shall be generated.
7. Communication – If the device fails to communicate to one of its peripherals and cannot
function properly, a Fault shall be generated.
8. Aspiration – If the aspirator is not working and requires immediate attention, an Fault
shall be generated.
9. Filter – As the filter approaches a pre-set threshold, an initial warning shall be given to
change the filter and a Fault shall be generated.
10. Isolate – If the device is put into the Isolate mode, an Isolation fault shall be generated.
6 DISPLAYS
A. The system shall provide a user interface at the front of the detector with the following
displays:
1. Air Flow/Fault Display – The air flow/fault display shall consist of 10 bicolor LEDs and
operate in one of two modes: air flow or fault indication. Green segments shall indicate
how close the current air flow is to the high or low air flow threshold. The default
threshold for a fault condition is + or – 20% from the airflow baseline. During normal
operation two adjacent indicators shall be green and correspond to the current airflow
entering the detector. When airflow is at a balanced level, the two green segments
shall be centered on the graph. As airflow rises and falls, the green segments shall
move right and left accordingly. If a fault is activated on the device, the corresponding
LEDs shall illuminate in amber and an additional “fault” LED shall be triggered to
signal a fault has been generated. All 10 faults shall be indicated on the User
Interface.
2. 10 particulate levels – The particulate level display shall consist of ten amber LEDs that
correspond to the current level of the particulate detected. The LEDs shall illuminate in
order from Level 1 to Level 10, starting from the bottom of the display and moving up
as the particulate level increases. Each LED shall represent a 10% increase in the
particulate level necessary to reach the Alert Alarm level.
3. (3) 5 alarm levels – All (3) 5 Alarm levels shall be indicated on the User Interface. The
Alarm Level Display shall consist of (3) 5 red LEDs that correspond to the current
1. Test
2. Reset
3. Isolate
4. Information Generation – the detector shall provide the local device address and the IP
address of the device through a coded sequence or via the LCD interactive function.
5. Password input if required to activate detector.
C. Liquid Crystal Display for XS and XT models shall provide detailed information of the
de¬vice status and configuration. The LCD will enter a sleep state if the screen has
re¬mained unchanged for a period of 30 seconds. The home screen shall display the
device’s current state which includes local address, date, time, current percent of smoke,
and the highest priority state. The LCD shall support multiple languages. Navigation
through the menus shall be done with the keypad located on the right hand side and shall
be able to perform the following functions:
1. Isolate
2. Disable
3. Reset Baseline
4. Monitor Airflow per pipe
5. Test
6. Sounder Test
7. Reset IP Network
8. Password input if required to activate detector.
7 SOFTWARE
A. The software shall be based on a single program, PipeIQ, which provides pipe network
design, ASD configuration, and system monitoring. The software shall provide the ability
to remotely monitor the system and provide the following functions:
1. The internal pipe diameter of the network may range from 0.59 inches to 1.03 inches
(15-26 mm) with a smooth bore internal surface.
2. The ASD shall accept both nominal 3/4 inch and 25 mm pipe diameters.
3. Inflow and Exhaust pipes shall enter the device from either the top or the bottom of the
unit so that the unit does not have to be inverted.
4. The system exhaust must be located back into the room being monitored. If the ASD is
located within the same room being monitored, no exhaust pipe is required to be
connected to the ASD.
5. Material for pipe and fittings shall be orange chlorinated polyvinyl chloride (CPVC)
PIPE. The pipe shall be UL Listed as an accessory for plenum use as per UL 1887
standard.
6. The pipe shall be identified as “Smoke Detector Sampling Tube” along its entire length,
in requirements per local codes and standards and manufacturer’s recommendations.
7. Pipe material substitution may be acceptable to accommodate environments where pipe
network will be installed but must be approved by the specifying engineer and
authority having jurisdiction, and if applicable, insurance underwriters.
8. The substitution pipe must comply with both inner and outer pipe diameter
requirements.
9. All joints and sampling pipes must be glued and connected, free of any air gaps using
solving cement throughout the pipe network, with the exception of the pipe connected
to detector.
10. The pipe network shall be designed based on a multi-branch system from a single pipe
inlet. The system shall have the ability to cover up to 8,000 sq. ft. (744 sq. m) per
detector. Final square footage shall be based on classification requirements per
NFPA.
11. A single pipe network cannot exceed a maximum of 262 linear ft (80 m) on a single run
and 450 ft (137 m) on an aggregate pipe network. Final pipe lengths shall be verified
with PipeIQ software and comply with NFPA classifications.
10 SAMPLING PORT
A. Sample port spacing shall comply with the requirements of NFPA classifications and
manufacturer’s recommendations.
B. The minimum sample port diameter must not be less than 5/64” and shall not exceed a
diameter larger than 1/4".
C. All sample ports must be identified in accordance with NFPA.
D. In areas with a suspended ceiling the pipe network shall be installed above the ceiling
utilizing a 3/8 inch diameter, flexible capillary tubing attached to an approved
manufacturer’s capillary sample port supported by the ceiling.
E. The size of sample ports shall be verified and confirmed with PipeIQ calculations software.
A. Provide power supply/charger to convert 115 VAC/60 Hz input into a single 12 VDC or 24
VDC Class 2 Rated power limited output, with UL listing UL1481.
B. Power supply shall be provided with appropriately sized batteries to accommodate the
system’s power requirements in the event main AC power is interrupted.
C. Upon loss of AC power, the external battery shall have sufficient capacity to power the fire
alarm system for not less than 24 hours plus 5 minutes of alarm.
12 FILTER ASSEMBLY
B. Multi-stage 30 micron field-replaceable filter. A fault shall be generated when the filter
needs replacement due to a reduction of air of more than 20%.
13 WIRING
A. Wire gauge shall range from 24 to 12 AWG (0.5-2.05 mm). Wire or conduit shall enter the
detector from either the top or the bottom of the device. Pluggable terminals shall be used
to wire the detector.
2.05 SYSTEM COMPONENTS - ADDRESSABLE DEVICES
A. Addressable Devices - General
1. Addressable devices shall employ the simple-to-set decade addressing scheme.
Addressable devices which use a binary-coded address setting method, such as a DIP
switch, are not an allowable substitute.
2. Detectors shall be addressable and intelligent, and shall connect with two wires to the Fire
alarm control panel signaling line circuits.
3. Addressable smoke and thermal (heat) detectors shall provide dual alarm and
power/polling LEDs. Both LEDs shall flash under normal conditions, indicating that the
detector is operational and in regular communication with the control panel, and both
LEDs shall be placed into steady illumination by the control panel, indicating that an alarm
condition has been detected. An output connection shall also be provided in the base to
connect an external remote alarm LED.
4. Using software in the FACP, detectors shall automatically compensate for dust
accumulation and other slow environmental changes that may affect their performance.
The detectors shall be listed by UL as meeting the calibrated sensitivity test requirements
of NFPA Standard 72, Chapter 10.
5. Detectors shall be ceiling-mount and shall include a separate twist-lock base with tamper
proof feature. Base options shall include a base with a built-in (local) sounder rated for a
minimum of 85 DBA, a relay base and an isolator base designed for Style 7 applications.
6. Detectors shall provide a test means whereby they will simulate an alarm condition and
report that condition to the control panel.
7. Detectors shall also store an internal identifying type code that the control panel shall use
to identify the type of device (ION, PHOTO, THERMAL).
8. Detectors shall provide address-setting means using decimal switches.
2.06 BATTERIES
A. Upon loss of Primary (AC) power to the control panel, the batteries shall have sufficient
capacity to power the fire alarm system for required standby time (24 or 60 hours) followed by 5
minutes of alarm.
3.03 INSPECTION
A. At the final inspection, a minimum NICET Level II technician shall demonstrate that the system
functions pr 1. Perform a visual inspection of the physical installation, checking adequate size
batteries are used, piping is securely connected and installed, and all sample ports comply with
the design.
B. Verify ASD communicates to fire alarm control, and if applicable, has the ability to network via a
dedicated IP address and Modbus protocol.
3.04 COMMISSIONING
A. The system shall be commissioned in the presence of the manufacturer or installing contractor
representative and client representative. The contractor shall provide the following necessary
instrumentation, equipment, materials, and labor for the test:
1. PipeIQ Pipe Layout Report
2. Aerosol smoke (Home Safeguard Industries Model 25S or equivalent)
3. Stopwatch capable of measuring 1 second intervals
4. A total of two (2) qualified personals when testing is being performed
1. Introduce canned smoke (Home Safeguard Industries Model 25S or equivalent) directly
into the sampling hole in to farthest sample hole for a duration of 2 seconds at a distance
of 6 inches from the sample hole. Start the timer once the smoke has been introduced.
2. Stop the timer once the first particulate bar is illuminated on the front of the device, above
what was displayed during normal device operation. The device need not go into alarm to
verify the transport time – an increase on the particulate meter is a successful
measurement of transport time.
3. Compare the observed transport time with the results on the Pipe Layout report from
PipeIQ. If there is more than a 20% discrepancy, verify the sample hole quantity, sizes,
location, and the integrity of pipe and that the installed pipe network is identical to the
PipeIQ Pipe Layout report.
4. Once transport times for the farthest sample points are verified, test the remaining holes
for airflow by introducing smoke into each hole and verifying a response at the device or
panel. Transport times are not required on each of the remaining holes, only a verification
that air is flowing.
5. Document test results as required per NFPA to include the client’s contact information,
transport times, and sensitivity levels.
3.05 INSTRUCTION
A. Instruction shall be provided as required for operating the system. Hands-on demonstrations of
the operation of all system components and the entire system including program changes and
functions shall be provided.
B. The contractor or installing dealer shall provide a user manual indicating "Sequence of
Operation."
3.4 TRAINING
A. CONTRACTOR QUALIFICATIONS
1. All contractors involved with the design and installation of ASD systems shall be very
experienced with the systems that they are designing / installing per the occupancy use.
A minimum of 5 years experience in the installation of fire alarm systems and a NICET
level III fire alarm technician or equivalent on staff to supervise the design and installation
is required.
2. The installing contractor shall have passed the manufacturer certification training and be
certified to model, design, install, program, test and maintain the ASD system and shall be
able to produce a certificate stating such upon request.
3. The installing contractor shall maintain appropriate licensing and certifications from the
jurisdiction in which the work occurs.
3.5 WARRANTY
A. The manufacturer shall guarantee the product by warranty for a period of three years. All
components of the detector shall be replaced with the exception of regular maintenance
accessories: replaceable micron filter. Any damage to the ASD due to poor handling or
operating outside of the listed criteria will void any such warranty. The installation and
programming of the ASD shall be completed by factory-trained installer.
3.6 OWNER TRAINING
A. Train Owner’s maintenance personnel to adjust, operate and maintain ASD systems.
B. Prior to final acceptance, the installing contractor shall provide operational training to each shift
of Owner’s personnel. Each training shall include ASD system operation, trouble procedures,
supervisory procedures, auxiliary functions and emergency procedures.
END OF SECTION
SPECIFICATIONS
Part 3 of 3 (Divisions 31 to 33)
END OF SECTION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Soil treatment.
2. Wood treatment.
3. Bait-station system.
4. Metal mesh barrier system.
B. Related Requirements:
1. Section 061000 "Rough Carpentry" for wood preservative treatment by pressure process.
2. Section 076200 "Sheet Metal Flashing and Trim" for custom-fabricated, metal termite
shields.
C. Soil Treatment Application Report: After application of termiticide is completed, submit report for
Owner's records and include the following:
D. Wood Treatment Application Report: After application of termiticide is completed, submit report
for Owner's records and include the following:
A. Soil Treatment:
1. Environmental Limitations: To ensure penetration, do not treat soil that is water saturated
or frozen. Do not treat soil while precipitation is occurring. Comply with requirements of
the EPA-Registered Label and requirements of authorities having jurisdiction.
2. Related Work: Coordinate soil treatment application with excavating, filling, grading, and
concreting operations. Treat soil under footings, grade beams, and ground-supported
slabs before construction.
1.6 WARRANTY
A. Soil Treatment Special Warranty: Manufacturer's standard form, signed by Applicator and
Contractor, certifying that termite control work consisting of applied soil termiticide treatment will
prevent infestation of subterranean termites, including Formosan termites (Coptotermes
formosanus). If subterranean termite activity or damage is discovered during warranty period,
re-treat soil and repair or replace damage caused by termite infestation.
B. Wood Treatment Special Warranty: Manufacturer's standard form, signed by Applicator and
Contractor, certifying that termite control work consisting of applied wood termiticide treatment
will prevent infestation of subterranean termites, including Formosan termites (Coptotermes
formosanus) requirement. If subterranean termite damage is discovered during warranty period,
repair or replace damage caused by termite infestation and treat replacement wood.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Source Limitations: Obtain termite control products from single source from single
manufacturer].
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Applicator present, for compliance with
requirements for moisture content of soil per termiticide label, interfaces with earthwork, slab
and foundation work, landscaping, utility installation, and other conditions affecting performance
of termite control.
B. Proceed with application only after unsatisfactory conditions have been corrected.
A. General: Prepare work areas according to the requirements of authorities having jurisdiction
and according to manufacturer's written instructions before beginning application and
installation of termite control treatment(s). Remove extraneous sources of wood cellulose and
other edible materials, such as wood debris, tree stumps and roots, stakes, formwork, and
construction waste wood from soil within and around foundations.
B. Soil Treatment Preparation: Remove foreign matter and impermeable soil materials that could
decrease treatment effectiveness on areas to be treated. Loosen, rake, and level soil to be
treated, except previously compacted areas under slabs and footings. Termiticides may be
applied before placing compacted fill under slabs if recommended in writing by termiticide
manufacturer.
1. Fit filling hose connected to water source at the site with a backflow preventer, according
to requirements of authorities having jurisdiction.
A. Application: Mix soil treatment termiticide solution to a uniform consistency. Distribute treatment
uniformly. Apply treatment at the product's EPA-Registered Label volume and rate for maximum
specified concentration of termiticide to the following so that a continuous horizontal and vertical
termiticidal barrier or treated zone is established around and under building construction.
A. Wood Treatment: Apply wood treatment after framing, sheathing, and exterior weather
protection is completed but before electrical and mechanical systems are installed.
B. Application: Mix borate wood treatment solution to a uniform consistency. Apply treatment at the
product's EPA-Registered Label volume and rate for the maximum borate concentration allowed
for each specific use so that wood framing, sheathing, siding, and structural members subject to
infestation receive treatment. Apply treatment to the height of 244 mm above grade] <Insert
requirement>.
A. Bait-Station System: Install during construction to determine areas of termite activity and after
construction, including landscaping, is completed.
B. Place bait stations according to product's EPA-Registered Label and manufacturer's written
instructions, in the following locations:
C. Spacing: Place bait stations according to manufacturer's written instructions and at a frequency
no less than the following:
A. Install metal mesh barrier system to provide a continuous barrier to entry of subterranean
termites, according to manufacturer's written instructions.
1. Fit mesh tightly around pipes and other penetrations and terminate at slab and foundation
perimeters.
2. Install mesh under the perimeter of concrete slab edges and joints after vapor retarder
and reinforcing steel are in place.
3.7 PROTECTION
A. Avoid disturbance of treated soil after application. Keep off treated areas until completely dry.
1. Include annual inspection for termite activity and effectiveness of termite treatment
according to manufacturer's written instructions.
END OF SECTION
PART 2 PRODUCTS
2.01 PRECAST CONCRETE PAVERS
A. Interlocking Concrete Pavers: Hydraulically pressed concrete, configured for interlocking with
adjacent units and complying with ASTM C936/C936M.
1. Compressive Strength: 55 MPa average, with minimum of 50 MPa.
2. Absorption: 5 percent average, with maximum of 7 percent.
B. Non-interlocking Concrete Pavers:
1. Compressive Strength: Minimum of 50 MPa.
2. Absorption: 5 percent average, with maximum of 7 percent.
3. Air Entrainment: 5 to 7 percent.
C. Pattern, Size, Color, Style, Thickness, Surface Texture and Finish: As indicated on Drawings
(Hardscape details).
D. Topsoil Fill: For filling voids and joints, provide topsoil conforming to ASTM D5268.
E. Edging: Concrete curb; made from normal-weight concrete with a compressive strength not
less than 41 MPa and water absorption not more than 5 percent, in shapes and sizes as
indicated on Drawings.
2.02 SANDSTONE TILES
A. General: Type, Pattern, Color, and Texture: As selected by the Architect and approved by
KAUST.
2.03 ARTIFICIAL TURF
A. General: Type, Pattern, Color, and Texture: As selected by the Architect and approved by
KAUST.
2.04 PEBBLES AND OTHER TILE PAVERS
A. Gravel / Pebble Stones: Provide round edge white pebble stones with varied sizes ranging from
20 mm to 50 mm minimum overall thickness.
B. Tile Pavers: Provide durable (heavy-duty) tile pavers suitable for hard landscaping..
1. Material, Pattern, Size and Finish: As indicated on Drawings.
2.05 ACCESSORIES
A. Compressible Foam Filler: Preformed strips complying with ASTM D 1056, Grade 2A1.
2.06 MORTAR SETTING-BED MATERIALS
A. Portland Cement: ASTM C 150, Type I or Type II.
B. Delete first paragraph below if latex-modified portland cement mortar mix is specified for setting
bed.
C. Hydrated Lime: ASTM C 207, Type S.
D. Revise first paragraph below for latex-modified portland cement mortar bed if latex-additive
manufacturer requires coarser aggregate complying with ASTM C 33.
E. Sand: ASTM C 144.
F. Retain first paragraph below for thickset applications if latex additive is required to improve
flexibility and other properties of mortar setting bed or if latex additive is used for mortar-bed
bond coat.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that substrate is level or to correct gradient, smooth, capable of supporting pavers and
imposed loads, and ready to receive work of this Section.
B. Verify gradients and elevations of substrate are correct.
C. Do not begin installation until all unsatisfactory conditions are resolved. Beginning work
constitutes acceptance of site conditions and responsibility for defective installation caused by
prior observable conditions.
D. Verify that substrates, membranes, and protection boards are ready for installation of pedestal
system, and pavers.
1. The substrate that is to receive pedestals shall have positive slope to provide adequate
drainage in accordance with good building practices.
2. Inspect to insure that all substrates have been properly prepared to accept the pedestals.
Any surface defect which may impair performance of the pedestals or waterproofing
membrane shall be appropriately repaired. Commencement of work shall imply
acceptance of surfaces.
3.02 PREPARATION
A. Establish accurate lines, levels, and pattern.
B. Assure that the surface to accept the pedestals is clean and free of debris which would impair
the performance of the pedestal system.
C. Insulation and/or protection board must be applied over the waterproofing/roofing substrate. If
specified, drainage mat, insulation and/or protection board must be installed according to
manufacturer's recommendations. If protection is specified only under the pedestal, then each
pad must extend beyond the edge of the pedestal system bottom cap or buffer pad, by a
minimum of 50 mm.
1.1 SUMMARY
A. Section Includes:
1. Decorative steel fences.
2. Swing gates.
3. Gate operators, including controls.
B. Related Requirements:
1. Section 03 30 00 "Cast-in-Place Concrete" for concrete bases for gate operators, drives,
and controls and post concrete fill.
2. Section 281300 "Access Control" for access control devices installed at gates and
provided as part of a security system.
3. Division 26 Sections for electrical service and connections for system disconnect
switches and powered devices including, but not limited to, motor operators, controls, and
limit switches.
1. Include plans, elevations, sections, gate locations, post spacing, and mounting,
attachment details, and grounding details.
2. Gate Operator: Show locations and details for installing operator components, switches,
and controls. Indicate motor size, electrical characteristics, drive arrangement, mounting,
and grounding provisions.
3. Wiring Diagrams: Include diagrams for power, signal, and control wiring.
C. Samples: For each fence material and for each color specified.
B. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate
aesthetic effects, and to set quality standards for fabrication and installation.
PART 2 - PRODUCTS
A. Wind Loading:
A. Decorative Steel Fences: Fences made from steel tubing bars and shapes, hot-dip galvanized.
C. Post Caps: Formed from steel sheet and hot-dip galvanized after forming.
D. Rails:
1. Steel Tube Rails: Square steel tubing (64 by 64 mm with 3.2-mmwall thickness.
2. Steel Channel Rails: Steel channels 51 by 25 mm.
1. Fabricate sections with clips welded to rails for field fastening to posts.
2. Drill posts and clips for fasteners before finishing to maximum extent possible.
1. Fabricate rails with clips welded to rails for field fastening to posts.
2. Drill posts, clips, and bar grating for fasteners before finishing to maximum extent
possible.
K. Galvanizing: For items other than hardware that are indicated to be galvanized, hot-dip
galvanize to comply with ASTM A 123/A 123M. For hardware items, hot-dip galvanize to comply
with ASTM A 153/A 153M.
M. Finish for Steel Items Other Than Bar Grating Infill: High-performance coating.
N. Finish for Metallic-Coated-Steel Items Other Than Bar Grating Infill: High-performance coating.
F. Frame Corner Construction: Welded or assembled with corner fittings and 7.9-mm diameter,
adjustable truss rods for panels 1.52 m wide or wider.
G. Additional Rails: Provide as indicated, complying with requirements for fence rails.
I. Picket Size, Configuration, and Spacing: Comply with requirements for adjacent fence.
1. Treillage: Provide iron castings of pattern indicated between each pair of pickets. Finish
as specified for [adjacent fence] [gates].
J. Hardware: Latches permitting operation from both sides of gate, hinges, and keepers for each
gate leaf more than 1.52 m wide. Provide center gate stops and cane bolts for pairs of
gates. Fabricate latches with integral eye openings for padlocking; padlock accessible from both
sides of gate.
1. Function: 621 - Latchbolt by key from outside and by turn from inside. Latchbolt is held
retracted by device from inside.
2. Material: Cast, forged, or extruded brass or bronze.
3. Mounting Plate: Configuration necessary for mounting locks. Fabricate from 3.2-mm
thick, steel plate; galvanized.
O. Electric Strikes: BHMA A156.31, Grade 1, of configuration required for use with lock specified,
fail-safe, and suitable for exterior use.
1. Mounting Plate: Configuration necessary for mounting electric strikes. Fabricate from 3.2-
mm thick, steel plate; galvanized.
2. Mounting: Mortise into post.
P. Exit Hardware: BHMA A156.3, Grade 1, Type 1 (rim exit device), with push pad actuating bar,
suitable for exterior use.
Q. Cane Bolts: Provide for inactive leaf of pairs of gates. Fabricated from 19-mm diameter, round
steel bars, hot-dip galvanized after fabrication. Finish to match gates. Provide galvanized-steel
pipe strikes to receive cane bolts in [closed position] [both open and closed positions].
R. Finish exposed welds to comply with NOMMA Guideline 1, Finish #4 - good-quality, uniform
undressed weld with minimal splatter.
S. Galvanizing: For items other than hardware that are indicated to be galvanized, hot-dip
galvanize to comply with ASTM A 123/A 123M. For hardware items, hot-dip galvanize to comply
with ASTM A 153/A 153M.
A. Provide factory-assembled automatic operating system designed for gate size, type, weight,
and operation frequency. Provide operation control system with characteristics suitable for
Project conditions, with remote-control stations, safety devices, and weatherproof enclosures;
coordinate electrical requirements with building electrical system.
E. Motor Characteristics: Sufficient to start, accelerate, and operate connected loads at designated
speeds, within installed environment, with indicated operating sequence, and without exceeding
nameplate rating or considering service factor. Comply with NEMA MG 1 and the following:
1. Voltage: 208-220 V.
2. Horsepower: Not less than 3/4.
3. Enclosure: Manufacturer's standard.
4. Duty: Continuous duty at ambient temperature of 40 deg C and at altitude of 1005 m
above sea level.
5. Service Factor: 1.15 for open dripproof motors; 1.0 for totally enclosed motors.
6. Phase: Polyphase.
G. Remote Controls: Electric controls separated from gate and motor and drive mechanism, with
NEMA ICS 6, Type 1 enclosure for concrete base mounting, and with space for additional
optional equipment. Provide the following remote-control device(s):
1. Control Station: Keyed, three-position switch with open, stop, and close function; located
remotely from gate. Provide two keys per station.
2. Control Station: Momentary-contact, three-button-operated with open, stop, and close
function; located remotely from gate. Key switch to lock out open and close buttons.
3. Card Reader: Functions only when authorized card is presented. Programmable,
multiple-code system, permitting four different access periods; face-lighted unit fully
visible at night.
4. Digital Keypad Entry Unit: Programmable, multiple-code capability of not less than 500
possible individual codes, consisting of 1 to 7-digit codes, and permitting four different
access periods.
5. Radio Control: Digital system consisting of code-compatible universal receiver for each
gate, located where indicated, with remote antenna with coaxial cable and mounting
brackets designed to operate gates. Provide two programmable transmitter(s) with
multiple-code capability permitting validating or voiding of not less than 1000 codes per
channel configured for the following functions:
H. Vehicle Loop Detector: System includes automatic closing timer with adjustable time delay timer
cutoff switch, and loop detector designed to open and close gate. System includes electronic
detector with adjustable detection patterns, adjustable sensitivity and frequency settings, and
panel indicator light designed to detect presence or transit of a vehicle over an embedded loop
of wire and to emit a signal activating the gate operator. System includes number of loops
consisting of multiple strands of wire, number of turns, loop size, and method of placement, as
recommended in writing by detection system manufacturer for function indicated, at location
indicated on Drawings.
I. Vehicle Presence Detector: System includes automatic closing timer with adjustable time
delay, timer cutoff switch, and presence detector designed to open and close gate. System
includes[retroreflective detector with adjustable detection zone pattern and sensitivity, designed
J. Obstruction Detection Devices: Provide each motorized gate with automatic safety sensor(s).
Activation of sensor(s) causes operator to immediately function as follows:
1. Action: Reverse gate in both opening and closing cycles, and hold until clear of
obstruction.
2. Action: Stop gate in opening cycle and reverse gate in closing cycle, and hold until clear
of obstruction.
3. Internal Sensor: Built-in torque or current monitor senses gate is obstructed.
4. Sensor Edge: Contact-pressure-sensitive safety edge, profile, and sensitivity designed for
type of gate and component indicated, in locations as follows. Connect to control circuit
using gate edge transmitter and operator receiver system.
K. Limit Switches: Adjustable switches, interlocked with motor controls and set to automatically
stop gate at fully retracted and fully extended positions.
1. Type: Integral fail-safe release, allowing gate to be pushed open without mechanical
devices, keys, cranks, or special knowledge.
M. Operating Features:
1. Warning Module: Visual, constant-light alarm sounding three to five seconds in advance
of gate operation and continuing until gate stops moving; compliant with the United
States Access Board's ADA-ABA Accessibility Guidelines.
2. Battery Backup System: Battery-powered drive and access-control system, independent
of primary drive system.
3. External electric-powered solenoid lock with delay timer allowing time for lock to release
before gate operates.
4. Fire box.
5. Fire strobe sensor.
6. Intercom System: <Insert requirements>.
7. Instructional, Safety, and Warning Labels and Signs: Manufacturer's standard for
components and features specified.
8. Equipment Bases/Pads: Precast concrete, depth not less than 305 mm, dimensioned and
reinforced according to gate operator component manufacturer's written instructions and
as indicated on Drawings.
2.5 ALUMINUM
A. Aluminum, General: Provide alloys and tempers with not less than the strength and durability
properties of alloy and temper designated in paragraphs below for each aluminum form
required.
B. Bars (Pickets): Hot-rolled, carbon steel complying with ASTM A 29/A 29M, Grade 1010.
1. Bars: Hot-rolled steel strip, ASTM A 1011/A 1011M, Commercial Steel, Type B.
2. Wire Rods: ASTM A 510/A 510M.
F. Galvanized-Steel Sheet: ASTM A 653/A 653M, structural quality, Grade 340, with Z180 coating.
G. Aluminum-Zinc, Alloy-Coated Steel Sheet: ASTM A 792/A 792M, structural quality, Grade 340,
with AZM180 coating.
A. Shop Primers for Steel: Provide primers that comply with Section 099600 "High-Performance
Coatings."
B. Shop Primer for Steel: Manufacturer's standard lead- and chromate-free, nonasphaltic, rust-
inhibiting primer complying with MPI#79 and compatible with topcoat.
C. Epoxy Zinc-Rich Primer for Uncoated Steel: Complying with MPI #20 and compatible with
coating specified to be applied over it.
D. Epoxy Primer for Galvanized Steel: Epoxy primer recommended in writing by topcoat
manufacturer.
E. Epoxy Intermediate Coat for Uncoated Steel: Complying with MPI #77 and compatible with
primer and topcoat.
G. Polyurethane Intermediate Coat and Topcoat: Complying with MPI #72 and compatible with
undercoat.
A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy
welded.
A. Comply with requirements of Section 260526 "Grounding and Bonding for Electrical Systems."
B. Grounding Conductors: Size as indicated on Drawings. Bare, solid wire for No. 6 AWG and
smaller; stranded wire for No. 4 AWG and larger.
A. Baked-Enamel or Powder-Coat Finish: AAMA 2603 except with a minimum dry film thickness of
0.05 mm. Comply with coating manufacturer's written instructions for cleaning, conversion
coating, and applying and baking finish.
A. Surface Preparation: Clean surfaces according to SSPC-SP 5/NACE No. 1, "White Metal Blast
Cleaning. After cleaning, apply a conversion coating compatible with the organic coating to be
applied over it.
B. Powder Coating: Immediately after cleaning, apply manufacturer's standard two-coat finish
consisting of epoxy primer and TGIC polyester topcoat to a minimum total dry film thickness of
not less than 0.20 mm. Comply with coating manufacturer's written instructions.
C. Primer Application: Apply zinc-rich epoxy primer immediately after cleaning, to provide a
minimum dry film thickness of 0.05 mm per applied coat, to surfaces that are exposed after
assembly and installation, and to concealed surfaces.
1. Match approved Samples for color, texture, and coverage. Remove and refinish, or
recoat work that does not comply with specified requirements.
A. Galvanized Finish: Clean welds, mechanical connections, and abraded areas and repair
galvanizing to comply with ASTM A 780/A 780M.
B. Surface Preparation: Clean surfaces of oil and other contaminants. Use cleaning methods that
do not leave residue. After cleaning, apply a zinc-phosphate conversion coating compatible with
the organic coating to be applied over it. Clean welds, mechanical connections, and abraded
areas and apply galvanizing repair paint, complying with SSPC-Paint 20, to comply with
ASTM A 780/A 780M.
C. Powder Coating: Immediately after cleaning and pretreating, apply manufacturer's standard
TGIC polyester powder-coat finish to a minimum dry film thickness of 0.05 mm.
1. Match approved Samples for color, texture, and coverage. Remove and refinish, or
recoat work that does not comply with specified requirements.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with requirements for site
clearing, earthwork, pavement work, construction layout, and other conditions affecting
performance of the Work.
B. Do not begin installation before final grading is completed unless otherwise permitted by
Architect.
C. Proceed with installation only after unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Stake locations of fence lines, gates, and terminal posts. Do not exceed intervals of 152.5 m or
line of sight between stakes. Indicate locations of utilities, lawn sprinkler system, underground
structures, benchmarks, and property monuments.
1. Construction layout and field engineering are specified in Section 017300 "Execution."
C. Post Excavation: Drill or hand-excavate holes for posts in firm, undisturbed soil. Excavate holes
to a diameter of not less than 4 times post size and a depth of not less than 600 mm plus 75
mm for each 300 mm or fraction of a 300 mm that fence height exceeds 1.2 m.
D. Post Setting: Set posts in concrete with mechanical anchors by mechanically driving into soil at
indicated spacing into firm, undisturbed soil.
1. Verify that posts are set plumb, aligned, and at correct height and spacing, and hold in
position during setting with concrete or mechanical devices.
2. Concrete Fill: Place concrete around posts and sleeves] and vibrate or tamp for
consolidation. Protect aboveground portion of posts from concrete splatter.
a. Exposed Concrete: Extend 51 mm above grade. Finish and slope top surface to
drain water away from post.
b. Concealed Concrete: Top 51 mm below grade as indicated on Drawings to allow
covering with surface material. Slope top surface of concrete to drain water away
from post.
3. Posts Set in Concrete: Extend post to within 150 mm of specified excavation depth, but
not closer than 75 mm to bottom of concrete.
4. Posts Set into Concrete in Sleeves: Use galvanized-steel pipe sleeves with inside
diameter at least 20 mm larger than outside diagonal dimension of post, preset and
anchored into concrete for installing posts.
5. Posts Set into Voids in Concrete: Form or core drill holes not less than 20 mm larger than
outside diagonal dimension of post.
6. Mechanically Driven Posts: Drive into soil to depth of 914 mm. Protect post top to prevent
distortion.
7. Space posts uniformly at 2.44 m o.c.
A. Install gates according to manufacturer's written instructions, level, plumb, and secure for full
opening without interference. Attach hardware using tamper-resistant or concealed means.
Install ground-set items in concrete for anchorage. Adjust hardware for smooth operation and
lubricate where necessary.
A. General: Install gate operators according to manufacturer's written instructions, aligned and true
to fence line and grade.
B. Excavation for Concrete Bases: Hand-excavate holes for bases in firm, undisturbed soil to
dimensions and depths and at locations as required by gate operator component
manufacturer's written instructions and as indicated.
C. Concrete Bases: Cast-in-place or precast concrete, depth not less than 300 mm, dimensioned
and reinforced according to gate operator component manufacturer's written instructions and as
indicated on Drawings.
D. Vehicle Loop Detector System: Cut grooves in pavement and bury and seal wire loop according
to manufacturer's written instructions. Connect to equipment operated by detector.
E. Comply with NFPA 70 and manufacturer's written instructions for grounding of electric-powered
motors, controls, and other devices.
A. Comply with Section 260526 "Grounding and Bonding for Electrical Systems."
a. Gates and Other Fence Openings: Ground fence on each side of opening.
E. Grounding Method: At each grounding location, drive a grounding rod vertically until the top is
150 mm below finished grade. Connect rod to fence with No. 6 AWG conductor. Connect
conductor to each fence component at grounding location.
F. Bonding Method for Gates: Connect bonding jumper between gate post and gate frame.
A. Testing Agency: Engage a qualified testing agency to perform tests and inspections.
3.8 ADJUSTING
A. Gates: Adjust gates to operate smoothly, easily, and quietly, free of binding, warp, excessive
deflection, distortion, nonalignment, misplacement, disruption, or malfunction, throughout entire
operational range. Confirm that latches and locks engage accurately and securely without
forcing or binding.
B. Automatic Gate Operators: Energize circuits to electrical equipment and devices. Adjust
operators, controls, safety devices, alarms, and limit switches.
1. Hydraulic Operators: Purge operating system, adjust pressure and fluid levels, and check
for leaks.
2. Operational Test: After electrical circuitry has been energized, start units to confirm
proper motor rotation and unit operation.
3. Test and adjust controls, alarms, and safeties. Replace damaged and malfunctioning
controls and equipment.
3.9 DEMONSTRATION
END OF SECTION
1.04 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Shop Drawings: Indicate manhole locations, elevations, piping sizes and elevations of
penetrations.
C. Product Data: Provide manhole covers, component construction, features, configuration, and
dimensions.
1.05 QUALITY ASSURANCE
A. Manufacturer: Company specializing in manufacturing products specified in this section with
minimum three years documented experience.
1.06 FIELD CONDITIONS
A. Cold and Hot Weather Requirements: Comply with requirements of ACI 530/530.1/ERTA or
applicable building code, whichever is more stringent.
1. Description: Complying with ACI 318, ACI 350 M/ 350RM, and the following:
a. Cement: ASTM C150, Type II.
b. Fine Aggregate: ASTM C33, sand.
c. Coarse Aggregate: ASTM C33, crushed gravel.
d. Water: Potable.
2. Portland Cement Design Mix: 27.6 MPa minimum, with 0.45 maximum water/cementitious
materials ratio.
a. Reinforcing Fabric: ASTM A 185/A 185M, steel, welded wire fabric, plain.
b. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (420 MPa) deformed steel.
C. Frames and Grates: ASTM A 536, Grade 60-40-18, ductile iron designed for A-16, structural
loading. Include flat grate with small square or short-slotted drainage openings.
1. Size: 24 by 24 inches (610 by 610 mm) minimum unless otherwise indicated.
2. Grate Free Area: Approximately 50 percent unless otherwise indicated.
D. Frames and Grates: ASTM A 536, Grade 60-40-18, ductile iron designed for A-16, structural
loading. Include 24-inch (610-mm) ID by 7- to 9-inch (175- to 225-mm) riser with 4-inch (102-
mm) minimum width flange, and 26-inch- (660-mm-) diameter flat grate with small square or
short-slotted drainage openings.
1. Grate Free Area: Approximately 50 percent unless otherwise indicated.
E. Configuration, Sizes and Details: As indicated.
2. Use detectable warning tape over nonferrous piping and over edges of underground
structures.
B. Warning tape should be installed during backfilling 300mm below finished surface or as
directed by Engineer. Text in Arabic and English indicating the protected services lying below
the tapes shall be permanent ink bonded to resist prolonged chemical and minerals attack by
corrosive acid attack and alkalis with the message repeated at maximum interval of two meters.
Tapes shall be color coded as follows, with black text as indicated. The design and styles of the
text shall be approved by the Engineer.
1. Storm: Yellow
2. Caution: Sewer Below
3. Storm pressure mains: Yellow
4. Caution: Storm Pressure main below
3.18 CLEANING
A. Clean interior of piping of dirt and superfluous materials. Flush with water.
END OF SECTION
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Conduit and duct:
1. Polyvinyl chloride (PVC) plastic utilities duct.
2. High density polyethylene (HDPE) conduit.
B. Precast concrete manholes.
C. Cast-in-place manhole accessories.
D. Accessories:
1. Underground warning tape.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide for metallic conduit, nonmetallic conduit, and manhole accessories.
C. Shop Drawings: Indicate dimensions, reinforcement, size and locations of openings, and
accessory locations for precast manholes.
D. Manufacturer's Instructions: Indicate application conditions and limitations of use stipulated
by product testing agency specified under Quality Assurance. Include instructions for
storage, handling, protection, examination, preparation, and installation of product.
E. Field Samples: Provide sample of actual plastic duct delivered to site, two each 2 feet (610
mm) long.
F. Project Record Documents: Record actual routing and elevations of underground conduit
and duct, and locations and sizes of manholes.
PART 2 PRODUCTS
2.01 CONDUIT AND DUCT
A. Polyvinyl Chloride (PVC) Plastic Utilities Duct: Comply with NEMA TC 6&8 and ASTM
F512; Type EB-20 listed and labeled as complying with UL 651, suitable for burial with
concrete encasement.
1. Fittings: Comply with NEMA TC 9.
a. Manufacturer: Same as manufacturer of duct to be connected.
B. High Density Polyethylene (HDPE) Conduit: NFPA 70, Type HDPE; comply with NEMA TC
7 and list and label as complying with UL 651A; Schedule 40 unless otherwise indicated.
2.04 ACCESSORIES
A. Duct Bank Spacers: Nonmetallic; designed for maintaining conduit/duct spacing for
concrete encasement in open trench installation; suitable for the conduit/duct arrangement
to be installed.
B. Bore Spacers: Nonmetallic; designed for maintaining conduit/duct spacing for installation
within casing; furnished with roller wheels to facilitate installation, openings to facilitate grout
flow, and holes for stabilization cable; suitable for the casing and conduit/duct arrangement
to be installed.
C. Underground Warning Tape: Polyethylene tape suitable for direct burial.
1. Legend: Type of service, continuously repeated over full length of tape.
2. Color:
a. Tape for Buried Power Lines: Black text on red background.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify that field measurements are as indicated.
B. Verify routing and termination locations of duct bank prior to excavation for rough-in.
C. Verify locations of manholes prior to excavating for installation.
D. Duct bank routing is shown in approximate locations unless dimensions are indicated.
Route as required to complete duct system.
E. Manhole locations are shown in approximate locations unless dimensions are indicated.
Locate as required to complete ductbank system.
END OF SECTION
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Electrodes, connectors, and conductors.
B. Grounding wells.
C. Treatment wells.
1.05 SUBMITTALS
A. See Section 01 3000 - Administrative Requirements, for submittal procedures.
B. Product Data: Provide for grounding electrodes and connectors.
C. Shop Drawings: Indicate layout of grounding system and installation details.
D. Test Reports: Indicate overall resistance to ground at each system.
E. Manufacturer's Instructions: Include instructions for storage, handling, protection,
examination, preparation and installation of exothermic connectors.
F. Manufacturer's Qualification Statement.
G. Project Record Documents: Accurately record actual locations of electrodes and
connections.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify completion of filling and backfilling before beginning grounding work.
B. Verify that trenching is completed before installing horizontal electrodes.
3.02 INSTALLATION
A. Install products in accordance with manufacturer's instructions.
B. Install rod electrodes ________.
C. Install interconnecting wire 2 feet (600 mm) below finished grade level.
D. Provide grounding wells and grounding boxes as indicated.
E. Provide cast-in-place concrete grounding well under provisions of Section 03 3000.
Construct as indicated.
END OF SECTION
PART 1 - GENERAL
1.1 SCOPE OF WORK
A. The work required under this Section consist of all feeder, distribution underground ducts and
raceway, including maintenance holes for the project as shown on drawings and/or as
specified herein.
B. The Contractor is held responsible to be familiar with the provisions contained herein and with
other Sections of this Specification as applicable to provide a complete underground outside
plant infrastructure for cable installation. The approved vendor, designed agent or employee is
held responsible to be familiar with the provisions contained herein and is assumed to possess
the proper license(s), bonding, knowledge, manpower, and material applicable to the
completion of the installation.
1.3 REFERENCES
A. Design and install and test data distribution systems per manufacturer’s requirements and in
accordance with local codes, requirements of authorities having jurisdiction, and particularly the
following standards and practices. The Contractor is responsible to determine and adhere to the
most recent edition of these standards when developing their responses and completing the
project installation.
PART 2 - PRODUCTS
2.1 GENERAL:
A. The number, size, raceway duct material and arrangement shall be as indicated on
drawings and / or as specified herein.
2.2 PVC DUCT/CONDUIT:
A. General:
1. All conduits shall minimally be 110mm in diameter with 4x25mm HDPE sub-ducts
2. PVC utility ducts shall meet NEMA TC-6 standard. PVC conduit s shall be
minimum of schedule 40 constructions, including if concrete encased.
3. All bends shall be factory made and be 10 times the diameter of the conduit.
4. Provide bushing on all conduit terminations.
5. Splice conduits with fittings approved by the conduit manufacturer for the
specified applications.
2.3 COMMUNICATIONS MAINTENANCE HOLES:
A. Maintenance holes shall meet the requirements established in this section unless
otherwise approved by client.
1. Provide as specified in the project drawings, specifications and as specified herein
this section. All manhole specifications shall be submitted to client for approval prior
to installation by RFI. Manholes are to be specified for all splice points unless
otherwise specified.
2. Any conflicts in the requirements of these specifications shall be communicated to
client in writing by RFI submittal.
3. Typical full size manholes:
• (Type 1B) shall be inside dimensions 2750mm long by 1500mm wide 2000mm
high unless otherwise specified on the Drawings and Specifications. The exact
manhole size and configuration shall be submitted to client for approval.
4. Only Pre-cast shall be installed.
5. The manhole hole shall be constructed of reinforced pre-cast concrete, 316.4 kg/cm2
and designed for truck loading.
6. Pulling irons shall to be provided on opposite side of the ducts, rated at 453.6
kilograms pulling tensions.
7. Bonding jumpers shall be provide between each section and attached to
reinforcing steel.
8. Pre-cast maintenance holes with reinforcing steel bonded together do not require an
END OF SECTION