Project Management Process Steps
Project Management Process Steps
In the Project Management Body of Knowledge (PMBOK), the Project Management Institute
(PMI) outlines five project management process groups:
Initiating: processes that are required to define and authorize a new project, or a new phase of
an existing project.
Planning: processes that are required to create the project scope, evaluate objectives, and
establish the plan to accomplish these objectives.
Executing: processes that are required to carry out the plan, in a manner that satisfies all project
requirements.
Monitoring & Controlling: processes required to track, assess, and regulate project performance
and progress, as well as identify and initiate changes as necessary.
Closing: processes required to formally end a project, or a phase of a project.
The following chart illustrates the integrated nature of all five project management process
groups:
Below is a highly simplified overview of the five project management process groups:
Initiating
The initiating project management process group governs the tasks and steps that are needed to
define and formally authorize a new project, or a major new phase of an existing project. It also
ensures that project selection aligns with overall organizational strategy. Typically, there are two
critical outputs of this process: the project charter, and the stakeholder register.
The project charter formally authorizes a project, and includes elements such as a high-level
scope statement, timeline and cost estimate, as well as a list of key risks, opportunities and
stakeholders. Once the project charter is formally accepted by all required stakeholders, it
grants the project manager the necessary authority to obtain and allocate organizational
resources (personnel, equipment and capital), in order to ultimately carry out project activities.
The stakeholder register identifies the expectations of each stakeholder/stakeholder group, and
is used by the project manager (together with other members of the executive project team) to
align expectations. This can be a difficult and time consuming task, but it is absolutely essential
to ensure long-term support for projects once they begin.
Planning
The planning project management process group governs the tasks and steps that are necessary to
establish the complete scope of the project (effort, resources and objectives), and the actions
necessary to carry out the scope.
Planning is the most detailed and largest process group, and typically leads to several key outputs
include:
Each of these planning-related documents should be developed in collaboration with all relevant
stakeholders. The time and effort invested in developing the Project Charter and Stakeholder
Register will pay big dividends here.
Once the overall project management plan is approved (which as noted above is composed of
multiple sub-plans, baselines, and other documents), then the project is formally authorized to
start.
Executing
The executing project management process group governs the tasks and steps necessary to carry
out the work defined in the project management plan. In other words, this is where the “rubber
hits the road” and the project takes flight.
Deliverables
Work performance data
Issue logs
Change requests
Updates to the project management plan
Updates to project documents
Updates to organizational process assets
Updates to environmental factors
Lessons learned register
Quality reports
Test and evaluation documents
Project team assignments
Resource calendars
Team performance assessments
Selected vendor lists
Vendor agreements
As noted above, change requests are a key output of the executing process group. Determining
how, what and when to change any aspect of the project plan can be (and usually is) difficult and
challenging. This is because the project plan is not modular. Changing one aspect can triggers
changes in another — which in some cases may be positive, and in others negative. To make the
situation even more complex, sometimes it is not clear whether proposed changes will be
positive or negative. Or alternative, a change that was expected to have a positive impact turns
out to have a negative consequence.
The bad news for project managers and other members of the project executive team, is that
there is no crystal ball, magic mirror, or other handy device that reveals whether a proposed
change will be rewarding or regrettable. The good news, however, is that advanced project
management software supports scenario (i.e. “what if?”) planning, that highlights the likely
impact of decisions such as potential resource reallocation.
The monitoring & controlling project management process group governs the tasks and steps in
three key areas: tracking, reviewing and optimizing project progress and performance;
identifying areas in which changes to the project plan are beneficial or necessary; and carrying
out approved changes.
Key outputs typically created during the monitoring & controlling process include:
Project management plan updates
Approved change requests
Accepted deliverables
Updated schedule forecasts
Updated cost forecasts
Quality control measurements
Closed procurements
Before moving to the next and final process group (closing), it is helpful to pause and focus on
an issue that can confuse and frustrate some new project managers, as well as those outside of
the formal project management professional who nevertheless find themselves working on
projects.
Project “control” in the context of project management does not mean rigidly executing the
project plan. Rather, it means continuously measuring actual project progress against planned
estimates and expectations. It is a foregone conclusion that there will be a variance between
actual vs. planned performance, and it is the responsibility of the executive project management
team (led by the project manager) to determine if corrective action is necessary. This analysis
and decision-making should be documented so that it may guide the current project, and
potentially enhance future project planning and execution.
Closing
The closing project management process group governs the tasks and steps necessary to formally
close out a project, or close out a major phase of an existing project.
This process group should also include documentation and any other project assets that address
the early termination or suspension of a project (which may or may not have anything materially
to do with the project itself; e.g. major changes in the marketplace, new regulations, etc.).