Drawing No:
Equipment:
                                                                                 Panel Ref: -
                                                                                 Page:
                                                                                 Date:
                               SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                                     COMMISSIONING FORM
 TYPE:               11KV MV         SITE        TANZANIA              PROJECT           KINYEREZI II
                      PANEL
                                                                                            240MW
                                                                                            CCPP
LOCATION           MV SWITCH         SUB                                CLIENT            TANESCO
                   GEAR ROOM       STATION
                                    NAME
   N                               Panel                                 Status                 Date
   o                                                                    YES / NO
  1           All the panels are erected and in position
  2           Control cable termination
  3           Power cable termination
  4           Helper to assist Commissioning team
  5           Equipment Earthing connection
  6           Auxiliary supply availability (DC and AC
              source)
  7           Interpanel wiring
                   TESTED BY                 WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
  NAME…………….............                NAME…………………………………                  NAME……………………………….
  DESIGNATION……………..                    DESIGNATION………………………….             DESIGNATION………………………..
  DATE……………………..                        DATE………………………………….                 DATE………………………………..
                                                                           Drawing No:
                                                                           Equipment:
                                                                           Panel Ref: -
                                                                           Page:
                                                                           Date:
                             SITE TEST PROCEDURE AND REPORT FOR MV PANEL
8           Approved drawings and cable schedule
9           FAT Report
10          Panel room cleanliness
11          Witness Engineer availability
12          Bus bar tightness
CHECKED BY                           NAME                             SIGNATURE
Consultant
End user
                 TESTED BY                  WITNESSED BY CONSULTANT       WITNESSED/APPROVED BY OWNER
NAME…………….............               NAME…………………………………                 NAME……………………………….
DESIGNATION……………..                   DESIGNATION………………………….            DESIGNATION………………………..
DATE……………………..                       DATE………………………………….                DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                                SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                              TEST PROCEDURE FOR CURRENT TRANSFORMERS:
    1. Date of Erection             :
    2. Equipment Details            :
                                    LINE I                       LINE II                  LINE III
 Make
 Type
 CT. Ratio
 Burden
 Class
 Ratio
 Selected Ratio
 Sl. No.
 Mfg Year
    3. INSULATION RESISTANCE MEASUREMENT TEST
Aim:
To ensure the insulation healthiness of the primary and secondary circuits by measuring
Insulation resistances
Equipment Required:
The major equipment required for performing IR measurement test are,
                  TESTED BY                  WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
 NAME…………….............                 NAME…………………………………                    NAME……………………………….
 DESIGNATION……………..                     DESIGNATION………………………….               DESIGNATION………………………..
 DATE……………………..                         DATE………………………………….                   DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                              SITE TEST PROCEDURE AND REPORT FOR MV PANEL
i) 0-5kVdc Megger.
ii) Test Leads.
Test Procedure:
The above test to be conducted at following points,
a) Primary to Earth
b) Primary to Secondary
c) Secondary to Earth
d) Between Secondary Cores
Note: a) Remove the connected earthing to system involving CT under test
b) Disconnect the connected terminals of CT M. Box.
a. Primary to earth
1) Connect the line terminal of the Megger (5000V) to either P1 (or) P2 of the Current
Transformers
2) Connect the Earth terminal of the Megger to the earth stud provided at the equipment
3) Switch on the Megger.
4) Take down the readings (It should be in Mega Ohms).
b. Primary to Secondary
1) Connect the line terminal of the Megger (5000V) to either P1 (or) P2 of the Current
Transformers
2) Connect the Earth terminal of the Megger to the S1 (or) S2 of the Current transformers
3) Switch on the Megger
4) Take down the readings (It should be in Mega Ohms)
c. Secondary to Earth
1) Connect the line terminal of the Megger (500V) to either S1 (or) S2 of the Current
Transformers
2) Connect the Earth terminal of the Megger to the earth stud provided at the equipment
3) Switch on the Megger.
Insulation Resistance Test Result :
                  Ref                      LINE I                  LINE II                  LINE III
                  TESTED BY                  WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
 NAME…………….............                NAME…………………………………                     NAME……………………………….
 DESIGNATION……………..                    DESIGNATION………………………….                DESIGNATION………………………..
 DATE……………………..                        DATE………………………………….                    DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                              SITE TEST PROCEDURE AND REPORT FOR MV PANEL
 Primary to Earth
 Primary to Sec.1
 Primary to Sec-2
 Sec-1 to Earth
 Sec-2 to Earth
 Sec-1 to Sec-2
4 . SECONDARY WINDING RESISTANCE TEST
Aim:
To check for the winding resistance on the secondary side value, so that the value matches
With the factory test values
Equipment Required:
The Secondary winding resistance test can be performed with the following equipment,
i) Milli ohm meter.
ii) Test Leads.
Test Procedure:
a) Select the Multi meter in Resistance Mode.
b) Connect the Multi meter across the secondary terminals of various cores.
c) Note down the readings
d) Compare the test results with Factory Test Report (If available)
Winding Resistance Test Result : (Using Equipment Details)
            Ref                     LINE I                      LINE II
          Core-1
                  TESTED BY                  WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
 NAME…………….............                NAME…………………………………                      NAME……………………………….
 DESIGNATION……………..                    DESIGNATION………………………….                 DESIGNATION………………………..
 DATE……………………..                        DATE………………………………….                     DATE………………………………..
                                                                                    Drawing No:
                                                                                    Equipment:
                                                                                    Panel Ref: -
                                                                                    Page:
                                                                                    Date:
                                SITE TEST PROCEDURE AND REPORT FOR MV PANEL
          Core-2
    4. POLARITY TEST
Aim:
To check for the correct sequence of polarity on the primary and secondary side of the
Current transformer (for eg., When P1 is positive w.r.t. P2, then S1 also must be positive w.r.t S2,
According to the scheme requirement)
Equipments Required:
The equipments required for polarity tests are as follows,
i) Battery of suitable rating or Polarity tester.
ii) Analog Multimeter / Galvanometer.
iii) Connecting leads.
Test Procedure:
i) Connect battery + Ve to P1(Primary) Terminal of CT
ii) Connect battery - Ve to P2(Primary) Terminal of CT
iii) Connect Multi meter (Analog)+ Ve to S1(Secondary) Terminal of CT
iv) Connect Multi meter (Analog)- Ve to S2(Secondary) Terminal of CT
v) Momentarily apply the D.C Voltage across the Primary terminals of CT
If the meter deflects forward then the polarity is O.K
Polarity Test Result : (Using Equipment Details)
                          Ref              LINE I                  LINE II                 LINE III
                  TESTED BY                    WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
 NAME…………….............                 NAME…………………………………                      NAME……………………………….
 DESIGNATION……………..                     DESIGNATION………………………….                 DESIGNATION………………………..
 DATE……………………..                         DATE………………………………….                     DATE………………………………..
                                                                                    Drawing No:
                                                                                    Equipment:
                                                                                    Panel Ref: -
                                                                                    Page:
                                                                                    Date:
                              SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                    Core-1
                    Core-2
   5.    MAGNETIZING CURRENT CHARACTERISTIC(KNEE POINT VOLTAGE) TEST
   Aim:
             To prove that the CT cores do not saturate during the application of peak voltage and
   ensure that the saturation of the core is avoided at knee point voltage
    Equipment Required:
             The following are the equipment required for performing magnetizing current characteristics,
                              i) High Voltage Transformer test kit.
                              Ii) Digital Multimeter.
                               iii) Clamp Meter.
                              iv) Connecting cables
  Test Procedure:
    Note: a) CT should not saturate at 110% of KVp
              b) If knee point voltage is not mentioned the knee point current may be taken
              into consideration
              c) Magnetization of Metering core should not been done.
   i)         Connect the Hi-voltage Transformer across the secondary terminals of PS Class
              core.
             ii) Apply 10% of Knee point Voltage mentioned in rating plate
             iii) Then Raise the voltage to 20%, 30%, 40% ….. and 110%
             iv) Note down the Magnetizing
              Current.
                 TESTED BY                         WITNESSED BY CONSULTANT         WITNESSED/APPROVED BY OWNER
NAME…………….............                    NAME…………………………………                    NAME……………………………….
DESIGNATION……………..                        DESIGNATION………………………….               DESIGNATION………………………..
DATE……………………..                            DATE………………………………….                   DATE………………………………..
                                                                                   Drawing No:
                                                                                   Equipment:
                                                                                   Panel Ref: -
                                                                                   Page:
                                                                                   Date:
                              SITE TEST PROCEDURE AND REPORT FOR MV PANEL
             v) Repeat the test for all cores.
Knee Point voltage & Excitation Current mentioned in name plate
 Applied                                             Applied               Measured Current
 Voltage(V)1S1-              Measured Current       Voltage(V)2S1-         (mA)
 1S2                         (mA)                   2S2
 10%                                                10%
 20%                                                20%
 30%                                                30%
 40%                                                40%
 50%                                                50%
 60%                                                60%
 70%                                                70%
 80%                                                80%
 90%                                                90%
 100%                                               100%
 110%                                               110%
   6.    PRIMARY INJECTION (RATIO) TEST
   Aim:
             To check the ratio of the primary turns to the secondary turns and compare it with the
    given rated values.
                 TESTED BY                       WITNESSED BY CONSULTANT          WITNESSED/APPROVED BY OWNER
NAME…………….............                    NAME…………………………………                    NAME……………………………….
DESIGNATION……………..                        DESIGNATION………………………….               DESIGNATION………………………..
DATE……………………..                            DATE………………………………….                   DATE………………………………..
                                                                                      Drawing No:
                                                                                      Equipment:
                                                                                      Panel Ref: -
                                                                                      Page:
                                                                                      Date:
                             SITE TEST PROCEDURE AND REPORT FOR MV PANEL
    Equipment Required:
             The equipment required for primary injection test or ratio test are as
                             follows, i)Primary injection test kit I Loading Transformer.
                             ii) Clamp Meter.
                             iii) Connecting cables.
   Test Procedure:
          a) Connect the Primary injection kit across the primary terminals (Pl, P2)
          b) Initially apply 10% of rated current
          c) Then Raise the current to 20%, 40% and 50%
          d) Note down the corresponding Secondary current at various cores.
         Ratio Test Result: (Using Equipment Details)
            Circuit Ref      CT Ratio        Applied Current              Measured Current in Sec (mA)
                                                in Pri(A)
                                                                      R ph             Y ph           B ph
              Core – 1
              Core – 2
                 TESTED BY                      WITNESSED BY CONSULTANT               WITNESSED/APPROVED BY OWNER
NAME…………….............                  NAME…………………………………                        NAME……………………………….
DESIGNATION……………..                      DESIGNATION………………………….                   DESIGNATION………………………..
DATE……………………..                          DATE………………………………….                       DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                                   SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   6. Functional Checks                :
               1         CT Secondary Spare Terminal Should be Short & Earthed
               2         CT Secondary All Terminals Tightness Should be Checked
   7. Remarks                  :
                          TEST PROCEDURE FOR VOLTAGE TRANSFORMERS
   1. Date of Erection                 :
   2. Equipment Details                :
                                       LINE I                       LINE II                LINE III
Make
Type
VT. Ratio
Burden
Class
Ratio
Sl. No.
Mfg Year
                   TESTED BY                    WITNESSED BY CONSULTANT           WITNESSED/APPROVED BY OWNER
NAME…………….............                     NAME…………………………………                  NAME……………………………….
DESIGNATION……………..                         DESIGNATION………………………….             DESIGNATION………………………..
DATE……………………..                             DATE………………………………….                 DATE………………………………..
                                                                                        Drawing No:
                                                                                        Equipment:
                                                                                        Panel Ref: -
                                                                                        Page:
                                                                                        Date:
                                SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   3.    INSULATION RESISTANCE MEASUREMENT TEST
         Aim :
             To ensure the insulation healthiness of the primary and secondary windings by measuring
   the insulation resistance value
   Equipment Required:
                     1 1) Insulation Tester.
                     2) Test leads.
   Test Procedure:
          The Above test to be conducted at following
        points a) Primary to Earth
        b) Primary to Secondary
        c) Secondary to Earth
        d) Between Secondary cores
             Note:       a) Remove the connected earthing to system involving CVT/PT under
                         test b) Disconnect the connected terminals of CVT/PT M. Box.
                          c) Permissible values for 400 kV > 400 MΩ and for 220 kV > 200
                                                         MΩ
                a.    Primary to earth
        1) Connect the line terminal of the Megger(5000V) to either P1 (or) P2 of the Voltage
        Transformers
        2) Connect the Earth terminal of the Megger to the earth stud provided at the equipment
        3) Switch on the Megger
        4) Take down the readings (It should be in Mega Ohms).
                 TESTED BY                        WITNESSED BY CONSULTANT               WITNESSED/APPROVED BY OWNER
NAME…………….............                     NAME…………………………………                     NAME……………………………….
DESIGNATION……………..                         DESIGNATION………………………….                DESIGNATION………………………..
DATE……………………..                             DATE………………………………….                    DATE………………………………..
                                                                                     Drawing No:
                                                                                     Equipment:
                                                                                     Panel Ref: -
                                                                                     Page:
                                                                                     Date:
                                SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                b.   Primary to Secondary
        1.    Connect the line terminal of the Megger (5000V) to either P1 (or) P2 of the
              Voltage transformers
        2.    Connect the Earth terminal of the Megger to the a (or) n of the Voltage transformers
        3.    Switch on the Megger
        4.    Take down the readings (It should be in Mega Ohms)
                c.   Secondary to Earth
        1.    Connect the line terminal of the Megger (500V) to either a (or) n of the Voltage transformers
        2.    Connect the Earth terminal of the Megger to the earth stud provided at the equipment
        3.    Switch on the Megger
        4.    Take down the readings (It should be in Mega Ohms)
                d.       B etween Secondary cores
        1.    Connect the line terminal of the Megger (500V) to either a (or) n of one core of the
              Voltage transformers
        2.    Connect the Earth terminal of the Megger (500V) to either a (or) n of the other cores of the
                    Voltage
                 transformers
        3.    Switch on the Megger
         4. Take down the readings (It should be in Mega Ohm)
         Insulation Resistance Test Result : (Values in Meg Ohms)
                                                    LINE I                LINE II             LINE III
             Primary to Secondary
             Primary to Earth
                 TESTED BY                      WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
NAME…………….............                   NAME…………………………………                      NAME……………………………….
DESIGNATION……………..                       DESIGNATION………………………….                 DESIGNATION………………………..
DATE……………………..                           DATE………………………………….                     DATE………………………………..
                                                                                      Drawing No:
                                                                                      Equipment:
                                                                                      Panel Ref: -
                                                                                      Page:
                                                                                      Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
             Secondary to Earth
    4.    SECONDARY WINDING RESISTANCE TEST
    Aim:
              This test is mainly done in order to calculate the winding resistance value and compare it
    with the factory test report and approve if the values are found satisfactory.
     Equipment Required:
                    1)    Multimeter.
                    2)    Test Leads.
    Test Procedure:
            a) Select the Multi meter in Resistance Mode.
            b) Connect the Multi meter across the secondary terminals of various
            cores. c) Note down the readings
            d) Compare the test results with Factory Test Report (If available)
    Winding resistance Test Value :
                          CORE                  LINE I                    LINE III                   LINE III
    7. POLARITY TEST
Aim:
To check for the correct sequence of polarity on the primary and secondary side of the
                  TESTED BY                     WITNESSED BY CONSULTANT              WITNESSED/APPROVED BY OWNER
 NAME…………….............                  NAME…………………………………                        NAME……………………………….
 DESIGNATION……………..                      DESIGNATION………………………….                   DESIGNATION………………………..
 DATE……………………..                          DATE………………………………….                       DATE………………………………..
                                                                                     Drawing No:
                                                                                     Equipment:
                                                                                     Panel Ref: -
                                                                                     Page:
                                                                                     Date:
                                  SITE TEST PROCEDURE AND REPORT FOR MV PANEL
voltage transformer (for eg., When A is positive w.r.t. N, then S1 also must be positive w.r.t S2,
According to the scheme requirement)
Equipment Required:
The equipment required for polarity tests are as follows,
i) Battery of suitable rating or Polarity tester.
ii) Analog Multi meter / Galvanometer.
iii) Connecting leads.
Test Procedure:
i) Connect battery + Ve to A(Primary) Terminal of VT
ii) Connect battery - Ve to N(Primary) Terminal of VT
iii) Connect Multi meter (Analog)+ Ve to S1(Secondary) Terminal of VT
iv) Connect Multi meter (Analog)- Ve to S2(Secondary) Terminal of VT
v) Momentarily apply the D.C Voltage across the Primary terminals of VT
If the meter deflects forward then the polarity is O.K
    Polarity Test Value :
                          R ph                     Y ph                     B ph
    8.    RATIO TEST
    Aim:
              To calculate the value of the turns ratio and compare it with the name plate details
     and approve it, if the values are found to be satisfactory.
     Equipment Required:
                    1)    Ratio test kit.
                    2) Test
    Leads. Test Procedure:
           a) Connect the Ratio Test kit across the primary terminals (Pl, P2)
                  TESTED BY                      WITNESSED BY CONSULTANT            WITNESSED/APPROVED BY OWNER
 NAME…………….............                     NAME…………………………………                    NAME……………………………….
 DESIGNATION……………..                         DESIGNATION………………………….               DESIGNATION………………………..
 DATE……………………..                             DATE………………………………….                   DATE………………………………..
                                                                                        Drawing No:
                                                                                        Equipment:
                                                                                        Panel Ref: -
                                                                                        Page:
                                                                                        Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
           b) Apply 415V (For220 KV), 4000V (For 400 KV)
           c) Note down the corresponding Secondary Voltage at various
          cores. d) Compare the ratio with Factory Test Reports (If available)
         Voltage Ratio Test Result :
     Phase                      Primary Voltage                              Secondary Volts
                                      Rated                Tested                  Core-1              Core-2
   9. Functional checks: (Whether Operational Checks OK / Not OK / Not Available)
               1         Wiring checks
               2         Correct operation of appropriate indicator / aux. relay
               3         Correct initiation of alarm contacts
               4         Correct circuit breaker tripping contacts
               5         Relay cover properly fixing
                   TESTED BY                       WITNESSED BY CONSULTANT              WITNESSED/APPROVED BY OWNER
NAME…………….............                      NAME…………………………………                       NAME……………………………….
DESIGNATION……………..                          DESIGNATION………………………….                  DESIGNATION………………………..
DATE……………………..                              DATE………………………………….                      DATE………………………………..
                                                                                      Drawing No:
                                                                                      Equipment:
                                                                                      Panel Ref: -
                                                                                      Page:
                                                                                      Date:
                                   SITE TEST PROCEDURE AND REPORT FOR MV PANEL
               6         Correct operating reset switch
               7         Relay Draw out conditions VT shorting link should be short
   7. Remarks                  :
                                      TEST PROCEDURE FOR CIRCUIT BREAKERS
   1. Date of Erection                 :
   2. Equipment Details                :
Make
Type
Rated Volts
Rated Current
                   TESTED BY                      WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
NAME…………….............                     NAME…………………………………                   NAME……………………………….
DESIGNATION……………..                         DESIGNATION………………………….              DESIGNATION………………………..
DATE……………………..                             DATE………………………………….                  DATE………………………………..
                                                                                   Drawing No:
                                                                                   Equipment:
                                                                                   Panel Ref: -
                                                                                   Page:
                                                                                   Date:
                                   SITE TEST PROCEDURE AND REPORT FOR MV PANEL
 Sl. No.
 Mfg Year
    3.    INSULATION RESISTANCE MEASUREMENT TEST
          Aim :
              To find the insulation resistance value of the equipment and ensure the performance of
    the equipment based on the values obtained.
    Equipment Required:
                          1) Insulation
                             tester.
                           2) Test leads.
    Test Procedure:
    The above test is to be conducted at following
           points. a) Control Circuit of Breakers
           b) Main Circuit of Breakers (pole)
           a) Control Circuit of Breakers
         i) Connect The Megger across the various points on the control
         circuit ii) Switch ‘ON’ the Megger
         iii) Take down the readings
         b) Main Circuit of Breakers (pole)
         i) Connect The Megger across the Interrupter while Breaker on ‘Open’ Condition
ii) Connect The Megger across the Pole & Earth while Breaker on ‘Close’ Condition iii) Switch ‘ON’ the Meggar
          Insulation Resistance Test Result :
                  TESTED BY                      WITNESSED BY CONSULTANT          WITNESSED/APPROVED BY OWNER
 NAME…………….............                     NAME…………………………………                 NAME……………………………….
 DESIGNATION……………..                         DESIGNATION………………………….            DESIGNATION………………………..
 DATE……………………..                             DATE………………………………….                DATE………………………………..
                                                                                     Drawing No:
                                                                                     Equipment:
                                                                                     Panel Ref: -
                                                                                     Page:
                                                                                     Date:
                                   SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                             Ref                   R-R’                   Y-Y’              B-B’
            CB open condition
                             Ref                   R-E                    Y-E               B-E
            CB close condition
                             Ref                   R-Y                    Y-B               B-R
            CB close condition
   4.    TRIP COIL & CLOSE COIL RESISTANCE MEASUREMENT TEST
   Aim:
             To find the value of trip and coil resistance across the respective coils and compare with
   the factory approved values.
    Equipment Required:
                    1) Multi meter.
                    2) Test Leads.
   Test Procedure:
           a) Select the Multi meter in Resistance Mode.
           b) Connect the Multi meter across the Trip/Close
           coils.
                 TESTED BY                      WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
NAME…………….............                     NAME…………………………………                     NAME……………………………….
DESIGNATION……………..                         DESIGNATION………………………….                DESIGNATION………………………..
DATE……………………..                             DATE………………………………….                    DATE………………………………..
                                                                                    Drawing No:
                                                                                    Equipment:
                                                                                    Panel Ref: -
                                                                                    Page:
                                                                                    Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
           c) Note down the readings
           TRIP COIL & CLOSE COIL RESISTANCE MEASUREMENT TEST RESULT
                                         Ref                                     OHMS
            OPEN COIL
                                         Ref                                      OHMS
            CLOSE COIL
   5.    OPENING & CLOSING TIME MEASUREMENT TEST
   Aim:
             To calculate the timing of the opening and closing of the breaker contacts and ensure that
   the values are within acceptable limits.
    Equipment Required:
                   o     Single I three pole timer.
                   o     Test leads.
   Test Procedure:
        a) Connect the Timer across the Breaks for the Opening Time
        b) Connect the Timer across the Pole for the Closing Time/ "Close-Open" Time
   Breaker Closing & Opening Time Test Result : (timings in milli-seconds)
                                               LINE I               LINE II           LINE III
                 Close Time
                 TESTED BY                            WITNESSED BY CONSULTANT      WITNESSED/APPROVED BY OWNER
NAME…………….............                       NAME…………………………………                  NAME……………………………….
DESIGNATION……………..                           DESIGNATION………………………….             DESIGNATION………………………..
DATE……………………..                               DATE………………………………….                 DATE………………………………..
                                                                                            Drawing No:
                                                                                            Equipment:
                                                                                            Panel Ref: -
                                                                                            Page:
                                                                                            Date:
                                     SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                  Open Time
                 Close - Open
    6.    CONTACT RESISTANCE MEASUREMENT TEST
    Aim:
              To calculate the value of the contact resistance and compare the value with factory
     report and approve the equipment for further use.
     Equipment Required:
                    o      Contact resistance meter.
                    o      Test leads.
    Test Procedure:
                          i) Connect the CRM kit across the contact while Breaker in
                          Close Condition.
                          ii) Switch ON the test kit.
Contact Resistance Test Report : (values in micro ohms)
                 Applied Current(A)                       Rph                     Yph              Bph
                               100
    7. Operational Checks :
             1       Manual
                  TESTED BY                             WITNESSED BY CONSULTANT            WITNESSED/APPROVED BY OWNER
 NAME…………….............                         NAME…………………………………                       NAME……………………………….
 DESIGNATION……………..                             DESIGNATION………………………….                  DESIGNATION………………………..
 DATE……………………..                                 DATE………………………………….                      DATE………………………………..
                                                                               Drawing No:
                                                                               Equipment:
                                                                               Panel Ref: -
                                                                               Page:
                                                                               Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                    Close
                    Open
            2       Electrical
                    Close
                    Open
            3       Protection Tripping
            4       Anti Pumping Function
   8. Functional Checks : (Whether Operational Checks OK / Not OK / Not Available)
            1       Emergency Trip
            2       ON-OFF Indication
            3       Spring charge Limit Switch
            4       CB Aux. contacts
            5       Auto Trip Indication
            6       Trip circuit healthy
   9. Remarks                :
                                   TEST PROCEDURE FOR HV CABLES
                 TESTED BY                       WITNESSED BY CONSULTANT      WITNESSED/APPROVED BY OWNER
NAME…………….............                     NAME…………………………………               NAME……………………………….
DESIGNATION……………..                         DESIGNATION………………………….          DESIGNATION………………………..
DATE……………………..                             DATE………………………………….              DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
      1. Date of Erection              :
      2. Equipment Details             :
Make
Type
Size / Length
Rated Current
Sl. No.
Mfg Year
System (Earthed (or) Unearthed)
 3.     INSULATION RESISTANCE MEASUREMENT TEST
        Aim :
                To find the value of insulation resistance of the cable, and ensure that the value is
      in acceptable limit.
      Equipment Required:
                   o     Insulation tester.
                   o     Test leads.
      Test Procedure:
         i) Connect the Megger across conductor & Earth
          ii) Switch 'ON' the Megger
         iii) Take down the readings
         iv) Repeat the test for other phases of the cable
                  TESTED BY                        WITNESSED BY CONSULTANT       WITNESSED/APPROVED BY OWNER
NAME…………….............                        NAME…………………………………               NAME……………………………….
DESIGNATION……………..                            DESIGNATION………………………….          DESIGNATION………………………..
DATE……………………..                                DATE………………………………….              DATE………………………………..
                                                                                          Drawing No:
                                                                                          Equipment:
                                                                                          Panel Ref: -
                                                                                          Page:
                                                                                          Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   Insulation Resistance Test Result : (Values in Meg Ohms)
                         Ref                      Before HV Test               After HV Test
            R ph to Earth
            Y ph to Earth
            B ph to Earth
            R ph to Y ph
            Y ph to B ph
            B ph to R ph
   4.    DC HIGH VOLTAGE TEST
   Aim:
             To ensure that the power cables are withstanding the high voltage and to spot out
   minute defects in cables and approve the performance of the cables under operation.
   Equipment Required
                  o      High voltage test kit.
                  o      Test leads.
   Test Procedure:
          i) Connect the Hi-Pot test kit across the conductor and cable armour
         ii) Connect the other conductors (other phases) and connect it to the
         earth
         iii) Switch “on” the kit for 1 Minutes.
         iv) Repeat the test for other phases of the cable
         v) Take down the leakage current reading
                 TESTED BY                           WITNESSED BY CONSULTANT             WITNESSED/APPROVED BY OWNER
NAME…………….............                       NAME…………………………………                       NAME……………………………….
DESIGNATION……………..                           DESIGNATION………………………….                  DESIGNATION………………………..
DATE……………………..                               DATE………………………………….                      DATE………………………………..
                                                                                  Drawing No:
                                                                                  Equipment:
                                                                                  Panel Ref: -
                                                                                  Page:
                                                                                  Date:
                                  SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   DC High Voltage Test:
                 Ref          Voltage Applied           Leakage Current             Result
                                  Between                 in milli Amps
                                                      Start          Finish
                         R ph to Earth + Y + B
                         Y ph to Earth + Y + B
                         B ph to Earth + Y + B
   5. Functional Checks: (Whether Operational Checks OK / Not OK / Not Available)
             1     Check Cable Proper clearance
             2     Check Cable Earthed or Unearthed, When Earthed Cable Should be Earthed
             3     Cable End Lugs Properly Crimped
             4     After Hi Pot Test Terminals Tightness to be checked
   6. Remarks                 :
                  TESTED BY                      WITNESSED BY CONSULTANT         WITNESSED/APPROVED BY OWNER
NAME…………….............                      NAME…………………………………                 NAME……………………………….
DESIGNATION……………..                          DESIGNATION………………………….            DESIGNATION………………………..
DATE……………………..                              DATE………………………………….                DATE………………………………..
                                                                                     Drawing No:
                                                                                     Equipment:
                                                                                     Panel Ref: -
                                                                                     Page:
                                                                                     Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
                                              TEST PROCEDURE FOR BUS BAR
   1. Date of Erection                 :
   2. Equipment Details                :
                                       LINE I                          LINE II                LINE III
Make
Type
No. of Joints
Size / Length
Sl. No.
Mfg Year
   3.    INSULATION RESISTANCE MEASUREMENT TEST
         Aim :
             To find the insulation resistance value of the equipment and ensure the performance of the
   equipment based on the values obtained.
   Equipment Required:
                  o      Insulation Tester.
                  o      Test leads.
   Test Procedure:
          The Above test to be conducted at following
        points
                 TESTED BY                         WITNESSED BY CONSULTANT          WITNESSED/APPROVED BY OWNER
NAME…………….............                        NAME…………………………………                  NAME……………………………….
DESIGNATION……………..                            DESIGNATION………………………….             DESIGNATION………………………..
DATE……………………..                                DATE………………………………….                 DATE………………………………..
                                                                               Drawing No:
                                                                               Equipment:
                                                                               Panel Ref: -
                                                                               Page:
                                                                               Date:
                               SITE TEST PROCEDURE AND REPORT FOR MV PANEL
        a) Each Phase to Earth
        b) Between Phase to Phase
        a.    Phase to earth
        1) Connect the positive terminal of the Megger (5000V) to one phase.
        2) Connect the Earth terminal of the Megger to the common earth terminal.
        3) Switch on the Megger.
        4) Take down the readings.
        5) Similarly note down the reading for all phases and earth.
        b.     Between one phase to other phase
        1) Connect the positive terminal of the Megger (5000V) to one phase.
        2) Connect the Earth terminal of the Megger to the other phase.
        3) Switch on the Megger
        4) Take down the readings.
        5) Similarly note down the reading for all phases.
        Insulation Resistance Test Value:
             REF                                  MEASURED VALUE
             R ph – Y ph
             Y ph – B ph
             B ph – R ph
             R ph – Earth
             Y ph – Earth
                 TESTED BY                  WITNESSED BY CONSULTANT            WITNESSED/APPROVED BY OWNER
NAME…………….............                 NAME…………………………………                   NAME……………………………….
DESIGNATION……………..                     DESIGNATION………………………….              DESIGNATION………………………..
DATE……………………..                         DATE………………………………….                  DATE………………………………..
                                                                                Drawing No:
                                                                                Equipment:
                                                                                Panel Ref: -
                                                                                Page:
                                                                                Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
           B ph – Earth
   4.    CONTACT RESISTANCE MEASUREMENT TEST
         Aim :
         To calculate the value of the contact resistance and compare the value with the factory
         report and approve the equipment for further use.
   Equipment Required:
                  o      Contact resistance meter(CRM).
                  o      Test leads.
   Test Procedure:
            The contact resistance measurement of each of the bus bar is measured by the following
         method
   a)    Ensure the required tightness of each bus bar joints.
   b)    Short one end of any two phases.
   c)    Now connect the CRM kit across the other end of the shorted phase.
   d)    Note down the reading.
         Contact Resistance Test: (Values in micro Ohms)
           Ref                    Measured value(micro Ohms)
           R ph – Y ph
           Y ph – B ph
           B ph – R ph
                 TESTED BY                        WITNESSED BY CONSULTANT      WITNESSED/APPROVED BY OWNER
NAME…………….............                      NAME…………………………………               NAME……………………………….
DESIGNATION……………..                          DESIGNATION………………………….          DESIGNATION………………………..
DATE……………………..                              DATE………………………………….              DATE………………………………..
                                                                                    Drawing No:
                                                                                    Equipment:
                                                                                    Panel Ref: -
                                                                                    Page:
                                                                                    Date:
                                  SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   5.    HIGH VOLTAGE MEASUREMENT TEST
      Aim :
      To ensure that the bus bar withstands high voltage and to spot out minute defects in the
   bus bar and approve the bus for usage.
   Equipment Required:
                  o      High voltage test kit.
                  o      Test leads.
   Test Procedure:
              The test is done by the following ways.
   a)    Connect the positive terminal of the test kit to one of the phase.
   b)    Short the other two phases to earth.
   c)    Connect the earth terminal of the kit to the same earth point.
   d)    Supply the rated high voltage to the bus bar.
   e)    Note down the reading.
         AC High Voltage Test :
   Test Voltage___________________ Duration __________________
              Ref.           Voltage Applied            Leakage Current In micro-Amps
                                  Between               Start          Finish     Result
                          R ph – Earth + Y + B
                          Y ph – Earth + Y + B
                          B ph – Earth + Y + B
                 TESTED BY                         WITNESSED BY CONSULTANT         WITNESSED/APPROVED BY OWNER
NAME…………….............                        NAME…………………………………                 NAME……………………………….
DESIGNATION……………..                            DESIGNATION………………………….            DESIGNATION………………………..
DATE……………………..                                DATE………………………………….                DATE………………………………..
                                                                            Drawing No:
                                                                            Equipment:
                                                                            Panel Ref: -
                                                                            Page:
                                                                            Date:
                                 SITE TEST PROCEDURE AND REPORT FOR MV PANEL
   6. Remarks                :
                 TESTED BY                    WITNESSED BY CONSULTANT      WITNESSED/APPROVED BY OWNER
NAME…………….............                   NAME…………………………………              NAME……………………………….
DESIGNATION……………..                       DESIGNATION………………………….         DESIGNATION………………………..
DATE……………………..                           DATE………………………………….             DATE………………………………..