Kurva S Proyek Gedung (Jahiras Siringoringo 188110067)

This document is a schedule showing the planned progress and timeline for construction of a building for the Meteorology, Climatology and Geophysics Agency in 2009. It is broken down into sections including preparatory work, foundation work, groundwork, building the tower structure by floor, exterior and interior walls, and building the auditorium structure by floor. The timeline is shown in columns for each date with the planned percentage of work to be completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views1 page

Kurva S Proyek Gedung (Jahiras Siringoringo 188110067)

This document is a schedule showing the planned progress and timeline for construction of a building for the Meteorology, Climatology and Geophysics Agency in 2009. It is broken down into sections including preparatory work, foundation work, groundwork, building the tower structure by floor, exterior and interior walls, and building the auditorium structure by floor. The timeline is shown in columns for each date with the planned percentage of work to be completed.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

KURVA S

PEMBANGUNAN GEDUNG
BADAN METEOROLOGI, KLIMATOLOGI DAN GEOFISIKA

TAHUN 2009
BOBOT
NO. URAIAN PEKERJAAN JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER DES KET
(%)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

I PEKERJAAN PERSIAPAN 2.88 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
II PEKERJAAN PONDASI 6.84 0.86 0.86 0.86 0.86 0.86 0.86 0.86 0.86
L
III PEKERJAAN TANAH 5.11 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 I
IV PEKERJAAN STRUKTUR TOWER
4.1 Basement 2.08 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 0.23 B
4.2 Lantai 1
4.3 Lantai 2
1.65
2.38
0.83 0.83
1.19 1.19 U
4.4 Lantai 3
4.5 Lantai 4
1.91
1.71
0.96
0.85
0.96
0.85 R
4.6 Lantai 5 1.59 0.80 0.80
4.7 Lantai 6 1.56 1.56
4.8 Lantai 7
4.9 Lantai 8
1.56
1.51
0.78 0.78
0.76 0.76 I
4.10 Lantai 9
4.11 Lantai 10
1.45
1.43
0.72 0.72
0.72 D 0.72
4.12 Lantai 11
4.13 Lantai 12
1.43
1.41 U 1.43
0.70 0.70
4.14 Lantai 13
4.15 Lantai Atap
1.40
1.45
L 1.40
0.73 0.73
4.16 Lantai Executive Lounge 0.28 0.28
4.17 Lantai Instrument 0.25 0.13 0.13
4.18 Rangka Atap
4.19 Lantai Atap / Lantai Antena
0.30
0.28
F 0.04 0.04 0.04 0.04
0.09
0.04
0.09
0.04
0.09
0.04

V PEKERJAAN ARSITE PEKERJAAN DINDING


5.1 Eksterior 14.13 0.59 1.18
I 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.18 1.77
5.2 Interior 1.61 0.13 0.13 0.13 T 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13 0.13
VI PEKERJAAN STRUKTUR AUDITORIUM
6.1 Basement 8.47 0.94 0.94 0.94 0.94 0.94 0.94 0.94 0.94 0.94 R
6.2 Lantai 1
6.3 Lantai 2
3.94
1.46
0.39 0.39 0.39 0.39 0.39 0.39 0.39
0.37
0.39
0.37 I 0.39
0.37
0.39
0.37
6.4 Lantai 3 0.99 0.49 0.49
6.5 Rangka Atap 1.81 0.30 0.30 0.30 0.30 0.30 0.30
VII PEKERJAAN ARSITEKTUR AUDITORIUM 1.97 0.28 0.28 0.28 0.28 0.28 0.28 0.28
VIII PEKERJAAN MEKANIKAL & ELEKTRIKAL 25.14 0.33 0.33 0.33 0.33 0.33 0.33 0.33 1.32 1.32 1.32 1.32 1.65 1.65 1.99 1.99 2.32 2.65 2.65 2.65

JUMLAH TOTAL 100.00


Rencana Mingguan 1.41 1.41 2.92 2.92 3.31 4.13 5.32 6.31 5.06 6.72 7.09 6.45 - - 7.21 7.53 4.58 4.27 3.84 4.18 4.41 4.37 4.37 2.18
Kumulatif Rencana - 1.41 2.82 5.74 8.66 11.96 16.10 21.42 27.73 32.79 39.51 46.60 53.05 53.05 53.05 60.27 67.79 72.37 76.65 80.49 84.67 89.08 93.45 97.82 100.0