Operations & Training Risk Management Plan
Author: Project Manager Created: Mar 1
Status: Draft / Final Updated: Mar 31
Objective
The objective of this document is to identify and determine potential risks for Plant Pals
operations launch
Executive Summary
RISK TYPE ONE: Going over the project budget
Scenario Risk to project Mitigation Plan
(L/M/H)
A product vendor loses a Probability- L ACCEPT
product shipment Impact- M The IR is low, the estimated risk of losing
Inherit risk- L
shipment is 5%
A product vendor charges Probability- M AVOID
a higher rate than Impact- M The IR is medium, it’s recommended to
Inherit risk- M
expected find another vendor
Each delivery truck costs Probability- H TRANSFER
$16,000 more than initially Impact- M As the IR is high, it is recommended to hire
Inherit risk- H
quoted a car leasing company or a delivery
company or a private delivery contractor
RISK TYPE TWO: Falling behind the training schedule
Scenario Risk to Mitigation Plan
project
(L/M/H)
More than 50% of Probability- L ACCEPT
employees quit after a Impact- L The IR is low, it is recommended to launch a
Inherit risk- L
difficult training process, more comprehensive pre-training campaign,
leaving the company set up a meeting to get all employees buy-in
short-staffed
Your Training Manager Probability- L ACCEPT
gets sick and misses a Impact- L The IR is low, it is recommended to
Inherit risk- L
week of training cooperate with the HR as they are
responsible for training programs
You cannot hire enough Probability- M Transfer
employees in time to train Impact- M The IR is medium, it is recommended to
Inherit risk- M
them before launch cooperate a contractor HR to hire more
employees before launching the training
program
Appendix:
Probability chart:
Probability
Qualitative Quantitative (if measurable)
Low Very low chance of risk occurring. Less than <10% chance of risk occurring.
Medium Medium chance of risk occurring. 10%-49% chance of risk occurring.
High High chance of risk occurring. 50%-100% chance of risk occurring.
Impact chart:
Types of
Impact Low Medium High
Low financial impact, Medium financial impact, High financial impact,
costing the company $0- costing the company costing the company
Financial $14,000 $15,000-$29,000 $30,000 or more
Medium impact to project
Low impact to project operations, High impact to project
operations, causing with potential to delay operations,
delays of a few days to a project by a month or with potential to cause
Operational few weeks more project failure
Low impact to employee Medium impact to High impact to employee
attrition, with 5%+ of employee attrition, with attrition, with 50%+
employees quitting 25%+ of employees employees quitting
People quitting
Probability and Impact Matrix:
Inherent Risk
Impact
Low Medium High
High Medium High High
Probability Medium Low Medium High
Low Low Low Medium