181103-CCECC-MAX-DCRP-BR-18-F-0439 Resubmission of Method Statment For Cast-in-Place Concrete Pilot Piles Construciton (500mm Dia. & 600mm Dia) For Stations & Buildings
181103-CCECC-MAX-DCRP-BR-18-F-0439 Resubmission of Method Statment For Cast-in-Place Concrete Pilot Piles Construciton (500mm Dia. & 600mm Dia) For Stations & Buildings
9 9. Quality Assurance and Quality Control: • QAQC System as per the updated
• Please insert and describe it comprehensively into this Item QAP Ref. No. DCRP/CMJV/Q/QAP-01
9, the Implementation of QAQC System as per the updated in connection to the works of the CIP
QAP Ref. No. DCRP/CMJV/Q/QAP-01 in connection to the Concrete Piles Construction (500mm
works of the CIP Concrete Piles Construction (500mm dia & dia & 600mm dia) for Stations &
600mm dia) for Stations & Buildings. Buildings inserted in section 9 with
• A Detailed & Specific Inspection & Test Plan (ITP) showing comprehensive description (page-22).
the Quality Acceptance Criteria in the work process and • Detailed & specific Inspection & Test
inspection & testing process of this CIP Concrete Piles plan inserted accordingly as Appendix-
Construction (500mm dia & 4 (page-49).
600mm dia) for Stations & Buildings shall be submitted to the
Engineer for the Approval (Please see and refer to the
comments no. 6 and 7 above).
10 Appendix-2 Typical Pile Elevation and Section - Working We have submitted working drawing
Drawings: (ref: CCECC-MAX-DCRP-BR-18-D-
Please attached the Working Drawings instead of the Final 0400) for your approval. Submitted
Tender Design Drawings in A3 Size Sheets. drawing of CIP work is inserted in A3
size Sheets as Appendix-2 (page-45).
Besides, as per section 1.8.2, Prior to
commencement of the work, working
drawing will be submitted as another
document.
METHOD STATEMENT FOR PILES CONSTRUCTION (STATIONS & BUILDINGS)
DCRP/CMJV/MS-009, Rev. B
METHOD STATEMENT FOR PILES CONSTRUCTION (STATIONS & BUILDINGS)
Table of Contents
1. INTRODUCTION ............................................................................................................................................................... 5
1.1 GENERAL INFORMATION ........................................................................................................................... 5
1.2 PURPOSE OF WORKS ................................................................................................................................. 5
1.3 SCOPE OF WORKS ...................................................................................................................................... 5
1.4 RESPONSIBILITIES ...................................................................................................................................... 6
1.5 PROJECT ORGANIZATION CHART............................................................................................................... 6
1.6 QUALITY OBJECTIVE ................................................................................................................................... 6
1.7 QUALITY CONTROL PROCESS APPROACH .................................................................................................. 6
1.8 GENERAL DRAWING .................................................................................................................................. 6
1.8.1 TYPICAL WORKING PILE ELEVATION AND SECTION ............................................................................ 6
1.8.2 WORKING DRAWING .......................................................................................................................... 6
2. RELEVANT SPECIFICATIONS, STANDARDS ................................................................................................................ 7
2.1 RELEVANT SPECIFICATION, STANDARDS ................................................................................................... 7
2.2 BOQ/PAY ITEM .......................................................................................................................................... 7
3. WORK FLOW CHART ...................................................................................................................................................... 8
3.1 WORK SEQUENCE ...................................................................................................................................... 8
3.2 WORK FLOW CHART .................................................................................................................................. 9
4. WORK PROCEDURE ..................................................................................................................................................... 10
4.1 DETAILS OF WORKS ................................................................................................................................. 10
4.1.1 SITE PREPERATION............................................................................................................................ 10
4.1.2 MOBILIZATION OF EQUIPMENT ....................................................................................................... 10
4.1.3 SETTING OUT OF PILE CENTER.......................................................................................................... 10
4.1.4 BORE HOLE DRILLING ....................................................................................................................... 10
4.1.5 1ST BOTTOM CLEANING ................................................................................................................... 12
4.1.6 FABRICATION OF REBAR CAGE ......................................................................................................... 12
4.1.7 VERTICALITY OF BORE HOLE ............................................................................................................. 13
4.1.8 INSTALLATION OF REBAR CAGE ........................................................................................................ 13
4.1.9 SETTING OF TREMIE PIPE.................................................................................................................. 14
4.1.10 2ND BOTTOM CLEANING BY TREMIE ............................................................................................. 14
4.1.11 CONCRETE POURING ...................................................................................................................... 15
4.1.12 REMOVAL OF TEMPORARY CASING ............................................................................................... 18
4.1.13 BACK FILLING .................................................................................................................................. 18
4.2 COUNTER MEASURES .............................................................................................................................. 18
11.7 MEASURES FOR EASING SOCIAL IMPACT DURING CONSTRUCTION PERIOD ........................................ 40
11.7.1 CONSTRUCTION ACCESS ROAD ...................................................................................................... 40
11.7.2 PUBLIC DISTURBANCE .................................................................................................................... 40
Appendix-1 Work Sequence of Cast in Place Concrete Pilot Pile Construction ................................................................. 41
Appendix-2 Typical Working Pile Elevation and Section ..................................................................................................... 45
Appendix-3 U-Bolt Details ................................................................................................................................................... 47
Appendix-4 Inspection and Testing Plan ............................................................................................................................. 49
Appendix-5 Inspection Checklist ......................................................................................................................................... 52
Appendix-6 Approval of construction materials ................................................................................................................... 59
Appendix-7 Approved Mix Design ....................................................................................................................................... 61
Appendix-8 Bentonite Certificate from Manufacturer........................................................................................................... 62
1. INTRODUCTION
Bangladesh Railway has awarded to CCECC-MAX JV for execution of Lot-2: Chakaria to Cox’s Bazar via Ramu Including
Cox’s Bazar station building of package WD1: The Construction of New Dual Gauge Single Railway Line from Dohazari to
Cox's Bazar via Ramu.
Construction of bored cast-in-place comprises for buildings and overhead tanks will be carried out in accordance with the
Specification E1.4: Bored Cast in Place Piles. This Method Statement is based on the specification and in conformity with
the requirements of the drawings. In case of any discrepancies or deviations observed in the Method Statement, the
specification and drawings will prevail and method statement shall be amended unless agreed by the Engineer on the
specific issues.
The objective of this method statement is to describe the construction methodology and procedure of 500mm & 600mm
piles for cast-in-place concrete piling (CIP) works of buildings & water tank respectively by Percussion Drilling Method under
“The Construction of New Dual Gauge Single Railway Line from Dohazari to Cox’s Bazar via Ramu, LOT-2” project.
The work shall be done according to this method statement and use of materials, tools and equipment stated herein in order
to achieve a quality of works pursuant to relevant specification, standard and working procedure.
1.2 PURPOSE OF WORKS
The purpose of this method statement is to describe the construction methodology and procedure for bored pile
work on land.
The bored pile construction technique is to construct independent circular cast in-situ reinforced concrete piles
from the designed depth to the designed cut-off level.
The type of bored piling rig shall be selected properly to suit the required drilling length. The sizes of the piles to
be covered by this method statement are diameter 500 mm & 600 mm.
1.4 RESPONSIBILITIES
Responsibility and authorization shall be followed as stated in Section 2.2, Chapter II-Management Responsibility of
approved Quality Assurance Plan (Ref. No: DCRP/CMJV/Q/QAP-01, REV.C).
1.5 PROJECT ORGANIZATION CHART
Project Organization Chart will be followed as stated in Appendix-12 of approved Quality Assurance Plan (Ref. No:
DCRP/CMJV/Q/QAP-01, REV.C).
1.6 QUALITY OBJECTIVE
It is the responsibility of the Contractor to ensure that experienced & qualified supervision staff to deploy as per the contract
and that they are both aware of, and trained in the specific duties they are to carry out. Clear lines of communication and
reporting procedures shall be established. To this approach the EMPLOYER/ ENGINEER with the Contractor technical
people will hold team meetings on routine basis and as and when necessary.
Contractor shall submit RFI with Method Statement of work complying the hold points to obtain prior approval to the
commencement of the works and ensure that they all fully understand their roles and responsibilities,
Through this approach, it could be immediately notified of problems that may occur on site such as nonconformance of
quality control tests, inadequate health, and safety/security etc. It will then be a matter for the Contractor to take the action
appropriately.
The Contractor shall implement Quality Assurance in accordance with project requirements & specifications, ISO 9001:2008
and ISO 14001:2005, and modern good engineering and construction practices, and develop a Quality and Environmental
Management System for the Project based on the requirements of this Specification.
The Contractor shall nominate a member of its management staff to act as the Quality Assurance Manager for this Contract.
The Material Engineer shall be provided with adequate resources and shall be delegated with the necessary authority to
enable the quality of Work on the Contract to be managed effectively and in accordance with ISO 9001:2008 and ISO
14001:2005. necessary authority to enable the quality of Work on the Contract to be managed effectively and in accordance
with ISO 9001:2008 and ISO 14001:2005.
1.7 QUALITY CONTROL PROCESS APPROACH
Responsibility and authorization shall be followed as stated in Section 2.2, Chapter II-Management Responsibility of
approved Quality Assurance Plan (Ref. No: DCRP/CMJV/Q/QAP-01, REV.C).
1.8 GENERAL DRAWING
As attached in Appendix-2
1.8.2 WORKING DRAWING
Prior to commencement of the work, working drawing will be submitted as another document.
14. Specification
E1.9.2: Material
E1.10: Reinforcement
2.2 BOQ/PAY ITEM
N/A
Mobilization
Preparation
Ref. Specification Equipment Section
Materials E 1.9.2 14. Stations & Buildings
Concrete E 1.9 Batching plant 14. Stations & Buildings
Reinforcement E 1.10 Rebar Cutter 14. Stations & Buildings
(Bentonite) Slurry D 4.2.3 Mixing Tank, Mud tank 14. Bridges and Culverts
Construction Works
Excavation D 4.3.5 Excavator 14. Bridges and Culverts
Temporary Casing Driving D 4.3.5 Tripod Rig 14. Bridges and Culverts
Tremie Pipe D 4.3.7 Tripod Rig with Winch 14. Bridges and Culverts
machine
Casting D 4.3.7 Tripod Rig & Concrete 14. Bridges and Culverts
mixer Machine
Field Test
Test of (Bentonite) Slurry D 4.2.3 Test kit for (Bentonite) 14. Bridges and Culverts
Slurry
Site Preparation
Mobilization of Equipment
Drilling Work
Pouring of Concrete
Static Load Test (01 nos. test for Separate Method of Statement will be
each overhead tank and building)
submitted prior to commencement of
work
Report Submission
4. WORK PROCEDURE
The location of Bored Pile will be free from any obstacle such as concrete foundation, underground utilities, trees /shrub and
will be leveled properly with stability for equipment of bored pile works and also construction entrance along the existing
road will be provided. Prior to start construction, stability and safety of the platform and crane foundation will be ensured.
4.1.2 MOBILIZATION OF EQUIPMENT
Mobilized machines and equipment such as tripod rig, Winch machine, excavator, casing pipe, slurry mixer, rebar cutter,
generator, submerged pumps etc. will be inspected by the contractor prior to commencement of the work.
4.1.3 SETTING OUT OF PILE CENTER
Positioning drilling hole is based on the approved drawings, positioning benchmarks and piling arrangement layout for
specifying positions of pile center in compliance with the approved design. The pile center location coordinate (N=Y, E=X)
will be shown on the working drawing and will be marked on the ground by total station and will be confirmed by The Engineer
prior to commencement of the piling work.
Checking of the bored hole location shall also be carried out for all the piles after the commencement of boring, but not later
than when boring has reached the top of the first stiff layer. The Centre of the completed pile at the cut off level shall not be
deviate more than 75mm from the theoretically correct plan position shown on the drawing.
4.1.4 BORE HOLE DRILLING
Bored pile construction will be commenced from setting out pile location and pre-drilling and installing temporary casing.
The length of the casing will be considered and justify based on the soil condition and underground water level for
maintaining the stability of the pile excavation holes against collapse, the casing length is from 5m to 9m. Pre-boring/casing
pipe installation by using tripod rig & Winch machine will be executed to make smooth installation of casing pipe, thickness
8-10mm, and diameter will be as below:
Casing pipe will be installed by Tripod Drilling rig and Winch machine, the offset value from the reference points will be
equidistance so that the casing pipe could be installed at design position. The elevation of the top of casing pipe is planned
around 0.3m above the formation ground level and at least 1.5m above the underground water level and the toe of casing
pipe is 0.5m in the dense soil layer. Boring will be done by cutting the borehole with chisel and removing the cutting materials
with continuous flow of slurry.
The soil profile near the cast-in place Pile will be attached with working drawing. The drilling will be executed by Percussion
Drilling Method. Slurry level in the hole will be always kept 2m above the river water or ground water to maintain the stability
of the boring. Properties of (bentonite) slurry will be controlled as below table.
Property Units Fresh Ready for reuse Before concreting Test Method
Viscosity
Sec 32 to 50 32 to 60 32 to 50 Marsh Funnel
(946ml)
pH 9 to 11.5 9 to 11.5 N/A pH Meter
Width (ft) = . .
After completion of the drilling an interval 15 minute is required to allow the fine materials to settle then Drilling chisel required
to set 300mm above the pile toe level to wash out the sediment slime by flushing with slurry. Flashing of bore hole shall be
continued with the circulation of slurry until all course materials comes out from the bottom of the hole. Consequently,
sediment slime will be removed to the ground and bottom elevation will be rechecked to confirm sufficient removal. The time
between final excavation and bottom cleaning and the start of the concreting will be kept as short as possible and shall not
exceed 4 hours. To achieve this, the final 2 meters of excavation will not start until all preparation for cleaning, reinforcing
and concreting are finished.
4.1.6 FABRICATION OF REBAR CAGE
Rebar cage will be fabricated and transported into building and water tank site from fabrication yard. Each piece of the rebar
cage shall be fabricated and assembled according to the approved drawings basically prior to commencing drilling work.
The hoop bar is fixed by steel wire or welding according to the approval by the Engineer. After completion of fabrication for
one segment of rebar cage, it shall be carefully kept in the dry and stable condition of stockyard which is elevated at least
20 cm higher than the ground level. Wooden beam or equivalent material will be used for stocking the assembled rebar
cage.
Spiral rebar
The verticality of bore will be checked before lowering the steel casing by spirit level by inverted plumb- bob to ensure that
inclination not more than 1/100 and if found more than 1/100 than it should rectify to bring it within tolerance.
4.1.8 INSTALLATION OF REBAR CAGE
The length of the rebar cage is variable for all the buildings. The full length will achieve by lapping method to facilitate
installation and transportation and also to avoid bending, twisting of the rebar cage. Rebar case have to be lower in the bore
hole without bending the cage. The main bar and spiral will be fixed by alternate spot welding and by GI (18 SWG) wire
binding. The vertical rebar lapping will be fixed with U-bolt splicing method. U-bolt will be used for splicing of rebar cage.
Cages and additional hoop reinforcement bars will be fastened by steel wire. Working drawing of rebar fabrication will be
prepared and submit for the Engineer’s approval. U-bolt details are attached as appendix-3.
Tremie shall be inspected before installation. The length of each pipe, water tightness at the joint, cleanliness inside the
pipes will be checked to avoid any troubles such as segregation of concrete due to ingress of water into the pipe cause
insufficient water tightness at the joints. The pipe pieces will be connected together from bottom with checking the length of
each pipe and water tightness at the joint and finally the top adjusting piece will be installed to connect it to concrete hopper
at top of the casing pipe. Tremie pipe will be minimum 200mm diameter; both pipe and hopper will be water tight.
Specific gravity of the slurry from the base collected having value less than 1.1g/ml. The density of the slurry may rise to
1.25g/ml, but must be brought down to 1.12g/ml. After borehole Drilling completion, min 30 minutes is required to bring out
the chisel, then lowering the rebar cage & tremie pipe. Within this time sedimentation may occur. After setting the tremie
pipe, sediment slime will be washed out by flushing wit slurry to brought down the specific gravity. If Mud Density is less
than 1.12 g/ml before 2nd cleaning then 2nd cleaning will not be applied. This process will continue until to get the required
specific gravity.
Concrete placing work will be scheduled for early morning or late afternoon as much as possible to minimize the effects of
rapid drying conditions that may cause plastic shrinkage cracking.
Prior to commencement of the concrete casting, it will execute the following checking for prevention of blocking Tremie pipe.
Workability of concrete
Selection of the suitable Tremie pipe (diameter, length per pipe and joint)
Inlet of Tremie
Temporary
casing
Tremie pipe
Temporary casing will be extracted while the concrete within them remains sufficiently workable to ensure that the concrete
is not lifted. When the casing is being extracted a sufficient quantity of concrete will be maintained within it to ensure that
pressure from external water, drilling fluid or soil is exceeded and that the pile is neither reduced in section nor contaminated.
The temporary casing will be kept a minimum of 2 meters under the outlet of tremie. No concrete will be place once
temporary casing has been lifted above the top of the concrete; it will be placed continuously as the casing is extracted until
the desired head of concrete is obtained. The pile will be concreted to a over height of 1000mm above the pile cut off level
shown in the approved drawing to allow for chiseling off the top concrete down to sound hard concrete. The pile top wills,
after clean cutting, be embedded 100mm above the bottom level of the pile cap as shown the drawings.
4.1.13 BACK FILLING
After 1 hour to 2 hour of removal temporary casing bore hole will be filled by sand or soil.
4.2 COUNTER MEASURES
Countermeasures for difficulties encountered during bored pile works are stated as follows;
Incidents of cave-ins or Borehole collapse
1. Before commencement work, existing utility will be surveyed and removed. After finishing removal, relevant authorities
will be confirmed.
2. If unforeseen non-use utility obstructs, it must be removed before casing installation work. Excavation will be executed
to remove obstruction.
Incidents during concrete placement and counter measure
1. Prior to casting concrete all preparation shall be completed and checked by engineer, access
road, equipment, concrete mixer, and material volume shall be checked to avoid concrete supply interruption.
2. In case tremie pipe is blocked, Spare pipe shall be use instead. Generally spare pipe shall be prepared previously.
3. In case rebar cage rise with concrete, stop casting concrete and move tremie pipe to make
separate of rebar cage and concrete. Additionally, shock or vibrate head of re-bar cage with taking care not to
harm cage.
4. Concrete Interruption, to avoid concrete interruption two mixer machine will be prepared for every concreting
schedule, one will be used for concreting, and one will be reserved for back-up.
5. Collapse Solution, a long steel pipe will be used for temporary casing based geo-technical
Investigation report to avoid collapsed on the upper part of the hole.
6. In case tremie pipe is blocked, pile will be rejected and the pile shall be replaced as instructed by the
Engineer and as per specification.
The tremie pipe will be inserted in the center of the pile to reach
4.3 Site Engineer/ Foreman
the toe of the pile.
4.4 The tremie pipe to be lifted 150-300 mm above the pile toe. Site Engineer/ Foreman
Pouring of concrete into the pile borehole, the length of the
tremie pipe will be shortened if necessary, but the tremie pipe
Site Engineer/ Foreman
4.5 should be maintained continuously into the concrete of at least
1.50m. During concreting, the level of concrete within the pile
will be monitored by use of an end- weighted tape measure
Concreting will continue until the overflow of concrete is seen
4.6 Site Engineer/ Foreman
from the casing top.
The final concrete level and the volume poured will be recorded
4.7 Site Engineer/ Foreman
and noted on the pile record sheet.
5. PILE TESTING
6. RECORD
The Contractor will keep the records as indicated below for installation of each pilot pile and will submit two signed copies
of these records to the Engineer not later than noon of the next working day after pile is installed. The signed records will
form a record of the work. The following data will be submitted:
a) Pile Location,
b) Pile Reference number,
c) Pile type,
d) Nominal cross-sectional dimension or diameter,
e) Date and time of boring,
f) Date and time of concreting,
g) River bed / ground level at commencement of installation of pile,
h) Working level,
i) Pile toe level,
j) River water level,
k) Pile head level,
l) Length of temporary casing,
m) Soil samples taken and situ test carried out,
n) Standing water level,
o) Length and details of reinforcement,
p) Volume of concrete supplied to pile and corresponding levels of concrete and casing,
q) All information regarding obstructions, delays and other interruptions to the sequence of work.
7. RESOURCES TO BE USED
3 Mud Tank Volume = 1.5 x 2 Nos 1 No. for recycling, another one for fresh
volume of bore hole slurry.
Tripod Rig 1 Nos For handling of steel cages & concreting
4
works
5 Generator 150 kva 1 Nos
6 Excavator 0.7m3 1 Nos
7 Dump Truck 1 Nos Excavated soil removal
8 Welding Transformer 1 Nos
Detail material information such as source, brand, approval status and Mix design are attached as appendix – 6 & appendix-
7 respectively.
7.3 TRAVELLING TIME FROM THE MIXING PLANT TO CONCRETING WORK SITE
The general requirement for ready mixed concrete plants or off-site batching and mixing plants, is that concrete shall be
discharged from the truck mixer within two hours of the time of loading. Travelling time from the mixing plant to concreting
work site is given below:
Serial Mixing plant location Concrete work site Travelling time (Approx.)
Cox’s Bazar station Office buildings , residential buildings &
1 5 min
area water tank at Cox’s Bazar station
Cox’s Bazar station
2 Water tank of Ramu station 30 min
area
Napitkhali Yard at
3 Water tank of Islamabad station 30 min
(Ch 70+100)
Napitkhali Yard at
4 Water tank of Dolahazra station 30 min
(Ch 70+100)
Table-9: travelling time from the mixing plant to concreting work site
Slump at the time of placing concrete in underwater through Tremie is 150mm – 200 mm. This slump value shall be ensured
after travelling from the mixing plant to concrete work site at the time of placing.
7.4 MANPOWER LIST (EACH SITE)
8. CONSTRUCTION SCHEDULE
Construction schedule for Cast-in-place Concrete Pilot Piling Work in “The Construction of New Dual Gauge Single Railway
Line from Dohazari to Cox’s Bazar via Ramu, LOT-2”.
To assure & control quality bored cast-in-situ piles for stations & buildings shall be done in accordance with the
Specifications and in conformity with the requirements of the Drawings or other parts of the Contract Documents.
The pile boring shall be carried out using a temporary steel casing bored to the pile toe or to a level approved by the
Engineer. The temporary casing shall be withdrawn.
Under any circumstances, if permanent steel casing is required as per site condition the CCECC-MAX JV will provide
minimum 10 mm thickness or as approved by the Engineer.
Under certain circumstances, the CCECC-MAX JV may be permitted to bore all or part of the pile without casing under
water or use drilling fluid to stabilize the borehole.
9.1.1 CONCRETE
The concrete shall conform the Clause D6 of these Specification (Concrete Class 35). Concrete placed under water or
drilling mud by tremie shall have a cement content of not less than 430kg/m3.
The density and consistency of the concrete shall conform to the tremie casting method and the maintenance of sufficient
workability (slump) of all the concrete during the casting and casing handling period, including reasonably calculated delays,
shall be secured by a design mix, subject for approval by the Engineer.
All relevant concrete properties such as slump, time of setting, temperature and strength shall be measured in trial mixes.
9.1.2 REINFORCEMENT
The CCECC-MAX JV shall comply with the following clauses if bentonite mud is used to stabilize the boreholes:
Before concreting a pile, the CCECC-MAX JV shall take measures to remove any heavily contaminated bentonite
suspension which could impair the free flow of concrete from the tremie pipe. A sample of the bentonite suspension shall
be taken from the base of the boring using an approved sampling device and if the specific gravity of the suspension exceeds
1.25, placing of concrete shall not proceed and the CCECC-MAX JV shall modify or replace the bentonite as approved by
the Engineer.
Control tests for density shall be carried out daily on the support fluid using suitable apparatus. The measuring device shall
be calibrated to read within 0.01 g/ml.
Mixing
Bentonite 5-6.5% and any other material shall be mixed thoroughly before 24 hours of boring with clean water to make a
suspension which shall maintain the stability of the pile excavation for the period necessary to place concrete and complete
construction.
Where saline or chemically contaminated groundwater occurs, special precautions shall be taken to modify the bentonite in
fresh water so as to render it suitable in all respects for the construction of piles. Subject for surveillance by the Engineer.
Apparatus: Slurry Sampler, or equal, approximately 76mm inside diameter and 305-356 long.
Procedure:
Hold the right Cylinder with one hand.
With the other hand, let the bottom of the sampler slowly descend until it reaches the bottom of the hole
containing bentonite slurry.
While holding the rope above cylinder, let the right circular cylinder drop into slurry slowly.
After the right cylinder reaches the bottom, pull up the sampler slowly.
Place the contents of the sampler in a container of approximately 1-2gal.(3.8-7.6L)
SCOPE: This part determines the density used in slurry construction techniques, such as those for barriers to control
horizontal movements of liquids.
Apparatus:
Mud Balance, Hydrometer or any instrument of sufficient accuracy to permit measurement within±0.01g/cc;
however, the mud balance is the instrument generally used.
The mud balance consists of a mud cup attached to one end of a beam, which is balanced on the other end by a
fixed counterweight and a rider free to move along a graduated scale.
A level bubble is mounted on the beam.
Attachments for extending the range oh the balance may be used.
The mud balance or Hydrometer shall be calibrated annually; calibration of mud balance can be checked by;
iii) Procedure:
i) Scope
ii) Apparatus
Stopwatch.
Marsh Funnel, calibrated to outflow 1 qt. of fresh water at a temperature of 70 + 5°F (21 + 3°C) in 26 + 0.5 seconds.
iii) Procedure
Cover the funnel orifice with a finger, and pour freshly sampled drilling fluid through the screen into the clean, upright funnel.
Fill until fluid reaches the bottom of the screen. Remove finger and start stopwatch. Measure the time for the mud to fill to
the 1 qt. (946 cm³) mark on the cup. Report the time to nearest second as Marsh funnel viscosity.
Marsh funnel
The Marsh funnel viscometer is a simple device for measuring viscosity from the time it takes a Known volume of liquid to
flow from the base of a cone through a short tube. It is particularly used by mud engineers to check the quality of drilling
mud.
A modern plastic Marsh Funnel
It consists of a cone 6 inches (152 mm) across and 12 inches in height (305 mm) to the apex of which is fixed a tube 2
inches (50.8 mm) long and 3/16 inch (4.76 mm) internal diameter. A mesh is fixed near the top across half the cone.
In use, it is held vertically and end of the tube closed with a finger. The liquid to be measured is poured through the mesh.
(This removes any particles which might block the tube.) This ends when the mesh is reached, which gives a volume inside
of about 1.5 liters. To take the measurement, the finger is released as a stopcock is started, and the liquid is allowed to run
into a measuring container. The time is seconds is recorded as measure of the viscosity.
In American practice (and most of the oil industry) the volume collected is a quart. If water is used, the time should be 26+/-
0.5 seconds. [1] If the time is less than this the tube is probably enlarged by erosion, if more it may be blocked or damaged,
and the funnel should be replaced, In some companies, and Europe in particular, the volume collected is a litre, for which
the which the water funnel time should be 28 seconds. Marsh himself collected 0.50 litre, for which the time was 18.5
seconds.[2]
The Marsh funnel time is often referred to as the Marsh funnel viscosity, and represented by the abbreviation MF. The unit
(seconds) is often omitted. Formally, the volume should also be stated. The (quart) Marsh funnel time for typical drilling
muds is 34 to 50 seconds, though mud mixtures to cope with some geological conditions may have a time of 100 or more
second.[3]
While the most common use is for drilling muds, which are non-Newtonian fluids, the Marsh funnel is not a rheometer,
because it only provides one measurement under one flow condition. However the effective viscosity can be determined
from following simple formula.[4]
DCRP/CMJV/MS-009, REV.B Page 25 of 63
METHOD STATEMENT FOR PILES CONSTRUCTION (STATIONS & BUILDINGS)
μ=p (t-25)
ρ= density in g/cm³
For example, a mud of funnel time 40 seconds and density 1.1 g/cm³ has an effective viscosity of about 16.5 сP. For the
range of times of typical muds above, the shear rate4 in the Marsh funnel is about 2000-s.[4]
The term Marsh cone is sometimes used, particularly within the concrete industry, but also in the oil industry, sometimes it
means the Marsh funnel, sometimes a similar device with the same cone aspect ratio, but a different tube. European
standard EN445[5] for measuring the flow properties of cement grout mixtures specifics a funnel similar to that described
above but fitted with a tube of 10 mm internal diameter and of length 60 mm, which is often referred to as a Marsh cone.
Some manufacturers supply devices which they call Mar4sh cones, with removable tubes with size ranges from 5 to 15 mm.
These can be used for quality control by selecting a tube which gives a convenient time, say 30 to 60 seconds.
Other cones of different geometries and with different orifice arrangements are in use in specialist areas, but with the same
general operating principle. They are generally called flow cones. Thus a Marsh cone is a flow cone with an aspect ratio of
2:1 and a working volume of at least a litre. A Marsh funnel is a Marsh cone with a particular orifice and a working volume
of 1.5 liters.
iv) Tests
The frequency of testing drilling fluid and the method and procedure of sampling shall be proposed by the CCECC-MAX JV
and approved by the Engineer prior to the commencement of the work. The control tests shall cover the determination of
density, viscosity, gel strength and pH values.
The CCECC-MAX JV shall check the casing position for each pile during and immediately after placing the casing, and
agree it with the Engineer.
9.3.2 DIAMETER OF PILES
The diameter of a pile shall be not less than the specified diameter detailed in the Drawing of Bored cast in place piles.
9.3.3 TOLERANCES
The Centre of the completed pile at the cut off level shall not deviate more than 100 mm from the theoretically correct
position shown on the Drawings. The inclination of the pile shall not deviate more than 1:100 from vertical. The CCECC-
MAX JV shall provide suitable equipment, such as an inverted pendulum, to check the verticality of the boreholes at intervals
during drilling and prior to concreting.
All piles shall be formed to at least 1000 mm above the cut-off level with a tolerance of +75 mm - zero.
Piles shall not be bored so close to other piles which have recently been cast and which contain workable or unset concrete
so that a flow of concrete could be induced from or damage caused to any of the piles. Boring and excavation for a pile shall
not be commenced until 24 hours after completion of any pile within a radius of 6 meters, center to center.
Temporary casing of approved thickness, length and quality or an approved alternative method shall be used to maintain
the stability of pile excavations, which might otherwise collapse.
Temporary casings shall be free from significant distortion. They shall be of uniform cross-section throughout each
continuous length. During concreting they shall be free from internal projections and encrusted concrete which might prevent
the proper formation of piles.
Pumping from a borehole shall not be permitted unless a casing has been placed into a stable stratum which prevents the
flow of water from other strata in significant quantities into the boring, and unless it can be shown that pumping will not have
a detrimental effect on the surrounding soil or property.
9.3.7 BORING RECORDS
During the boring of the pile, the CCECC-MAX JV shall compile a 'boring log' indicating depths and types of the various soil
layers encountered. Disturbed samples shall be submitted to the Engineer as requested
The CCECC-MAX JV shall allow for carrying out sampling and tests to check soil strengths as required by the Engineer.
The reinforcement shall be placed as indicated on the Drawings. Reinforcement in the form of a cage shall be assembled
with additional support, such as spreader forks and lacings, necessary to form a rigid cage. Hoops, links or helical
reinforcement shall fit closely around the main longitudinal bars and be bound to them by approved wire, the ends of which
shall be turned into the interior of the pile or pour. Reinforcement shall be placed and maintained in position.
Joints in longitudinal steel bars shall be permitted unless otherwise specified. Joints in reinforcement shall be such that the
full strength of the bar is effective across the joint and shall be made so that there is no relative displacement of the
reinforcement during the construction of the pile.
Joints in longitudinal bars in piles with tension (for instance for test loading) shall not be carried out by welding but by splicing
or coupler.
If the final pile toe level instructed by the Engineer is deeper than that indicated on the Drawings, the section of the pile
deeper than the toe level indicated on the Drawings is required to be reinforced, unless otherwise instructed by the Engineer.
9.3.9 PLACING CONCRETE
i) Approval
No concreting shall take place before the bottom of the excavation has been cleaned, the borehole inspected and
approval obtained in writing from the Engineer.
The method for placing concrete shall be approved and conform to the following:
The method of placing and the workability of the concrete shall be such that a continuous monolithic concrete
shaft of the full cross section is formed.
The concrete shall be placed continuously, and without such interruption as would allow the previously placed
batch to have hardened. In this respect the CCECC-MAX JV shall submit details of his contingency plans,
standby plant, etc. to be utilized in the event of an equipment failure.
The use of pumped concrete and the methods in its use shall have to be approved by the Engineer.
The CCECC-MAX JV shall take all precautions in the design of the mix and placing of the concrete to avoid
arching of the concrete in a casing. No spoil, liquid or other foreign matter shall be allowed to contaminate the
concrete.
The optimum consistency of various type of structures shall be in accordance with below table;
Concrete to be placed under water or drilling fluid shall be placed by tremie and shall not be discharged freely into the water
or drilling fluid.
Before placing concrete, the CCECC-MAX JV shall ensure that there is no accumulation of silt, other material, or heavily
contaminated bentonite suspension at the base of the boring, which could impair the free flow of concrete from the pipe of
the tremie. A sample of the bentonite suspension shall be taken from the base of the boring using an approved sampling
device. If the specific gravity of the suspension exceeds 1.25, the placing of concrete shall not proceed. In this event the
CCECC-MAX JV shall modify the mud quality.
The concrete shall be a rich coherent mix of high workability and shall be placed in such a manner that segregation does
not occur.
During and after concreting, care shall be taken to avoid damage to the concrete from pumping and dewatering operations.
The CCECC-MAX JV shall maintain a continuous record of the volume of concrete used and the level of the concrete in the
pile. Any deviations from the theoretical, or expected, volume/level relationship shall be immediately reported to the
Engineer.
Concrete shall not be placed in water having a temperature below 5º C. The temperature of concrete, when deposited, shall
not be less than 16 º C, nor more than 30ºC.
The tremie pipe shall not be less than 200 mm in diameter and shall be large enough to allow a free flow of concrete and
strong enough to withstand the external pressure of the water in which it is suspended, even if a partial vacuum develops
inside the pipe.
iv) Reinforcement Cage
During concreting and pulling the casing, the reinforcement cage shall be secured against uplift and the top shall be kept
under close inspection.
v) Supervision
The execution of the pile concreting shall be supervised by a qualified person of the CCECC-MAX JV’s staff, who will keep
records on the relation between quantity of concrete used, level of concrete and withdrawal of casing, inspection shall be
carried out in the presence of the Engineer.
10.1 OBJECTIVES
Identify hazards involved in the work that have the potential to harm the health or safety of an
employee or any other person legally at the place of work.
Assess the risk of harm to health and safety arising from the hazards identified that have the potential to
harm the health or safety of an employee or any other person at the place of work.
Eliminate or control any foreseeable risks.
Review risk assessment and control measures.
Provide instruction, training and information about safety procedures and certain other matters for
employees and other persons.
Provide reasonable supervision for employees.
Provide personal protective equipment (PPE) where required.
Obtain all information needed to fulfill their obligations under the Regulation.
Provide emergency procedures for the workplace, including arrangements for emergency
communications and appropriate medical treatment to injured persons.
Provide and maintain amenities (such as facilities for toilets, drinking water and shelter). Provide
appropriate First Aid facilities and trained personnel.
All Contractor persons shall use a ‘risk management’ approach to address workplace health and safety issues. This
involves:
These are the key elements of a risk management process, and shall be done in consultation with the people most likely to
be affected, such as employees, sub-Contractors of Contractor, and vendors who may also be working on the same work
site. Consultation is basic to effective safety management and shall be followed for all workplaces. It shall make sense to
consult with workers, because these people are likely to be aware of the particular risks at their workplace, and may have
good ideas about how to eliminate or control them.
Contractor shall also adopt a systematic approach for managing safety by developing, writing and implementing policies
and procedures. Establishing reporting arrangements and assigning formal responsibilities for all these functions is also
important. A systematic approach shall be adopted for managing safety effectively, and enabling Contractor persons to
demonstrate how they are meeting their duty of care for safe working.
The information from the risk assessment will help to know what measures shall be included in Safe Work Method
Statement, and how it shall be tailored to ensure that the risk control measures decided upon are actually carried out on
the job.
Safe Work Method Statements shall specify the procedures which the workers will follow to ensure that the work is
done safely. This is an essential step in eliminating or controlling risks.
10.3 HAZARD ANALYSIS AND MITIGATION
Scaffolding
Overhead protective structures
Safe means of lowering materials
Site security
Laser work
Demolition work, Electrical work, Plant.
Risks to health and safety are being assessed or reviewed.
Decisions are being made about measures to be taken to eliminate or control risks
Introducing or changing procedures for identifying and monitoring workplace risks
Changes are proposed for the workplace, systems of work, plant and substances used for work that may
affect health and safety
Decisions are made about the adequacy of facilities for the welfare of workers.
Decisions are made about setting up consultation arrangements.
The site supervisors and staff of the Contractor will be provided with helmets, safety jackets, hand gloves, safety shoes,
spectacles etc. as necessary
The information from the risk assessment will help to know what measures shall be included in Safe Work Method
Statement, and how it shall be tailored to ensure that the risk control measures decided upon are actually carried out on the
job.
Safe Work Method Statements shall specify the procedures which the workers will follow to ensure that the work is
done safely. This is an essential step in eliminating or controlling risks.
10.3.4 SAFETY TOOLS
The Contractor shall provide for his own staff, and the Engineer, all appropriate protective clothing, including safety vests,
helmets, and steel capped boots, and other equipment for the work to be done, and ensure proper use of the protective
clothing. The safety nets, belts, harnesses and lines shall be provided. Where work is in, over or near water more than
one meter deep, life vests and rescue boats shall also be provided. All safety and rescue equipment shall be fully maintained
and made available at site at all times.
10.3.5 TRAINING, AWARENESS AND SUPERVISION
The Contractor shall take all reasonable steps including training and drills to ensure the safety of all persons on the Site,
and shall at all times promote the merits of safety awareness.
No worker shall be allowed to access the Site unless they have undergone an induction course prepared by the Contractor
and approved by the Engineer. Participants who successfully complete such a course shall be presented with a laminated
card and lanyard, indicating their authority to enter the site, such card being prominently displayed for the period that the
holder is on site.
Training is one of the most important ways to ensure that the workers are capable and effective in maintaining a safe and
healthy work environment. All workers (including casual, hired and trainee workers) need to be included in this training.
The objective of a general health and safety induction course is to familiarize workers with basic principles of health and
safety in the construction industry to assist in the prevention of injury and illness at work. This training shall be
provided in the form of a documented training course approved by Engineer.
10.3.8 WORK ACTIVITY-BASED HEALTH AND SAFETY INDUCTION TRAINING
The objective of Work Activity-based health and safety induction in the railway sector is to give workers knowledge of the
OHS issues relevant to railway construction and maintenance.
If this training is conducted as a training course, where the employer has 10 or more employees it must be developed by
a person who holds a ‘Certificate IV in Workplace Assessment and Training’ and be run by a person who has
Statement of Attainment in ‘Train Small Groups’.
10.3.9 SITE SPECIFIC HEALTH AND SAFETY INDUCTION
A Site-Specific induction shall be undertaken before commencing work at designated work site. The objective of Site Specific
induction training is to provide workers with knowledge of the procedures and risks and hazards specific to a particular
workplace or site.
Trainers conducting Site Specific health and safety induction courses must have relevant knowledge and/or experience to
competently provide the training.
10.4 CERTIFICATION
Persons operating certain types of plant and doing certain work shall have a Certificate of Competency.
This work includes:
Scaffolding.
Dogging.
Rigging.
Crane operation (including ‘cherry pickers’).
Operation of load shifting devices such as excavators, backhoes and front-end loaders.
Concrete placing boom operation.
Hoist operation.
10.4.1 RECORDS
Contractor shall keep a record of any induction training undertaken for each person carrying out construction work on the
project, until the project is completed. Contractor shall keep records of all training, certification and accreditation.
Hazards are:
Walking though the workplace. This is a simple visual check of the work site
Looking at the type of work being performed; the way work is done and work practices
Looking at the type of plant, machinery and equipment used, and its condition
Looking at the premises and working environment, including the layout
Speaking with workers about what they think are the safety issues
Looking at the workplace records on ‘near misses’, incidents, accidents and injuries
Reviewing information supplied by manufacturers and suppliers about the proper use of hazardous
substances and plant (for example: material safety data sheets, product labels and manuals)
Contractor shall list and identify all hazards including where it occurs, factors that contribute to the hazard, and the persons
likely to be exposed to the hazard. This list is the first step in the development of Safety Procedures and Safe Work Method
Statements.
Contractor will check for hazards in the following areas:
By using this information to assess the risks involved in the work, Contractor shall develop plans to eliminate or control the
risks that may be introduced by work system, or work being conducted by others.
Other issues to consider include emergency planning, first aid and the provision of adequate amenities.
Contractor shall be controlling the following risks associated with construction work:
Falling objects
Scaffolding
Overhead protective structures
Safe means of lowering materials
Formwork
It is important that Contractor aware of these particular requirements and include them when completing Safe.
CCECC-MAX JV
11.1 INTRODUCTION
All work shall be executed so as to comply with the environmental requirements for works as required by the Laws of
Bangladesh, and any other requirement set out in any specific environmental requirements in the Specification, and in
accordance with General Requirements. The Contractor shall implement, at times and locations as required, a Temporary
Protection Plan during construction that includes temporary drainage, and other protection measures as summarized below:
To Prepare and secure proper stockpiling and disposal area of excavated materials.
To cover the stockpile of plastic sheet to prevent from erosion or mudslide during heavy rain.
To prepare a car and truck washing bay prior to entering the public road at all locations.
To avoid equipment oils and others from contamination of surface and underground matters that will
cause pollution.
To ensure strict compliance of the environmental, soil and water conservation plan.
Table-13: Environmental Protection Plan-Implementation and Supervision Institutions and Their Functional
Responsibilities
Baseline data on environment shall be collected to assess the region's existing physical and environmental characteristics.
Information and data presented in this chapter are based on primary surveys and secondary data. The information on the
baseline environmental conditions forms the basis to analyze the probable impacts of the proposed development activities
vis-à-vis the present environmental quality of the study area. The area of canal relocation has been surveyed on air quality,
ground water quality, noise quality, surface water quality of the river/canal and ecological feature were measured.
11.3 PHYSIO-CHEMICAL ENVIRONMENT
Ambient air quality measurements are essential to provide a description of the existing conditions, to provide a baseline
against which changes shall be measured and to assist in the determination of potential impacts of the proposed area of
canal relocation.
During field survey, no particular problem with air quality could be noticed. The apparently good air quality is attributed to
the fact that there are no large industrial installations near the work site that could serve as a major source of air pollutants.
The locations were selected on the basis of power availability of the equipment and areas which represents baseline
condition.
11.3.2 NOISE POLLUTION
Noise-monitoring of stations shall be selected to undertake noise monitoring to characterize existing noise environment
around the proposed project site. Noise level readings and any unusual local noise sources were recorded. Measurements
shall be taken instantly on-site using Noise level meters (LUTRON SL-4010) during the day (6am-9pm).
11.4 WATER RESOURCE
There are number of rivers crosses in between Dohazari to Cox’s Bazar double tracking way. The water quality of this river
shall be tested to assess the baseline condition. Based on the baseline data affect by change during construction period
shall assessed and mitigation measures shall be taken according to approved EMP.
11.4.2 GROUND WATER POTENTIAL AND QUALITY
Reasonably good quality and quantity of ground water is available in and around the project site. Manually operated hand
pumps and power-driven tube wells extract groundwater from a depth of approximately 200 to 250 feet. A study of the
ground water potential shall be carried out for the hydro-geological assessment.
The concentration levels of pH, Alkalinity, Mn. As, Fe, Ammonia Nitrate, total hardness, Chloride, Fecal Coliform and total
Coliform for tube well shall be measured and shall be compared with the acceptable limit set by the DOE, GOB for
ascertaining the pot-ability of ground.
11.5 ENVIRONMENTAL IMPACT AND ITS EVALUATION
In the course of the railway construction, water loss and soil erosion may occur after the damage to and disturbance with
the native ground vegetation and the soil. The areas in which soil erosion may occur include sections with deep-excavation
and high-filling, borrow pit, spoil site, temporary construction site, sections with special geology and other sections interfering
with the ground soil layer. The soil erosion may occur due to the failure of the complete recovery of the vegetation in the
first 1~2 years’ operation.
11.5.2 NOISE:
The noise occurring in the construction period is mainly caused by the construction machinery, the result of the prediction
using the attenuation mode of noise synergistic effect shows the noise at the area with a distance greater than 60m away
from the construction site by day and 120m away from the construction site by night can reach the national standard.
Therefore, the noise will exert obvious effect on the residents with a distance less than 60m from the construction site by
day and with a distance less than 120m from the construction site by night.
11.5.3 SURFACE WATER:
The construction of the river/canal-crossing bridge may influence the quality of the surface water. The influences mainly
include the leakage of oil and its entry into water, suspension of the bed mud and the loss of the discarded construction
waste or building materials caused by the underwater works for bridge construction, and the construction mud at the
construction site and the domestic wastewater at the camp. The pollution will influence downstream of the bridge site or of
the construction yard near river, and the pollution may last in the construction period and after the completion of the
construction.
11.5.4 AIR:
The major air pollution in the construction period is the construction dust, and the dust mainly comes from the uncompleted
sub-grade, the stock yard and the transportation road. Many factors may result in dust, including climatic conditions and the
type of construction activities, the dust formation are principally depend on the wind direction, wind speed, and air humidity.
The impacted area can reach a distance of 150~200m from the construction site and both sides of the road.
11.6 POSSIBLE MITIGATION MEASURE
In order to reduce the damage on ecological environment along the line, comprehensive measures combining works, plant
with land reclamation measure etc. shall be adopted during construction. Meanwhile, strengthening management
of construction and assurance of project quality etc. can mitigate the damage on ecological environment and make the
ecological environment at local section be better for the purpose of economic development and ecological protection, with
detailed mitigation measures as following:
11.6.2 RECLAMATION OF LAND TEMPORARILY-USED
At those sections where farmland is occupied for temporary land use by the Project, measure of reclamation shall be actively
adopted to accelerate secondary ploughing. The detailed measures are:
when using farmland, stripping for piling or collecting for storage of 30~40cm bellow earth layer on surface soil, after
construction, it shall be cleared in time and loosened and covered for tillage; on the condition that it is impossible to
reclamation or financing is not enough, e.g., the borrow pit or dumped earth with great depth Shall be degraded for use
such as for afforestation or other land use.
Temporary land used for earth borrowing and dumping shall be reclaimed and cultivated, which can, to a certain extent,
compensate for the impact on farmland occupied as temporary land use for earth borrowing or dumping field etc. For
temporary land use of hills and mountains, try to transplant tall and big trees as much as possible and strip and pile the
mellow earth on surface layer for reservation, finally restore it to be woodland, which is beneficial to the recovery of woodland
resources and improvement of woodland environment along the railway line.
11.6.3 CONDITIONS OF SOIL BORROWING FILED AND SLAG DUMPING FIELD
During construction, materials shall be procured from vendors and earth shall be borrowed from mound, hilly land,
wasteland, dry land or other works, avoiding taking farmland as earth borrowing field; in addition, the status of earth in all
earth borrowing fields shall be investigated to confirm the depth of earth borrowing for the purpose of reserving proper
superficial clay to prevent soil deterioration and make it be reserved resource for recycling.
Dump area will be located at waste land or field with low production where is low in terrain and not easily affected by river
and stream water washing.
After dump area is completely filled the field will be levelled with side slope 1:1.5.
Slope protection shall be provided through grass planting or masonry stone protection or re-
cultivation.
Cut off drain gutter will be built at the upstream of dump area and drain ditch constructed at
downhill accordingly.
The surface water flow will be discharged through these ditches so as to prevent spoils from
erosion. All the drainage system will be connected to natural water system and thus avoid
erosion to the ambient environment.
After substantial completion of earthwork, the dump areas shall be treated level and re-
cultivation carried out to suitable areas. It is suggested to use spoils as filling material. If the
dump area is not determined the spoils shall be well handled to far place.
During next design stage, the design institute shall further carry out and select the dump area
by combining with the practical situation and comments of local government, and try to reuse
spoils as local construction filling material. If a suitable dump area is founded and agreed by
the Employer, the construction unit shall hand over to local environmental bureau or water
conservancy bureau for approval, and consult with local government.
11.6.4 STRENGTHENING PUBLICITY AND EDUCATION OF ECOLOGICAL PROTECTION
Suitable management measures can get twice the result with half the effort on ecological protection during construction,
while the measure of construction supervision is the best one for management during construction.
During the construction period, full-time staff for environmental protection from Supervision Department and Construction
Department of the Project will temporarily carry on ecological supervision, in the manner of inspection and supervision, and
check the implementation of ecological protection measures and behaviors of ecological protection by constructors.
11.6.6 MEASURES FOR NOISE PREVENTION AND CONTROL DURING CONSTRUCTION
Combining with the actual condition of this Project, the following measures and suggestions on the impact of noise on
environment during construction:
The construction of machines such as pile hammer with high sound level must be stopped at
night from 18:00pm to 7:00am.
Try to carry on construction activities with high noise during the holiday of schools as much as
possible, and
Adopt temporary protection measures such as erection of wooden sound insulation plates etc.
If continuous construction is necessary due to special requirement, it must be approved by
relevant department in advance and communication with residents shall be carried on.
Those machines with high noise level such as generator, air compressor etc. shall be put at
remote positions far away from sensitive spots of sound environment such as the residential
areas and schools,
If it is difficult to choose reasonable position, measure of covering for noise insulation shall be
adopted and the machines shall be maintained on periodic basis and the operating rules shall
be strictly implemented.
11.6.7 MEASURES FOR VIBRATION PREVENTION AND CONTROL DURING CONSTRUCTION
During construction, control and management of construction machinery with strong vibration shall be strengthened, when
foundation construction is carried out near large sensitive spots, it is forbidden to carry out explosion and monitoring of
nearby buildings shall be made.
11.6.8 MEASURES FOR WASTEWATER TREATMENT DURING CONSTRUCTION
The construction sites of railway line sections are generally set at local villages which is near
to the construction sites and has convenient traffic and ample power supply and water supply,
and where wastewater from kitchen and bathroom Shall be drained through existing drainage
facilities;
If on those construction sites there are no drainage facilities, combined with local actual
situation, terrain condition and direction of drainage, simple self-built septic tanks shall be
used for treatment of domestic wastewater and before draining into local trenches.
The pollution impact of wastewater used for flushing machines and vehicles for construction
shall be controlled, as per the distribution of construction sites, fixed places for washing
constructional machines and vehicles are set for convenience of drainage of wastewater.
It is suggested that during construction, spots for washing and maintenance of constructional
machines and vehicles shall be set as per the division of constructional bidding sections made
by construction unit, in principle, the sections where major project is located shall be chosen to
ensure the drainage of wastewater for flushing at certain position.
The machines and vehicles entering the construction site shall be inspected and repaired,
avoiding “Trickling and leakage”.
Construction plant and vehicles shall be repaired on periodic basis on periodic basis at certain
positions where the oily wastewater shall be drained after being separated into oil and water
through oil collecting tank and integrally de-toxication treatment shall be carried on for
recovered floating oil.
11.6.9 CONTROL AND TREATMENT MEASURES FOR WASTE GAS AND DUST DURING CONSTRUCTION PERIOD
In order to avoid raising dusting during construction, borrow pits, spoil sites and sections of
high side slopes shall be afforested as soon as possible to prevent the topsoil from long term
disposure;
Measures for dusts falling by sprinkling shall be taken regularly in sections where construction
vehicles and machinery pass;
When passing through towns, villages and main traffic roads, earth transportation vehicles
shall be covered with canvas;
Architectural waste materials generated during construction shall be reclaimed and utilized to
the fullest extend;
The residual waste shall be sent to local waste landfills for filling and burial or shall be
otherwise appropriately treated;
The residual waste shall not be stacked or discharged randomly.
In construction fields and construction camps, environmental and sanitary facilities such as
dustbins and trash grounds shall be arranged separately in a unified way with suitable
quantities;
Domestic waste shall be centralized, collected and sent to local landfills for filling and burial;
The domestic waste shall not be discharged randomly in order to avoid polluting local
environment and affecting local landscape
11.7 MEASURES FOR EASING SOCIAL IMPACT DURING CONSTRUCTION PERIOD
Shall it be proved necessary to employ existing roads as construction access roads, first
consult with local government in order to prevent existing roads from traffic jams.
The construction schedule shall be rationally prepared so as to minimize impacts over lives of
residents along the lines.
At locations where construction vehicles enter and exit regularly, warning signs or signs
indicating no entry shall be set up.
Reasonably select material transportation routes and transport roads by avoiding passing
through areas and villages that are dense with residents.
11.7.2 PUBLIC DISTURBANCE
Ensure that public service facilities shall not be destroyed by construction activities of the
railway;
Any damages caused therein shall be promptly repaired and restored;
Each Contractor of the Project shall provide with facilities for temporary power supply,
communication, water supply and other required equipment;
A billboard shall be set up at the entrance of every construction field, indicating the
Contractor of the Project, hotline telephone numbers and names of contact persons of the
construction supervision units and local environmental protection department, so that the
public may get in contact with relevant departments shall they are affected by the noise,
atmospheric pollution, traffic problems and other unfavorable impacts generated during
construction.
DETAIL OF PILE-HEAD -
SCALE 1:50 -
1 of 4-20mm REBAR
1 of 4-16mm REBAR 10mmØ EXTRA TIE BAR FOR
20mm & 16mm REBAR TO 8-20mmØ COVER BLOCK FIXING AT
4-20mmØ+4-16mmØ BE PLACED ALTERNATIVELY 1000mm INTERVALE
SPIRAL: 10mm Ø 150mm C/C
SECTION
SCALE 1:25
A
1 of 4-20mm REBAR
1 of 4-16mm REBAR 800mm LAP LOCATION
D 20mm & 16mm REBAR TO
SPIRAL : 10mm Ø
@100mm C/C PLAN SHOWING PILE BARS WITH CC COVER BLOCK
BE PLACED ALTERNATIVELY
SCALE 1:10
10mmØ SPIRAL @150mm C/C
800mm LAP LOCATION
SPIRAL: 10mm Ø
@100mm C/C
6 25 mm THICK
SECTION
B 1
15 mm Ø HOLE
SPIRAL: 10mm Ø 200mm C/C
SCALE 1:25
8-16mmØ
1 of 8-16mm REBAR
8-20mm Ø
PILE TOE LEVEL : 30m BELOW FGL SECTION PILE LONG SECTION CIRCULAR C.C BLOCK FOR CLEAR COVER
SCALE 1:25
C SCALE 1:5
- LONG SECTION OF PILE
- NOT TO SCALE
U-BOLT
U-BOLT
U-BOLT
8-20mm Ø
Engineer: Legend:
SMEC Consultants Inc.in W (Witness Point)
Inspection and test plan (ITP) for cast-in place concrete piles H (Hold point)
JV Contractor: construction (500mm dia & 600mm dia) Employer: Bangladesh Railway S (Surveillance)
CCECC-MAX JV R (Review)
RW (Random Witness)
Responsiblities(H、W、R、S)
Acceptance
S/ Inspection/Activity/Test Frequency of test Verification Reference CCECC-MAX JV
criteria/Tolerance/ Remarks
N Description or inspection record document Field Engineer
Parameters Surveyor QA/QC
Engr.
1 Materials
1.1 Supply High Yield Each batch ASTM A615 Test certificates Specification(D
Deformed Steel Reinforcing 7) H R
Bars
1.2 Sample testing for High Every consignment ASTM A615 Test report Specification(D
Yield Deformed Steel 7) H H/R
Reinforcing Bars
1.3 Supply Cement Every consignment Approved by Material Specification(D Chemical, physical
of cement Engineer certificate 6.2.1) H W/R requirements & chloride
contents
1.4 Tests of samples drawn for Every consignment Specification(D 6.2.1) Test report Specification(D Lot size for independent
cement(compressive of cement 6.2.1) testing of cement at site
strength and setting times) shall be the quantity
H H/R
received at site on any day,
subject to a maximum of
500 tones.
1.5 Coarse and Fine Each batch IS:383;Specification( Test report Specification(D
Aggregates Table D 6.1&Table D 6.2.2 and H H/R
6.2) D6.2.3)
1.6 Supply Drilling Fluid Every consignment Approved by Certificate from Specification(D Apparent viscosity range (in
Engineer the 4.2.3) centipoises) and the gel
manufacturer H W/R strength range for solids in
water.
1.7 Water quality for mixing and All samples of water Specification/IS: Test report Specification(D
curing (including potable 516/IS:4031/IS:3025 6.2.4) H H/R
water)
1.8 Chemical admixtures Prior to the Specification(D Certificate from Specification(D Established manufacturer
commencement 6.2.5); IS: 9103 the 6.2.5) H H/R with quality assurance
manufacturer
2 Survey
2.1 Survey of Pile Location Every bored pile Pile Centre shall not RFI records & Approved
deviate more than inspection working
75mm from checklist drawing H H H
theoretically correct
plan
3 Boring
3.1 Excavation and drilling Every bored pile; The inclination of the inspection Specification(D
Verticality pile shall not deviate checklist 4.3)
more than 1:100 from H R/S
vertica
3.2 Drilling Fluid control Every bored pile As per method inspection As per method Sample test
test(density, viscosity and before excavation statement checklist statement H W W/R
pH values)
3.3 Final Pile Toe Level check Every bored pile The final excavation inspection Approved
depth shall not be checklist working
H H
exceed more than drawing and
200 mm specification
4 1st cleaning
4.1 1st cleaning Every bored pile No accumulation of inspection As per method
silt, other material, or checklist statement
heavily contaminated
bentonite suspension H S
at the base of the
boring
5 Reinforcement bar cage
5.1 Reinforcement bar cage Every bored pile Approved working RFI and Approved
check drawing checklist working
H H
drawing and
specification
6 2nd cleaning
6.1 2nd cleaning by Tremie Every bored pile No accumulation of inspection As per method
pipe after installation of silt, other material, or checklist statement
rebar case heavily contaminated
H S
bentonite suspension
at the base of the
boring
7 Concrete pouring
7.1 Pre pouring inspection Every bored pile Approved by the RFI records Specification(D
H H H
Engineer 4.3.7)
7.2 Concrete grade As per approved Mix. Specification and inspection Specification Verify the correct concrete
Design approved working checklist and approved Mix design and grade used
drawing working H H H/R and Q’ty as per estimated
drawing volume. Cube Test result
acceptance criteria
7.3 Slump Every truck 150mm - 200mm inspection Specification(T
checklist able D.7) H H
7.4 Temperature Every truck not more than 30° inspection Specification(
celsius checklist D.6.8.5) H H
0
1 Date
3
2 Weather
6
3 Method
9
4 Pile Location/ Bridge No :
12
5 Pile No:
15
6 Length (m) & Dia of Pile (mm)
18
Depth (m)
24
0.2 Installation of casing pipe
27
0.3 Boring
30
0.4 Sedimentation Time
33
0.5 1st Cleaning
36
0.6 Rebar Cage Installation
39
0.7 Installation of Tremie Pipe
42
0.8 2nd Cleaning
45
0.9 Pouring Concrete
48
0.10 Removal of Casing Pipe
Completion Time :
Notes:
NANE: NAME:
SIGNATURE: SIGNATURE:
DATE: DATE:
NANE: NAME:
SIGNATURE: SIGNATURE:
DATE: DATE:
10
11
12
13
14
15
16
17
18
19
20
Comments:
NAME: NAME:
SIGNATURE: SIGNATURE:
DATE: DATE:
SL
Ref. Document No. Name of Material Source/Brand Date Status Remarks
No.
ADMIXTURE
RFIM-CMJV-0012 /
1 Admixture Megaflow P4 & Sikaplast 2004NS 17-Jul-18 Approved
SMEC-5060126-CSC1-2018-121(DM)
AGGREGATE
RFIM-CMJV-0002 /
1 Coarse and Fine Aggregate Malaysia Stone & Sylhet Sand 31-May-18 Approved
SMEC-5060126-CSC1-2018-122(DM)
RFIM-CMJV-0043 /
2 Coarse Aggregate Masafi Crusher UAE 4-Aug-18 Approved
SMEC-5060126-CSC1-2018-435 (HM)
REBAR
RFIM-CMJV-0012 /
1 Rebar KSRM 500W (72.5 Grade) 17-Jul-18 Approved
SMEC-5060126-CSC1-2018-123(DM)
RFIM-CMJV-0012 /
2 Rebar BSRM 500W (72.5 Grade) 17-Jul-18 Approved
SMEC-5060126-CSC1-2018-123(DM)
CEMENT
RFIM-CMJV-0012 /
1 Cement Ruby OPC CEM-I (52.SN) 17-Jul-18 Approved
SMEC-5060126-CSC1-2018-143(DM)
RFIM-CMJV-0012 /
2 Cement Confidence OPC CEM-I (52.SN) 17-Jul-18 Approved
SMEC-5060126-CSC1-2018-143(DM)
RFIM-CMJV-0012 /SMEC-5060126-CSC1-
3 Cement Basundhara OPC CEM-I (52.SN) 17-Jul-18 Approved
2018-143(DM)
WATER
Mix Design No
Temperature
Design per Cum
RFIM-CMJV-
Max. Size of
Aggregate
Target (Agg.)
Trial Mix Grade s/a Admixture
Class
(mm)
Trial No Structure Mean W/C Status
C
Date (%) Dosage (%)
o
Strength Coarse Agg Fine Agg Water Coarse Fine Date of Strength Date of Strength
By Spec. actual Cement (Kg) Admixture (Kg)
(Kg) (kg) (kg) (%) (%) Testing (Mpa) Testing (Mpa)
0021 14-May-18 14 TM-02 Super Structure 52 20 0.40 75-150 135 27.8 Ruby OPC 450 Malaysia 1159.00 565.54 180 MegaFlowP4 4.5 0.47 2.52 48.80% 1.00% 21-May-18 50.63 11-Jun-18 56.43 Approved
0025 17-May-18 M 40 18 TM-01 Super Structure 52 20 0.40 75-150 130 29.4 Confidence OPC 450 Malaysia 1159.00 565.54 180 MegaFlowP4 4.5 0.47 2.52 48.80% 1.00% 24-May-18 50.07 14-Jun-18 55.93 Approved
0025 5-Jun-18 18 TM-02 Super Structure 52 20 0.40 75-150 87 28.5 Bashundhara 450 Malaysia 1159.00 565.54 180 MegaFlowP4 4.5 0.47 2.52 48.80% 1.00% 12-Jun-18 53.10 3-Jul-18 59.60 Approved
0003 29-Mar-18 3 CUET Lab Pile 47 20 0.37 150-200 OK OK Confidence OPC 440 Malaysia 1120.00 690.00 160 MegaFlowP4 3.96 0.48 1.42 61.61% 0.90% 5-Apr-18 43.83 26-Apr-18 50.77 Approved
0003 29-Mar-18 4 CUET Lab Pile 47 20 0.36 150-200 OK OK Bashundhara 450 Malaysia 1120.00 670.00 160 MegaFlowP4 4.05 0.48 1.42 59.82% 0.90% 5-Apr-18 40.93 26-Apr-18 46.57 Approved
M 35
0007 12-Apr-18 5 TM-01 Pile 47 20 0.40 150-200 190 28 Ruby OPC 430 Malaysia 1157.00 600.00 172 MegaFlowP4 6.45 0.47 2.52 51.86% 1.50% 19-Apr-18 44.73 10-May-18 47.33 Approved
0009 15-Apr-18 7 TM-01 Pile 47 20 0.40 150-200 175 29 Ruby OPC 440 Malaysia 1073.20 666.35 176 MegaFlowP4 5.72 0.47 2.52 62.09% 1.30% 22-Apr-18 40.96 13-May-18 47.03 Approved
0020 14-May-18 13 TM-02 Structure 47 20 0.4 75-150 150 29 Ruby OPC 420 Malaysia 1116.10 667.40 168 MegaFlowP4 3.36 0.47 2.52 59.80% 0.80% 21-May-18 48.30 11-Jun-18 54.93 Approved
0024 17-May-18 M 35 17 TM-01 Structure 47 20 0.40 75-150 80 27.4 Confidence OPC 420 Malaysia 1116.10 667.40 168 MegaFlowP4 3.36 0.47 2.52 59.80% 0.80% 24-May-18 50.13 14-Jun-18 56.07 Approved
0024 5-Jun-18 17 TM-02 Structure 47 20 0.40 75-150 120 27 Bashundhara 420 Malaysia 1116.10 667.40 168 MegaFlowP4 3.36 0.47 2.52 59.80% 0.80% 12-Jun-18 50.37 3-Jul-18 57.80 Approved
0019 13-May-18 12 TM-01 Structure 42 20 0.45 75-150 128 29.5 Ruby OPC 390 Malaysia 1159.00 628.85 175.5 MegaFlowP4 3.9 0.47 2.52 54.26% 1.00% 20-May-18 37.47 10-Jun-18 53.67 Approved
0023 19-May-18 M 30 16 TM-01 Structure 42 20 0.45 75-150 142 27.8 Confidence OPC 390 Malaysia 1159.00 630.79 175.5 MegaFlowP4 3.12 0.47 2.52 54.43% 0.80% 26-May-18 47.63 16-Jun-18 57.83 Approved
0023 5-Jun-18 16 TM-02 Structure 42 20 0.45 75-150 93 28.4 Bashundhara 390 Malaysia 1159.00 630.79 175.5 MegaFlowP4 3.12 0.47 2.52 54.43% 0.80% 12-Jun-18 50.57 3-Jul-18 55.50 Approved
0018 15-May-18 11 TM-02 Structure 36 20 0.40 75-150 125 28.6 Ruby OPC 360 Malaysia 1180.50 716.91 144 MegaFlowP4 2.88 0.47 2.52 60.73% 0.80% 22-May-18 41.03 12-Jun-18 55.17 Approved
0022 17-May-18 M 25 15 TM-01 Structure 36 20 0.40 75-150 145 28.4 Confidence OPC 360 Malaysia 1180.50 716.91 144 MegaFlowP4 2.88 0.47 2.52 60.73% 0.80% 24-May-18 42.83 14-Jun-18 44.80 Approved
0022 5-Jun-18 15 TM-02 Structure 36 20 0.40 75-150 75 28 Bashundhara 360 Malaysia 1180.50 716.91 144 MegaFlowP4 2.88 0.47 2.52 60.73% 0.80% 12-Jun-18 43.83 3-Jul-18 51.40 Approved
0013 24-Apr-18 9 TM-01 Lean Concrete 30 20 0.50 25 8 27 Ruby OPC 310 Malaysia 1180.50 737.79 155 0.47 2.52 62.50% 0.00% 1-May-18 39.97 22-May-18 43.97 Approved
M 20
0013 28-May-18 9 TM-02 Lean Concrete 30 20 0.5 25 20 28 Confidence OPC 310 Malaysia 1137.60 780.31 155 0.47 2.52 68.59% 0.00% 4-Jun-18 36.13 25-Jun-18 44.93 Approved
0013 24-Apr-18 8 TM-01 Lean Concrete 25 20 0.50 25 24 27.5 Ruby OPC 280 Malaysia 1180.50 802.16 140 0.47 2.52 67.95% 0.00% 1-May-18 25.27 22-May-18 37.67 Approved
0013 27-May-18 8 TM-02 Lean Concrete 25 20 0.5 25 15 29 Confidence OPC 280 Malaysia 1180.50 802.16 140 0.47 2.52 67.95% 0.00% 3-Jun-18 31.17 24-Jun-18 39.83 Approved
M 15
0003 29-Mar-18 1 CUET Lab Lean Concrete 25 20 0.50 25 OK OK Confidence OPC 330 Malaysia 1120.00 820.00 165 0.48 1.42 73.21% 0.00% 5-Apr-18 17.23 26-Apr-18 26.03 Approved
0003 29-Mar-18 2 CUET Lab Lean Concrete 25 20 0.49 25 OK OK Bashundhara 325 Malaysia 1120.00 820.00 160 0.48 1.42 73.21% 0.00% 5-Apr-18 19.63 26-Apr-18 29.43 Approved
DCRP/CMJV/MS-009,REV.B Page 61 of 63
METHOD STATEMENT FOR PILES CONSTRUCTION (STATIONS & BUILDINGS)