ISTRUZIONE TECNICA 7.5 Rev. 2.
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 1 di 6
TECHNICAL SPECIFICATION FOR CHEMICAL CLEANING
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08
PURPOSE AND SCOPE
Technical specification for carbon steel alloys chemical cleaning with Ferroquest FQ product solution.
Process derivation: BAMA s.r.l. Turbigo factory.
The existing safety and accident prevention laws must be followed.
Safety measures have been specified when necessary.
REFERENCE
➢ MQA Sec. 7.5
RESPONSIBILITY
Who Where What Checks
Unit resp. Bama Initial controls Presence of instructions
On site works resp. On site works Utilization Understanding instructions
Workers Final controls Training
Environment Effectiveness if training
Security
➢ Responsibility for management and check of preparation’s operations are borne in SQA, DIR, HR
➢ Responsibility of information and training are borne in HR, SQA
➢ Responsibility of the correct application and execution of test are borne in SQA, DIR.
LEGEND
MQA SQA DIR HR
Quality and Environment Manual Quality and Environment System Direction Human Resource
Rev. Data Emissione Descrizione Modifica Redatto Verificato
0 09.08.2012 First emission G.De Bernardi S. Castoldi
1 22.02.2016 General Revision G. Be Dernardi S. Castoldi
2 15.02.2017 General Revision G. Be Dernardi S. Castoldi
2.1 30.09.2021 General Revision L. Grassi G. De Bernardi
2.2 07.10.2021 General Revision L. Grassi G. De Bernardi
Revision in accordance to Suez
2.3 01.03.2022 L. Grassi G. De Bernardi
datasheet (pH modified)
This technical instruction is exclusive property of BAMA s.r.l., all rights reserved. Any disclosure, reproduction, or transfer of the contents of the third parties are prohibited
without prior permission of the Company. All information contained herein are confidential and, such as, cannot be transferred to other people or organizations without our
permission.
The copy delivered are “Copy controlled” or “Copy Uncontrolled”. In the first case, the Quality Manager is committed to venture further delay of any new version of the
document; in case of Uncontrolled copy, however, we ask to you to consider the document valid only after making sure that the one you have is the latest revision issued.
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460
Filename: \\10.0.1.10\documenti\SISTEMA QUALITA' E AMBIENTE\7.Istruzioni tecniche\SPECIFICHE NUOVE RELEASE 08\BA010-CARBONIO\CLIENTI-BA010\RESTA\RESTA JOB 2918\BA010REV2.3-FQUEST-
08-BARHAIN-NC-JOB-29-18-280921-ENG.doc
ISTRUZIONE TECNICA 7.5 Rev. 2.3
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 2 di 6
INDEX
TECHNICAL SPECIFICATION FOR CHEMICAL CLEANING ................................................................................................................ 1
PURPOSE AND SCOPE...................................................................................................................................... 1
REFERENCE ....................................................................................................................................................... 1
RESPONSIBILITY .............................................................................................................................................. 1
1. PURPOSE ........................................................................................................................................................................... 3
2. GENERAL RECOMMENDED PRECAUTIONS ............................................................................................................................ 3
3. HANDLING ......................................................................................................................................................................... 3
4. MATERIALS ........................................................................................................................................................................ 3
5. DEFINITIONS ..................................................................................................................................................................... 3
6. PREPARATION OF THE CLEANING SOLUTION ....................................................................................................................... 3
7. CHEMICAL INLET PREPARATION ......................................................................................................................................... 4
8. CHEMICAL PARAMETERS MONITORING................................................................................................................................ 4
9. CHECK OF IRON CONTENT .................................................................................................................................................. 4
10. FQ7102 ADDITION FOR PH CONTROL .............................................................................................................................. 4
11. PASSIVATION STEP COMPLETE ....................................................................................................................................... 4
12. DRAIN THE ITEM ........................................................................................................................................................... 5
13. FINAL FLUSH OF THE ITEM ............................................................................................................................................. 5
14. DRYING ......................................................................................................................................................................... 5
15. CHEMICAL AND PHYSICAL CHARACTERISTICS OF THE WATER .......................................................................................... 5
16. CERTIFICATION ............................................................................................................................................................. 5
17. ATTACHMENT ................................................................................................................................................................ 6
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460
Filename: \\10.0.1.10\documenti\SISTEMA QUALITA' E AMBIENTE\7.Istruzioni tecniche\SPECIFICHE NUOVE RELEASE 08\BA010-CARBONIO\CLIENTI-BA010\RESTA\RESTA JOB 2918\BA010REV2.3-FQUEST-
08-BARHAIN-NC-JOB-29-18-280921-ENG.doc
ISTRUZIONE TECNICA 7.5 Rev. 2.3
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 3 di 6
1. PURPOSE
This technical specification defines the details about carbon steel/austenitic steel/Ni alloys vessels, pipes and tanks and
exchangers chemical treatment by circulation system using Suez Ferroquest FQ product solutions (or equivalent).
2. GENERAL RECOMMENDED PRECAUTIONS
The producers instructions of the solutions and their thresholds must be followed (reference to material safety data sheet).
Personal safety measures and the laws about use, storage and disposal of chemical substances must be followed.
3. HANDLING
Carried out using exclusively Teflon or nylon bands.
4. MATERIALS
Carbon steel alloys, CrMo steel, austenitic stainless steel and Ni alloys.
5. DEFINITIONS
Passivation is the process where a very thin film of rust is purposely formed and phosphates are placed on freshly
cleaned carbon steel to prevent excessive rust. Instead of the carbon steel being left in the active state (prone to
corrosion), the metal is left passive (non-reactive). The intent is to protect the freshly cleaned metal while the equipment is
out of service.
Passivation Chemicals used: FQ7101/:F07102 (or equivalent):
Organic passivating agent liquids. FQ7101/FQ7102 work by chelating any soluble iron (like the surface rust present in
the new exchanger) in the system and promoting a Phosphate/Iron conversion layer on the metal surface. This layer
is then in the optimum form to prevent 'iron throw’ to the Cooling Water.
Ratios of chemicals to use for Cleaning/Passivation
For pre-cleaning on new equipment, the below concentrations on the chemicals are suggested:
• FQ7101 5% by volume (cleaner)
• FQ7102 0.2% by volume (pH corrector)
The recirculating solution pH shall be between 6.0 and 7.2 (Optimal value is 6.5).
If it’s not possible to calculate the actual thickness of the deposit to remove, use a standard 10% FQ7101 solution with
1%-2% of pH corrector FQ7102.
To ensure a performing chemical cleaning on the internal surfaces of the exchangers, and to reduce the product
replenishment (also considering the variable volumes caused by pipes, pumps and recirculation tank) it is suggested to
use a 15% FQ7101 solution.
6. PREPARATION OF THE CLEANING SOLUTION
• Calculate amounts of Ferroquest 7101/7102 (or equivalent) to be used (Table 1).
• Fill the circulation tank and the equipment to be treated with Quality 2 Water – Tap Water (Table 2)
• Add chemicals to the circulation tank while circulating water. Turn material over one time for mixing before
proceeding.
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460
Filename: \\10.0.1.10\documenti\SISTEMA QUALITA' E AMBIENTE\7.Istruzioni tecniche\SPECIFICHE NUOVE RELEASE 08\BA010-CARBONIO\CLIENTI-BA010\RESTA\RESTA JOB 2918\BA010REV2.3-FQUEST-
08-BARHAIN-NC-JOB-29-18-280921-ENG.doc
ISTRUZIONE TECNICA 7.5 Rev. 2.3
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 4 di 6
Table 1
SHELL SIDE TUBE SIDE FQ7101 VOLUME FQ7101 VOLUME FQ7102 VOLUME FQ7102 VOLUME
ITEM
VOLUME VOLUME FOR SHELL SIDE FOR TUBE SIDE FOR SHELL SIDE FOR TUBE SIDE
018E1006 4.3 m3 / 645 L / 43 to 86 L /
018E2003 1.4 m3 / 210 L / 14 to 28 L /
018E2006 4.3 m3 2.2 m3 645 L 330 L 43 to 86 L 22 to 44 L
018E2007 0.45 m3 0.38 m3 68 L 57 L 4.5 to 9 L 4 to 8 L
021E0003 / 1.6 m3 / 240 L / 16 to 32 L
021E0005 / 1.7 m3 / 255 L / 17 to 34 L
021E0009 1.4 m3 0.9 m3 210 L 135 L 14 to 28 L 9 to 18 L
7. CHEMICAL INLET PREPARATION
• Limit and tag all the working area around the exchanger and temporary equipment area.
• Prepare pumping station equipment for service. If using a diaphragm pump, start a small air flow.
• Hook up connection hoses from acid supply container to injection pump and to manifold off discharge of pump
and open vent on storage container.
• As equipment has been installed properly, start chemical injection.
8. CHEMICAL PARAMETERS MONITORING
PH, conductivity, and Iron content every 60 minutes shall be monitored in order to target the desired concentration of
Ferroquest chemicals.
Additional Ferroquest FQ7102 (or equivalent) will be added to control pH; all results shall be logged as certification.
9. CHECK OF IRON CONTENT
Take a sample of return water for iron as Fe 2O3.
The iron levels will increase rapidly when the cleaning is first started since the easiest iron deposits will be removed.
After a period of time, the iron level will not increase at the same rate, indicating that the passivation step is almost
complete.
10. FQ7102 ADDITION FOR PH CONTROL
Sample return water for pH on an hourly basis to target a pH range of 6.0 to 7.2 (optimal value is 6.5)
If needed, add Ferroquest 7102 (low pH) to maintain target.
11. PASSIVATION STEP COMPLETE
Passivation phase is complete when the iron concentration does not significantly increase over time, even after
additional FQ7101/7102 has been added to the system or if all the Ferroquest chemicals have been added to the
recirculation tank and have been in circulation for 24 hours, then passivation can be considered complete.
In any case recirculation time can be performed from 24h – to 72h.
After BAMA and Resta Site Supervisor agree that passivation step is complete, proceed to drain exchanger.
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460
Filename: \\10.0.1.10\documenti\SISTEMA QUALITA' E AMBIENTE\7.Istruzioni tecniche\SPECIFICHE NUOVE RELEASE 08\BA010-CARBONIO\CLIENTI-BA010\RESTA\RESTA JOB 2918\BA010REV2.3-FQUEST-
08-BARHAIN-NC-JOB-29-18-280921-ENG.doc
ISTRUZIONE TECNICA 7.5 Rev. 2.3
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 5 di 6
12. DRAIN THE ITEM
• Shut down circulation pump.
• Open high point bleed.
• Drain exchanger to empty storage tank(s).
13. FINAL FLUSH OF THE ITEM
Connect water (Quality 2 - Tap Water) to inlet connection and fill the system with fresh water until flow back to tank is
observed.
Drain the item to empty storage tank(s) or sewage.
14. DRYING
After chemical treatment the surfaces shall be drained completely.
Drying can be performed using forced dry air, air treatment unit (UTA), vacuum pump, nitrogen flushing.
Drying shall be completed when dew point at the outlet is 0° or less.
15. PRESERVATION WITH N2
Conditioning by nitrogen purging according to the preservation procedure No. WQA0107-2918 REV.2
16. CHEMICAL AND PHYSICAL CHARACTERISTICS OF THE WATER
Table 2
Quality 1 (Demi water) Quality 2 (Tap water)
Aspect Clear Clear
Colour Absent Absent
pH (25°C) 5.5/7.5 5.5/8
Chlorides < 1.5 ppm < 50 ppm
Fluorides < 0.1 ppm < 0.1 ppm
Sulphates < 1.0 ppm < 45 ppm
Silicon dioxide (SiO2) < 0.1 ppm
Total solids < 0.1 ppm < 600 ppm
Conductivity < 5 microsiemens
Filtration grade < 10 micron
If quality 2 (Tap Water) it is not available on-site, water with maximum +10% of chlorides can be used (chlorides <55 ppm)
17. CERTIFICATION
After the chemical treatment and inspections, the certificate will be issued (see attachment 1 for further information).
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460
Filename: \\10.0.1.10\documenti\SISTEMA QUALITA' E AMBIENTE\7.Istruzioni tecniche\SPECIFICHE NUOVE RELEASE 08\BA010-CARBONIO\CLIENTI-BA010\RESTA\RESTA JOB 2918\BA010REV2.3-FQUEST-
08-BARHAIN-NC-JOB-29-18-280921-ENG.doc
ISTRUZIONE TECNICA 7.5 Rev. 2.3
BA010REV2.3/FQUEST/BAHRAIN/NC/JOB2918/08 Date: 01/03/2022
Pag. 6 di 6
18. ATTACHMENT
Attachment 1
HARDCOPIES OF THIS DOCUMENT WITHOUT RELEASE SIGNATURES ARE CONSIDERED NOT CONTROLLED, HENCE WITHOUT ANY VALIDITY.
BAMA S.r.l. Via Novara, 20029 Turbigo, Italy - http://www.bama-technologies.com - Email [email protected] - tel. +39 0331898460