JOB SAFETY ANALYSIS
PROJECT JSW PROJECT (CIVIL) DATE / MONTH 18. November ’ 2021
Pixef and Tempo etc.
COMPANY ITD CEMENTATION INDIA LTD EQUIPMENT INVOLVED
Helmet, shoes, goggles, hand
PROJECT MANAGER Mr. ONKAR KULKARNI gloves, noise mask etc.
PPE / SAFETY DEVICE REQUIRED
Mr. Shripad Patil Mr. Pramod Singh
Mr. Sawarvar Zomadekar
SITE ENGINEER Mr. Laxuman Madane TEAM MEMBER Mr.Ranjeet Prasad
Mr.Tarun Kumar Mr.Retesh P. Salokhe
Mr.Shishir Kr. Singh
SAFETY OFFICER PERMIT REQUIRED YES
Mr.Pintu Kumar
ACTIVITY DESCRIPTION GAS CUTTING WORK JSA NO. 01
JSA For Steel Yard & Plot-A
Area
(Cover shed)
No. Activity Potential Hazards Preventative Measures Responsibilities Remark
1 Loading & unloading of * Toppling of rebar’s while 1. Competent operator for Pixef / Crane. Mr Preshant Zutshi
rebar’s from Tempo loading/unloading 2. Competent driver for Tempo. Mr Shripad Patil
3. Ground compacted for location of loading unloading. Mr Laxman Madane
4. Avoid loading & unloading in running rain or in fog weather. Mr Tarun Kumar
5. Use hand break & wheel stoppers for Tempo wheels. Mr. Pramod Singh
6. Proper Illumination. Mr. Sawarvar
7. Working area must be barricaded Zomadekar
8. Prohibited to public movement. Mr.Ranjeet Prasad
9. Helper for Tempo during loading unloading. Mr.Retesh P. Salokhe
10. Provide proper supervision.
11. Take appropriate PTW for the work with supporting doc’s.
2 Transportation of Rebar’s * Fall of rebar’s from Tempo in 1. Valid driving licenses holder person deputed for job. Mr Preshant Zutshi
from steel Yard location to transit. 2. Ensure back horn, side indicators, rear mirrors, head lights Mr Shripad Patil
Plot A cover shed through & banks man for safe movement of trailer or other vehicles. Mr Laxman Madane
Tempo. 3. Vehicles with valid documents like insurance, PUC etc. Mr Tarun Kumar
4. Materials tied properly on board of vehicle by using rope, Mr. Pramod Singh
cargo belts or chain slings. Mr. Sawarvar
5. Avoid overloading. Zomadekar
6. Follows speed limit 20km/hr Mr.Ranjeet Prasad
7.Follows traffic rules and JSW rules. Mr.Retesh P. Salokhe
8. Follow Alcohol and mobile policy.
9. Provide helper with vehicle for assist to driver during
reversing of vehicles.
3 Loading & unloading of * Failure of the boom. 1. Ensure that brakes, limit switch, boom alarm, swing horn Mr Preshant Zutshi
Rebar’s (Ring) from Tempo * Fall of materials during lifting and over hoist and safe load indicators are working properly. Mr Shripad Patil
by crane / Pixef. & placing. 2. Inspect boom once a week for damages if any Mr Laxman Madane
* Toppling of Crane 3.Lift only SWL Mr Tarun Kumar
* Misunderstanding between 4.Ensure that the area is barricaded and personnel kept away Mr. Pramod Singh
operator and signal man (Lack 5. Preventive maintenance should be carried out on time. Mr. Sawarvar
of communication 6. Restriction unauthorized entry. Zomadekar
* Inclement weather, rain, sun, 7.Competent operator for crane. Mr.Ranjeet Prasad
storm etc & poor visibility 8.Competent Rigger & Signal man Mr.Retesh P. Salokhe
* Incorrect lifting procedure. 9. Use tested ( TPI ) Crane & Tools and tackles.
10.Regular checking of crane & slings for cracks & kink
11. Maintain the correct radius of crane
12. Prohibit using of Mobile phones & music.
13. Compacted & even ground.
15.Follows company mobile & alcohol policy
16. Operation should be carried out with authorized
signalmen only.
17.Use of PPE’s.
4 Maintance of Crane / Pixef * Damage of crane boom/ high 1. Only trained and licensed personnel must undertake. Mr Preshant Zutshi
pressure hydraulic pipe of Repairs and maintenance on the hydraulic system of the Mr Shripad Patil
Pixef. plant. Mr Laxman Madane
Oil spillage or leakage. 2. Before commencement of work the engine must be shut Mr Tarun Kumar
down and hydraulic system depressurized. Mr. Pramod Singh
3. Any spills must be cleaned prior to commencement of Mr. Sawarvar
work. Zomadekar
4.Ensure suitable PPE is worn when carrying out this Mr.Ranjeet Prasad
operation Mr.Retesh P. Salokhe
6. Use only approved containers to collect all contaminates.
7. During maintenance a suitable absorbent agent must be on
hand.
8. Site safety rules must be adhered to.
9. Approved containers must be used to collect oils during
routine service.
5 Placing of Crane / Pixef / * Hit to person 1. Driver should be trained and experienced. Mr Preshant Zutshi
Tempo * Hit to Property 2. Driver should have valid License. Mr Shripad Patil
3. No body stand or work near moving vehicle. Mr Laxman Madane
4. Banks man should be present in driver side while Mr Tarun Kumar
reversing. Mr. Pramod Singh
5. Follow traffic rules while driving at site. Mr. Sawarvar
6. Competent deriver should be deployed. Zomadekar
7. No body stand or work near moving vehicle Mr.Ranjeet Prasad
8. Use proper PPE Mr.Retesh P. Salokhe
6 Fixing of tools & tackles * Damaged of tools & tackles. 1.Use only tested tools for lifting materials Mr Preshant Zutshi
2. Trained and experienced person should fix the sling and d Mr Shripad Patil
shackle. Mr Laxman Madane
3. Check Sling & D shackle fixed properly before lifting. Mr Tarun Kumar
4. Signal man & lifting supervisor should be available while Mr. Pramod Singh
lifting load. Mr. Sawarvar
5. Do not lift materials more than its capacity Zomadekar
6. Use proper PPE.’s. Mr.Ranjeet Prasad
Mr.Retesh P. Salokhe
7 Protruding rebar’s (ring) * Hit to person / other vehicle / 1. Visibility sign must be display end of rebar. Mr Preshant Zutshi
beyond the tempo other structure.. 2. Road should be clear before leaving one location to other Mr Shripad Patil
location. Mr Laxman Madane
3. Speed limit 20k.m. per hours. Mr Tarun Kumar
4. Follow traffic rules while driving. Mr. Pramod Singh
5. Authorized deriver should be deployed Mr. Sawarvar
6. Check as per checklist for transporting of materials. Zomadekar
7. Close supervision. Mr.Ranjeet Prasad
For Trailer Mr.Retesh P. Salokhe
Note- Deployment of flagman for signaling & controlling the
traffics.
) Speed limit of vehicle should be maintain as per flagman.
)
Checked by :
Prepared by : Approved by :
Sign. Mr. Kapil Bhongale Sign. Sign.
Mr. Shishir Kr. Singh Mr. Onkar Kulkarni
Date : 18.11.2021 Date 18.11.2021 Date : 18.11.2021
Drawing for Rebar’s shifting by Tempo