MINUTES OF MEETING
I. Date of Meeting 06 August 2021 Time: 5:20PM-7:00PM Meeting No: 18
ATTENDEES:
NAME FIRM NAME FIRM
Joven Sore BFI-PMG Jerry Carreon Jamvi
Arche Vale Alibiano Jamvi Marvin Castulo Makima
Jennie John Agoot Jamvi Moi Villanueva Jamvi
Joyce T.Maglasang Amcoop Michael Vincent Calaque Amcoop
Japet Estrellan Makima Romeo Castillo Jamvi
Dominador Manatad
II. AGENDA:
1. Safety Updates and Concerns
2. Project Updates and Look Ahead Plan
3. QC Concerns
4. Others
III. MEETING SUMMARY
S/N Topics Action by Target Date Status &
Remarks
PROGRESS & PROGRAM
GENERAL UPDATE
1. SAFETY UPDATE AND CONCERNS
*Sir Japet Estrellan
1.Accidents and Incident Report root cause is due negligence in Safety Week 32 For Follow
terms of PPE usage-PPE's are to arrive the soonest.ETA not yet Team Up
identified-Hard Hats Arrived Supplied by KCC,Boots and
Gloves no Feedback,CRS and P.G Weekly Meeting Gives info
about PPE's -
2.Exit passes and filed leave greatly affects daily manfill. Safety
- Exit pass consideration- Emergency cases and Sending Team
money
- Can only go out on their respective schedules ON GOING
3.Hand washing and foot bath must be observed accordingly.105
will provide the powder to be added on the water for the hand
wash. For follow up Safety Week 32 PENDING
4.To Provide and Implement smoking and Non-Smoking Areas on Team
Sites and Bunkhouses
-to Identify areas and on bunkhouses,Seek Help on Site Engineers Timekeeper
regarding Setting Up Smoking Areas on Site s/Sir Japet
5.Sleeping on site During Night Shift-monitoring in charge are the
timekeepers. Check also the bunkhouses.
6.Cellphones confiscated on site must release Memorandum on this Sir Japet OPEN
one
CONCERNS:
1.Additional CR on Nucleus- site not yet ready and also Water INFO OPEN
closets not on site.Safety team can trigger for the local purchasing
of the water closets needed. No supply/materials yet.
- Sir Arche will make a temporary CR. Culvert will provide
by Sir Michael. Sir Japet
- Fabrication of Ash trays and Trash cans
2. Strictly monitor the exit of workers-Red Tag Workers who Sir Arche On goings
always leave site premises. Coordinate with the PS about this Issue.
3. Provide Stickers and Signages for the ash trays and trash cans
4. Releasing of Memorandum about confiscating of phone during Safety
working hours. Team
5. Signatories of Entry/Exit passes
- Project Engineers
- Project Supervisors
- Safety Lead
6. Early overtime out of the workers instead of 7:30pm minimum,
some workers are already there at Biometric/Face scanner area
7:18pm waiting for the time until 7:30pm to out.
7. Strict Implementation of Permitting to Have it prepared a day
before the start of work.Have it displayed on site.
Strict Implementation of Safety Standards-Prioritization of PPE's
Needed,
8. No lights on walkways with a lot of tripping and falling hazards
3. PROJECT UPDATE AND CONCERNS
Boar Stud Office and Building
-Clines started paneling Works
-Painting works ongoing Sir Arche
-Civil Works-prepare for Tile Works
-PC 270 Needed for Benching Works-Needs additional Dump truck
for backfilling Works-
-
Powerhouse Nucleus
-Generator Set for Powerhouse- is temporary the permanent one
will arrive in December .Genset connected to LVSG
-13200 Cable to Transformer needed to provide supply for Finisher
Buildings Sir Arche
-Remaining Works : Rectification of Cable tray is on going.
-Cables are all on site and laid but not yet terminated-Waiting for
ATS (Automatic Transfer Switch)and Lights and Power Panel
Ceiling activity hampered.
Main supply form 13200 line to be replaced.High Tension Cable Sir Arche
from 13200 to Switch Gear to be replaced-
- Electrical must be on site to be updated on the ongoing progress
on site
-Report on the Damage Wires is needed
CONCERNS:
-Poor Housekeeping
-Rack pipes Sir Arche
Mechanical
Nursery 4 Nucleus Teams
-Plastering on Both sides done ONGOING
-Trusses Erection Ongoing Sir Arche
-FDT on Monday and Soil Poisoning Wednesday
Done
Sir Arche
Finisher 2 and 3 Nucleus On going
-Ongoing Trusses Erection On going
-Pit wall Construction ongoing Week 31
Sir Arche
Finisher 4 and 5 nucleus
-Settled Pedestal Rectification Works ongoing
-Pit Wall Construction Ongoing
-Plumbing Works on 5 almost done
Aug. 2, 2021
UPDATES ON REPAIR WORKS ON HIGHBIO Aug. 2, 2021
-Farrowing 2 and 3 Repair Works ongoing-5/8 columns repaired Sir Arche Done
On going
TRANSFER CORRIDORS
-Layouts and Repair ongoing ,Excavation started -with 12pax
manpower deployed
On going
CONCERNS: On going
-Power supply on 500 cu.m Cistern Tank 2-to investigate why the
supply is low.
-Change of Cable Lines to be used-ongoing deliberation and Sir Arche
coordination
-Once Powerhouse Nucleus is energized we will solve all low
supply concerns. On goings
Sir Arche
SOW SITE On going
Breeder Gestation Sow Site
-Generator Set in Gestation is Enough for Breeder Gestation and
Gestation but the Double Throw in Gestation is Guba-Powerhouse
to MTS to supply for Breeder and Gestation
Farrowing 2 Sow site
-Rebars Installation on SOG Span BC
-Possible pouring of SOG will be Next week, Week 32
Nursery 1-3 Sow Site
-Must drill Dowels with 100mm depth and start rebar installation-
grinder availability is a concern.
-Bottom Beams of Nursery 2 Done
Sir Marvin
Finisher 1 Sow Site
-to start SOG Preparation
-Backfilling concerns on the material used to backfill pipes on front
of Finisher 1 Sow Site.
Finisher 2 Sow Site On going
-Clearing inside buildings to transfer to Finisher 4 Sow Site-not
enough space in Finisher 4 must create temporary facility for the
materials. It depends on the availability of the haulers.
Finisher 3 Sow Site
- Pennings – almost done
-Roxell-start Works-conflict on EE Conduits with Flex auger Pipes
-
Sir Moi
Finisher 7 Sow Site
-Plumbing Works must start-staking done
Powerhouse Sow Site
-MVSG not yet on site,Genset On going
-Needs Epoxy Primer
-Stationary-December
-Mobile -For Repair
Sir John On going
Site Development On goings
Nucleus:
- Backfilling Works on Boar Stud Building Pending due ti Sir Moi
inavailabilt
-Forecast of aggregates for the next months will be provided.
-PC 70 (1)is badly needed on site but Priority is in Nucleus- repair
works on FA2
-PC 70 (1) assigned on Duct Banks excavation.Set target date of
completion on all scope of works.
Sow Site: Sir Mike
- Establishing access road from Finisher 5 – Finisher 8
-Finisher 6 Sow Site NGL Leveling- not yet finished
-Follow up on the Hiring of site Supervisors in replacement for Pending
Sir Clark On going
-Must request additional Backhoe Operator for Night Shift
-Phase 4 activity – on going On going
Concern:
1 bagger mixer – damage. Parts needed.
Breeder Gestation Catch Basin is Flooded and Destroyed .Water is
flowing heavily towards Phase 3. Sir Mike
On going
Electrical Team
- Capacitor for ICT Area to be installed tomorrow.As per confirmed
by Sir James
-EE Room Revised Drawings will be provided later tonight
Slurry Line
Finisher 2 and 3.
-Nucleus to Breeder -materials available- cobbles not yet
delivered-manpower already provided-area must be developed to
create catch basin-no equipment available
-Nucleus(Mechanical works)- catch basin is on going
-Fast-Tracking of main Slurry line at Nucleus
-Staking done for Finisher 7 Sow Site
-Leak Test must be conducted and proper documents must be
provided-leaks on which joint must be recorded on IR
Nursery 4-Finisher 5 Sow site – Excavation is on going. Sir Mike
Dewatering and Desilting is on going.
Nursery 3 to ICT
-Ongoing already at powerhouse-culverts must be cleared to
continue excavation-to be removed
-Slurry line is on going
-Rechecking of layout near Finisher 1 to ICT
-At 99 Office to ICt- for checking of elevation-road is lower in
elevation if pipes are installed it will be expose-elbow can be used
to embed the pipes
Sir Marvin
ICT 2 AND 3
-HDPE Welding Machine availability affects progress-support
installation for pipes ongoing
-Pump Skid to ICT 3 line already created only 1 booster available - Sir Marvin
ICT 3 first then directly to
Biogas.To deploy workers highbio to connect pipes.
-How High is the riser?
ICT 3 TO BIOGAS ALREADY CONNECTED
ICT 2 TO PUMP SKID THEN PUMP SKID TO BIOGAS Sir Marvin
-CHB Piling ongoing for fences
-Manpower will transfer to Farrowing building for Slurry line.
-Needs Leak Test Document asked copy form Contractor
Cistern 1000
-already Disinfected- To put roof to avoid contamination in times
when the cover is open.To talk to Sir James about roofing On hold as
-to Provide Fences to make sure water is clean. Sir Moi per advice
-Verbal instruction from CNM for Pipe Connections by CM
Maam Lyka-Surveying Team
-Elevation of Slurry line at Fin. 5 -checking
-Checking of Road elevation from Powerhouse to BPPP Sir MOI
-Finisher 6 & 7 Nucleus- Checking and Lay-outed 4 perimeter.
-Phase 3 (Concrete lagoon)- Survey and Staking tomorrow.
-Slurry Line from Finisher 1 to ICT 3
-Nursery 3 Sow Site-IR for Checking on Saddles "No IR,No
Checking"
-Survey Request to be submitted to Maam Lyka-okay Maam Lyka
QC CONCERNS
1.IR must be submitted prior to inspection along with the Survey Sir Jasper/
Request. MaamLyka
2.Culvert Collaring must be checked prior to backfilling works
3.Proper Scheduling of Pouring Request. Sir Jasper
4.Pavement – compact well. Checking first before gravelling.
5.Leak test – Inform the QC and submit IR for inspection.
6.Finisher 1 Sow site- catch basin 1.3 meters
7.Pavement- thickness .1 meter, steels 10mm space at .6meters.
3000 psi.
8.Drainage must be constructed at the back prior to silo Pad
9.Documentation on All Scopes of Work esp. On possible Change
Orders
OTHERS
1. Material Storage esp. Of Panels are put on Floors directly on soil
2. Farrowing 2 Slab on sump -chipping on sump is not acceptable it
should be finished hours after the slab pouring
3. Plumbing works must be Fast tracked
4. Access Roads must be established on Boar Stud Nucleus-
Backfilling Works must be done.
5. 4 Operators for Night shift already requested.
6. Workers sitting around and huddling on site
Biotech Farms, PMG prepared these minutes for recording the information discussed at the meeting. Should anyone object to the
statements or interpretations contained herein, please advise Joyce T. Maglasang ([email protected])
Prepared by:
Joyce T. Maglasang
Planner
AMCOOP
Noted by:
Joven Sore
Planner/Scheduler
Project Management Group
Biotech farms Incorporated