Assessing The Deformation Response of Double-Track Overlapped Tunnels Using Numerical Simulation and Field Monitoring
Assessing The Deformation Response of Double-Track Overlapped Tunnels Using Numerical Simulation and Field Monitoring
a r t i c l e i n f o a b s t r a c t
Article history: The unprecedented rate of metro construction has led to a highly complex network of metro lines.
Received 23 December 2020 Tunnels are being overlapped to an ever-increasing degree. This paper investigates the deformation
Received in revised form response of double-track overlapped tunnels in Tianjin, China using finite element analysis (FEA) and
8 June 2021
field monitoring, considering the attributes of different tunneling forms. With respect to the upper
Accepted 17 July 2021
Available online 28 August 2021
tunneling, the results of the FEA and field monitoring showed that the maximum vertical displacements
of the ground surface during the tail passage were 2.06 mm, 2.25 mm and 2.39 mm obtained by the FEA,
field monitoring and Peck calculation, respectively; the heaves on the vertical displacement curve were
Keywords:
Double-track overlapped tunnels
observed at 8 m (1.25D, where D is the diameter of the tunnel) away from the center of the tunnel and
Deformation response the curve at both sides was asymmetrical. Furthermore, the crown and bottom produce approximately
Finite element analysis (FEA) 0.38 mm and 1.26 mm of contraction, respectively. The results of the FEA of the upper and lower sections
Field monitoring demonstrated that the tunneling form has an obvious influence on the deformation response of the
Upper and lower tunneling double-track overlapped tunnel. Compared with the upper tunneling, the lower tunneling exerted
significantly less influence on the deformation response, which manifested as a smaller displacement of
the strata and deformation of the existing tunnel. The results of this study on overlapped tunnels can
provide a reference for similar projects in the future.
Ó 2022 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by
Elsevier B.V. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/
licenses/by-nc-nd/4.0/).
https://doi.org/10.1016/j.jrmge.2021.07.003
1674-7755 Ó 2022 Institute of Rock and Soil Mechanics, Chinese Academy of Sciences. Production and hosting by Elsevier B.V. This is an open access article under the CC BY-
NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/).
Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447 437
Fig. 1. Overview of the project: (a) location of M6 and (b) section of the double-track overlapped tunnel (Google Maps, annotations made by author).
horizontally parallel and intersecting arrangements, while few 2. Engineering background of the case study
have focused on vertically parallel arrangements.
Among the studies that did consider vertically parallel double- 2.1. Project overview
track overlapped tunnels, Ng et al. (2015) used centrifuge tests
and numerical modeling to analyze the deformation response The section of double-track overlapped tunnels investigated be-
during tunneling with a focus on the response of a pile group. Fang longs to the interval between Wenhuazhongxin and Leyuandao sta-
et al. (2016) investigated the ground surface settlement due to the tions of Rail Transit Line 6 (M 6) in Tianjin, China. The total length of
tunneling process and considered the influence of different geo- the interval between the two stations is 776 m and that of the double-
metric arrangements; however, the tunnel section had a horseshoe track overlapped section of the tunnels is 392 m, as shown in Fig. 1.
shape and the shallow tunneling method was used for excavation. An earth pressure balancing (EPB) shield machine with a
Few studies have considered the deformation response of vertically diameter of 6.4 m was used to excavate the tunnel, and its face
parallel double-track overlapped tunnels excavated by the shield pressure was 0.25e0.3 MPa. The shield started from the working
tunneling method and with a circular tunnel section. shaft of Wenhuazhongxin station and reached the working shaft of
The tunneling form also affects the deformation response of Leyuandao station. During the tunneling process, the shield passed
double-track overlapped tunnels during the tunneling process. Ma the adjacent existing tunnels of Tianjin Rail Transit Line Z1 (M Z1)
et al. (2018) studied a pipeline’s settlement and load-transfer to form the section of the double-track overlapped tunnels. The
mechanism induced by double-track overlapped tunneling with tunnel lining was assembled with prefabricated reinforced con-
different tunneling forms. Soomro et al. (2020) employed centri- crete segments in staggered joints, which consisted of one cap
fuge tests and numerical modeling to explore the stress-transfer block, two adjacent blocks, and three standard blocks. The strength
mechanisms and settlement of a pile group during double-track grade of the segments is C55, and the segments are connected by
overlapped tunneling with different construction sequences. bending bolts. In addition, the tunnel lining was designed to
However, the above studies focused on the response of existing pile function with an outer diameter of 6.2 m and a thickness of 0.35 m,
groups and pipelines but did not evaluate the deformation with the width of each ring being 1.5 m.
response of existing tunnels.
In this study, finite element analysis (FEA) and field monitoring 2.2. Geological conditions
were employed to investigate the deformation response on the
ground surface and new tunnel (longitudinal and transverse) dur- Tianjin is located in the east of the North China Plain and
ing upper tunneling activity for the double-track overlapped tun- downstream of the Haihe River Basin. It is an alluvial plain with flat
nels in Tianjin, China. Moreover, the FEA of the upper and lower terrain and extensive soft soil. Fig. 2 shows the illustration of the
tunneling was used to explore the influence of the tunneling form ground profile in the direction of the tunnel axis. It can be seen that
on the deformation response of the double-track overlapped tun- the main strata of the interval between Wenhuazhongxin and
nels. The displacement in the strata (vertical and horizontal) and Leyuandao stations consist of soft soils (including silty clay, sandy
deformation of the existing tunnel (longitudinal and transverse) silt and silt), and the strata crossed by the double-track overlapped
were analyzed in detail. The study of overlapped tunnels described tunnels mainly consist of silty clay and silt. In addition, the mini-
in this paper can provide a reference for similar projects in the mum cover thickness of M 6 is 6.8 m, and the minimum vertical
future. distance between M 6 and M Z1 is 7.2 m.
438 Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447
Fig. 2. Illustration of the ground profile in the direction of the tunnel axis.
Fig. 3 shows the variations of the typical geotechnical properties software, ABAQUS, was used to numerically explore the distur-
of the simplified soil layers with depth. These indices include unit bance effect of the tunneling process on the double-track over-
weight, water content, void ratio, plasticity index, liquidity index, lapped tunnels (Sun, 2015; Zhang et al., 2016). This paper chooses
constrained factor, constrained modulus, cohesion, internal friction the small-strain FEA in the ‘‘Soils’’ step to calculate the deformation
angle and standard penetration test (SPT) blow counts; and the of soil, which can improve the computational efficiency (Liu et al.,
minimum, maximum and average values of each index are given. 2014).
During the construction process, the impact of unfavorable When taking into account factors such as the burial depth and
geological sections should be fully considered and the driving pa- spacing of the two tunnels, it is generally appropriate to select a
rameters should be properly set to avoid engineering risks. The calculation range that is not less than 3De4D along the tunnel
groundwater table in the site is within the range of 0.8e1.9 m. diameter in all directions, where D is the diameter of the tunnel (Sun,
2015). Therefore, the dimensions of the finite element model were
2.3. Field monitoring layout determined to be 63 m 40 m 46 m (length width depth), as
shown in Fig. 5. The finite element model includes five types of
Fig. 4 shows the field monitoring layout used in this study. The components (soil part, shield part, grouting part, lining part, and an
monitoring points were only arranged in the new tunnel (M 6) and existing tunnel part) and two pressure types (support pressure of the
on the ground surface to measure the deformation response of the shield tunneling face and grouting pressure); the dimensions of the
double-track overlapped tunnels to the upper tunneling process, parts and pressures are consistent with the actual project.
with a total of 5 monitoring points for vertical displacement of the In this study, the C3D8P elements (8-node trilinear displace-
ground surface, 18 monitoring points for longitudinal deformations ment and pore pressure) were selected to simulate soil strata
of the tunnel, and 36 monitoring points for transverse de- because the pore water pressure must be considered. A non-
formations of the tunnel. Fig. 4a shows the top view of the field uniform grid was used with a fine grid in the region close to the
monitoring layout, and section A-A0 in the transverse direction was tunnel and a coarser grid in the far field. The C3D8I elements (8-
chosen to show the field monitoring layout of the new tunnel, as node linear brick, incompatible mode) were employed to simulate
shown in Fig. 4b. “GS”, “LS” and “TS” represent the monitoring the shield, grouting, lining, and existing tunnels (Dong et al., 2014).
points of vertical displacement on the ground surface, the longi- The finite element model has a total of 26,688 elements. Among
tudinal deformation of the tunnel, and the transverse deformation these, the dualistic interactions between the soil and grouting
of the tunnel, respectively. The automatic leveling level DS05 parts, the soil and shield parts, the grouting and lining parts, and
(Suzhou FOIF Co., Ltd., China), the total station SET1X and prisms the soil and existing tunnel parts were connected by the tie. In
(Sokkia Co., Tokyo, Japan) and the hand-held laser rangefinder addition, the boundary conditions of the model along the X and Y
DLE50 (Robert Bosch GmbH, Stuttgart, Germany) were used in this axes separately limited “U1” and “U2” to ensure that the horizontal
study. displacement was constrained, whereas the vertical direction could
be spontaneously moved. In the Z direction, “U1”, “U2” and “U3” on
3. FEA of the double-track overlapped tunneling process the base surface were limited (both the horizontal and vertical
directions are constrained).
3.1. Finite element model Based on the upper tunneling activity, the finite element model
of the lower tunneling (the existing tunnel is above and the new
Given the engineering background of the double-track over- tunnel is below) is proposed as a basis for the discussion of the
lapped tunnels (upper tunneling), the three-dimensional FEA influence of the tunneling form on the deformation response of the
Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447 439
double-track overlapped tunnels. In the finite element model in the FEA and field monitoring results were compared to investigate
lower tunneling process, everything apart from the tunneling form the deformation response of the double-track overlapped tunnels
is the same as that in the upper tunneling case. during the upper tunneling process. The following aspects were
primarily analyzed: (1) vertical displacement of GS-1 during
3.2. Material properties different tunneling stages, (2) vertical displacement of the ground
surface, (3) longitudinal deformation of the new tunnel, and (4)
The material properties in this finite element model can be transverse deformation of the new tunnel. Based on this, the in-
divided into two categories: elastoplastic material (soil) and linear fluence of different tunneling forms on the double-track over-
elastic material (shield, lining, grouting, and the existing tunnel). lapped tunnels was evaluated via an FEA of the upper and lower
For the soil, the elastic part adopts the porous elastic model, tunneling.
whereas the plastic part adopts the modified Cam-Clay model. As
the materials are relatively uniform and have a high degree of 4.1. Vertical displacement of GS-1 during different tunneling stages
stiffness, linear elastic constitutive models were used for the shield,
lining, grouting, and existing tunnel (Zhang et al., 2016). The ma- Fig. 7 shows the vertical displacement of the ground surface at
terial parameters of the constitutive model used in the FEA are monitoring point GS-1 during different tunneling stages. Before GS-
listed in Table 1. The finite element model considers the grouting 1 was reached (face pre-arrival), the heave occurred, which was
hardening process, “soft” indicating that the grouting has just been observed in both the FEA and field monitoring. Liu et al. (2014)
injected and “hard” indicating that it has hardened. Furthermore, stated that the face pressure (i.e. the pressure of earth acting on
owing to the fact that the bolted connection between the linings in the tunnel face) is the main influencing factor before the tunnel
the actual project reduces its strength (Zheng et al., 2015; Zhang face is reached during the tunneling process. Therefore, it can be
et al., 2021), the Young’s modulus of the linings was discounted deduced that this heave was primarily caused by face pressure.
Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447 441
was still revealed by the two approaches, but the difference be-
tween field monitoring and FEA was greater than that for the face
arrival. The settlement at this stage may be attributed to the
grouting pressure and contraction during grouting.
In this study, the conicity of the shield machine was considered
in the field monitoring but not in the FEA. In addition, the field
monitoring indicated non-uniform contraction during grouting
(Fig. 8b), whereas the FEA revealed uniform contraction. These
explain the differences between field monitoring and FEA.
Compared with the maximum vertical displacements observed for
a single tunnel (FEA: 20 mm; field monitoring: 7.5 mm) (Liu et al.,
2014), the maximum vertical displacements in this study were
significantly smaller (FEA: 2.5 mm; field monitoring: 1.5 mm). This
may be attributed to the effect of the existing tunnel.
Table 1
Material constitutive parameters used in the finite element analysis.
Silty Clay 2.5 18.4 0.86 0.058 0.0072 0.32 0.00018 0.776
Sandy Silt 3 17.9 1.03 0.031 0.0039 0.35 0.00050 0.742
Silty Clay 10.3 18.1 0.89 0.055 0.0069 0.35 0.00031 0.764
Silt 12.2 19.8 1.37 0.020 0.0025 0.3 0.00020 0.595
Silty Clay 18 18.6 0.90 0.047 0.0059 0.35 0.00485 0.683
Note: E: Young’s modulus; n: Poisson’s ratio; M: Slope of the critical state line in qep0 space; l and k: Slopes of the normal compression and recompression lines in eeln p0
space; e0: Initial void ratio; k: Permeability coefficient.
442 Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447
the crown and bottom of the tunnel mean that they underwent
expansion and contraction, respectively. Furthermore, the positive
value of the difference between the bottom and crown means that
the tunnel collectively moved upward.
It can be seen from Fig. 11 that the longitudinal deformation
trends of the FEA and field monitoring after tunneling are almost
identical. The trend can be divided into three stages: Stage I: the
longitudinal deformation increases and reaches the maximum
(positive) at 42.5 m (3.2D) away from the end of tunnel; Stage II: the
longitudinal deformation drops sharply and reaches the minimum
(negative) at 56.5 m (1D) away from the end of tunnel; and Stage III:
the longitudinal deformation has a slight increase. This indicates
that the tunnel deformation changed from upward movement to
downward movement at 1De3.2D away from the end of the tunnel.
Attention should be given to the tunnel deformation at 3.2D away
from the end of the tunnel for the construction of double-track
overlapped tunnels. The difference between the FEA and field
monitoring may be attributed to the difference in connections be-
tween the linings. In other words, the FEA adopted the equivalent
stiffness method, while bolted connections were used in the actual
engineering project.
Fig. 8. Influence factors: (a) conicity of the shield machine and (b) nonuniform contraction.
5. Conclusions
Fig. 9. Transverse vertical displacement of the ground surface in the middle of the
tunnel: (a) Face arrival, and (b) Tail passage.
Fig. 11. Longitudinal deformation of the new tunnel after tunneling completion.
Fig. 13. Vertical displacement of the stratum: (a) longitudinal (after tunneling) and (b)
transverse (in the middle of tunneling).
Fig. 12. Transverse deformation of the new tunnel in the middle of tunneling (unit:
mm). The numbers around the circle are in degree.
Acknowledgments
Chehade, F.H., Shahrour, I., 2008. Numerical analysis of the interaction between
twin-tunnels: influence of the relative position and construction procedure.
Tunn. Undergr. Space Technol. 23 (2), 210e214.
Chen, R.P., Zhu, J., Liu, W., Tang, X.W., 2011. Ground movement induced by parallel
EPB tunnels in silty soils. Tunn. Undergr. Space Technol. 26 (1), 163e171.
Chen, R.P., Lin, X.T., Kang, X., Zhong, Z.Q., Liu, Y., Zhang, P., Wu, H.N., 2018. Defor-
mation and stress characteristics of existing twin tunnels induced by close-
distance EPBS under-crossing. Tunn. Undergr. Space Technol. 82, 468e481.
Das, R., Singh, P.K., Kainthola, A., Panthee, S., Singh, T.N., 2017. Numerical analysis of
surface subsidence in asymmetric parallel highway tunnels. J. Rock Mech.
Geotech. Eng. 9 (1), 170e179.
Dias, D., Kastner, R., 2013. Movements caused by the excavation of tunnels using
face pressurized shields - analysis of monitoring and numerical modeling re-
sults. Eng. Geol. 152 (1), 17e25.
Dong, Y., Burd, H., Houlsby, G., Hou, Y., 2014. Advanced finite element analysis of a
complex deep excavation case history in Shanghai. Front. Struct. Civ. Eng. 8 (1),
93e100.
Fang, Q., Tai, Q., Zhang, D.L., Wong, L.N.Y., 2016. Ground surface settlements due to
construction of closely-spaced twin tunnels with different geometric arrange-
ments. Tunn. Undergr. Space Technol. 51, 144e151.
Ji, Q., Huang, Z., Peng, X., 2008. Analysis on influence of conicity of extra-large
diameter mixed shield machine on surface settlement. In: Complimentary
Special Issue to the 6th International Symposium on Geotechnical Aspects of
Underground Construction in Soft Ground. Shanghai, China, pp. 237e242.
Jin, D., Yuan, D., Liu, S., Li, X., Luo, W., 2019. Performance of existing subway tunnels
Fig. 16. Transverse deformation of the existing tunnel in the middle of tunneling (unit: undercrossed by four closely spaced shield tunnels. J. Perform. Constr. Facil. 33
mm). The numbers around the circle are in degree. (1), 04018099.
Lai, H.P., Zheng, H.W., Chen, R., Kang, Z., Liu, Y., 2020. Settlement behaviors of
existing tunnel caused by obliquely under-crossing shield tunneling in close
upper tunneling caused the strata to settle on the ground proximity with small intersection angle. Tunn. Undergr. Space Technol. 97,
surface and to heave at the monitoring point MD, whereas 103258.
Y. Hu et al. / Journal of Rock Mechanics and Geotechnical Engineering 14 (2022) 436e447 447
Liu, C., Zhang, Z.X., Regueiro, R.A., 2014. Pile and pile group response to tunnelling Zhang, T.Q., Taylor, R.N., Divall, S., Zheng, G., Sun, J., Stallebrass, S.E., Goodey, R.J.,
using a large diameter slurry shield e case study in. Shanghai. Comput. Geo- 2019. Explanation for twin tunnelling-induced surface settlements by changes
tech. 59, 21e43. in soil stiffness on account of stress history. Tunn. Undergr. Space Technol. 85,
Ma, S., Liu, Y., Lv, X., Shao, Y., Feng, Y., 2018. Settlement and load transfer mechanism 160e169.
of pipeline due to twin stacked tunneling with different construction se- Zhang, Z.X., Liu, C., Huang, X., Kwok, C.Y., Teng, L., 2016. Three-dimensional finite-
quences. KSCE J. Civ. Eng. 22, 3810e3817. element analysis on ground responses during twin-tunnel construction using
Marshall, A.M., Klar, A., Mair, R.J., 2010. Tunneling beneath buried pipes: view of soil the URUP method. Tunn. Undergr. Space Technol. 58, 133e146.
strain and its effect on pipeline behavior. J. Geotech. Geoenviron. 136 (12), Zhang, J.Z., Huang, H.W., Zhang, D.M., Zhou, M.L., Tang, C., Liu, D.J., 2021. Effect of
1664e1672. ground surface surcharge on deformational performance of tunnel in spatially
Mollon, G., Dias, D., Soubra, A.H., 2013. Probabilistic analyses of tunneling-induced variable soil. Comput. Geotech. 136, 104229.
ground movements. Acta Geotechnol. 8 (2), 181e199. Zheng, G., Lu, P., Diao, Y., 2015. Advance speed-based parametric study of greenfield
Ng, C.W.W., Hong, Y., Soomro, M.A., 2015. Effects of piggyback twin tunnelling on a deformation induced by EPBM tunneling in soft ground. Comput. Geotech. 65,
pile group: 3D centrifuge tests and numerical modelling. Geotechnique 65 (1), 220e232.
38e51. Zheng, G., Fan, Q., Zhang, T., Zheng, W., Sun, J., Zhou, H., Diao, Y., 2019. Multistage
Peck, R.B., 1969. Deep excavations and tunneling in soft ground. In: Proceedings of regulation strategy as a tool to control the vertical displacement of railway
the 7th International Conference on Soil Mechanics and Foundation Engineer- tracks placed over the building site of two overlapped shield tunnels. Tunn.
ing. Mexico City, Mexico, pp. 225e290. Undergr. Space Technol. 83, 282e290.
Qian, W.Q., Qi, T.Y., Zhao, Y.J., Le, Y.Z., Yi, H.Y., 2019. Deformation characteristics and
safety assessment of a high-speed railway induced by undercutting metro
tunnel excavation. J. Rock Mech. Geotech. Eng. 11 (1), 88e98.
Shahin, H.M., Nakai, T., Ishii, K., Iwata, T., Kuroi, S., 2016. Investigation of influence of
tunneling on existing building and tunnel: model tests and numerical simula- Dr. Huayang Lei has obtained her BSc degree in Engineering
tions. Acta Geotechnol. 11, 679e692. Geology at College of Changchun Geology, China, in 1994, and
Soomro, M.A., Mangi, N., Xiong, H., Kumar, M., Mangnejo, D.A., 2020. Centrifuge and MSc and PhD degrees in Geotechnical Engineering at Jilin
numerical modelling of stress transfer mechanisms and settlement of pile University, China, in 1997 and 2001, respectively. She is pro-
group due to twin stacked tunnelling with different construction sequences. fessor of geotechnical engineering and deputy director of
Comput. Geotech. 121, 103449. Department of Civil Engineering at Tianjin University. Dr. Lei
Standing, J.R., Selemetas, D., 2013. Greenfield ground response to EPBM tunnelling has hosted a number of key projects from Chinese govern-
in London Clay. Geotechnique 63 (12), 989e1007. ment, such as National Key Research and Development Pro-
Suwansawa, S., Einstein, H.H., 2007. Describing settlement troughs over twin tun- gram of China, National Key Basic Research and Development
nels using a superposition technique. J. Geotech. Geoenviron. 133 (4), 445e468. Program of China (973 Program), and National Natural Sci-
Sun, F.M., 2015. Analysis of Interaction between Small-Spacing Parallel Shield ence Foundation of China. She has authored or co-authored
Tunnel Excavations. MSc Thesis. Zhejiang University, Hangzhou, China (in more than 130 academic papers and compiled 9 tutorial
Chinese). books and monographs. Dr. Lei’s research interests cover
Wei, G., 2009. Study on calculation for width parameter of surface settlement soft soil engineering characteristics, foundation treatment,
trough induced by shield tunnel. Ind. Constr. 39 (12), 74e79 (in Chinese). soil constitutive relationship and urban underground engineering.