Annexure I - Scope & Specification For Construction of Rock Silo-D - Rev 0
Annexure I - Scope & Specification For Construction of Rock Silo-D - Rev 0
ANNEXURE-I
CONSTRUCTION, COMMISSIONING
OF
P a g e 1 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
CONTENTS
P a g e 2 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
1. INTRODUCTION :
Phosphate rock is generally imported from Jordan, morocco, Peru, Egypt and Vietnam
while sulphur and ammonia are imported from Gulf countries. The complex has a jetty
at Paradeep Port with two grab unloaders having capacity of 1500 tonnes per hour each
and one screw unloader with capacity 1800 tonnes per hour. Presently Paradeep Unit
has six silos for storage of solid raw materials which receives materials from the jetty
through 5.5 km long cross country conveying system.
To enhance the storage facility for Rock Phosphate an additional Silo is required with all
ancillary systems.
Therefore IFFCO Paradeep intends to engage a competent & experienced vendor for
design, engineering, supply, construction & commissioning of a new Rock Phosphate
Storage Silo on LSTK basis within a minimum time period.
P a g e 3 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
2. SITE DATA
Metrological data
Dry Bulb Temperature (Max ) 41 °C
Dry Bulb Temperature (Min) 8 °C
Wet Bulb Temperature 7.5-30 °C
Plant location
Paradeep, Jagatsignhpur District, Orissa state, India
20 0, 15’ 56.44’’ N
86 0 , 14’ 34.62’’ E
Altitude above sea level 6.0 m (Average)
Atmospheric pressure 762 mm Hg
Mean annual rainfall 1800 mm (Average)
Relative humidity
Average 75.0 %
Minimum 50.0 %
Maximum 90.0%
Wind velocity (Max.) 260 Km/h
Wind direction (wind rose attached) Mainly SW ↔ NE
Super cyclone prone area
Earth quake zone
Indian seismic zone No. III
Modified Mercalli scale,1931 VII
Soil Condition Site Geotechnical Report is to be
referred. Will be provided shortly
Fugitive dust in surrounding
3. DESIGN REQUIREMENTS
3.1. Construction of storage Silo & Conveying system
Proposed Rock Phosphate Silo-D shall be designed by a combination of RCC & Steel
structural sections. Suitable type of pilings shall be considered for all RCC foundations
P a g e 4 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
depending upon the geo technical study carried out to confirm the soil strata. Gable
end wall, retaining wall, underground conveyor gantry shall be made up of RCC. Silo
roof structure, unloading & transfer conveyor gantry, transfer tower, maintenance
tower, and all structural supports for conveying system shall be considered to be made
from steel structural.
The scope of work of this enquiry shall comprise of design, engineering, supply,
erection/construction, testing & commissioning of the following for successful completion of
the job.
P a g e 5 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
Vendor has to arrange a site survey & detail technical discussion with IFFCO team for
better understanding of the complete scope before bidding.
Design & detail engineering of complete storage shed, transfer tower, maintenance tower,
transfer & underground reclaiming conveying system, travelling tripper shall be in
vendor’s scope. Before going for detail engineering vendor has to submit the basic
engineering documents for review & approval of IFFCO.
All the design calculations & drawings for civil, structural, conveying system shall be
vetted by M/s PDIL, New Delhi at the cost of LSTK contract.
4.2. Civil
Design specification, supply of material & execution procedure for relevant civil &
structural job shall be guided by the “Detail Specification for Civil & Structural
Works” attached as Annexure-II.
P a g e 6 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
4.1.1 Earthwork
All type of earthwork like excavation of earth for foundations, footings, columns, plinth
beams, walls, machine/equipment foundations, isolated pits, pavements, trenches for
pipelines/cables, drains , removal & disposal of extra earth material from site, providing
Mechanically Stabilised Mix (MSM) layer of suitable grade at required location and
supply & filling of sweet sand as per requirement shall be considered.
4.2.2 Piling
A geo technical survey is being carried out to know the existing soil strata at designated
location for the proposed Rock Silo-D. Pile type & detail design shall be done as per the
soil data received from the study. No. of piles, Pile diameter, Pile length shall be
designed considering all the load data (dead load & dynamic load). Pile type may be
Bored cast in situ or Driven cast in situ depending on load data & soil data. The designed
data of pile shall be verified by executing test piles at the desired locations before
execution of piling job.
i) Pile cap & pedestal for columns of silo, conveyor trestle, transfer tower,
maintenance tower.
ii) Retaining wall & Gable end wall.
iii) Encasing/Embedding of steel column depending upon design.
iv) Underground Reclaiming Conveyor gallery.
v) Pent House (Exit point of underground reclaiming conveyor)
vi) Flooring of Silo inside area & plinth area, transfer tower &
maintenance tower area.
4.2.4 Roofing
Supply & installation of high impact PVC corrugated sheets of Palruf make over storage
shed, monitor area, transfer & maintenance tower and conveyor gantry made up of steel
structure. Wind Ties made up of GI flat of suitable size shall also be considered.
P a g e 7 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
Supply & application of suitable waterproofing material over roof of Pent House and any
other RCC roof exposed to atmosphere shall also to be considered.
All concrete and structural steel works shall be provided with protective coating as
specified in the bid. The painting system should conform to the stipulations of ISO
12944‐1998 for C‐5M environment or condition & more than 15 years durability. It is
required that the system should be valid for 10 years guarantee period. The painting shall
be carried out by agency approved by the paint manufacturers strictly in compliance with
the specifications under joint supervision of the applicator & manufacturer’s
representatives. ES 2001, attached with the bid may be referred in this regard
The supply of all materials for completion of the project shall be in contractor scope,
broadly as follows
4.2.7.1 Cement
4.2.7.2 Sand: The material should confirm to the specification enclosed in the bid.
However, only river sand shall be used by the contractor.
P a g e 8 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
4.2.7.3 Water: To be supplied by owner free of cost. However IFFCO will provide the
same at one point. Further distribution during construction shall be in the scope of
contractor
4.2.7.5 Concrete: Only controlled concrete of M35 grade & above as specified shall be
used confirming to IS 456, except for the paving, filler walls which shall be of
grade M‐25
4.2.7.7 Structural steel: Structural steel materials shall conform to IS 2062 with a
minimum yield strength of 36000 psi, and designed in accordance with IS.
Supply, erection, commissioning & load trial of following conveying systems shall be in the
vendor’s scope.
i) Material Discharge facilities from existing R-10A conveyor to new R-10B conveyor.
ii) New R-10B Conveyor
iii) New R-15 Unloading Conveyor along with Travelling Tripper
iv) New Underground Reclaiming Conveyor 103D
v) Pneumatic/ Motorised Gate along with hopper for feeding to Underground
Reclaiming Conveyor.
vi) New Transfer Conveyor 104B.
Following Components of conveying system is to included but not limited for smooth &
trouble free operation of the complete conveying system.
Supply, installation & commissioning of all electrical items shall be in scope of the
vendor, majority comprising of the following.
i) New MCC for all electrical equipment
ii) Tripper Control Panel
iii) CRD control panel
iv) Ultrasonic Heap Sensing arrangements.
v) Belt weighing system including Load Cell for reclaimed material.
vi) Scoop Coupling Control panel
vii) Power, control , CRD cable
viii) Raychem make Heat shrinkable end termination kits for HV Cables.
ix) Cable Termination material for LV cables.
x) Cable Tray & Tray support system
xi) Conveyor safety switches (Pull Cord switch, Zero speed switch, Belt sway switch
etc.)
xii) Local Control station
P a g e 10 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
5. APPLICABLE STANDARDS
Following is a general listing of Codes and Standards to be used in the design &
engineering for construction of Rock Phosphate Silo-D with all ancillary systems. Specific
applicable codes and standards will be identified in System Design Descriptions /
Technical Specifications as appropriate. The latest editions/ revision of following codes
and standards along with addendums/ amendments, if any, shall be followed:
5.01 Earthwork
5.02 Concrete
5.03 Foundations
P a g e 13 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 14 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
5.08 Waterproofing
P a g e 16 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 17 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 18 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 19 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
5.15 Painting
P a g e 22 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 23 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 24 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.1.1.7 Specification for Earth work shall also apply to excavation in rock in general.
The excavation in rock shall be done such that extra excavation beyond the
required width and depth as shown in drawings is not made. If the
excavation done in depth greater than required / ordered. The Contractor
shall fill the extra excavation with concrete of mix 1:5:10 as the foundation
concrete at his own cost.
6.1.1.8 The Contractor shall make all necessary arrangements for
dewatering/defiling as required to carry out proper excavation work by
bailing or pumping out water, which may accumulate in the excavation pit
from any cause / source whatsoever.
6.1.1.9 Contractor shall provide suitable draining arrangements at his own cost to
prevent surface water entering the foundation pits from any source.
6.1.12 Excavations in hard rock - meant excavation made in hard rock to be done
manually, or by blasting using only explosives and / or pneumatic hammers.
In case of blasting, control blasting should be adopted depending on site
conditions. For using explosives, Contractor shall follow all provisions of
Indian Explosive Act/Rules 1983, corrected/ revised up to date.
6.1.13 In case of hard rock excavation to be carried out using explosive the
Contractor shall obtain the written approval in advance.
6.1.2 Filling
P a g e 25 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.1.2.2 Soil filling - Soil material shall be free from rubbish, roots, hard lumps and
any other foreign organic material. Filling shall be done in regular horizontal
layers each not exceeding 20 cm. Depth.
6.1.2.3 Back filling around completed foundations, structures, trenches and in plinth
shall be done to the lines and levels shown on the drawings.
6.1.2.4 Back filling around pipes in the trench shall be done after hydro testing is
done.
6.1.2.5 Back filling around liquid retaining structures shall be done only after leakage
testing is completed and approval of Owner / Consultant is obtained.
6.1.2.6 Sand used for filling under foundation concrete, around foundation and in
plinth etc., shall be fine / course, strong, clean, free from dust, organic and
deleterious matter. The sand filling under foundation shall be rammed with
Mechanical compactor. Sand material shall be approved by Owner /
Consultant.
6.1.2.7 Moorum for filling, where ordered, shall be obtained from approved pits and
quarries which contain siliceous material and natural mixture of clay. Moorum
P a g e 26 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
shall not contain any admixture of ordinary earth. Size of Moorum shall vary
from dust to 10 mm.
6.2.1 Materials
6.2.1.1 Cement: Any of the following cements may be used as required.
IS: 269 Ordinary Portland Cement, 33 Grade.
IS - 455Portland Slag Cement.
6.2.1.2 Water: Water used for mixing and curing concrete and mortar shall conform
to the requirements as laid down in clause 4.3 of IS: 456. Sea-water shall
not be used for concrete work.
P a g e 27 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.2.1.3 Aggregates : Coarse and fine aggregates for cement concrete plain and
reinforced shall conform to the requirements of IS : 383 and / or IS : 515.
Before using, the aggregates shall be tested as per IS: 2386.
6.2.1.4 Coarse aggregate: Coarse aggregate for all cement concrete work shall be
broken or crushed hard stone, black trap stone obtained from approved
quarries or gravel.
6.2.1.5 Sand: Fine aggregate for concrete work shall be coarse sand from
approved sources. Grading of coarse sand shall be within grading zones I, II
or III laid down in IS: 383, table-4. If required the aggregates (both fine and
coarse) shall have to be thoroughly washed and graded as per direction of
Owner / Consultant.
6.2.2 Mixing
Design mix Concrete from batching plant set up by contractor will only be
allowed for RCC as well as PCC work. Hand mixing will not be allowed in
any circumstances.
6.2.4 Laying
Concreting shall be commenced only after the Owner /Consultant has
inspected and passed the sub-base / base or the centering, shuttering and
reinforcement. Concrete in slab, beams, columns, footings etc., shall be laid
gently in layers not exceeding 15 cm and shall be properly consolidated by
means of approved mechanical vibrators.
6.2.5 Curing
P a g e 28 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) After the concrete has begun to harden, it shall be protected with moist
gunny bags, sand or any other material approved by the Owner
/Consultant against quick drying. After 24 hours of laying concrete, the
surface shall be cured by flooding with water or by covering with wet
absorbent materials for 7 days as per the direction of Owner /
Consultant.
ii) Approved curing compounds may be used in lieu of moist curing with
the permission of the Owner /Consultant. Such compounds shall be
applied to all exposed surfaces of the concrete as soon as possible
after the concrete has set. No extra payment shall be made for the
same.
6.2.6.2 Grades lower than M-15 shall not be used in reinforced concrete.
P a g e 29 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.2.6.3 M-7.5 grades of concrete may be used for lean concrete bases and simple
foundation for masonry walls.
6.2.6.4 A sieve analysis test of aggregates shall be carried out as and when the
source of supply is charge without extra charge notwithstanding the
mandatory test required to be carried out as per CPWD Specification.
6.2.6.5 All test in support of mix design shall be maintained as a part of records of
the contract. Test cubes for mix design shall be prepared by the Contractor
under his own arrangements and at his costs, but under the supervision of
the Owner / Consultant.
6.2.7.1 Design mix shall only be allowed for all concrete works where it is
contemplated to be used by installing weigh batch mixing plant as per IS-
4925. At the time of tendering, the Tenderer, after taking into account the type
of aggregates, plant and method of laying he intends to use, shall allow in his
tender for the design mix i.e., aggregate/cement and water/cement ratios
which he consider will achieve the strength requirements specified, and
workability for concrete, to be properly furnished.
6.2.7.2 Soon after the Tenderer gets L.O.I. to commence the work, he shall carry out
preliminary tests for design mix on trial mixes proposed by him in design of
mix to satisfy the Owner/ Consultant that the characteristic strength specified
in clause 3.6.1 is obtained. Prior to this, the Contractor has to get design mix
done as per IS : 10262 through Government approved / reputed institute and
the Contractor shall arrange the same at his own cost. The concrete mix to be
actually used shall be approved by the Owner / Consultant.
6.2.7.3 Notwithstanding the above, the following shall be the maximum combined
weight of coarse and fine aggregate per 50 Kg of cement.
P a g e 30 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
1. M - 10 480 kg.
2. M - 15 350 kg.
3. M - 20 250 kg.
6.2.7.4 The workability of concrete produced shall be adequate, so that the concrete
can be properly placed and compacted. The slump shall be as follows, when
vibrators are used.
6.2.7.5 The minimum consumption of the cement irrespective of design mix shall not
be less than the following:
Grade of
SL. No. Minimum consumption of Cement.
Concrete.
2. M - 10 ( 1 : 3 : 6 ) 220 Kg / C.um.
3. M - 15 300 Kg / C.um.
4. M - 20 350 Kg / C.um.
6.
6.2.8.2 A slump test shall be taken at each mixer at least once in every fifty batches
mixed. Any batch for which a slump test is being made shall not be
transferred to the place of laying until the slump test has been completed. Any
batch which gives a slump in excess of that described at the time of
preliminary tests shall be rejected and removed from the site.
6.2.8.3 At least six cubes shall be taken for every 30 Cu.m. metres of concrete or part
thereof deposited in the work on any day. Three cubes shall be tested for 28
days strength.
6.2.8.4 If a test for particular work does not meet the specified requirements, the
Owner / Consultant in his absolute discretion may accept the work at a
correspondingly reduced rate provided the average strength at 28 days is not
less than 85% of the specified strength.
6.2.8.5 If the results are poorer than 85% of the specified strength, the Owner /
Consultant may order further testing of any kind as may be deemed
necessary in his opinion, including load tests. The load tests shall be carried
on the portion of the structure involving concrete represented by the
unsatisfactory works test and such other adjoining elements of a building as
the Owner / Consultant may decide.
P a g e 32 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
If the results of the load tests are not satisfactory, the Contractor shall at his
own cost undertake remedial measures including dismantling and
reconstruction according to the directions and to the satisfaction of the Owner
/ Consultant. If the load test is successful, the Owner/ Consultant may
exercise his judgement before accepting or rejecting the work and shall still
have the power to apply a reduction in rate as herein stated before, in case
the work in question is accepted.
6.2.9 Proportioning
Mixes of cement concrete shall be as ordered. Where the concrete is
specified by grade, it shall be prepared by mixing cement, sand and coarse
aggregate by weight as per mix design. In case the concrete is specified as
volumetric mix, then dry volume batching shall be done, making proper
allowances for dampness in aggregate and bulking in sand. Equivalent
volume batching for concrete specified by grade may however be allowed by
the Owner / Consultant at his discretion.
P a g e 33 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 34 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.3.2 All joints in reinforcement shall be lapped adequately to develop the full
strength of the reinforcement, unless reinforcement are as per provision of IS:
456 as per instruction of Owner /Consultant.
Following procedure shall be followed for welding of Tor steel reinforcement
bars:
i) Welding of Tor steel reinforcement bars shall be taken up only after
specific approval by Owner / Consultant.
ii) Lap welding with longitudinal beads shall only be adopted.
P a g e 35 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
iii) Thickness of weld bead should be 0.2 x diameter of bar and the length
of the longitudinal bead required shall be 10 x diameter of bar, however,
the maximum length of continuous bead shall be limited to 5 x diameter
of bar with intermediate gap. When welding is done on both sides bead
length shall be 5 x diameter of bar on each side.
iv) Stripper at closer spacing shall be provided in the lap welded joints as
directed by Owner / Consultant.
6.3.3 M.S. round bars shall be hooked at ends as specified. Ribbed Tor-steel shall
be bent at right angles at ends as indicated or directed.
6.4.1 The shuttering or form work shall conform to the shape, lines and dimension
as shown on the drawings and be so constructed as to remain sufficiently
rigid during placing and compacting of the concrete and shall be sufficiently
tight to prevent loss of liquid from the concrete. The surface that becomes
exposed on the removal of forms shall be examined by Owner / Consultant
or his authorised representative before any defects are made good. Work
that has sagged or bulged out or contains honey combing, shall be rejected.
All shuttering shall be plywood or steel shuttering.
6.4.2 The vendor shall be responsible for sufficiency and adequacy of all form
work. Centering and form work shall be approved by the Owner/Consultant,
before placing of reinforcement and concreting.
P a g e 36 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
4.
Removal of props under slab
i). Spanning up to 4.5 m
7 days.
ii). Spanning over 4.5 m
7 days.
5. Removal of props under beams and
arches.
i). Spanning up to 6.0 m 14 days.
ii). Spanning over 6.0 m 21 days.
For other types of cements, the striping time recommended for ordinary
Portland Cement may be suitably modified.
P a g e 37 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.5.2 Mortar
6.5.3 Cement and water shall conform to the requirements laid down for cement
concrete work.
6.5.4 Sand for masonry mortar shall be coarse sand conforming to IS: 2116.
Maximum quantities of clay, fine dust shall not be more than 5% by weight.
Organic impurities shall not exceed the limits laid down in IS: 2116.
6.5.5 Mixing of mortar shall be done a mechanical mixer. When quantity involved is
small, hand mixing may be permitted by the Owner / Consultant. Any mortar
remaining unused for more than 30 minutes after mixing shall be rejected.
6.5.8 Laying
All iron fixtures, pie spouts, hold fasts of doors and windows, which are
required to be built into the wall shall be embedded in cement concrete
blocks 1: 2: 4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm
P a g e 38 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.5.9 Curing
Brick work shall be protected from rain by suitable covering when the mortar
is green. Masonry work shall be kept constantly moist on all faces for a
minimum period of seven days.
6.5.10.1 Mortar
Cement and water shall confirm to the requirements laid down for cement
concrete work.
6.5.10.2 Sand for concrete block masonry mortars shall be coarse sand generally
conforming to IS: 2116. Maximum quantities of clay, fine dust, shall not be
more than 5% by weight. Organic impurities shall not exceed the limits laid
down in IS: 2116.
6.5.10.3 Mix of mortar for building concrete block shall be as specified in the item of
work.
6.5.10.4 Mixing of the mortar shall be done in a mechanical mixer. When quantity
involved is small hand mixing may be permitted by Owner / Consultant. Any
P a g e 39 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
mortar remaining unused for more than 30 minutes after mixing shall be
rejected.
6.5.13 Laying
All iron fixture, pipes spouts, hold fasts of doors and windows which are
required to be built into the wall shall be embedded in cement concrete blocks
1: 2: 4 mix ( 1 cement: 2 coarse sand : 4 graded stone aggregate 20 mm
nominal size ) 150 mm x 100 mm x 100 mm size unless otherwise indicated
in the item.
6.5.14 Curing
Concrete block masonry shall be protected from rain by suitable covering
when mortar is green. Masonry work shall be kept constantly moist on all
faces for minimum period of seven days.
6.6.1.1 The area to be paved shall be divided into suitable panels. Form work shall
be provided. The boarding / battens shall be fixed in position with their toe at
P a g e 40 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
proper level, giving slope where required. Alternatively base concrete may be
deposited in the whole area at a stretch.
6.6.1.2 Before placing the base concrete the sub-base shall be properly wetted and
rammed. The concrete of the specified mix shall then be deposited between
the forms where provided, thoroughly tamped and the surface finished level
with the top edge of the forms. The surface of base concrete shall be spread
uniformly. The surface shall be finished rough to provide adequate bond for
the topping. Two or three hours after concrete has been laid the surface shall
be brushed with wire brush to remove any scum or latinate and swept clean
so that coarse aggregate is exposed.
6.7 Plastering
6.7.1 Sand for plastering shall be 50% fine sand and 50% coarse sand from
approved sources.
P a g e 41 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 42 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.8.1.1 Where white wash is indicated, 3 coats of white wash shall be applied. The
surface shall present a smooth and uniform finish.
6.8.1.2 White wash shall be prepared from lime slaked at site and mixed and stirred
with 5 litres of water for 1 Kg. of unslaked lime to make a thin cream. The
cream shall be screened through a clean, coarse cloth and suitable adhesive
such as DDL or equivalent as per manufacturer specification shall be added.
About 1.3 Kg of sodium chloride in hot water shall also be added for every 10
Kg. Of lime for making the coat hard and rule resistant. Indigo shall also be
mixed @ 3 gm/Kg of lime. Each coat shall be allowed to dry before next coat
is applied. When dry the wash should show no sign of cracking, one coat
consists of application with brushes in horizontal stroke followed by vertical
stroke.
6.8.2.2 Only colour stainer of approved brand not affected by lime. Shall be added to
colour wash. Indigo (Neel) shall, however, not be added in colour wash.
6.8.2.3 The colour wash shall be applied as described for white wash. After the
surface has been prepared the first primary coat shall be of white wash.
Minimum two coats of colour wash shall then be applied. The entire surface
shall present a smooth and uniform finish of even tint or shade.
6.8.3 Distempering
6.8.3.1 Where distempering is required, two coats of distemper oil emulsion or dry
distemper over a priming coat as specified in the item shall be applied. Each
P a g e 43 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.8.3.2 The surface to be distempered shall be cleaned of dust, dirt, chalking and
other foreign matter. All cracks, holes and surface defects shall be repaired
with gypsum to give a smooth surface, and papared and wiped clean. The
surface shall then be rubbed down again with sand paper and made smooth.
The surface thus prepared shall be given a coat of alkali resistant priming
paint conforming to IS: 109, or any other primer as specified by the
manufacturer and allowed to dry at least for 48 hours.
6.8.3.3 Dry distemper shall be of approved make and shade conforming to IS : 427
and shall be prepared as per manufacturer’s specification. The surface to be
distempered shall be cleaned of dust, dirt, chalking and other foreign matter.
All cracks, holes and surface defects shall be repaired with gypsum to give a
smooth surface, and papered and wiped clean. The surface shall then be
rubbed down again with sand paper and made smooth. The surface thus
prepared shall be given a coat of alkali resistant, priming paint conforming to
IS: 109, or any other primer as specified by the manufacturer and allowed to
dry at least for 48 hours.
6.8.3.4 After the primer coat has dried for at least 48 hours, the surface shall be
lightly sand papered to make it smooth for receiving the distemper, taking
care not to rub cut the priming coat and then dusted off. Prepared distemper
shall then be applied with brushes in horizontal strokes followed immediately
by vertical ones which together constitute one coat.
P a g e 44 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.8.3.5 Subsequent coats shall be applied in the same way, with time intervals of at
least 24 hours between consecutive coats.
6.8.3.6 A uniform finished surface without patches, brush marks, or distemper drops
shall be obtained.
6.8.4.1 Cement paint shall comply with IS: 5410 specification for cement paint of
colour as required.
6.8.4.2 Where shown on drawings for external surfaces of sand faced plaster, or any
other surface, two coats of cement paint shall be applied of tint and shade as
approved by the Owner / Consultant.
6.8.4.3 On external plastered surfaces, sand faced or plain plastered and concrete
surfaces, cement paint shall be vigorously scrubbed on to work the paint into
the voids and provide a continuous paint film free from pin holes and other
openings. Curing shall be done between the coats and for at least 2 days
following the final coat.
P a g e 45 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.9.2 Acid Proof Brick Lining: 65 mm thick acid resisting bricks may be used if
required.
P a g e 46 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
6.10.2 High Impact PVC sheet should have chemical resistance to corrosive
chemical environment like acids, alkalis, fluorine gas, SO3 gas, SO2 gas,
rock phosphate dust, sulphur dust etc.
6.10.3 High Impact PVC sheet should have resistance to high humid coastal
environment.
6.10.4 High Impact PVC sheet should be able to sustain the wind load of 110
kg/cm2.
6.10.5 High Impact PVC sheet should have low thermal insulation property.
6.10.6 High Impact PVC sheet should have UV resistance for at least 10 years.
6.10.7 High Impact PVC sheet should be Fire retardant and meets the highest
standards.
6.10.8 Material shall be supplied in Beige Color.
6.10.9 10 years warranty on the product & relevant certificate from the OEM shall
be obtained & submitted to IFFCO
6.10.10 The fixing screws (SS 410) & washers (SS 304) shall be supplied along with
washer (EPDM rubber moulded).
6.10.11 MOC of fixing screw with washer shall be SS410 of Hilti make. For any other
make screws, except Hilti make, prior approval have to be taken from
IFFCO.
6.10.12 IFFCO shall check the MOC of supplied screws by Alloy Analyser & the
rejected materials will be replaced by the vendor free of cost within stipulated
time frame.
6.10.13 Size of sheets to be fixing as per the site requirement, no excess over
lapping should be allowed or the cutting of sheets to bring as site
requirement not allowed.
6.10.14 Utmost safety has to be adhered during installation of the PALRUF sheeting
job. Cat Ladder or Roof Ladder should be made use of while laying sheets or
working on the roof, to ensure safety to the workmen. Further, life line and
safety belts shall be used while working on the roof. Cat ladders shall cover
at least three spans between purling and cross pieces shall not project at the
P a g e 47 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
edges of the purlin. Walking or working directly on the sheets may cause
cracks and sheet failure, leading to serious accidents which shall be strictly
adhered to. It shall be the responsibility of party to follow all safety norms and
all safety equipment required for carrying out the work and will be the full
responsibility of the party.
6.10.15 The Contractor shall deploy skilled and well trained workforce / labours with
supervisor(s) who have sufficient experience in sheeting work. They have to
obtain necessary height pass before undergoing a technical training
regarding for fixing of AC sheets. Only certified and qualified persons having
height pass will be allowed for Gate Entry. Hence, any violation in fixing of
sheets thereafter shall be levied on penalty as per direction of IFFCO.
P a g e 48 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.2.2 Dead, live, wind, earthquake, thermal & other relevant load calculations shall
be considered for design of steel structural.
7.2.3 Detailed design calculations for each item with design assumptions if any,
design parameters, loads/forces and references to section of the
Code/Standard on which the designs are based shall be submitted for review
of client or vetting by client’s appointed consultancy/design organisation .
7.2.4 Structural steel materials shall conform to IS 2062 with a minimum yield
strength of 36000 psi, and designed in accordance with IS.
7.2.6 Where required, for safety, structural steel support columns shall be fire
proofed. The fire retardant coating/insulation shall be suitable for one hour
rating.
P a g e 49 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.2.8 Design drawings for each structural building are required. The design
drawings shall consist of plans, elevations, erections and details which define
completely the building designs, forces and member sizes/weights to permit
a structural steel fabricator to calculate design stresses and detail, supply
and fabricate the building structural steel requirements.
7.2.12 The steel section sizes shall be as mentioned in design specification. The
bolts to be used for connection should be of class 4.6 or 8.8.
Manufacturers test certificate shall be submitted to the OWNER, when
asked for. For bolted joints, shanks and threaded bolts should be used
and it should be ensured that to achieve adequate shearing and bearing
values, the threaded length do not encroach the thickness of
connected members of dimension beyond the following limit:
7.3 Fabrication
7.3.1 Fabrication of steel structure shall be carried out in conformity with the best
modern practices and with due regard to speed with economy in fabrication
and erection and shall conform to IS: 800. All members shall be so fabricated
as to assemble the members accurately on site and erect them in correct
positions. Before despatch to site the components shall be assembled at
P a g e 50 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
shop and any defect found shall be rectified. All members shall be free from
kind, twist, buckle, bend, open joints etc., and shall be rectified before
erecting in position. Failure in this respect will subject the defective members
to rejection.
7.3.2 Fabrication and erection drawings shall be prepared by the Contractor on the
basis of design drawings to be issued to the Contractor in stages. These
drawings shall be prepared by the Contractor or by an agency approved by
the Owner / Consultant.
7.3.7 The Contractor shall however ensure accuracy of the following and shall be
solely responsible for the same.
i) Provision for erection and erection clearance.
ii) Marking of members.
iii) Cut length of members.
iv) Matching of joints and holes.
v) Provision kept in the members for other inter connected members.
vi) Bill of Materials.
7.3.8 Connections, splices and other details not shown on the design drawings
shall
be suitably designed and shown on the fabrication drawings based on good
Engineering practice, developing full strength of member.
7.3.9 Contractor shall incorporate all the revisions in his fabrication drawings
resulting from revision in design drawings if needed during the course of
execution of work at no extra cost.
7.3.10 Contractor shall supply three (3) prints of each fabrication drawing submitted
for checking to Owner /Consultant. After approval of fabrication drawings,
Contractor shall supply six (6) prints and soft copies of each approved
fabrication drawing to Owner / Consultant. The rates quoted by the
Contractor shall include the same.
P a g e 52 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.3.11 Every portion work shall have its erection mark or number stencilled on the
member for guidance in erection and bear all necessary marks of erections
as directed by the Owner / Consultant.
7.3.12 No part of the work is to be oiled, painted (except contact surfaces ) packed,
bundled, crated or despatched until it has been finally inspected and
approved by the Owner / Consultant or his authorised representative. The
whole steel work before being despatched from the Contractor’s shop shall be
dry and after being thoroughly cleaned from dust, mills scale, rust etc., and
shall be given two coats of primer and one coat of final paint as per painting
specification attached in this enquiry. Unless otherwise specified, all surfaces
inaccessible after welding shall be given two coats of primer and two coats of
paints as per painting specification attached in this enquiry.
7.3.13 The Owner / Consultant or his authorised representative shall have free
access at all reasonable time to all places where the work is being carried
out, and shall be provided by the Contractor at his own expenses all
necessary facilities for inspection during fabrication and erection. The Owner /
Consultant or his authorised representative shall be at liberty to reject the
work in whole or in part if the workmanship or materials do not conform to the
terms of the specifications mentioned herein. The Contractor shall remove,
replace or alter any part of the work as ordered by the Owner / Consultant or
his authorised representative.
7.4 WELDING
7.4.1 Welding shall be adopted in most of the cases for fabrication of steel
structure. Welding work shall be carried out as shown in relevant drawings as
per IS-816 or as required and approved by the Owner /Consultant. Welding
of joints shall be so arranged that the resulting tensile and compressive
stresses produced by each part of weld tend to balance each other.
P a g e 53 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.4.2 The step back method of welding shall be adopted for continuous runs.
Members which offer greater resistance to compression shall be welded first.
The work shall be securely held in position by means of tack weld, clamps or
jig before commencing of welding work so as to prevent relative movement
due to distortion or other cause. All welds with blow holes, slag-intrusion and
other defects must be removed from each run before another run is super
imposed and also from the final run. Any defects in the work shall be rectified
by the Contractor at his own expense. Bends, twists or distortion caused in
any member due to faulty workmanship and method adopted during welding or
in transit will be rejected and will have to be replaced / rectified by the
Contractor at his own expense. According to the size of electrodes used, the
Contractor is expected to adjust the current rating in the welding machine.
7.4.3 The Owner /Consultant reserves the right to have test done at any time for any
welding and the cost of the test shall be borne by the Contractor.
7.4.4 Wherever continuous plates are used in built up member such as girders,
columns, etc., the continuity of such plates shall be first ensured by full
strength butt joints before welding such plates with the main member to form
part of the built up member.
7.4.5 All connection / joints made in shop shall wherever possible be welded
connections and connections / joints made at site shall be bolted connections
/site welded connections. Continuous welding shall be done for all box
members even if it is not required from design point of view.
7.4.6 Electrodes used for welding shall comply with IS: 814 or IS: 815 or any
specification provided to the Contractor from time to time. No electrodes
remaining in open containers for more than 72 hours shall be used.
P a g e 54 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.4.7 No welder shall be employed to carry out welding in any position except those
who are fully qualified to weld in that position as per IS: 7318, Part-1
Qualifying tests for metal arc welders. Welders employed shall be required
both before commencing work and at intervals during the progress of work to
make test pieces as laid down in IS: 817 and IS: 7318, Part-1 for the purpose
of grading of welders and according to the said grading, welders will be
employed on jobs. Welders are to be got approved by Owner / Consultant
before engaging on work.
7.5.1 The Contractor shall be responsible for the suitability, safety and capabilities of
all plant and equipment used for erection.
7.5.3 The Contractor shall erect the structural steel members in position to
dimension and level, as in relevant drawings and shall take care to see that
component parts are not interchanged. Girders, stanchions etc., must rest
fairly on their beds and will not be taken as erected until completely plumbed,
aligned levelled, bolted or welded and strengthened, in every respect. The
camber, if any, is to be maintained as shown in relevant drawings.
7.5.4 Particular care should be taken to ensure free expansion and contraction
wherever provided in the relevant design / drawings or so directed on site.
P a g e 55 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.5.5 While erecting, the holes in different component parts of structure should be
made concentric with the use of drifts before any service bolts are fitted. No
drifting shall be allowed except for bringing together several parts forming a
member but the drifts must not be driven with such force as to disturb or
damage the metal above the holes. Hammering of bolts to make holes
concentric shall in no case be allowed. No nuts should be allowed to become
loose and no unfilled bolt holes are to be left in any part of the structure unless
otherwise specified in the relevant drawings. Welding should be adopted
wherever specified in the drawings. Wooden rams or mallets shall be used in
forcing members to position, in order to protect metal from injury or shocks.
Chipped edges shall be finished off smooth and all concave surface rounded
off.
7.5.6 All erection tools and plants viz. Derricks, Cranes etc., will have to be provided
by the Contractor as required in the erection work. All erection devices must
be removed after the work is over in such a way that no damage is done to the
erected structures. Any damage, in this respect must be rectified by the
Contractor at his own cost.
7.5.7 The maximum tolerance for line and level of the steel work shall be ± 3.0 mm
on any part of the structure. The structure shall not be out of plumb more than
3.5 mm on each 10.0 m. section of height and not more than 7.0 mm per 30.0
m section. These tolerances shall apply to all parts of the structure unless
mentioned in the drawings issued for erection purposes.
P a g e 56 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
ii) All pieces shall be stamped on at least two sides with erection marks
as per fabrication drawings to facilitate identification on receipt and
assembly.
All parts pertaining to one assembly shall be transported in the same lot. All
materials shall be transported in sequence of erection. Fabricated materials
transported not in sequence of erection shall not be paid until erection reaches
that stage.
This section covers the design, engineering, supply, fabrication & erection of
miscellaneous steel structures like working platforms, walkways, support
structures for various equipment & hoists etc.
The Design drawings shall consist of plans, elevations, sections and details
which define completely the platforms/attachments including, but not limited to,
dimensions loads/forces, member sizes/weights, handrail, ladders, stairs, type
of flooring, brackets to permit a structural steel fabricator for detailing and
preparation of shop drawings, supply and fabricate the steel requirements for
the platforms/attachments.
7.8.1 All flooring for working platforms, walkways shall be covered with standard GI
grating. Bearing Bar thickness and depth shall be suitable for its intended
service and loads with acceptable deflection. The minimum size for frame bars /
bearing bar shall be 32 mm x 6 mm. and cross bar shall be 8 mm square
twisted. Pitch for bearing bar & cross bar shall be 35 mm & 75 mm respectively.
Grating shall be supplied galvanised. Thickness of Zinc coating as per IS 4759.
P a g e 57 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
7.8.2 Minimum clear width of stairs should be 1000 mm and maximum slope of stair
should not exceed 41 degree. Treads should be minimum 250 mm and made
of MS galvanized grating with suitable antiskid nosing.Stairs shall be in
accordance with IS.
7.8.3 Ladders may be provided to platforms which do not require frequent access by
the operating personnel as per OSHAS guideline (1910.27). Safety cages
should be provided as per safety norms.
7.8.4 Handrails shall be provided around the edge of platforms, stairs and places
where there is a difference in adjacent levels greater than 0.5m.Handrails
around platforms shall be of the two rail type with the top rail set 1100 mm
above finished floor level. Dismountable handrails, shall be provided around the
perimeter of hoist walls. Loading for handrail design shall be in accordance with
IS 4912.Spacing of handrail standards shall be commensurate with the design
loadings quoted above. Corner stanchions shall be located within 300mm of the
corner. MOC of Handrails pipes, Kick flats shall be ASTM A240 TP 304 .Kick
flats shall be not less than 100mm high above finished floor level. Thickness of
kick flats/toe guards shall be 4 mm. Kick flats shall be provided along all open
edges of platforms, walkways, landings and floors except at access points to
stairs and ladders.
P a g e 58 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
8.1 Scope
8.1.1 The contractor shall arrange procurement, receipt, storage in his own safe
custody along with handling and transportation of all materials to be used for
painting work in a safe manner.
8.1.2 The contractor shall arrange at his own cost & maintain against weather, light
and fireproof storage facility for storage of all painting materials.
8.1.3 All required consumable paint material, shall be provided by the contractor.
Painting-brushes, wire-brushes, cotton waste, emery papers, abrasives for blast
cleaning purpose of required size, etc. shall also be provided by the contractor.
The contractor has to submit the challan of the paint manufacturer along with
manufacturer test certificates duly signed by the paint manufacturer for each lot
of paint purchased from the manufacturer/trader.
8.1.4 Contractor shall make their own arrangement for preparation of scaffolding /
shuttering, Platforms etc, for safe and satisfactory completion of job. Above three
meter safety net must be used for painting jobs, Rigid steel cup lock type
scaffolding along with ladder & hand railing shall be use for scaffolding. MS cup
lock scaffolding pipes is in the scope of contractor.
8.1.5 It is the responsibility of the contractor to train the paint application crew through
the experts/certified trainer (NACE Level) of respective paint manufacturers i.e.
how to apply their supplied paints throughout the contract period including
surface preparation. The trained manpower has to be certified by the paint
manufacturers & the expenses of training have to be bear by the contractors.
8.1.6 The contractor shall not alter any of the specifications except as directed in
writing by the Owner, but the owner shall have full right to alter, amend,
add/omit/vary any of the specifications and the contractor shall carry out such
variations
P a g e 59 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
8.1.7 All empty paint drums, caps. used brushes & other debris shall be collected on
daily basis and shall be placed on a designated area jointly identified by the
owner & contractor.
8.1.8 On periodical basis, in every two months all the collected drums shall be taken
from IFFCO plant.
8.1.9 The out gate pass of the empty drums shall be submitted along with the RA bill/
Final bill. No RA Bill and Final Bill will be accepted until unless empty paint drums
taken out from the IFFCO against the work Order.
8.2.0 All relevant safety gadgets/equipment like pressure gauges in air compressor &
blasting hopper, dead-man handle for safety of blaster etc. required for blasting &
painting job as per standard shall be maintained by the contractor at designated
area for painting job. Apart from the above all PPE like safety Helmets, Goggles,
Shoes, Hand Gloves, nose masks, required for the application crew shall be in
the scope of contractor.
P a g e 60 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
For the removal of loosely adhering mill scale, paint and dust Power wire brushes,
needle guns grinders and disc sanders are generally used. Care should be taken,
particularly when using power wire brushes,
Not to polish the metal surface. It should be to ST-3 grade of Swedish Standard or
ISO: 8501:1988. Power tool cleaning shall be done as per the site condition and
Instruction of IFFCO.
Color : Red
P a g e 61 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
A two pack glossy Finish paint (Colour shade shall be specified by IFFCO
according to the area to be painted)
8.4 Application
8.4.1 The interval between surface preparation and application of first coat of primer shall
be as short as practicable and in no case more than 4 hrs. Fertilizer/dust
accumulated must be completely removed prior to application of primer/paint.
8.4.2 Preparation of paint mixture, time gap between successive coating, period between
paint mixing and application of paint should be strictly as per recommendation of
paint manufacturers.
P a g e 62 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
8.4.3 Coating Inspection report shall be reviewed by NACE Level – 2 certified painting
inspector.
8.5.1 SYSTEM S1: Blast cleaning SA 2½ quality + 1 coat of epoxy primer + 1 coat of
epoxy MIO + 1 coats of epoxy finish paint (Color shade shall be specified by IFFCO
at the time of painting according to the area to be painted)
8.5.2 SYSTEM S2: Surface Preparation to power tool cleaning + Water washing followed
by solvent swab + 1 coat of surface tolerant aluminum pigmented epoxy primer + 1
coat of HB modified epoxy + 1 coats of finish paint (Color shade shall be specified
by IFFCO at the time of painting according to the area to be painted).
8.5.3 Painting will be carried out according to painting systems given above. The paints
used for above painting system should be of same as specified by manufacturer.
8.5.4 Inspection
SL STAGE INSPECTION
Prior to
1 1. Material 2. Dilution 3. Surface Preparation
Painting
After
1. DFT measurement 2. Finish Colour 3. Appearance 4.
3 completion
Identification mark
of Painting
P a g e 63 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
8.5.5 Guarantee
Guarantee of minimum 10 Year shall be provided on painting by successful Vendor.
Mode of guarantee shall be discussed & mutually agreed at the time of technical
discussion.
IS: 1477 Part 1 : Code of practice for painting of ferrous metal in buildings
Pre-treatment.
IS: 1477 Part 2 : Code of practice of painting of ferrous metal in buildings
painting.
IS: 2379 : Color code for pipe lines color for ready mixed paints.
IS: 5 : Color for ready mixed paint
P a g e 64 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
9.1.1 Cleaning & removal of existing facilities if any, at proposed location, shall be done
by IFFCO. However cleaning of any debris left out, levelling of land, cutting of
existing plantations and construction of any temporary roads to facilitate the
erection activities shall be considered in the vendor’s scope.
P a g e 65 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
9.1.6 The bidders are advised to visit the proposed location at IFFCO, Paradeep to
access the exact requirements, conditions of existing system to hook up &
discharge and the site layout before bidding.
After visiting the site & accessing the actual requirement, the bidders shall prepare
a comprehensive list of items / equipment needed for supply, modifications required
in the existing facilities and furnish such list along with the offer.
However the supply & installation of the equipment shall not be limited to the above
only and the vendor has to provide all the equipment/ items required for satisfactory
& smooth commissioning of the system (with designed load condition) within their
quoted price.
ii) Similarly existing 104-A conveyor is the endmost conveyor which receives
materials from Rock Silo-C through underground reclaiming conveyor 103-
C.To transfer the materials from new Rock Silo-D to PAP, discharge of
material shall be done to existing conveyor 104-A through new reclaiming
conveyor 103-D & new transfer conveyor 104-B.For the above arrangement,
modification may be required at existing TP-1A.
P a g e 66 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
However Bidder is free to design a better & trouble free conveying system against
the proposed scheme to avoid any major modification if any.
P a g e 67 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
9.4.2.1Fluid Coupling
Scoop type fluid coupling with actuator shall be supplied by the contractor. The fluid
coupling shall be flame proof. It must be fitted with double oil seal at the output
shaft. The coupling as well as its individual components shall be dynamically
P a g e 68 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
balanced. The coupling shall be tested for pressure tightness against leakage and
at least 125% of the rated speed.
P a g e 69 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
ii) Pulleys shall be of welded construction, continuous rim and two end disc
type. Pulley hub arrangement to be of ring feeder type for easy removal of
shaft (for all pulleys).
iii) Pulleys shall be statically balanced and concentric about the shafts. The out
of roundness shall not exceed 0.5 mm for pulley diameter upto 400 mm and
1.0 mm for pulley diameter above 400 mm.
iv) Drive pulley shall have 20 mm thick rubber lagging with Herringbone groove.
v) Rubber lined/ lagging of all the pulleys should be hot vulcanized.
vi) Tail pulley, snub pulley, bend pulley and take up pulley shall have 12mm
thick smooth neoprene lagging with Duero meter hardness of 60 to 70 shore
“A” scale.
vii) Pulley faces shall be at least 200 mm greater than the belt width.
viii) Head and Tail pulley shall be flat faced.
ix) Shaft deflection shall be limited to 0.066% of bearing centers. All shafts shall
be provided with accurately machined key seats.
x) Shaft ends shall be flush with bearing edge, unless the extension is required
for mounting components.
xi) Minimum shaft diameter shall be 100 mm for all conveyor pulleys. Shaft
diameter calculation shall be submitted to IFFCO for their review before
manufacturing.
xii) The pulley rim thickness shall not be less than 10 mm.
P a g e 70 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
9.8 Idlers
i) All conveyor idlers, carrying and return shall be constructed of constructed of
ERW tubes as per IS: 9295, GR-YST-210, having a minimum shell thickness of
4.85 mm (after machining) for roll diameter up to 139.7 mm. Shell thickness
shall be minimum 5.4 mm (after machining) for roll diameter above 139.7 mm.
ii) For all idlers material for the shaft shall be 40 C8 Black bar confirming to
IS: 1570.
iii) Tube diameter shall be 152.4 mm (min) and the shaft diameter shall be 30 mm
(min) for carrying idlers.
iv) The carrying idlers shall be 3 roll 45o Garland type. The carrying idlers to be
provided at 1000 mm (max) pitch.
v) Transition carrying idlers shall be 3 roll 35o, 25o, 10o garland type to help
carrying side of belt to flatten out before it goes to the terminal pulley at Head
end and tail end.
vi) Return idlers shall be of 2 roll garland type at 10o and the diameter of the tube
and idler shaft shall be 139.7 mm (min) and 30 mm (min) respectively. Return
idlers to be provided @ 3000 mm (max) pitch.
vii) The impact idlers shall be 3 roll 45o Garland type and the idler shaft diameter
shall be 35 mm (min). Impact idlers to be provided @ 500 mm (max) pitch.
viii) For lubrication, idlers shall be grease packed and sealed for life.
ix) All idler bearings shall be sealed and lubricated for L-10 life equal to 60,000hrs.
Make of idler bearing shall be SKF or FAG only. Bearing for idler having shaft
dia of 30 mm shall of series 6306 and for idlers having shaft dia. of 35 mm shall
be of 6307 series.
P a g e 71 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
x) Idlers are provided with double labyrinth sealing, back seal, weather seal and
dust seal cap and internal construction as per standard.
xi) Idlers shall be provided with two coats of Red Oxide primer paints and one coat
of polyurethane finish paint to protect from corrosion at sea shore area.
xii) Idlers shall be heavy duty in construction suitable for handling the rock
phosphate handling @ 3000TPH.
9.10 Scrapper
The conveyor shall be provided with:
i) External Scrapper: Spring loaded external scrapper shall be provided at the
discharge of the tripper. The scrapper shall be provided with PU blades with
stainless steel carrier tubes.
ii) Internal scrapper: Self adjusting V-plough internal scrapper with PU blades
shall be installed to protect the take up and tail pulley from material build up.
iii) Rotary Scraper: A rotary type scrapper shall be installed at the head pulley of
the conveyor.
P a g e 72 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
MOC of Cable Reeling Drum, Enclosures of Slip Ring Assembly, CRD Control
panel, Tripper control panel shall be SS-304 as the atmosphere is very corrosive in
nature.
Telescopic chute with radar type heap sensor in both the chutes of tripper shall be
considered to minimise the generation of dust during unloading of rock phosphate
from the unloading conveyor through travelling tripper. There should be automatic
retraction of both telescopic chute when the chute closures to the heap from a pre-
set distance. For heap level control in the Silo, installation of Radar Level
Transmitters ( preferable Make – VEGA, Model – Vegapuls69 ) besides both the
discharge chutes on either side of Tripper is to be included in scope of supply. In
addition to the Radar Level transmitters, a Level Controller with local display should
be mounted besides the Tripper Control Panel along with an electrically operated
Hooter. The Controller shall detect high level on the basis of signal received from
the Radar Transmitters and energise the Hooter to alert the Tripper Operator.
P a g e 73 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
9.15 Fasteners
All bolt, nut and screw shall be provided with metric screw threads to IS-1362. The
pitch of the threads shall generally be coarse series. All the bolts and nuts shall be
provided with spring washers. Fasteners for fixing the drive unit and all the pulleys
shall confirm to ASTM A 193/194 Gr. B8. All the other fasteners to be used in the
technological structure shall confirm to IS-1367 (part-III). For connecting idlers and
conveyor stringer fasteners used shall be of HT grade with lock nut arrangement.
P a g e 74 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
10.1 Scope
Electrical system shall be comprising of, but not limited to following, for smooth,
safe & trouble free operation of the complete Silo.
10.2 Construction power for the project is made available by IFFCO. Contractor shall
make its own provision for connecting two nos. feeders from the nearby substation
at 415 volts & it is to be connected to Main Power distribution Board of contractor
P a g e 75 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
10.3 Design of the system shall take account of the climatic conditions as mentioned in
the site data and the Project environment is chemical, marine and dusty.
Power supply to Tripper Control panel, Scoop coupling control panel & Radiator for
R-15 conveyor, motorised diverter gate at TP 12, LSDB for illumination in R-10B &
R-15 conveyor galleries, power & welding socket outlets in conveyor galleries shall
be considered from Utility substation. Approx. distance of 750 meter shall be
considered for quote purpose
Frequency 50 Hz ± 5%
ix) All external hardware shall be of stainless steel up to 8mm dia. and those more
than 8mm dia. shall be of MS-cadmium plated or zinc passivated.
10.7 Motors
i) Motors shall be supplied as per the engineering standard for Induction motor
(IS: 325).
ii) The motor shall be energy efficient type having minimum efficiency class of
IE3 as per IS: 12615 – 2011.
iii) Duty cycle of the motor shall match with the driven machine requirement. The
margin between the installed power and absorbed power shall be as
recommended by the driven machine supplier but shall not be less than the
following:
Up to 22 KW 125
22 KW to 55 KW 115
Above 55 KW 110
In case of motor rated for 6.6 KV, the terminal box shall be suitably designed for
proper termination of XLPE insulated cables through heat shrinkable end
termination kit. Identical terminal box shall be provided on both side of motor so
that HT cable can be terminated on either side of motor as per site requirement.
10.8 Tripper Control Panel, CRD control panel, Local control panel for Scooping
Coupling Actuator & Radiator and Control Panel for Safety Switches:
P a g e 78 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) All control panels shall be of single front having bottom cable entry. All
DOL feeder and SFU feeders shall be fixed type.
ii) Enclosure shall be of IP 65 & suitable as per Area Classification.
iii) Control Panel incoming feeder shall be provided with heavy duty switch
with proper protection system, current transformers, ammeter and
voltmeter with selector switches, LED indication lamps. Outgoing motor
feeders shall be provided with switch fuse unit, HRC fuse, CT, ammeter,
contactor, thermal overload relay etc.
iv) Minimum 1 number spare feeder for each type and rating of motor feeder
shall be provided in the panel.
v) In Tripper control panel there shall be interlocking between CRD motor &
Tripper travel motor such that tripper travel motor stops whenever CRD
cable is tight to prevent cable damage. Also tripper movement shall be
restricted at both end by 2 nos. of end limit switch to be provided at each
end.
vi) In scooping & radiator control panel there shall be an interlocking for
automatic scooping out of fluid coupling whenever the oil temperature in
circulating line is more than the specified designed limit.
vii) Tripper control panel shall be wired to a local control station suitable for
mounting on tripper car for controlling tripper movement while standing
outside of tripper trolley.
viii) The compartment modules shall be liberally designed for easy operation
and maintenance.
ix) Make, type & rating of all components of control panel shall be as per
make list attached.
x) GA, power & control schematic drawings of control panels shall be
submitted to IFFCO approval. Manufacturing clearance shall be given
only after approval of IFFCO.
P a g e 79 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 80 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
ix) All LCS shall be of minimum two gland hole of 25 mm. dia.for control cable
entry & shall be supplied with required double compression stainless steel
cable glands.
x) All Local Control Stations shall have weather proof, dust & vermin proof IP-
65 enclosure and be suitable for outdoor installation. Spring loaded
transparent flapper shall be provided on LCS to protect the LCS from water,
dust & solution. A rain hood shall be offered as an additional protection.
Rain hood shall be of the same material as of the main enclosure. The
enclosure shall be suitable for mounting on wall or on steel structure. 4 Nos.
holes suitable for 12 mm bolts shall be provided outside the enclosure for
fixing the control stations.
i) Pull Chord Switch (IP 65 Protection): The pull cord switches shall be
installed on both sides of the conveyor at an interval of 25 meters with a
minimum of one for each conveyor for tripping the conveyor under
emergency. The switch shall be of heavy duty, suitable for 110 V AC control
supply. It shall be totally enclosed, dust & vermin proof in cast metal
enclosure with trip and reset levers shall be mounted along the walkway
side/s. The pull cord switch shall be operated through PVC coated stranded
steel wire rope running along the entire length on both side of each
conveyor. The trip lever shall have arrangement for fastening the pull cord by
securing through two opening in the lever head. In case of emergency
pulling of the rope shall trip the switch and stop the conveyor. When the
cause of emergency has been cleared the reset lever on the limit switch
shall be pressed to bring the trip lever to normal position. All pull chord
switches shall be grouped zone wise & connections done accordingly.
Indications as stated in this specification shall be taken on PLC/safety switch
control panel. Adequate length of pull cord rope shall be provided.
P a g e 81 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
Arrangement of Pull chord rope shall be such that it can be easily accessible
for operation.
ii) Belt Sway Switch (IP 65 Protection): The belt sway switch shall be suitable
for 110V AC, control supply. The switches shall be totally enclosed dust and
vermin proof in cast metal enclosure shall be installed as per this
specification. The limit switch lever arm shall be so connected that any
harmful deflection of belt from its design path shall actuate the lever and thus
trip the contacts inside the limit switch. Consequently the conveyor stops.
The lever mechanism shall be spring returned type and shall return to
normal position when the belt has been aligned. Indications as stated in this
specification shall be taken on Safety switch control panel. These shall be
mounted on both sides of conveyor at an interval of 50 meters or minimum
one pair for shorter length of conveyor.
iii) Zero speed switch (IP 65 Protection): The zero speed switches shall be
suitable for 110V AC/240 V AC control supply. The zero speed switches
shall be electronic type contact less, proximity switch comprising of sensing
element and relay unit having 2NO+2NC contact. The sensing element shall
be plastic moulded. Zero speed switches shall be mounted locally. 1 No.
Zero speed switch per conveyor and other equipment, as required, shall be
provided. In case speed falls down to abnormally low value, the switch
contact change over takes place and thus stops the equipment. Indications
as stated in this specification shall be taken on PLC/safety switch control
panel.
iv) Limit switches (IP 65 Protection): The switch shall be of heavy duty & shall
be totally enclosed dust and vermin proof in cast metal enclosure. The limit
switch type shall be selected to meet the specific requirement for different
position. There shall be 2NO+2NC contact wired up to terminal points for
P a g e 82 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
external connection. The lever mechanism shall be spring returned type and
shall return to normal position whenever the fault clears.
P a g e 83 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
vi) All jointing surfaces shall be smoothly machines and of shall be of sufficient
width to prevent ingress of dust. Further the cover shall be provided with
continuous gaskets made of neoprene to prevent ingress of dust.
vii) The Air break switches shall be quick make, quick break rotary type and of
utilization category AC-23.Switches shall be hand operated from outside the
cover. The switch handle shall remain fixed to the front cover while removing
the front cover.
viii) The sockets shall be provided with link type HRC fuses. The fuses shall be
capable of withstanding a short circuit current of 50 KA and shall be delayed
action type. These shall be mounted on a shrouded base.
ix) The socket outlet shall be located in the lower part of the enclosure and shall
be provided with a threaded aluminium/FRP cover attached to the body with
SS chain, to protect the socket after extraction of the plug. Spring loaded
automatic shutter shall not be acceptable.
x) The plugs shall be so constructed that these can be easily fitted in to the
socket outlets and shall be provided with knurled knob arrangement for
screwing on the body of the socket so that it can be securely fixed on the top.
The plug base and cover shall be firmly secured to each other and shall be
sufficiently robust in construction to withstand normal usage. The plug and
socket contacts shall be self-aligning type with best electrical continuity.
xi) The plug shall be provided with cable entry suitable for receiving TRS flexible
heavy duty copper conductor cable of specified size. The arrangement shall
be such that the conductors are relieved from strain including twisting where
they are connected to the terminals and that the outer surface of the cable at
the place of entry is not damaged.
xii) The switch shall be provided with 2 nos. single compression type cast
aluminium cable glands one on either side or both on the top. The external
bolts and nuts shall be of stainless steel.
P a g e 84 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
15 A & 63 A dust proof & weather proof heavy duty FRP junction boxes suitable for
mounting on structure or wall, complete with mounting accessories, required
numbers of cable glands and terminals of suitable sizes shall be used for looping
the cables wherever required. All unused cable entries shall be sealed with
threaded plug which shall be fitted with endless neoprene rubber gasket.
10.13 Cable
i) All Power cables shall be considered as per IS 7098 & all control cables shall
be as per
ii) All cables in addition shall be fire resistant low smoke (FRLS) type.
iii) The cable sizes shall be selected in accordance with current rating based on
load Current, site ambient condition, method of laying and the no. of cables
to be laid together.
iv) Permissible voltage drops as specified below
High voltage cables for general distribution - 1%
with max. Operating current
Medium voltage cables for distribution with - 1%
maximum operating current
Motor feeding cables referred to the full load current - 5%
Motor feeding cables referred to the starting current - 10%
Lighting cables
Main lighting distribution board to lighting - 2.5%
Sub distribution board / junction box
Lighting sub-distribution board / junction box - 2.5%
v) The minimum size of power cables shall be 16 sq. mm (Al) and 2.5 Sq. mm
(Cu).
vi) The control cables shall be 2.5 Sq. mm (Cu). However, wiring in the
panel/switch boards shall be by means of 1.5 sq. mm Cu cables except for
C.T. wiring which shall be 2.5 sq. mm. The voltage grade of cables for 6.6
kV system shall be 6.6kV (UE) /11 KV(E) & the voltage grade of cables for
415 V/220V system shall 1.1 kV.
P a g e 85 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
vii) Approximate length of power, control & lighting cable required for all
electrical equipment shall be finalised after joint survey & finalisation of
cable tray route layout drawing. However, for the estimation & bidding
purpose vendor may take the approximate distance mentioned in clause no.
10.1 with suitable margin. Accordingly contractor shall workout the actual
cable requirement.
viii) All HT & LT power and control cables from electrical field equipment to
switchgear & other control panel shall be supplied and laid by the contractor.
Terminations at switchgear end as well as at the equipment end shall be
done by contractor under supervision of owner’s representative. Termination
of HT motor at both ends includes supply of Raychem make heat shrinkable
end termination kits & for LT motors required size double compression SS
cable glands, lugs.
ix) All cables shall be used without any intermediate joints.
x) All cables shall have their Run Nos. marked close to their termination as well
as intermediate positions for proper identification.
P a g e 86 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
v) Instrument cables shall be run on racks dedicated to that duty and have
physical separation of a minimum of 0.5 metre from all other cabling. These
racks may also be used for telephone, communication and Public Address (PA)
system cabling.
vi) Provision for 25 % extra space shall be kept in cable racks for future use.
vii) GI Cable trays shall be earthed at regular intervals not more than 25M apart.
viii) Fabrication & installation of proper cable support system along with the supply
& laying of required GI angle cable trays shall be in the scope of the vendor.
ix) For the cable trays and supports, supplied and installed by the contractor,
payment shall be made to the contractor on the basis of unit rates indicated by
the vendor in their billing schedule.
P a g e 87 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
vi) Circuits controlling outdoor lighting and indoor lighting shall be separate.
Outdoor lighting shall be automatically controlled through astronomical timer
with provision for bypass manual control.
vii) Lighting layout drawings shall be submitted by party for approval.
viii) Light fixtures shall be installed at proper height for ease of maintenance.
i) Each LSDB shall have 1 No. incomer with 63A SFU and each outlets with 16 A
double pole MCB. All MCBs shall be of 10KA breaking capacity conforming to
IS: 8828.
ii) The enclosure for LSDB shall be made of high quality FRP and shall be suitable
for area mentioned in clause no. 2. Canopy for rain protection shall be
considered. The enclosure shall be suitable for mounting on wall or on steel
structure. 4 nos. holes suitable for 12mm bolts shall be provided outside the
enclosure for fixing the LSDB.
iii) The LSDB shall have all cable entries from the bottom only with heavy duty
double compression type SS cable glands suitable for 1.1 KV HRPVC-A-FRLS
PVC (ST2 type) outer sheathed cables. Incoming cable size shall be 3.5x50 sq.
mm armoured aluminium cable and outgoing cable size shall be 3x2.5 sq. mm.
armoured copper cable. Gland plate for cable glanding shall be of SS-304
detachable type.
iv) Three phase and neutral bus bar system of adequate size shall be provided to
which all outgoing and incoming MCBs shall be connected.
v) Individual earth terminals shall be provided for the earth conductor of the
outgoing cables beside the phase and neutral terminals.
vi) Suitable label inscription for the board and circuit nos. of all outgoing feeders
shall be provided. The label inscription of the board shall contain description and
code no. The circuit nos. of outgoing feeders shall be serially indicated as 1R,
1Y, 1B, 2R, 2Y, 2B……….
P a g e 88 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
vii) The board shall be complete with terminal block, cable glands, cable lugs and
other accessories as required.
i) All Light Fixtures shall be of LED type of suitable rating as per approved
illumination calculation.
ii) Lighting systems voltage throughout the area shall be 240 V single phase.
iii) For lighting fixtures, 3 core 2.5 sq. mm Cu armoured shall be used.
iv) Normally the load on one lighting Junction Box shall be limited to 1000W
approx.
10.16 Earthing
i) Complete earthing system design and installation shall be carried out as per IS:
3043.
ii) Common underground earthing grid shall be considered for the complete
system. The overall earth resistance (dry) shall be limited to 1 ohm.
iii) Earthing grid/ring shall comprise of buried GI earth strips and copper bonded
earth electrodes.
iv) For equipment earthing, minimum two numbers of electrodes shall be provided
around each section. However, all these earth electrodes shall be inter
connected. Tapping from existing nearest earthing grid shall be taken through
minimum of 2 Nos. 50 mm x 6 mm G.I. strip and fixed along the entire length of
all the conveyors to form local earth grid.
v) Inter-connecting pits having an earth bus in an enclosed brick chamber without
earth electrode shall be provided in the common underground earthing grid for
convenience of taking earth conductors inside the plants.
vi) All non-current carrying parts of various electrical equipment as well as cable
armouring, metal conduit, G.I. pipe, cable racks/trays, brackets, supporting
structure etc. shall be effectively earthed.
vii) All non-electrical equipment such as equipment base plate, steel structures,
pipelines, vessels, tanks etc. shall be effectively earthed.
P a g e 89 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
viii)
ix) As far as possible, the reinforcement rods inside concrete column shall be
connected to the earthing grid/ring to reduce the overall earth resistance.
x) Individual electrical equipment shall be earthed by GI strip/GI wire/Aluminium
cable. Earth buses shall be provided in plants for earthing groups of
electrical/non electrical equipment to earthing grid/rings.
xi) Size of earthing grid/ring and earth conductors of equipment for Sub-stations
shall be as per Clause.No.17.3.2 of IS: 3043. The fault current magnitude shall
be decided based on system fault level. The time duration shall be taken as 3
seconds for H.V. & 1 second for M.V.
xii) Size of earthing conductor for the electrical equipment in plants shall be as per
Clause.No.12.2.2 of IS: 3043.
xiii) All equipment shall have two external earth connections. For lighting fixtures,
earthing shall be provided through armouring of cables.
xiv) Earthing connection below ground shall be made by welding and connections to
the equipment shall normally be bolted type.
xv) The earth conductor shall be protected against mechanical damage and
corrosion particularly at the point of connection to earth, terminals of equipment
and accessories. Welded joints shall be protected by applying epoxy resin or
bituminous paint.
i) Complete lightning protection system design and installation shall be carried out
as per IS: 2309.
ii) The number of down conductors shall be minimum two.
iii) Bare metallic structures shall not have any air termination rods at the top. The
earth connections shall be welded to the bottom of structure at 300mm above
floor level. However, tall metallic columns with insulation at top shall be
provided with air termination rods.
P a g e 90 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
iv) Separate earth electrodes shall be provided for each down conductor of
lightning protection. However, these shall be inter-connected with the other
electrodes in main grid.
v) Horizontal air termination conductor shall be cleated on the top of the parapet
wall of the structure at suitable intervals. The down conductor shall be cleated
with wall / structure at regular interval.
vi) Down conductor / Earth conductor size shall be considered/design as per
applicable standard.
vii) Equipment earthing conductor and lightning protection conductor shall be run
separately without touching each other at any point.
Structures fabricated out of mild steel standard sections, i.e. channels, angels, flats
etc conforming to IS: 2062 shall be fixed on the conveyor structure at suitable
locations for mounting of LCS, safety switches, hooters and Junction Boxes, as per
mounting details of the respective items.
i) IFFCO will remove any material lying at site & provide a clear space at the
proposed location for site execution by successful bidder. However any levelling
& compassion of soil, construction of temporary roads for movement of vehicles
of the contractor shall be considered in vendor’s scope.
ii) Water and electricity for execution of the job shall be provided by IFFCO on free
of cost basis from the convenient tapping points within plant battery limit and
contractor shall manage for bringing the same to utility points in safe manner.
iii) IFFCO will provide space for storage of material supplied by the vendor at a
pre-determined space mutually agreed upon by the vendor & IFFCO. However
unloading & storing of material at site shall be in vendor’s scope.
P a g e 91 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 92 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 93 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
vi) Nothing in these clauses shall be deemed to deprive the owner of his right or in
any way relieve the contractor of his obligation under the contract.
A kick off meeting along with site survey by the engineering team of the vendor
shall be scheduled within 15 days of acceptance of LOI/PO.
i) Detailed Bar Chart : Vendor shall submit a detailed bar chart in MS Project up
to level 4 for complete design & engineering, supply, civil construction,
structural fabrication & painting, erection, installation of conveying system,
commissioning and load trial/GTR within 15 days from the date of Site visit &
kick off meeting.
ii) For Design & Engineering: 90 days from the date of Site visit & kick off
meeting.
iii) For Supply: Supply of all the items in contractor’s scope shall complete within
180 days months from the date of Site visit & kick off meeting.
iv) For Site Execution: 240 days / 8 months from the date of Site handover.
However vendor may planned parallel activities for Civil Construction, Structural
fabrication & painting job at site to minimise the complete execution period.
v) For Load test & Commissioning: 30 days from completion of mechanical
erection.
P a g e 94 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) All care shall be taken to ensure safe transport and protect the component parts
from such damages during transportation which may render them unsuitable for
use at site.
ii) Receipt & unloading practices will be as per prevailing rules & regulations at
IFFCO Paradeep site.
iii) Proper arrangement for Storage of Cement & Reinforcement items shall be
arranged by vendor at allocated site.
iv) All structural may be supplied in knocked-down condition but secured
completely and placed on wooden slabs to avoid direct contact with vehicle.
v) All other machinery parts including electrical and minor components shall be
supplied packed in wooden crates suitably and match-marked to ensure correct
assemble at site.
vi) The cargo shall be marked with the name of consignee, purchase order number
and other necessary information as indicated by the purchaser before dispatch.
vii) Loading, unloading and storage at site, safety and protection of various
components at site etc. shall be the sole responsibility of the contractor /
supplier. The contractor shall also arrange for the safe handling, storage,
protection and security of his goods at site. For this, IFFCO shall provide an
open space to the contractor which shall be developed by the contractor for
safe storage of supplied equipment.
ii) The machinery, conveyors and all drives are aligned and run or cycled under
no-load conditions.
iii) Instruments are installed, inspected and simulation test done.
iv) The electrical system is installed and tested in accordance with applicable
codes and specifications. All wiring is checked for correct hook-up. Motor
rotation is checked and power system protective devices are set. Following test
should be specifically conducted before commissioning of the system
Insulation Test.
Continuity Test.
Simulation Test.
Earth Resistance Test.
No Load & Load Run Test for motors
v) Painting is completed to the extent that the incomplete work does not prevent
plant start-up and commissioning.
vi) Successful completion of no-load test of all the equipment and the complete
system.
vii) Temporary construction facilities are removed to the extent necessary to permit
the plant start-up and commissioning.
viii) IFFCO shall inspect and certify that the contractor executed the job in
accordance with drawings and specifications.
ix) When the complete belt conveyors and related equipment have been fully
erected at site, CONTRACTOR shall request IFFCO for their agreement to start
the No-load Test Run. IFFCO shall, within 72 hours of receipt of such request,
issue his agreement or advise contractor in writing of any deficiencies noticed in
the equipment.
x) Omissions / Rectifications of minor items, if any, not affecting commissioning
shall not withhold MECHANICAL COMPLETION as long as the contractor
agrees to supply / rectify the same within the specified period. The decision of
the IFFCO is final in this regard.
17.2 Commissioning: After issue of Mechanical completion certificates by IFFCO,
CONTRACTOR & IFFCO shall mutually decide the date of Commissioning (feed
P a g e 96 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
in) of the equipment. From the date of Commissioning, the equipment shall be
gradually brought up to full load or any other load at the discretion of IFFCO, and
thereafter the equipment shall be run for a minimum period of 5 days. IFFCO shall
have the right to reduce this period where deemed necessary because of IFFCO’s
difficulties. During this period of 5 days of operation or the reduced period, the
system shall run at an average of 90% of rated capacity. If the CONTRACTOR is
not able to bring the load to 90% of the rated capacity as mentioned above within 2
(two) months, IFFCO shall, without prejudice to any of his rights under the
contract, has the right to take over the equipment and to proceed with
modifications / rectifications /additions as he considers necessary at
CONTRACTOR‟s cost and risk to achieve this sustained load run.
18. GUARANTEE
18.1 Performance Guarantee
i) Capacities: All the equipment and the complete System should be able to
achieve at least 100% of the specified design capacities at a particular period
and normally. However, a margin of 5% should be kept over the specified
design capacity while designing the equipment, for occasional over-loading.
ii) Power Consumption: In no case, the individual equipment shall consume
more than 10% of the specified power consumption. However, the complete
system shall not consume more than the specified guaranteed maximum
power consumption.
iii) Noise Pollution: The equipment shall be guaranteed against excessive noise
pollution. Noise should not exceed 85 dBA measured at a distance of 1.0
meters from the noise emitting source.
iv) The complete Handling system and its equipment including its all accessories
and auxiliaries shall be guaranteed for satisfactory operation while handling
the specified capacity continuously for 24 hours per day, 7 days per week and
330 days per year to ensure trouble free performance.
v) In case the equipment fails to show specified performance, the contractors
shall carryout modifications in design, provided materials and complete the
P a g e 97 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
equipment free of cost to the Purchaser and show load trial to achieve the
specified performance.
vi) In case, the contractor fails to achieve the specified performance even after
the modifications within one month time of the trial runs, the Purchaser
reserves the right to make alternative arrangements for modification /
rectifications at contractor’s cost & risk without any prejudice to any terms of
the contract.
18.2 Material & Workmanship Guarantee: Shall be valid for a period of 18 months from
the date of supply or 12 months from date of commissioning, whichever is earlier.
P a g e 98 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
19. DOCUMENTATION
19.1 With offer: Two stage bidding process will be applicable for this project.Bid
documents shall be submitted in two parts. Technical & Price bid will be submitted
in separate sealed envelope. Bidders, in their technical offer are required to furnish,
but not limited to, the following details/ documents:
19.2 After placement of order: After placement of order, bidder shall furnish a detailed
bar chart in MS Project up to level 4 and QAPs for the items to be supplied against
the order awarded. Drawings/ documents to be furnished during the course of
execution of this job are indicated below:
i) During detail design and engineering. Contractor shall furnish soft copies
of all the drawings/ documents through mail for IFFCO’s approval/ reference
as per approved QAP/ITP. List of documents/ drawings to be submitted by
P a g e 99 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
the contractor during the period of design and engineering is given as below.
However, an exhaustive list of all the drawings/ documents shall be prepared
by the contractor which shall be approved by IFFCO, after placement of
order.
For all other bought out items, contractor shall furnish their GA drawings for
IFFCO’s approval.
P a g e 101 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 102 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
1 Motor-HT BHEL
2 Motor-LT i) ABB
ii) BBL
iii) Crompton
iv) Siemens
3 MCC Panel i) L&T
ii) Interlec
4 LSDB i) Hensel
ii) Crabtree
iii) Cape Electric
iv) Obo
5 Cable i) Gloster
ii) KEC
iii) Cords Cable
iv) CCI
6 GI Cable tray i) Indiana
ii) Shruti Industries
iii) Pinax
7 LCS i) Sumip/Pushtron
8 Limit Switches and other safety i) Jayashree
devices ii) AG Systems
iii) BCH
9 LED Light Fixtures i) Philips
10 CRD i) Bengal Technocrat
ii) Electrozavod
11 Single Phase & Three phase Switch i) Hensel
Socket ii) Crabtree
12 Radar Type Heap Sensor i) Vega(Model- Vegapuls69)
P a g e 103 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
21. LIST OF SPARES: Bidder shall quote for following commissioning and two year
maintenance spare for the system.
Commissioning spares:
7. Oil seals for gear box One number for each type
8. Couplings NIL
6% of total qty
2. Return idlers
6% of total qty
3. Impact idlers
6% of total qty
4. Fluid coupling seal kit
P a g e 104 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
As per OEM
10. Spares for CRD recommendation
As per OEM
11. Spares for Thruster Brake Assembly recommendation
P a g e 105 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
xi) Contractor shall not permit the entry to the site of any persons not directly
connected / concerned with the work. All employees of contractor shall
confirm to any rules of conduct etc. established by IFFCO. Failure to do
so will be sufficient cause for removal of such a person from the site.
xii) Contractor shall make his own arrangement for the residential
accommodation of his staff and supervisors and for their transportation, to
and from the site, to the place of stay. However in exigent circumstances,
IFFCO may consider to provide chargeable accommodation subject to
availability of space.
xiii) The contractor shall write / maintain logbook for job allocated and its
progress, obtain signature immediately on completion of job from the
respective engineer. The job wise material consumption is also to be
recorded in the log book.
xiv) The contractor shall arrange necessary Gate pass for his personnel along
with photographs for security requirement. Contractor should be in
possession of the gate pass while inside plant premises and produce the
same on demand by IFFCO authority.
xv) The contractor shall be responsible for the performance of his workmen
to the entire satisfaction of IFFCO.
xvi) The contractor shall mobilize sufficient skilled manpower for executing job
at parallel fronts.
xvii) Contractor shall arrange for issue of material from IFFCO‟s Store and for
returning material to store or disposing the scrap to IFFCO‟s scrap yard
on completion of the job.
xviii) All measurement sheets shall be submitted for verification by IFFCO
Engineer within 07 days from date of completion of job and all monthly
running bills completed with all relevant documents shall be submitted
within 10 days of each passing month.
xix) IFFCO shall provide the space for construction of working shed and for
storage of the material required for completing the system. It will be the
P a g e 107 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 108 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
ii) 70% of order along with applicable taxes and duties on pro rata basis after
receipt & acceptance of supplied material at site.
iii) 10% of order after mechanical completion & receipt of all As-Built drawings
and documents including operation & maintenance manual.
iv) 10% after commissioning of all equipment & GTR.
B. Supply
P a g e 109 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 110 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) All requirements under the Factories Act 1948 and the rules framed there
under in the Orissa Factories Rules 1950, including all amendments thereto.
ii) All requirements of Employee Compensation Act & ESIS Act, including all
amendments thereto.
25.2 Qualification and Experience of Manpower to be deployed
i) Contractor shall deploy only experienced and qualified Engineers, Safety
Officer, Supervisors and Workmen.
ii) The Safety officer deployed by the contractor shall be qualified as per
statutory requirements.
iii) Contractor’s Skilled Workmen like Riggers, Scaffolders, Welders, Fitters,
Crane Operators, their specialized Equipment Operators like Welding
machine, Power Generators, etc. must have sufficient past experience and
skill on the relevant jobs. The Electricians to be deployed must have valid
qualification.
25.3 Training
i) Training in Fire & Safety is mandatory for all Contractors’ Supervisors &
workers and it will be conducted by IFFCO Fire & Safety Department.
ii) All contractors’ workmen must have to undergo Medical Examination, Height
Phobia Test and Safety training before they are issued gate passes by
Security Department of IFFCO Paradeep.
iii) Daily Tool Box talks must be conducted by the Safety Officer/Supervisor of
the contractor prior to starting of jobs at site. Attendance of workers with their
signatures in such Tool Box talks must be properly recorded in a register.
The register should also contain the name of the persons delivering Tool Box
talks with dates along with the bulletin of topics discussed.
i) Contractor shall not carry out any work without valid Work Permit issued by
the authorised person of IFFCO at the project site as per Work Permit
System.
ii) Contractor shall comply with all the Hot Works/Cold Works/Vessel
Entry/Work at Height Permit conditions specified in the Permit.
iii) Display of Permit shall be done at Worksite for random checking by the plant
Officials & Fire & Safety Department.
i) The PPEs shall be of Standard quality and BIS approved. For such PPEs
where BIS is not available, the PPEs shall be of any international standard
like CE/EN/FM marked.
P a g e 112 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
ii) All Supervisors and Workmen of the Contractor shall enter plant premises
wearing Safety Shoes & Helmet, failing which entry will be denied. The
Contractor should provide basic PPEs to all Supervisors and Workmen.
iii) Minimum requirements for all jobs are –
Safety Helmet (Industrial Safety Helmet), shall confirm to IS: 2925-
1984.
Safety Shoes with steel toe, shall confirm to IS: 15298.
Safety goggles
Hand Gloves.
Reflective jackets.
The contractor shall arrange necessary material to secure the work site and to warn
the plant personnel or other workers of hazards. This shall include - Warning signs,
Barricades around excavations and welding and cutting jobs at height, including
illuminating warning signs.
P a g e 113 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) All excavated pit & trenches shall be barricaded with tap and rigid pipelines.
ii) Pumping out of accumulated water from pit is to be done at regular intervals.
Run-away water shall be prevented from entering the excavated area, as
such water can cause erosion of soil and sudden collapse of earth.
iii) Excavated earth shall be stacked at least one meter away from cutting edge
to avoid collapse of trench and sliding of heaped earth into trench.
iv) All the safety precautions as stipulated in IS: 3764-1992- (Excavation work-
code of safety) shall be followed while excavation work.
v) Movement of heavy vehicles shall be restricted on loose soil.
i) Piling machine operators shall have sufficient past experience and properly
trained.
ii) Prior to piling, all underground services shall be located and made safe.
iii) There shall be a firm level base for the crane. If necessary crane mats shall
be provided.
iv) The workers shall use necessary personal protective equipment.
v) All cranes, lifting appliances and lifting gear must have appropriate
certificates of testing and shall be of capacity required for the job. The test
date, due date and identification mark shall be mentioned on all cranes,
lifting appliances and lifting gears.
vi) Particular attention shall be provided to the risk of damage to lifting gear from
sharp edges.
vii) Relevant BIS Safety Code for piling and deep foundations shall be followed.
P a g e 114 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) Only cup-lock type mild steel scaffolding shall be used by the contractor.
Scaffolding pipes shall be in good condition and preferably painted.
ii) Metal scaffolds shall confirm to IS: 2750-1964 in addition to IS:3696 (Part 1)
iii) Proper base plate supports must be provided in the scaffolding posts.
iv) Safe step ladder / monkey ladder with cage and hand rail shall be provided
to access scaffold platforms. The intermediate & final stage must be
provided with hand rails and toe guards on the working platforms.
v) Safety nets must be installed to catch workers and / or debris falling whilst
working on structural fabrications. The Safety nets shall confirm to
requirements made under IS: 11057- 1984.
vi) All members of metal scaffolding shall be checked periodically to screen out
defective /rusted members. All joints should be properly lubricated for easy
tightening.
vii) Clear access to scaffolds shall be maintained at all times. For prohibiting
entry of unauthorized persons in scaffolds area, barricades should be put up
and warning notices prominently displayed.
viii) It is essential to obtain stability certificate from the manufacturer about
safety and stability of metal scaffolds under likely worst combination of loads.
ix) While working at height using scaffolding, double lanyard full body harness
with scaffolding hooks must be worn.
x) All the scaffolds shall be initially and periodically certified by competent
scaffolding inspector and tagged appropriately. Only fit-to-use scaffolds shall
be in use.
xi) It shall be ensured that only trained & experienced workers are engaged in
scaffolding work.
Adherence to relevant codes and employment of qualified and tested welder are
two basic requirements for welding and gas cutting process. Hazards such as
P a g e 115 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
electricity, heat/flame, flammable gas etc. are present in this process. Hence
following precautions must be followed while carrying out these operations.
P a g e 116 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
prevent permanent damage to the eyes must wear suitable eye protection.
When not in use, power supply to the holder and electrode shall be turned off.
ix) Hose shall be in good condition, and properly clamped.
x) Welding cable shall have proper insulation with minimum number of joints.
xi) All equipment shall be properly earthed, and cables properly insulated and
connected.
xii) RCCB shall be provided in every welding circuit.
xiii) Earthing shall be dedicated for each circuit.
xiv) All portable grinder must be double insulated type. Before use grinding wheel
must be checked for any crack, damage etc.
xv) Never adjust the work piece or work mounting device when the machine is
operating.
xvi) Grinding wheel must be properly guarded. Never operate the grinding
wheels at speed in excess of recommended speed.
xvii) On-bench grinders, adjust tool rest 1/16 to 1/8 inch from the wheel.
xviii) Radiography shall be carried out under hot work permit. Radiography
to be carried out in ‘NO WORKMEN ZONE’ and preferably during evening/
night. Based on the maximum allowable radiation, area shall be cordoned off.
Adequate warning signs on the outskirt of cordoned area shall be provided.
All required Personal Protective Equipment’s must be used.
i) Safe working space for all handling equipment shall be provided. Proper
material stockyard should be made and all material should be
stacked/arranged/kept in orderly manner with proper moving space for
handling machinery. Proper wooden sleepers should be provided below steel
plates and such other materials.
P a g e 117 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
P a g e 118 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
i) The contractor shall ensure that all electrical equipment used by his
personnel are properly earthed or grounded and fitted with a proper plug top.
Use of damaged/bare cables/conductors for any machine is strictly
prohibited. Cable shall be laid preferably in one piece length to avoid joints.
All cable must be properly insulated.
ii) Work permit and isolation of the electrical system before taking up the work
must be ensured.
iii) All circuits shall be provided with dedicated ELCB/RCCB. There shall also be
dedicated earthing for each equipment and effectiveness of earthing shall be
checked every time before commencing work/switching on the electrical
system.
iv) Any earthing wire not to be connected to the structure/pipelines.
v) IS: 5216-1982 “Recommendations on safety procedures and practices in
Electric Works" shall be referred for further safety measures.
i) Contractor’s driver must get themselves familiarized with factory roads and
traffic regulations on certain roads.
ii) All vehicles entering or leaving the factory must come to a complete halt at
the security gates, for checking by the security Office.
iii) All the vehicles including heavy machineries like hydra, crane etc. shall be
registered on Contractor Vehicle Pass Entry System of IFFCO Paradeep
Unit.
iv) The maximum speed limit for all the vehicles with in the company premises
is 20 KMPH.
v) Anyone driving a motor vehicle on company property must be in possession
of a valid driving license.
vi) Transportation of contract personnel not permitted by goods carrier like
Tractor Trolley, forklift, Dumper etc.
vii) Hydra shall not be allowed to move with load outside the project site.
P a g e 119 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
viii) Within the project site Hydra shall not carry any material more than 6 m
long.
ix) No crawler mounted vehicles shall be allowed to move on the in-plant roads.
If necessary slip plates shall be provided.
Contractor must ensure the highest standard of housekeeping in his areas of work
on a daily basis. Good Housekeeping will eliminate many unnecessary hazards
causing accidents.
Any contractor violating the Factories act 1948 & Odisha Factory Rule 1950 shall
be issued Safety Offence notice and may be penalized with the approval of Unit
Head. Project In-charge or concerned engineers may inform to Fire & Safety
department about the penalty amount with Work order no. through email to penalize
the contractor.
Following actions on part of contractor may call for termination of the contract.
i) If the contractor does not maintain adequate resources to execute job in time
/ start the work / expedite the job.
ii) If the defects pointed out are not rectified and in case of defects that are
likely to cause severe accident of machinery or human beings.
iii) If the contractor executes work in unsafe manner violating prevailing safety
rules applicable in IFFCO as per clause no. 25.
iv) Not complying with the statutory requirements applicable to such contractors.
v) In case of theft of IFFCO property.
P a g e 120 | 121
Design, Engineering, Supply, Construction & Annexure-I
Commissioning of New Rock Phosphate Silo-D RFQ.No.252002220345,
Dated 14.06.2021
IFFCO,Paradeep Rev.0
If contractor fails to comply all the clauses stated above, IFFCO reserves the right to
invite third agency to complete work solely at the risk and responsibility of the
contractor.
P a g e 121 | 121