PREVAILING WIND
DIRECTION
TRUE
NORTH
PLANT
NORTH
DIESEL TANK
AIR COMPRESSOR
GENERATOR
BOP SKID
POWER SWIVEL
TANK COOLANT KOOMEY
Cat walk Carrier
Rig Floor
STORAGE TANK #1
MUD TANK #1 MUD TANK #2 MUD TANK #3
STORAGE TANK #1
MUD TANK #4
DIESEL TANK DIESEL TANK
MUD TANK #3
MUD TANK #4
MUD TANK #3
MUD TANK #4
KOOMEY
KOOMEY
GENERATOR GENERATOR
AIR COMPRESSOR AIR COMPRESSOR
TANK COOLANT
TANK COOLANT
BOP SKID BOP SKID
Carrier
Carrier
MUD TANK #2
MUD TANK #2
Rig Floor
Rig Floor
POWER SWIVEL POWER SWIVEL
MUD TANK #1
MUD TANK #1
Cat walk
Cat walk
STORAGE TANK #1
STORAGE TANK #1
STORAGE TANK #1
STORAGE TANK #1
TRUE
NORTH
PREVAILING WIND
DIRECTION
WP-B : 21 Wells
WATER LINE
EXISTING SOC FACILITIES
18" TRUNKLINE FROM
WP-02 TO FCP
WP-D : 26 Wells
363706
505577
588377
225175
225175
174510
140734
562937 140734
247692
315245 132290
562937
PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) WELLPAD
MODIFICATION PROJECT (PHASE 1) FOR PETRONAS CARIGALI IRAQ HOLDING B.V.’S GARRAF OPERATION
PLOT PLAN FOR
WELL PAD - E
GF-GEN-WPE-J-32-3345 04/05 2