Annexure-I of Schedule G Contract Price Weightages

This document outlines the contract price weightages for different stages of construction for a highway project with rigid pavements totaling Rs. 9910344659.70. It divides the contract price into various construction stages such as earthwork, granular work, bituminous work, rigid pavement, culverts, bridges, and assigns each a percentage weight of the total contract price based on the scope of work. It provides details of the construction stages for widening/strengthening existing roads, new realignments/bypasses and new major bridges.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
484 views3 pages

Annexure-I of Schedule G Contract Price Weightages

This document outlines the contract price weightages for different stages of construction for a highway project with rigid pavements totaling Rs. 9910344659.70. It divides the contract price into various construction stages such as earthwork, granular work, bituminous work, rigid pavement, culverts, bridges, and assigns each a percentage weight of the total contract price based on the scope of work. It provides details of the construction stages for widening/strengthening existing roads, new realignments/bypasses and new major bridges.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Annexure-I of Schedule G

Format for Contract Price Weightages for Highway Projects with Rigid Pavements

Contract Price Weightages

1.1 The Contract Price for this Agreement is Rs. 9910344659.70

1.2 Proportions of the Contract Price for different stages of Construction of the Project Highway shall be as specified below:
Weightage in percentage
Item Stage for measurement of Physical Progress Unit Qty.
to the Contract Price
1 2 3 4 5
A- Widening and strengthening of existing road
(1) Earthwork up to top of the sub-grade Km
(2) Granular work (sub- base, shoulders)
GSB Km
(3) Shoulders Km
(4) Bituminous work Km
(5) Rigid Pavement
(a) DLC Km
(b) PQC Km
(6) Widening and repair of culverts No.
(7) Widening and repair of minor bridges No.
B- New realignment/bypass
(1) Earthwork up to top of the sub-grade Km 34.881 29.76%
(2) Granular work (sub- base, shoulders)
2.1. CT Sub base and Base Courses (MCW) Km 34.881 7.22%
2.2. CT Base - MCW Km 34.881 6.01%
2.3. Crack Relief Layer Km 34.881 2.69%
(3) Shoulders Km
(4) Bituminous work Km 34.881 8.89%
2.4 Trumpet Road Works 2.43%
Road works including C- New culverts, minor bridges, underpasses, overpasses on existing
culverts, minor bridges, road, realignments, bypasses:
underpasses, (1) Culverts No. 75 1.19%
overpasses, (2) Minor bridges No.
approaches to (a) Foundation No. 15 0.81%
ROB/RUB/ Major (b) Sub-structure No. 15 4.11%
Bridges/ Structures (c) Super-structure (including crash barriers etc. complete) No. 15 3.34%
(but excluding service (3) Cattle/Pedestrian underpasses No.
roads) (a) Foundation No. NIL 0.00%
(b) Sub-structure No. NIL 0.00%
(c) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(4) Pedestrian overpasses
(a) Foundation No. NIL 0.00%
(b) Sub-structure No. NIL 0.00%
(c) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(5) Grade separated structures
(a) Underpasses
(i) Foundation No. NIL 0.00%
(ii) Sub-structure No. NIL 0.00%
(iii) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(b) Overpass
(i) Foundation No. NIL 0.00%
(ii) Sub-structure No. NIL 0.00%
(iii) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(c) Flyover No.
(i) Foundation No. 1 0.04%
(ii) Sub-structure No. 1 0.27%
(iii) Super-structure (including crash barriers etc. complete) No. 1 0.22%
(d) Foot over Bridge No.
A- Widening and repairs of Major Bridges
(1) Foundation
(a) Open Foundation No. NIL 0.00%
(b) Pile Foundation/Well Foundation No. NIL 0.00%
(2) Sub-structure No. NIL 0.00%
(3) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
B- Widening and repair of
(a) ROB
(1) Foundation No. NIL 0.00%
(2) Sub-structure No. NIL 0.00%
(3) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(b) RUB
(1) Foundation No. NIL 0.00%
Weightage in percentage
Item Stage for measurement of Physical Progress Unit Qty.
to the Contract Price
1 2 3 4 5
(2) Sub-structure No. NIL 0.00%
Major Bridge works (3) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
and ROB/RUB C- New Major Bridges No.
(1) Foundation
(a) Open Foundation No. 1 1.97%
(b) Pile Foundation/Well Foundation No.
(2) Sub-structure No. 1 2.01%
(3) Super-structure (including crash barriers etc. complete) No. 1 6.93%
D- New rail-road bridges
(a) ROB
(1) Foundation No. NIL 0.00%
(2) Sub-structure No. NIL 0.00%
(3) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
(b) RUB
(1) Foundation No. NIL 0.00%
(2) Sub-structure No. NIL 0.00%
(3) Super-structure (including crash barriers etc. complete) No. NIL 0.00%
LVUP & VUP No.
(1) Foundation No. 17 0.30%
Structures (elevated
(2) Sub-structure No. 17 0.96%
sections, reinforced
(3) Super-structure (including crash barriers etc. complete) No. 17 0.78%
earth)
(4) Reinforced Earth Wall (includes Approaches of ROB, Underpasses,
3.11%
Overpasses, Flyover etc.
Weightage in percentage
Item Stage for measurement of Physical Progress Unit Qty.
to the Contract Price
1 2 3 4 5
(i) Service roads/ Slip Roads Km 25.54 4.92%
(ii) Toll Plaza No. 1 1.41%
(iii) Road side drains Km 25.54 2.26%
(iv) Road signs, markings, km stones, safety devices, ….
(a)Road signs, markings, km stones, …. Km 34.811 1.41%

(b) Concrete Crash Barrier/ W-Beam Crash Barrier in Road work Km 33.47 2.18%

(v) Project facilities


(a) Bus bays No. 0 0.00%
(b) Truck lay-byes No. 2 0.12%
(c) Rest areas No. 1 0.38%
(d) Entry & Exit Ramps, Intersections & Junctions 1.19%
Other Works
(vi) Repairs to bridges/structures No.
(vii) Road side plantation Km 33.48 0.50%
(viii) Protection works
(a) Boundary fencing works Km 69.76 1.11%
(b) Toe/Retaining wall Km 2.50 0.23%
(c) Utlity Shifting Km 0.64%
(ix) Tunnel
(a) Excavation Metre
(b) Construction of support system including rock bolting, lining
Metre
etc.
(c) On complete completion of tunnel Metre
(x) Miscellaneous 1 0.61%
Total 100.00%
* The above list is illustrative and may require modification as per the scope of the work.

** Measurement of Progress

For example, if the total length of bituminous work to be done is 100 km, the physical progress of bituminous work shall be determined as follows:

Physical progress of bituminous work =Weightage for bituminous work x (L'/L)

L = Total length of bituminous work in km


L' = Executed length of bituminous work in km

Similarly, the physical progress for other stages shall be worked out and addition of all will give the total progress achieved.