INSPECTION AND TEST SCHEDULE KILANG PERTAMINA
BALIKPAPAN
Project : [IKAN] RDMP- Refinery Unit-V Balikpapan Project
Owners : Pertamina RU-V Balikpapan
Contractors : RDMP JO Balikpapan
Sub-Contractors : PT. PP URBAN (BD003)
NO. DATE TIME LOCATION RFI NUMBER INSPECTION AND TEST ITEM PP Urban's PIC REMARKS
Acces for inspection and
1 Tuesday, September 14th 2021 13.00 A-331-03B RFI-P-PU2-AR-02028 Inspection Before Pouring Concrete PD1 Aria Zulham pouring concrete should
installed
Release if inspection was
2 Tuesday, September 14th 2021 14.00 A-331-03B RFI-P-PU2-AR-02035 Inspection During Pouring Concrete PD1 Aria Zulham
accepted by IPMT
3 Tuesday, September 14th 2021 14.00 341/UCR-001 RFI-P-PU2-AR-02036 Inspection Before Pouring Concrete Slab 1st Floor (T.O.C +102.800) Aria Zulham Closing Comments
4 Tuesday, September 14th 2021 14.30 341/UCR-001 RFI-P-PU2-AR-02037 Inspection Before Pouring Concrete Girder 1st Floor (T.O.C +102.800) Aria Zulham Closing Comments
Release if any comments was
5 Tuesday, September 14th 2021 15.00 341/UCR-001 RFI-P-PU2-AR-02038 Inspection During Pouring Concrete Slab 1st Floor (T.O.C +102.800) Aria Zulham
accepted by IPMT
Release if any comments was
6 Tuesday, September 14th 2021 15.30 341/UCR-001 RFI-P-PU2-AR-02039 Inspection During Pouring Concrete Girder 1st Floor (T.O.C +102.800) Aria Zulham
accepted by IPMT
Note: Please submit RFI max 1 day before inspection and test agenda