Sakuti Method - Statement - For - HRSG - Works Crsher
Sakuti Method - Statement - For - HRSG - Works Crsher
DOCUMENT NO:NIS/626/MS/001_REV 00
            SUBCONTRACTOR:NASS INDUSTRIAL
                      SERVICES
GAMA REVIEW
                  Discipline                 HSE Manager                QA/QC Manager                 Site Manager
                Superintendent
Name
Date
Sign
Remarks:
Any such review or consent by GAMA, shall not relieve the Subcontractor, in any case or for any reason whatsoever,
from any obligation, liability or responsibility arising out of or in connection with the Contract, including without being
limited thereto, to the responsibility for errors, omissions, discrepancies and non-compliances. Within this context, this
document shall not prevail over or amend the Contract, or relieve the Subcontractor from any of its duties, obligations,
responsibilities or liabilities under the Contract.
Anything presented herein by the Subcontractor shall in no event
 i) excuse the Subcontractor’s non-performance under the Contract, or
ii) entitle him to a variation under the Contract or an adjustment to the Contract Price.
 SUBCONTRACTOR
 Rev.                                      Prepared          HSE            QA/QC                Site           Project
             Date         Description*
 No.                                          by            Manager         Manager            Manager          Manager
DOCUMENT HISTORY:
 Rev.                       Remarks
              Date
 No.                        (Reason for Revision)
* Description:
        Document issue purpose
        -   First Issue
        -   For Information
        -   For Review
        -   For Approval (or Issued for Construction)
CONTENT
1.0    PURPOSE
      This Method statement describes in detail of 3 Nos.Heat Recovery Steam Generator Erection
      works for SEC Power Plant Project PP-13 being carried at KSA by M/s NIS , Bahrain. This
      includes addressing programs for implementing commitments regarding the quality and Safety of
      works.
3.0    RESPONSIBILITIES
       Operation Manager/Project Manager shall be responsible for overall coordination of the
       activities and allocation of resources such that it meets the requirements of this MS.
5.0 PERSONNEL
6.0 MATERIALS
       NASS shall mobilise required materials ,tools & consumables as per the Scope and project
       schedule.
7.0    EQUIPMENT
       Equipment Histogram Attached.
9.0    EXECUTION
       9.1 Shifting,Storage & Handling of FIM:
       a)Transportation of Materials
       All relevant project materials shall be transported from Warehouse to NIS Laydown Area
      /Erection Site on a Trailor after completion of required Formalities.
      Materials in the open area shall be stored above ground (200mm) on a wood, on platforms or
      pallets in a manner that will prevent any deterioration from debris, grease, paint spray or any
      other foreign matter.
      c) Inspection/Verification:
      Incoming materials shall be offered for Inspection/Verification to ensure that the correct grade,
      quality, condition, painting, identification and dimension have been supplied and are in
      accordance with the Packing lists. Owner shall be informed immediately incase on any defects in
      Incoming materials with reports & photograph.
      Materials that cannot be identified by identification markings, new identification label have to be
      provided on that particular item.
      Damaged materials and Spare Materials shall be placed in a separate storage area from other
      usable materials, with sufficient safeguard to prevent its use.
Accepted FIM Materials shall be documented in the form of MRIR report for easy tracking.
A detailed Construcion Schedule shall be prepared using Primavera Project Planner/ Microsoft
Project/Spread Sheet highlighting:
b) Critical Path
c) Manpower Histogram
The construction schedule shall be regularly updated every week in accordance to Contractor
and Consultant requirements in terms of progress of works and forecast to finish.
The sequence of activities indicated in the construction schedule may be modified or updated at
later stage of execution due to non availability of Erection Front,Owner’s requirement,Climatic
and Environmental Condition,Routes Operability etc.
Materials receipt status, Work front status along with quarantine list if any shall be published
weekly in excel format.
2) Suitable Main and Trail Crane located for lifting of Casing Modules 1,primary-self standing
   type,casing (left or right) side panel.
3) Main crane Lifts Module 1 (Left or Right) side panel until become upright position.
4) Module 1 (Left or Right) side shall be place on foundation and bolts will be tightens.
7) Crane is located for lifting of Module1,primary self standing type,horizontal bottom beams of
   casing floor panel;
8) Crane lifts Module 1,primary-self standing type,horizontal bottom beams of casing floor panel;
9) Temporary supports are prepared to keep horizontal bottom beams of casing floor panel;
10) Main and Trailing crane shall be marched to other position for lifting the opposite casing side
    panel of Mdule 1 to the one already put in position.
Above sequence is repeated for next self standing type Module but when erecting this module the
casing floor shall be lifted as a complete panel,since there is no matter of interference with the
susequent internal piping installation.
After completion of Casing for primary Module,the erection proceed with the installation of not self
standing modules.
Casing Erection shall proceed by the Installation of casing enclosures panels as follow:
    (Note: Bottom panels of Module 1 shall be installed at a later stage when pressure part
    modules are set to the installation of boiler internal piping header.)
2) Installation Vertical side panels of bolier alignment using fit-up bolts,verifying that the panels
   are correctly oriented towards the flue gas path in accordance to the drawings.The installtion
   of same panels on both side alternatively shall be done It is recommended to complete the
   installtion of the same.Alighnment,Squaring,verticality of whole casing structure has to be
   maintained within tolerance especially the value at the top level.Transversal beams shall be
   progressively removed when vertical panels are fitted up and when squaring tolerance are
   well within limit.
4) Execution of final alignment, levelling and verticality of the whole casing structure, relevant
   control and control certification, to be carried out when all casing structures are erected,
   bolted and tack welded. Final checks have to be completed and certified in accordance to
   SUPPLIER design tolerances and Site Quality Control Plan before any final welding of the
   casing structures is allowed to commence.Measured values of alignment, levelling and
5) Execution of final welding of all casing panels, in accordance to here above listed drawings of
   the Project. All external welding have to be carried out in a continuous way, stitch welding
   inside, in accordance to the details shown on the here above listed erection drawings of the
   casing.
6) Installation of the field casing plates for sealing of the gap between the vertical panels and
   the bottom panels, as per details shown on the here above listed erection drawings of the
   casing.
8) Execution of paint touch up on all casing welds carried out at site, especially in the areas
   where insulation mattresses have to be installed, in accordance to the painting cycle
   applicable for the external casing sheets. It is compulsory that said activity is executed before
   starting with the restoration of insulation and setting of liner plates.
9) Execution of the insulation in the naked strips left void between adjacent vertical side panels,
   between vertical side panels and horizontal bottom panels, between adjacent horizontal
   panels,laying and pinning suitable mattresses of ceramic fibre between the panels (double
   layer,staggered when required) to be packed and covered by the loose lining filler plates.
   Fixing pins have to be installed and welded at site, retaining studs are installed on the casing
   sheets of the panels during prefabrication.
10) Installation of the loose lining enclosures plates, sent on site already pre fabricated, each of
    them identified by marking, with holes drilled, cut at suitable dimensions such as to mach
    shape and width/length of the specific area to be restored/coated. Loose lining filler plates are
    kept in position by round washers to be fixed to the lining threaded studs using nuts. Nuts
    have to be tack welded to the studs, no welding has to be carried out between adjacent loose
    lining filler plates. The liner assembly of casing/inlet duct sections is designed to allow the
    protective internal liner system to expand freely due to the temperature expansion of the
    components. The liner system is composed of a series of overlapping plates, pinned to the
    outside casing. It is important that the installation of the field seams be understood prior to
    beginning work. Failure to install field seams correctly can lead to casing hot spots, loss of
    insulation and general failure to the integrity of the liner system.
    11. Restoration of insulation and lining at the junction area of panels of HRSG casing and
    inlet ducthas to be carried out with the up most care and precision, to avoid any possible gas
    leakage throughout lining plates and insulation. Said hot gas paths, that are not easily
    detected and eliminated during boiler operation, will cause burning and damage of the
    external casing and duct structures of the HRSG.
    12. Installation of bumper pipes . Suitable scaffoldings have to be erected at each side of
    boilercasing to allow positioning and welding of the guiding boxes. Said scaffolding shall
    remain in place to allow the installation and shimming of the setting plates to be fixed to the
    tube bundles of the pressure part modules.
14. Installation of Header Spacers, provided to counter the thrust of the headers towards the
casing panels in case of the occurrence of a disrupting earthquake. Backstays are shop
welded to the casing panels.
15. Installation and welding of the plates connecting the external stiffeners of the casing
panels to the HRSG main structures (columns, beams), in accordance to the applicable
drawings of the Project.
16. When casing panels are fully welded and all non destructive tests and controls foreseen
by the applicable site Quality Control Plan (QCP) are executed, witnessed and certified by
the OWNER it is requested that base plates of columns are grouted by the Civil Contractor,
using a suitable non shrinkable-self levelling mortar, leaving the shim packing in position.
17. Final tightening of the nuts of embedded anchor bolt to the base plates of the casing
columns shall be executed when grouting has sufficiently set.
18. Beginning of the erection of pressure part modules is bound to completion of the erection
and welding of all casing structures, execution and certification of required NDT and the
inspections listed in the Site Quality Control Plan.
The inlet duct, possibly supplied in form of panels similar to casing panels,either insulated or
to be insulated at site condition.
Prefabrication and inner insulation before erection shall be evaluated keeping into account
availability of area, accessibility to the erection areas and availability of crane and truck.
5. Preparation of internal scaffolding for internal welding and insulation and external
   welding.
6. Positioning, welding and insulation of the connection pieces between exhauster (round)
   and duct (rectangular section).
HRSG Outlet Duct connects the boiler casing to the stack breeching using a fabric expansion
joint.
The type and degree of prefabrication, sequence and methods of erection of the boiler outlet
duct main components are similar to the ones of the boiler inlet duct.
Casing and inlet duct access doors shall be installed on the panels and sealed with a
designated bolting type gasket.
Care shall be taken to insure that the gasket is not damaged when doors are opened and/or
closed in the site. Casing access door gaskets should be replaced at the first sign of
becoming brittle. The bolting tape shall lay flat against the surface with no laps or gathering
on the material.
Each stack (5.5m of diameter, 60m high) shall be site pre-assembled in several segments of
variable length complete of all accessories and auxiliary components (access doors, ladders,
platforms, rain damper, silencer, personnel protection, mass damper and nozzles).
Each segment shall then be erected in sequential order by means of heavy lifting equipment
and jointed together by circumferential field welding.
The stack preassembly operations consist of prefabricating, at ground level in dedicated area
according to the general plant layout, the stack segments in which the whole stack is divided
into.
Stack segments are made of several shell courses. Maximum height and weight of segments
shall depend on the lifting equipment availability at site. The erection sequence is as follows
Or there maybe 5th Section also, depending upon available materials, Weight, Available
Equipment etc.
Each shell course (OD=5520mm) is made of 3 curved and beveled shell plates welded with
internal angle of 120° (at the time of welding there is to be no paint within 50mm of the weld).
Alignment of vertical joints is obtained by strong packs tack welded across the seams (50mm
clear from weld as a minimum) and by means of shim plates and wedges. All seam welds are
to be in accordance with the applicable WPS.
The strong packs will be removed by cutting after the completion of the vertical seams. The
surface where they were attached will be ground smooth and inspected for cracks by DPT.
Shell courses are to be completed with welding attachments according to the drawings.
Once the prefabrication operation of the segments are completed, all their surfaces shall be
spray / brush coated according to the corrosion protection specification prior to erection and
assembly of appurtenances with the only exception of the ends to be coupled.
Before starting with the erection of the segments making the stack, the installation of the
following stack components shall be completed:
- The ladders across the joints will be fixed after the completion of the erection
Once the above mentioned stack accessories have been assembled, stack section no. 2
shall be assembled directly on the main stack section no. 1.
The base plate will sit on steel packs and wedges to ensure the level and the planarity of the
underside of the base plate not to deviate from the specified values. After segments 1 and 2
have passed the verticality check, manual torque will be applied to the nuts of holding down
bolts.
- Lift stack section no. 3, fitted with appurtenances and temporary platforms near the top end,
if required;
- Align stack section no. 3 with strong packs tack welded across the seams (50mm clear from
weld as a minimum) and by means of shim plates and wedges;
- Release slings from temporary platforms fitted near the top of stack section no. 3 when
provisional connection to stack section no. 2 allows a safe release;
- Internal scaffolding is required to execute the back gauge weld of the two stack segments
joint. The access to the scaffold will be through a manhole 600x600 mm located some 800
mm lower than the joint. The scaffold shall be removed after weld acceptance GAMA/Owner.
Stack base plate will be grouted after the positioning of the last highest stack section and in
any case after stack verticality check acceptance.
The grout shall be non-shrink type. Immediately before grouting, the space under the base
plate will be cleaned. Steel packs will be left in place and totally enclosed by the grout. After
curing time, when grout has developed its nominal strength, holding down bolts will be snug
tight. Anchor bolts shall be re-tightened 30 days after grouting application.
Note: The erection of the HRSG main stack has to be limited to the top height of the
boiler casing at elevation ~ 30.00 to 35.00 meter, for safety reasons, due to the rotation
of the main crane loaded with pressure part modules.
Pressure Parts Modules for 1 HRSG consist of 8 (eight) modules probably shipped at site
completed with roof casing plate, hangers and interconnecting pipes between.
Unloading, Storage & Lifting of Modules shall be done with the help of 600 MT main crane
and 300 MT trailing crane and as per the special instruction of Supplier if any.
Pressure part modules shall be arranged inside the casing in 2 Nos./Row and from casing
module 1 to 4 or vice versa.
The boiler casing structure is fully installed, tightened, welded and NDEs tested.
All NDT activities has been performed and certified as quality plan.
While settling the modules into casing structure the nozzle connections shall be checked
against SUPPLIER specific erection drawings of the Project for correct displacement in
location and elevation. Nozzle location shall be checked with an inspection.
No other crane shall work in areas adjacent to the lifting area, including Civil Contractor tower
cranes if any, while pressure part modules lifting operation are in progress.
Tube skin thermocouple shall be welded on pressure part module on site wherever
applicable.
Lifting of pressure part modules shall be carried out in full accordance to specific drawings
and instructions issued by SUPPLIER to avoid any damaging of the modules.
All lifting equipment’s and devices at completion of each lift shall be checked to assure that
no damage has occurred during lifting. Any bent, worn or damaged component shall be
replaced.
When all pressure parts modules are installed into the boiler casing, it is possible to
commence the erection of boiler internal piping, headers and auxiliary structures, like:
1 Trusses for stiffening the tube bundles, guiding the down-comers, horizontal gas baffle
plates to confine the gas flow to the tube bundles of the pressure part modules.
2 Vertical Gas Baffle Plates for sealing the hot gas passes through the adjacent modules and
through casing structures (floor, walls, roof) and modules.
Suitable scaffoldings have to be erected in the row between two adjacent modules, starting
from casing floor up to the top of the tube bundles of the modules, to allow the installation of
aforesaid components.
The horizontal gas baffles, fixed to the upper and lower trusses by bolting because trusses
act as supporting frames for the gas baffles, are installed as a barrier to the hot gas flue
creating a dead chamber at the boiler floor (lower dead chamber) and the boiler roof (upper
dead chamber).
Upper and lower trusses and the horizontal gas baffles are delivered at site prefabricated,
singularly marked for an easy identification and installation.
Intermediate trusses at two different elevations (+10195 e +19995) for reinforcement
porpoises have to be installed only on MODULE 1.
Access doors to pressure part module connecting piping and tube bundles are provided at
suitable positions on the lower baffle plates.
Prefabricated Vertical Baffle plates duly marked for easy identification shall be installed at
both gas inlet and outlet side of each module.
Extra lengths are left on header nozzles and piping spool, to be trimmed at site, to facilitate
the erection and fitting up of the lines.
Piping bevels shall be carried out in accordance to SUPPLIER design and applicable WPS.
It is of paramount importance that the execution of welding, Post Weld Heat Treatment
(PWHTs), Nondestructive Tests (NDTs) are strictly executed and monitored in accordance to
the approved WPSs/WPQRs, PWHTs and NDTs specifications, prepared by the Erection
Contractor(s) and approved by NoBo.
Internal scaffolding previously installed before the installation of the pressure part modules
shall be modified accordingly.
Suitable metallic and textile expansion bellows shall be provided to allow the expansion of
piping linked to the pressure part modules throughout the casing lateral walls, roof and floor.
Some of the roof expansion joints which are not shop installed on pressure part modules
shall be installed at site, as per the applicable drawings and supplier Instruction.
Expansion bellows shall be protected from weld spatters and puncture during the erection
phase.
While mounting main and auxiliary frameworks, including ladders, gangways, service
platforms and gratings, it cannot be completely sequenced. It all depends on the availability
of material, lifting equipment, personnel, drawings and access availability and accordingly
Erection sequence shall be scheduled. However, sequencing shall be done in such a way in
order to avoid clashes with other equipment or installation of our own or those already
erected and/or installed by other sub-contractors on site.
Assembly and installation of the main boiler stairway, complete with gratings, handrails and
foot guards including the final tightening of the bolts after checking the verticality and
dimensions of the structure;
On-site assembly of all the secondary structures, beams, stairs, walkways, handrails, foot
guards, gratings etc., with arrangement and welding of cantilever attachments / connection
brackets with reinforcement to the bearing structures;
On-site assembly of the frame for the top support structures of the silencers;
Note: After each section of Installation, it shall be checked for verticality and
tightening of bolts.
2. Final check for verticality and, after shimming, if necessary, pouring of concrete;
The structural erection shall be sequenced in such a way that they do not interfere with
major installation and as per reference documents. Consequently, stairs and gangways shall
be erected as the progress of the main activities allows it, for easier accessibility to the
working areas. Main stairs shall be erected first provided that they do not interfere with major
plant erection.
 Bolts tightening;
               The coupling bolts of the secondary structures shall be protected, right after their
                tightening, with a coat of organic or inorganic zinc plating;
               The assembly of stairs and gratings will start right after the execution of the final
                perpendicular check of the single structure and shall be completed swiftly.
                Regulation railings shall be immediately installed on the boiler floors and also in
                spots which may be temporarily exposed (for example in correspondence of the
                boiler itself); those not compatible with access needs will be dismantled at the
                end of the assembly;
               Column-column couplings:
                Couplings between column sections, the surfaces of the tips in contact are
                worked. The coupling covers shall be mounted with the relative fillings and the
                complete contact between surfaces to be tightened as well as coaxially of the
                holes shall be obtained.
Gratings supplied in shaped-on-design panels with toe-guard already welded shall be directly
installed on the structure as per the drawings with the help of crane. Loose toe-guard shall be
welded after erection of gratings panel wherever applicable.
For the small bore piping and/or process pipes the passing hole shall be provided if applicable or
existing cut-out shall be adjusted.
The assembly of stairs and handrails, including gratings, shall be performed parallel to allow the
immediate access to erected components or to the ones still to be erected
The tightening of bolts shall be carried out by using a suitable mean to achieve desired result.
The contact surfaces between washer, nut and thread shall be greased. The riveted part surfaces
in contact with the head of the bolt and with the nuts shall be parallel. As an exception, the
surfaces can present inclinations as long as they are not compared to a surface perpendicular to
the bolt axis. For inclinations, inclined washers shall be used in order to guarantee a correct asset
of the nut head.
Coupling tightening shall be performed tightening first the central bolts and then alternating those
adjacent to them.
As soon as the bolts have been tightened it shall be clearly marked. Before beginning the
assembly of the parts under pressure, high resistance bolt tightening shall be completed.
Exceptions to this rule may be allowed only in special cases.
Steam drums shall be positioned on supporting structures, previously installed and welded to the
main roof beams of HRSG casing, just after completion of the erection of pressure part modules.
Lifting of HP drum shall be carried out using the 600 MT crane used for lifting the pressure part
modules, provided with cable slings of correct length and diameter, to be rigged not breaking
against any nozzle or nozzle reinforcement pad of the drum.
Proper Packing shall be used with cable slings to prevent scratching and/or damage to the
material.
Dedicated lifting plan shall be prepared for handling and lifting of the drum well in advance before
erection.
Drums shall be positioned in accordance to specific project erection drawings, taking into
consideration that the support saddles of drum shall be provided with Teflon pads, sliding on steel
plates lined with Teflon too.
Check shall be done to make sure to attach the Teflon sliding packs to both the drum base plates
and support steel prior to setting the drum on the support structure.
Guides shall be installed around each saddle after the drum is set in its final position
Anchor bolts for saddles should be warm tight. All anchor bolts shall be equipped with double
nuts.
It is important in having drums correctly installed and leveled with a difference in elevation of the
drum center line from one end to the other not greater than 10 mm. The elevation and the
location of drum nozzles shall be within the following tolerances:
Elevation: +/- 10 mm.
Location: +/- 6 mm.
After that final positioning of the HP drum has been completed, following activities shall be carried
out:
a) Erection and welding of all lines connected to the nozzles of the drum, including vents and
drains.
b) Erection of drum safety valves, silencers of safety valves and supporting structures (to be
carried out after completion of the hydraulic tests), valves, vents and drains.
c) Execution of pressure tests of the drum in accordance with contractual standards and codes
and SUPPLIER DESIGN.
d) Installation of internal filter pads (to be carried out after completion of HRSG chemical
cleaning).
e) Execution of final inspection, and general cleaning of the drum after completion of chemical
cleaning.
The filters shall be removed before carrying out drum pressure test for being reinstalled inside the
drum after completion of the boiler chemical cleaning.
The installation of all internals parts like cyclones and demisters commences after the completion
of all Mechanical Activities and when the Boiler has completed its chemical cleaning and/or
blowing.
The atmospheric blow down tank shall be installed on ground designed and specified within the
erection drawings. Placement and assembly will follow the site requirements after a proper check
of the foundation provided. Installation shall be as per relevant approved drawings
issued for such a purpose.
3. Positioning of tank on foundations, leveling the tank with suitable shim packing;
6. Execution of hydraulic pressure tests, including preparatory operations for the execution of
pressure tests, supplying of base materials for laying of temporary lines, blinding and/or capping
of flanges and nozzles, eventual removal of instrumentation, execution of pressure tests, final
restoring of lines and instrumentation after completion of the tests;
Piping shall be installed to meet the requirements of drawings, Codes & Standards as they
pertain to welding, procedure, qualification, post weld heat treatment, nondestructive
examination.
    Piping erection being major and the most critical activity of the whole construction schedule of the
    HRSG, therefore best resource shall be deployed for erecting the piping in accordance to
    contractual schedule.
    Prior to any operations, a check shall be made to ensure that the supplied spools and
    components are in accordance with the relevant documents (specifications, drawings,
    certifications). If anything found deviating from (specification, drawings, certification), same shall
    be reported to Owner.
    - Identification of materials shall remain possible, either by retaining or by transferring the mark
    stipulated by the product standard or by a unique code (Stamping by round edges is
    recommended).
    - Piping ≤ 2” spools, further cutting and adjustments on site, shall report on each part spared from
    the identification number a new marking (equal from the original mark) to ensure material
    traceability.
    -Drain line, which are likely to cause condensation shall be installed with adequate slopes and
    traps.
    - Internal and external surfaces to be welded shall be clean and free from paint, oil, rust, scale
    and other material that would be detrimental to either the weld or the base metal when heat is
    applied.
- Coated parts shall be free of coating products for a sufficient length of both sides of the weld.
    - To protect the ends of piping (e.g. bevels, screwed ends, flange faces) suitable measures shall
    be taken e.g. covering, coating, etc. The applied protection shall be removed only before the
    parts are joined.
    - Prefabrication of Spools (Cutting, Beveling, Welding) shall be done as per WPS, Drawings,
    Codes & Standards.
    - Pre-assembly of spools at ground shall be done as much as permitted for handling and
    accessibility for erection.
    - Before starting pipelines erection, pipe routing and accessibility of spools shall be checked, to
    anticipate and correct any interference with structures or parts already installed. Particularly,
    pipes connecting harp lower headers to headers external to the HRSG, shall be positioned, if
    available, before installation of the overhanging harps, to avoid possible interference during
    erection.
- While Installation proper dummies shall be installed in place of Non available valves.
- All lines > 2” shall be considered to be supplied as prefabricated, with primer coating applied.
-   All modification works shall be indicated on Erection drawings that have been carried out
    because of route changes of lines (mark-up drawings at site), to allow the easiest execution of
    the “as built” drawings,
- Excess length available in pipe spools shall be trimmed to fit site condition.
- Pipes supports shall be trial fit, trim to fit and shall be finally installed.
-   All piping spools shall be air blown using Compressor before erection in order to remove any
    foreign materials trapped inside spools.
- All piping equal or lower than 2” shall be fabricated and erected in suit to site condition.
-   All modification works shall be indicated on Erection drawings that have been carried out
    because of route changes of lines (mark-up drawings at site), to allow the easiest execution of
    the “as built” drawings,
-   Vents and drains of all HRSG equipment, piping, valves and safety valves, primary tubing, tanks,
    pumps and any other boiler components, shall be routed to the nearer collecting /discharging pit
    or equipment, even if the location of the discharging point and detailed routing of lines is not
    precisely shown on drawings and isometric drawings.
General
    Checking of spools, fittings, valves, supports, any component of the line, before commencing
    the erection of each specific pipe line. In case that any piping spool, support, valve and/or
    accessory has no identification tag shall be immediately notified to SUPPLIER.
    a) All site welding and associated Non Destructive Tests and controls shall be carried out in
    accordance to specifications, Code & ITP.
    c) It is compulsory that welding on pressure parts commences only when the execution of
    associated Non Destructive Tests is assured.
    d) Welded joints have to be carried out by electric arc welding. Electric arc manual welding
    process shall be in accordance with Standards and Codes
e) All site welders shall be qualified according to all Standards and Codes.
    f) Before starting any site welding, updated list of all welders shall be submitted for an approval
    , showing for each welder his welding qualification for different welding categories, positions and
    materials. Said list shall be kept updated during execution of work and shall be handed over to
    concern person if required.
    g) Each site welding shall be stamped with the number and/or initials of the qualified welder who
    carried out the welding.
    h) Welding record master book shall be maintained, indicating the names and punch numbers of
    all welders, the list of performed welding with date of execution, reference of any repairs that has
    been carried out. Such register shall be made available to concern person upon request.
j) Spools to be welded, especially for high alloy steel, shall be linked and aligned to each other by
means of suitable coupling devices before the execution of the first welding layer foreseen by
WPS. Temporary tack-welding has to be carried out by qualified welders and shall be eliminated
by grinding. Temporary tack welding is forbidden for materials to be heat treated.
k) Welding rods to be used shall ensure a deposit having the same chemical and physical
characteristics of the base material to be welded.
m) All welding defects shall be attended as per applicable procedure and standard.
n) Butt weld joints of carbon steel piping and low alloy steel piping shall be carried out with a
root pass made by TIG process (in Argon atmosphere).
o) In case that the thickness of spools and/or valves to be welded is different, the spool with
bigger thickness has to be internally/externally beveled and ground to get same diameters in
correspondence of the welding.
p) All primary lines starting from piping and/or equipment shall be completed up to the second
root valve (included).
q) All threaded junctions shall be in accordance with all applicable Standards and Codes.
s) Vertical runs of piping shall be supported by suitable blocks which shall be welded to piping
using approved welding procedures and welding rods
t) During the execution of works, care shall be taken to avoid any possible corrosion,
damage or presence of any foreign matter into piping, tanks or any other components of the
HRSG, by means of sealing caps installed at the piping and/or nozzle ends. Caps shall be
removed only just before lifting the pipe spool and, when possible, just before carrying out the
welding. It is compulsory that all piping spool have to be carefully blown before being fitted up.
u) All valves, particularly the motorized ones, have to be welded keeping the actuator in closed
(valve flap or plug in contact with relevant seat but not in a forced position) or open in
accordance to the instruction of the Valve Manufacturer and up to the completion of pressure
test of the line.
v) Fixing pins of spring supports shall be removed after completion of pressure tests and final
setting of the supports.
w) Primer coating shall be immediately applied to each welded joint for protection after
completion of welding, heat treatment and NDT, in accordance to contractual painting
specification.
x) Calibrated diaphragms of flanged flow meters shall be immediately removed after the erection
and installed only after completion of boiler steam blowing. Welded flow meters have to be
installed after completion of steam blowing at least for the main steam ad hot reheated steam
lines, using a temporary spool during HRSG steam blowing, to be erected, welded, removed.
y) Temporary spools shall be welded for welded flow meters before carrying out boiler pressure
tests, including the execution of required NDT and PWHT
Supports and hangers shall be erected according to erection drawing. Prior to erection, hangers
shall be inspected for damage, proper assembly and greasing.
- Structural attachment shall be accurately located with relation to columns and frame center line,
equipment location and required offset. Attachments for sliding supports, anchor bases and floor
stands shall be accurately leveled. Sliding supports and guide bearings shall be arranged in the
cold position such that the sliding pad is located on its supporting parts for all movements
predicted by the design.
- Variable spring hangers and constant hangers delivered by manufacturers as locked, shall be
kept locked during the installation and assembly of the piping, unless otherwise specified by
SUPPLIER.
- Supports shall be installed to ensure that the identification, load and travel scales are readily
visible. All threaded parts shall be fully engaged and locking nuts tightened.
- The fixing of the support to the structure shall be adjusted to ensure that the angles of support
rods are in accordance with the specified limits.
Pump assembly with all auxiliaries and accessories shall be stored indoor strictly in accordance
with Manufacturer’s instruction and on the basis of what indicated in the paragraph dedicated to
preservation of aforesaid machinery.
During storing into warehouses, installation, alignment and pre commissioning operations
preceding the first start up, the pumps shall be adequately protected with temporary sheds and/or
polythene sheets.
Pump rotors shall be weekly rotated to avoid damaging of the pump seals.
Pumps are supplied on skids, therefore following assembly activities shall be carried out:
      a) Control of foundations and relevant embedment, cleaning included, before positioning
      the pump skid.
        b) Control and execution, by means of suitable plates and/or shims, of pump elevation
        and preliminary alignment. Shims shall be made of rustproof material, possibly of unitary
        thickness and any packing of shims shall anyway not include more than three shims.
               c) Execution of the final alignment before and after connecting suction and discharge
               piping, in accordance with tolerances required by the Supplier of machinery, inclusive of
               the coupling/uncoupling operations of the pump/motor union joint.
       All equipment and accessories will be supplied with surface preparation and at least with primer
       coating. Where necessary, touch up painting shall be done after erection in full compliance with
       the applicable paint specification.
       Inspections and, if required, touch up of the painted surfaces of the equipment will be carried out
       prior to the final erection and completion.
       At touch up painting completion, an inspection will be undertaken of all activities and witnessed
       by parties as per ITP.
The acceptance of work and comments if any, shall be recorded on a general approved format
Note:
       Any damages of painting during Transportation shall be reported to Owner in the MRIR and
       supported by photo records.
       The QC inspection personnel, in coordination with Site Engineer/Supervisor, shall verify that the
       quality of the works and related testing activities are within the project specifications
       requirements.
       The Engineer/Supervisor shall verify that the works is accomplished in accordance with the
       specifications and the Supplier’s procedures. The Supervisor should verify any as-built record of
       works and testing, and confirm that the information meets the project requirements.
       The Supervisor shall verify that the personnel have sufficient knowledge of the procedure
       requirements. The Supervisor shall review any training and qualification records for those
       individuals who shall do the task to determine whether they are skilled enough to follow the
       procedure before the actual work is carried out.
       All NDE shall be performed in accordance with applicable Codes /Project Specification. Minimum
       NDE percentage shall be done as per applicable Project Specification. A separate written
       relevant NDE procedure shall be submitted to GAMA for approval.
       Details & Responsibilities of the Sub-Contractor for NDT work shall be submitted at a later
       stage.
       List of the Control and Test Equipment & Tools attached. Calibration certificate shall be submitted
       progressively after mobilizing to site.
       QA/QC Team:
       1) QA/QC Manager
          Mr. Yahiya Mahdi Hilal Abdualla Madan
          Diploma in Mechanical & Plant Engineering with 20 years of Experience.
           Additional Certifcation:
           NDT-ASNT LEVEL II in RT, UT, PT,MT& VT
           CSWIP 3.1 - Certified Welding Inspector, TWI 2008
           CSWIP BGAS 3.2– Certified Painting Inspector, TWI 2010
           IOSH Safety Management
           Electrical wire man license
       2) QA/QC Supervisor
       3) Mr. A. Shajahan
          Higher Secondary school Certificate with 17+ years of Experience.
Additional Certifcation:
1) HSE Manager
   Mr.Edwin Suganob
   Qualification:
   Diploma in Safety Engineering with 14+ years of Experience
   Additional Certifcation:
Certificate of Training for Tower crane Rescue (High Angle training Centre)
Certificate for Instructional Training course for Assisted Rescue Kit (ARK)
2) HSE Supervisor
   TBN
  General PPE’S like Helmet, Safety Shoes, safety Glass, coverall, Safety Harness etc. shall
  be provided to all workforce. Special PPE’S like Breathing Devices shall be arranged if
  required.
  HSE PLAN ATTACHED.
15.0   REFERENCES
       PP1314-00-Y-UP-WP-003                Project Quality Plan
       GEMSS-G-05                           Quality Control & Quality Assurance Plan.
17.0   ATTACHMENTS
       Attachment-1         Planned Manpower Distribution Histogram.
       Attachment-2         Equipment Histogram (Subcontractor & GAMA)
       Attachment-3         Detailed Schedule
       Attachment-4         Quality Assurance Plan & Inspection Test Plan
       Attachment-5         CV of the QA/QC Manager
       Attachment-6         Non-Conformities Procedure
       Attachment-7         List of the Control and Test Equipment & Tools attached. Calibration
                            Certificate shall be submitted progressively after mobilizing to site.
       Attachment-8         HSE Plan
       Attachment-9         Hazard Identification & Risk Assessment Procedure.