MINT CDA Mining Dams Bulletin 2014 EN Chrystian Alexander Caceres Dominguez Sr. of GEOHIDRAC SAC
MINT CDA Mining Dams Bulletin 2014 EN Chrystian Alexander Caceres Dominguez Sr. of GEOHIDRAC SAC
2014
Main entry under title: Application of Dam Safety Guidelines to Mining Dams
Issued also in French under title: Application des Recommandations de sécurité des
barrages aux barrages miniers.
ISBN 978-0-9936319-2-4
                                                       ii
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
TABLE OF CONTENTS
Preface       iii
1.0   Introduction .............................................................................................................1
2.0   Mining Dams – Description and Phases............................................................3
        2.1 Definition and Functions of Mining Dams......................................................................... 3
        2.2 Phases in the Life of a Mining Dam .................................................................................... 5
             2.2.1 Definitions ................................................................................................................ 5
             2.2.2 Site Selection and Design ....................................................................................... 6
             2.2.3 Construction ............................................................................................................. 7
             2.2.4 Operation .................................................................................................................. 7
             2.2.5 Closure ...................................................................................................................... 7
             2.2.6 Transition.................................................................................................................. 9
             2.2.7 Closure – Active Care ........................................................................................... 11
             2.2.8 Closure - Passive Care .......................................................................................... 12
        2.3 Possible Resumption of Operations .................................................................................. 13
        2.4 Landforms............................................................................................................................. 13
        2.5 Environmental Considerations .......................................................................................... 14
3.0   Construction, Operation and Transition Phases ............................................15
        3.1 Dam Safety Management ................................................................................................... 15
             3.1.1 General .................................................................................................................... 15
             3.1.2 Engineer of Record ................................................................................................ 16
             3.1.3 Consequences of Failure ....................................................................................... 17
        3.2 Operations, Maintenance, and Surveillance .................................................................... 20
        3.3 Emergency Preparedness and Response .......................................................................... 20
        3.4 Dam Safety Reviews ............................................................................................................ 21
        3.5 Analysis and Assessment ................................................................................................... 22
             3.5.1 Risk-Informed and Traditional Standards-Based Approaches ....................... 22
             3.5.2 Hydrotechnical ...................................................................................................... 23
             3.5.3 Seismic Criteria ...................................................................................................... 26
             3.5.4 Geotechnical ........................................................................................................... 27
4.0   Active and Passive Care Phases .........................................................................31
        4.1    Dam Safety Management ................................................................................................... 31
        4.2    Operations, Maintenance, and Surveillance .................................................................... 32
        4.3    Emergency Preparedness and Response .......................................................................... 32
        4.4    Dam Safety Reviews ............................................................................................................ 33
        4.5    Analysis and Assessment ................................................................................................... 33
5.0   Considerations for Covers ..................................................................................37
6.0   Future Ownership, Liability and Custodial Transfer ...................................38
7.0   References ..............................................................................................................40
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                 i
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
                                                 LIST OF FIGURES
Figure 2-1. Phases in the Life of a Mining Dam ....................................................................................... 6
Figure 3-1. Typical Appurtenances Required for EDF Storage and IDF Conveyance ..................... 23
LIST OF TABLES
                                                            APPENDIX
Appendix A.              Comparison to MAC and ICOLD Guidelines
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                 ii
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
Preface
The Canadian Dam Association publication Dam Safety Guidelines (CDA, 2013) outlines principles
that are applicable to dams of all types. These include “mining dams” which are retaining
structures at mine sites or metallurgical plant sites that retain solids or liquids that may or may
not be contaminated.
This Bulletin was prepared by the CDA Mining Dams Committee, which has members
representing a broad range of the mining community in Canada. The focus has been on the
Canadian context, but the principles are generally applicable to dams in any jurisdiction.
Regulatory requirements vary considerably and must be met in all cases. Other expectations and
requirements may also apply, including corporate policies and guidelines, industry standards,
and legislation at provincial and federal levels.
This Bulletin is not intended to duplicate or replace the extensive guidance that has been
prepared by other organizations. For example:
    •   The Mining Association of Canada (MAC) has published a number of guides for the
        mining industry, particularly in relation to management of mining facilities.
    •   The International Commission on Large Dams (ICOLD) has issued guidance on overall
        tailings systems, sustainable design and closure principles, and long term monitoring.
In making dam safety assessments and decisions, the responsible engineer or decision-maker
must assess and interpret guidance and information from all available sources and determine the
appropriate requirements for a specific situation.
While every reasonable effort has been made to ensure the validity and accuracy of the
information in this Bulletin, the Canadian Dam Association and its membership disclaim any
legal responsibility for use of Dam Safety Guidelines and this Technical Bulletin.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                 iii
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
1.0 Introduction
This Technical Bulletin (“Bulletin”) is intended to complement the Dam Safety Guidelines published
by the Canadian Dam Association (CDA, 2013) by providing additional explanation of how the
concepts described in the Dam Safety Guidelines (CDA, 2013) apply to mining dams. The Bulletin
identifies some specific issues that should be considered during the design and safety evaluation
of mining dams.
A number of documents provide guidance on the design of mining dams (in particular tailings
dams) and the reader is referred to the list of References included in this Bulletin for information.
A key reference document is the ICOLD Bulletin 139, “Improving Tailings Dam Safety: Critical
Aspects of Management, Design, Operation, and Closure,” issued in 2011. ICOLD Bulletin 139
provides information on the overall tailings system, including tailings deposition, design, water
management, environmental management, operation, closure, risk management, emergency
preparedness, and the role of the regulators. In 2013, ICOLD issued Bulletin 153, “Sustainable
Design and Post Closure Performance of Tailings Dams,” which builds on the previous bulletin
with a focus on sustainable design and closure principles and long term monitoring.
This Bulletin is intended for a technical audience familiar with mining operations and issues
related to managing mine waste, including: contact water, process water, leach solutions,
treatment solids, tailings, acid rock drainage/metal leaching (ARD/ML), leachates, etc. The focus
is on the dam safety aspects for dams typically associated with mining of metals (e.g. nickel, iron,
copper, lead, zinc, gold), non-metals (e.g. phosphate, potash, gypsum), structural materials
(aggregate and limestone) and fuels (uranium, coal, oil sands).
    •   Section 2 describes mining dams in general and the associated objectives of mining dams.
        It focuses on earth embankment dams and does not address concrete dams explicitly, but
        many of the concepts can be applied to concrete dams as well. Section 2 also describes the
        life phases of mining dams, an important concept used throughout this Bulletin.
    •   Section 3 describes how the Dam Safety Guidelines (CDA, 2013) can be applied to mining
        dams during operation and preparation for closure.
    •   Section 4 addresses closure, which is a significant issue for mining dams. It addresses
        criteria and minimum practices for dam safety during closure.
    •   Section 5 provides guidance on items that should be considered when designing for wet
        covers.
    •   Section 6 presents long term issues such as ownership, liability, and custodial transfer of
        mining dams back to the Crown.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                1
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                2
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
In this Bulletin, the term “mining dams” refers to retaining structures that exist at mine sites or
metallurgical plant sites that are designed to retain solids (that may or may not be contaminated 1)
and/or contaminated liquids. Examples of mining dams include:
Mining dams are built during the development and operation of mines. Many mining dams can
remain as part of the landscape, becoming permanent features that have to perform as designed
for many years after closure of the mine.
Tailings dams are the most significant type of mining dams as they usually contain large
quantities of fluids and solids that are generated from the processing of ore. These fluids and
solids can cause environmental damage if released and, in the majority of cases, this applies for
hundreds of years after the cessation of operations, and possibly in perpetuity.
Tailings dams are usually earthen dams that are constructed of:
      •   Naturally occurring materials including blasted or crushed rockfill, and/or borrow fill
          material
      •   Tailings either without additional processing or after cycloning
      •   Geosynthetic materials
A tailings dam may or may not have a water pond impounded directly against the dam.
In some cases, the tailings contained by a mining dam are not contaminated and do not present a
risk to the environment in terms of surface and groundwater chemistry, but the solids must be
contained.
In this Bulletin, the terms “pond” and “impoundment” are used interchangeably, referring to the
ponded water or deposited tailings upstream of the dam (or upstream of the structural portion of
an upstream constructed tailings dam).
1“Contaminated” means that the solids or fluids have concentrations of chemicals of concern that
have the potential to adversely affect the environment or human health.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                3
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
In the Dam Safety Guidelines (CDA, 2013), a dam is defined as a barrier constructed for the
retention of water, water containing any other substance, fluid waste, or tailings. Although there
is guidance provided with respect to the minimum size of a structure that could be considered a dam
(minimum of 2.5 m in height), the definition of a dam includes dams less than 2.5 m high if the
consequence of failure is likely to be unacceptable to the public, such as dams retaining
contaminated substances. Hence, in the context of mining dams, there is no minimum size if they
contain contaminated substances (fluids and/or solids) where the consequences of failure could
be unacceptable to the public.
Mining dams are designed, constructed, and operated to meet a number of objectives of their
owners that include:
    •   Ensuring safe storage of tailings or other mine wastes that are produced during operation
        and closure, both fluids and solids, in many cases for the long term.
    •   Protecting the environment from degradation due to the release of water from the
        containment ponds during their operation and after closure.
    •   Supporting the water management requirements of the site including recycle water,
        diversion of fresh water, and managing mine effluent to meet discharge requirements.
Many mining dams are built in stages over the life of the mine, rather than built in a single stage
prior to commissioning.
In some cases, a mine site may not have a concentrator 2 that produces tailings but still generates
contaminated water that requires containment and management on site.
In some cases, the term “dam” has been used by mine operators to refer to an entire tailings
storage facility. For the purpose of this Bulletin, the dam is considered to be the perimeter
containment structure(s) around the tailings facility. Within a tailings facility, there can also be
internal structures that should be treated as dams if they provide containment of solids and/or
fluids. The terms “dyke” or “dike” are used by some mining operators. In this Bulletin, these are
all treated as dams.
Mining dams can be located within mined out pits to isolate a portion of the pit for the storage of
the contaminated water and solids. In this instance, a failure of the in-pit dam may not have
significant environmental consequences, but there could be substantial operational issues and
threats to life (mine operators). In some cases, such as when depositing tailings in an open pit, the
natural ground areas (overburden and bedrock) on the sides of the pit are used for containment.
Or, when an open pit is excavated, a separating natural berm can be left in place to isolate the pit
from a nearby lake or pond. These cases need to be assessed to determine if the structure should
be treated as a dam and if so, then the guidance provided in this Bulletin and the Dam Safety
Guidelines would apply.
2In this Bulletin, the term “concentrator” is used to represent the facility that produces the
tailings but could also be referred to as a processing facility, mill, or upgrader.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                4
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
In many cases after mine operations cease, there is no pond or there is limited pond on the
surface of the facility such that the facility appears as a tailings “stack.” If a breach of the
perimeter containment, regardless of the triggering mechanism, can trigger liquefaction or flow
of the contents of the stack that can extend beyond the perimeter containment, then the perimeter
containment must be considered as a dam, even though there is no visible water on the surface of
the stack (i.e. no pond). In some cases, there can be water temporarily ponded on the surface from
precipitation. This is consistent with the definition of a dam as described above.
If the contents are not liquefiable and cannot flow, then the perimeter containment does not need
to be considered as a dam but rather an embankment slope, and the facility can be treated as a
waste disposal area similar to an overburden disposal area. The consequences of failure would
need to be evaluated for such a slope and appropriate slope design practice would apply. Often,
design guidance exists for dumps and overburden disposal areas and would be applicable in this
instance.
In this Bulletin, the term “conventional dam” is used to describe dams that control or manage
fresh water, such as for (i) the generation of hydroelectric power, (ii) flood control, and (iii) fresh
water storage. Fresh water containment and diversion dams can exist on a mine site and they are
still considered to be conventional dams. Often, these dams are intentionally breached shortly
after the mining operation ends. However, in some cases these dams are required to divert water
to support a wet cover over tailings (with or without free visible water at the surface), to maintain
separation of water that has been affected by mining from non-contact water, or for fish habitat
compensation or preservation during the closure phase. If such dams are required for the long
term, consideration of design criteria for mining dams in the closure phase may be appropriate
(see Section 4).
2.2.1 Definitions
        This section defines and describes the phases in the life of a mining dam as shown in
        Figure 2-1, discussed in the following sub-sections, and listed as follows:
        • Site Selection and Design
        • Construction
        • Operation
        • Transition
        • Closure – Active Care
        • Closure - Passive Care
        The term “life cycle” is often used to describe the life of a facility, but that term is most
        suitable for structures that are constructed and then removed. For many mining dams
        that cannot be removed, the term “cycle” is not applicable. For this reason, the term
        “phase” has been adopted for this Bulletin.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                5
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        On a single mine site, there may be several mining dams, each at a different phase of the
        life as described in the following sub-sections. Each dam is to be considered
        independently.
        Appendix A provides a comparison of the life phases described in this Bulletin with
        guidance from the Mining Association of Canada (MAC) and the International
        Commission on Large Dams (ICOLD). The concept of Transition Phase, as described
        below, is not explicitly addressed in the MAC and ICOLD documents.
        The Site Selection and Design phase includes all of the preparatory work that is
        undertaken prior to constructing the mining dam. Improper siting of a mining dam has
        resulted in dam safety problems as the mine development proceeds and the siting needs
        careful consideration. During this phase, design criteria will be established that recognize
        the planned operational life of the dam and also the anticipated closure requirements.
        The closure requirements for a mine site can have a significant bearing on the site
        selection and design of a mining dam.
Other items that merit consideration in siting a mining dam are as follows:
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                6
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
2.2.3 Construction
        Some mining dams may be completely constructed before a mine or mill commences
        operations. More often, a mining dam is initiated with a starter dam at the start of the
        operation and then periodically modified or raised during the Operation Phase.
        A mining dam can also be modified after operation as part of mine closure (typically
        within the Transition Phase described below).
2.2.4 Operation
        During the Operation Phase, the dam may continue to be modified. Changes in tailings
        composition or regulatory requirements may necessitate amendments of the original
        design criteria. The dam may also be raised or a new dam added to provide for
        additional storage capacity.
        The Operation Phase can last for decades. It should be noted that the duration of the
        Operation Phase is often different than the life that may have been contemplated during
        site selection and initial design, since mine life can be affected by the availability of
        resources and economic, technical, social and environmental factors that may evolve over
        time. Regardless of the mine life, the dam should be designed to anticipate the potential
        for temporary production suspension and the potential for that temporary condition to
        become permanent. During a temporary or indefinite suspension of mining activities, the
        dam owner should monitor the dam and maintain it, but no modifications are made to
        the structure. In this condition, measures are not implemented to prepare the dam for
        closure. The dam would be operated and maintained in anticipation of restarting
        production.
        In cases where the mining dam is constructed over the life of the mine, the design,
        construction, and operation phases are closely integrated and can be difficult to separate.
2.2.5 Closure
        As described above, many mining dams will need to remain in service well after the
        mining operation has ended. ICOLD (2011) defines closure as follows:
                “The shutting down and decommissioning of a mine and tailings dam when
                production has ceased including the transition of the mining area and dam into
                long-term stable structures. Normally, closure includes decommissioning,
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                7
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
                remediation (reclamation or rehabilitation) and after care at the site and the
                tailings dam.”
        Of interest, the ICOLD definitions infer that modifications to the dam are taken as
        mandatory for closure. Often, the dam can be “designed for closure” such that
        modifications at closure are not required. For tailings dams, closure of the tailings facility
        begins when the tailings storage ends. The same can be said for dams that store water
        treatment sludges.
        For other mining dams on a site, such as water treatment dams and diversion dams, the
        closure might not begin until the mine operation has ended and the rest of the mine is
        being decommissioned. Hence, for this Bulletin, there are two aspects with respect to
        closure. There is closure of the mine or processing facility after they are no longer
        required. This involves decommissioning structures and reducing the work force on site.
        However, for a tailings or sludge storage dam, closure can begin when the tailings or
        sludge storage facility has reached capacity. This can happen while the mine or
        processing facilities are still operating at the site, well before the mine or processing
        facility “closes.” For many mining dams, they have to provide their intended function for
        a very long time including closure. Hence, this Bulletin provides the following
        definition for closure of a mining dam:
                Closure is the process of establishing a configuration for the dam with the
                objective of achieving long term physical, chemical, ecological, and social
                stability and a sustainable, environmentally appropriate after use. This
                configuration can be achieved during or after mine operations.
        As noted above, on a mine site there may be several dams at different phases of their life,
        with some dams considered to be in closure while the mine is still operating. This would
        be considered part of progressive reclamation, but from the perspective of regulators,
        closure of a mining dam might not officially begin until the mine or processing facility is
        shut down (i.e. the site is closing).
        It is important to note that the closure of a mining dam has to be done in the context of
        the closure of the impoundment contents contained by the dam. The two are
        interdependent as the closure of the impoundment contents can have a direct bearing on
        the closure requirements of the dam.
        In this bulletin, the terms “reclamation” and “rehabilitation” both refer to upgrades or
        modifications of the mining dams to meet the design objectives for closure.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                8
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        The term “decommissioning” is often used when referring to closure of mining dams. In
        this Bulletin, the term “decommissioning” is used when referring to removal or breach of
        a dam so that it no longer retains tailings or water that may pose safety or environmental
        concerns. Partial breaching of a dam is considered rehabilitation not decommissioning.
        The portion of the dam that remains in place holding tailings back will still need to
        function as a tailings retaining dam (if the tailings can flow). In general, water retaining
        dams can be decommissioned by breaching. Decommissioning of a tailings retaining
        dams will typically require complete removal of the dam and relocation of tailings it
        retains. However, the consequences of failure would be significantly reduced through
        the partial breaching.
        In addition, the closure designs have to consider aboriginal and social issues associated
        with the future land use of the areas affected by the mining dams.
        As noted in Figure 2-1, there are three main phases in closure of a mining dam:
        Transition, Closure - Active Care, and Closure – Passive Care.
2.2.6 Transition
        The first phase of closure is Transition. This phase typically commences when the mining
        dam has reached its capacity and ceases to be operated or when the mine or processing
        operation is terminated permanently. Activities are undertaken during this period to
        prepare the mining dam for the Closure – Active Care or the Closure - Passive Care Phases.
        During the Transition Phase, the mining dam may be decommissioned through
        breaching or removal. From an environmental perspective, dams that contain non-
        contaminated solids are easier to breach than dams that contain contaminated solids.
        When there is no practical option to decommission the dam, the dam must be designed
        and maintained as a long term and possibly permanent structure.
        Where there are multiple storage facilities, it is not uncommon that tailings or sludge
        storage dams are progressively rehabilitated once they are filled and deposition
        commences in a newly developed area. In this case, such dams that are progressively
        rehabilitated would be in the Transition Phase during that rehabilitation period.
        The Transition Phase can be undertaken at the same time as other decommissioning
        activities at the mine site (e.g. demolition, sealing of mine openings, etc.)
        The Transition Phase can typically involve one or a combination of the following
        activities related to a mining dam:
        •   Breaching the mining dam, as noted above. Portions of the mining dam may remain,
            but the consequences of failure of these portions would be substantially reduced or
            eliminated.
        •   Modifying the dam, spillway, and discharge structures to accommodate a water
            cover and water treatment system. In some cases, the water cover is established
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                9
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
            within an upper layer of soil or gravel such that the water is not visible, but the
            closure concept for the impoundment requires an elevated water table to prevent
            acid generating and metal leaching. This is effectively the same concept as
            establishing a water cover, also referred to as a wet cover. The dam could be
            modified by re-grading or contouring to improve stability, the surface drainage
            systems could be modified to manage flood events while recognizing other long term
            factors (vegetation and beavers), the upstream and downstream slopes could be
            protected by placing erosion protection materials, site access could be controlled, and
            other measures may be undertaken to reduce the need for long term maintenance
            and surveillance. As noted above, the dam can initially be designed for closure such
            that these modifications would be minor. Note that Section 5 provides a discussion
            on considerations when designing for covers.
       •    Modifying the dams, spillways, and discharge structures to remove a pond and not
            allow a pond to remain on surface while also safely passing floods. This may also be
            done in conjunction with the installation of a reclamation cover on the facility, such
            as vegetating the tailings beaches. The items noted in the previous bullet related to
            regrading the dam, placing erosion protection materials, etc., would be applicable to
            this activity as well.
       If it can be demonstrated that the material contained by the mining dam (i.e. in the
       impoundment) is not liquefiable and will not flow if the containment structure is
       breached, then the containment structure is no longer considered a dam. (See Section 2.1
       for the discussion related to a stack.) Measures may be implemented during the
       Transition Phase to achieve this condition (i.e. to reduce liquefaction potential of the
       tailings). Factors that need to be considered in this assessment are discussed in Section
       3.5.
       The end of the Transition Phase occurs when the activities noted above are completed for
       entering the Closure – Active Care Phase. The mining dam may or may not have
       achieved a steady state condition with respect to pore water pressures, deformations,
       erosion, etc. While the physical modifications can be completed in a relatively short time
       frame (e.g., several years), the confirmation of performance can take longer and this
       would extend into the Closure – Active Care Phase.
       Typically, a closure plan for a mine will detail the measures that are to be implemented
       for closure including the required modifications to the dams. At the end of the Transition
       Phase, these measures will have typically been completed and the dams are considered
       “closed.” The Transition Phase can last from one year to decades. On some mine sites, a
       tailings facility and dam may end operation well before the end of the mine life and will
       be considered to either be in the Operation Phase or the Transition Phase until closure
       measures are implemented at the site that address this particular facility.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                10
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        This phase involves active care of a mining dam, including monitoring, inspection, water
        management, operation of a water treatment system, etc. after the Transition Phase is
        completed.
        For the case where the mining dam has been designed to accommodate a water treatment
        system, this phase would involve ongoing operation, maintenance and surveillance, and
        possibly management of the water levels. This phase is often referred to as “care and
        maintenance.”
        In many cases, these activities could last for decades or centuries. In some cases, a
        treatment system may be established to address a short term concern with respect to
        water quality and the treatment system may be needed for less than a decade. The
        treatment system can be decommissioned and the dams could move into the Closure –
        Passive Care Phase at that time.
        For the case where the pond has been removed from upstream of the dam and the mining
        dam still has to be treated as a dam because the contents upstream of the dam can flow
        upon failure of the dam, the following activities would typically be involved in this phase:
       In some cases, these activities may last for less than a decade and then the dams can
       move into the Closure – Passive Care Phase. The mine owner will typically have staff
       monitoring the site on a regular basis during the Closure - Active Care Phase.
       During the Closure – Active Care Phase, the performance of the dams should achieve a
       steady state condition. This could include the following:
       When this steady state condition has been achieved, the dam could be considered for
       Closure – Passive Care. Due to the time needed to reach a steady state condition, it is
       unlikely that a mining dam will be able to move directly from the Transition Phase to the
       Closure – Passive Care Phase. However, the length of the Closure – Active Phase could
       be quite short in some cases (i.e. a few years). In other cases, the Closure – Active Care
       Phase could last decades or longer.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                11
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        A key requirement of the Closure – Active Care Phase is that the mining company
        normally has resources on site that are able to respond to problems and possible
        emergencies that may develop. This is an important consideration when addressing the
        design criteria as noted in Section 4. Where there is no active effluent treatment or water
        management requirement, the mining dam could be monitored and maintained during
        the Closure – Active Care Phase using off site personnel who inspect the dam on a
        regular basis. As noted in Section 4, the surveillance program during the Closure - Active
        Care Phase should be clearly described in the Operation, Maintenance and Surveillance
        (OMS) Manual, including emergency response.
        ICOLD (2013) defined Active Care as the period when intervention and monitoring is
        required to achieve a final sustainable form. In this Bulletin, this period has been divided
        into the Transition and Closure - Active Care Phases where the majority of the
        intervention, if required, is in the Transition Phase and the Closure – Active Care Phase is
        operating, maintaining, and monitoring.
        In this phase, there is no active operation of the mining dam and no changes to the
        mining dam are expected to occur. The dam is considered to be in a steady state
        condition and sufficient experience has been gained with the structure and sufficient
        monitoring has taken place to demonstrate that no further intervention is required by the
        owner. There is no requirement for water treatment or intervention by operating
        personnel to manage water levels in the pond upstream of the dam. The system is in a
        passive state that does not require operating personnel on site or regular surveillance. A
        spillway has been established to passively release water from the system to the
        environment. Potentially erodible exterior slopes have been covered or otherwise treated
        (i.e. vegetation or rock fill).
       This phase is an important goal for a mining company - to have the structure in a stable
       form with low maintenance. Inspections by dam safety engineers and dam safety reviews
       will continue with maintenance undertaken as required. Remote monitoring systems
       might be employed. Special inspections may be required after extreme events.
        The monitoring plan discussed in Section 4 would describe the Owner’s plans for
        monitoring the dam during this phase and the plans would be subject to the regulator’s
        review and approval before implementing. This phase can last for hundreds of years or
        longer and is the longest phase in the life of a mining dam that is not decommissioned.
        It is important to note that Closure – Passive Care Phase is not the same as
        “abandonment” or “walk away.” Many dams are abandoned without the appropriate
        measures implemented to prepare the dam for Closure – Passive Care Phase. Such dams
        often pose an unacceptable risk because they were not prepared for closure properly. As
        discussed in Section 4, a dam in Closure – Passive Care Phase still requires some level of
        inspection, dam safety reviews, and emergency response. This should be spelled out in
        an OMS Manual for this phase.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                12
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        When a mining dam is on a lease from the provincial or federal government and is in the
        Closure – Passive Care Phase, then it may be eligible for transfer back to the Crown –
        referred to as Custodial Transfer. This is discussed further in Section 5.
In some cases, even though a mining dam and associated facility are in either the Closure –
Active Care or Closure – Passive Care Phase, the owner may wish to reactivate a dam. I f this
occurs, then the mining dam would revert back to the Construction or Operation phases and the
life phases would start over.
2.4 Landforms
ICOLD (2013) has identified the condition whereby a structure may not be considered a dam if
“in the opinion of the authorities, [the dam] is considered to be physically, chemically,
ecologically, and socially stable and no longer poses a risk to life or the environment.” One
approach to achieving this is to create the dam as a permanently stable landform where the risk
of release of solids and contaminated water is negligible. This is consistent with the discussion
above, where the facility contained by the mining dam can be modified such that it no longer
meets the definition of a mining dam in Section 2.1 and is consistent with the objective of moving
towards Closure – Passive Care.
In Canada, an initiative is underway in the oil sands industry, where tailings dams could be
designed and constructed to become landforms and no longer be considered dams. This
condition is achieved through shallow side slopes, wide spillways, changing the contents of the
pond, etc. Such structures might not require regulatory oversight. This approach could also be
considered for dams beyond the oil sands industry. General guidance for mining dams for what
would constitute a “landform” as opposed to a dam is not available at the time of this Bulletin.
The risk informed approach to support the creation of a landform would be consistent with
Section 6 of the CDA (2013). This approach could take a dam to a “walk away” condition.
The interaction between the dam owner and regulator to achieve this condition is specific to the
different jurisdictions in Canada. In Alberta, the oil sands initiative noted above is being
developed with input from the regulators, to provide guidance.
Most mining dams are not expected to be classified as landforms; hence, that “phase” of the
mining dam life was not included in Figure 2-1.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                13
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
This Bulletin focuses on structural failure modes (sliding, overtopping, internal erosion, etc.) as
these are the items of focus in Dam Safety Guidelines (CDA 2013). Environmental factors can affect
the structural stability of a dam, for example when precipitate formation clogs drains or damages
filters.
There are other failure modes associated with mining dams that are non-structural in nature and
are related to environmental protection. These include:
The first item above is addressed through the concept of the Environmental Design Flood
discussed in Section 3.5. The second, third, and fourth bullets relate to seepage through the dam
and foundation. Seepage control as it relates to protecting a dam from internal erosion is an
important structural consideration and is discussed below. But, the situation where the seepage
presents an environmental risk is not addressed in this Bulletin. The last bullet is an important
design consideration, but it does not affect the structural safety of the dam.
ICOLD (1996) and Szymanski (1999) further discuss the distinction between structural and non-
structural failure modes. The “Environmental Code of Practice for Metal Mines”(Environment
Canada 2009) provides a series of recommended environmental practices pertinent to mining
dams throughout the life of a mining dam. The focus of that code of practice is on metal mines,
including uranium. The document can be used to assist with the development of objectives and
criteria for the design of mining dams with respect to environmental protection requirements.
3Loss of water cover can also be due to high evaporation, but that is not related to the design of
the dam.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                14
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        3.1.1   General
        As previously noted, mining dams can exist for a very long time. Conventional dams are
        often decommissioned (removed), modified to become free overflow weirs, or
        rehabilitated to extend their service lives, but typically these dams may be designed for a
        service life of 50 to 100 years. The service life of a closed mining dam, however, can be
        over 1,000 years. Hence, to assist with considering the risk exposure for a mining dam
        and developing criteria for the design of a mining dam, the concepts of design life and
        design interval are discussed herein.
        Design life is the period for which a component is expected to function at its designated
        capacity without major repairs. In the context of a mining dam, design life is the expected
        service life of a structure, at the end of which either the structure is removed or it
        undergoes significant rehabilitation to upgrade and bring the dam to current design
        guidelines. If a mining dam is breached or removed from service, then that would end
        the design life of the dam. However, most mining dams are not expected to be breached
        and are required for the long term.
        Because the design life can be indefinite, the concept of the design interval is considered
        in this Bulletin. This concept is described in detail by Szymanski (1999) where the design
        interval is defined as “the period under which the conditions can be considered known
        or predicted and the design can be based.”
        For example, the Operation Phase of a mining dam typically lasts 20 to 50 years. The
        conditions during the Operation Phase can be reasonably predicted, there are staff on site
        conducting surveillance, and emergency response is possible. Hence, the design interval
        for the Operation Phase would typically be 20 to 50 years. The Dam Safety Guidelines
        (CDA, 2013) work well for this length of design interval.
        In some cases, the Construction Phase for mining dams can be similar to conventional
        dams, although for many mining dams the Construction Phase and Operation Phase
        occur at the same time, with the tailings dams raised over the life of the mining
        operation. Thus, Dam Safety Guidelines (CDA, 2013) apply to the Construction Phase of
        mining dams.
        As noted above, the Transition Phase can last from one year to decades. Like the
        Operation Phase, the conditions can be reasonably predicted, surveillance is conducted,
        and emergency response is possible. Hence, the Dam Safety Guidelines (CDA, 2013) apply
        to the Transition Phase as well.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                15
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        The remainder of this section discusses how the Dam Safety Guidelines (CDA, 2013) can be
        applied for the Construction, Operation, and Transition phases. Section 4 discusses how
        the guidelines can be applied for the Closure - Active and Closure - Passive Care Phases.
        The guidance in this section would also apply to those dams that are in a state of
        inactivity or temporary suspension, where the mining operation has been suspended and
        the potential remains to resume operation at some point in the future. This assumes that
        the mining company is conducting surveillance and emergency response is possible. If
        this is not the case, then other measures need to be considered.
        Section 2 of Dam Safety Guidelines (CDA, 2013) describes the overall process for managing
        dam safety, including the elements of a management system, supporting processes and
        dam classification. The section is applicable to mining dams with appropriate recognition
        and consideration of the different phases in the life of the dam. Some of the aspects that
        are often a challenge with mining dams because of their long life are as follows:
        •   CDA 2013 defines the owner of a dam as the person or legal entity, including a
            company, organization, government department, public utility, or corporation that is
            responsible for the safety of the dam. For mining dams, the ownership can
            sometimes be confounded because the person or legal entity that owns the dam is not
            well defined and there may not be a government license to operate the dam. The
            owner of the mining dam must be clearly identified.
        •   Records management becomes a challenge with the extended life of the dam. Pertinent records
            and documents must be available and protected well into the future.
        Section 2.3 of the Dam Safety Guidelines (CDA, 2013) states that “the owner’s policy
        should clearly demonstrate the organization’s commitment to safety management
        throughout the dam’s life cycle.” This includes “delegation and authority for all dam
        safety activities. Further, “the owner’s staff and any consultants and contractors who
        carry out dam safety activities on behalf of the owner should be made aware of the
        decision making process and who is accountable for that.” In support of these requirements,
        this Bulletin considers the Engineer of Record (EOR) as an important aspect of risk
        management for mining dams. The EOR should be a qualified and competent engineer
        who is responsible for the design and performance of a mining dam. For a single mining
        dam, there can often be several engineers and engineering firms involved in the design,
        construction, and performance assessment of the dam over its life and it may not be clear
        who the EOR is for the dam. This can present a challenge for the owner when managing
        the risks associated with the dam.
        The EOR should be clearly identified by the owner with the concurrence of the EOR.
        Typically, the EOR would be involved in the construction of the dam as well. Where the
        construction is directed by the owner and continuous construction inspection is not
        provided, the EOR is not responsible for the quality during construction, but is
        responsible for ascertaining that changes made to the design during construction
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                16
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        continue to meet the applicable design standards, criteria, and guidelines. The EOR may
        be declared after the construction is completed and, in this circumstance, the EOR and
        owner need to work together to make sure that the EOR is equipped with the appropriate
        information to be able to take on this responsibility.
        During the Construction, Operation and Transition Phases, the EOR could change over
        time and it is important that the EOR, with associated responsibilities, be clearly
        identified. If there is to be a handover of the dam as a result of a transfer of ownership,
        then the EOR must remain clearly defined. Also, the EOR can change due to changes in
        employment status (such as a transfer or retirement) and the owner should ensure that a
        replacement EOR is clearly named.
        Records management related to the dams should be an integral part of a transfer to a new
        EOR, or transfer of ownership.
        The concept of an engineering consulting firm as the EOR needs further consideration
        and is beyond the scope of this document at this time.
        The consequences of failure of a mining dam that contains liquefiable solids can be
        greater than the consequences for the same dam containing only water. Although tailings
        and liquefiable solids may travel a shorter distance than water, the material can act as a
        viscous fluid with a high specific gravity that can cause more damage than water alone.
        The damage can be both physical and environmental. Removal of released solids and
        clean-up could be impractical in many cases, for example in densely forested areas or
        water bodies.
       Dam break and inundation studies are necessary to support assessment of the
       consequences of potential failure of mining dams, as for conventional dams. However,
       there are a number of challenges associated with dam breaks for tailings dams because
       the science of predicting tailings dam breaches and flows is relatively new. The current
       techniques for predicting tailings flow slide inundation are limited and the lethality of
       tailings dam failures can be quite different than for conventional dam breach flooding.
       The limitations in accurately modeling the effects of a tailings flow slide need to be
       considered when assessing the consequences of failure.
        Section 2.5.2 of Dam Safety Guidelines (CDA, 2013) calls for conducting dam break studies
        for a “sunny day” and a “flood-induced” failure. The “sunny day” failure is one that
        occurs during normal operations. Because of the contaminated fluids and solids that are
        contained by the mining dams, the incremental environmental consequences are often
        worse for a sunny day failure than a flood induced failure.
        Since many mining dams are remote from population centres, the potential for loss of life
        is often not as prevalent as it is for conventional dams. There could be occasions where
        there are people in the area downstream of the dam temporarily due to seasonal cottages,
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                17
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        roads and highways, rail corridors, and recreational activities. Mining dams can also
        have the special case where the failure could threaten employees of the mine working
        downstream of the mining dam, such as in an open pit mine. In this instance the training
        of the mine staff can be considered with respect to evacuation procedures and the
        potential for reducing the potential for loss of life.
        Environmental losses are often the most significant aspect of a mining dam failure.
        Specific studies may be required to predict the degree of environmental loss. This could
        include damage to the downstream environment, but in some cases, mining dams have
        supported ponds and wetlands that have become suitable fish and terrestrial habitat and
        this habitat can be lost through a failure.
        The economic losses to a mining company can be substantial and may be much larger
        than the direct financial burden associated with a failure. Failures of mining dams can
        result in lost production, have a negative impact on the market capitalization of a
        company, and limit the ability of the company to engage in other mining projects.
        Mining dam failures can result in loss of site infrastructure such as roads, pump stations,
        power lines, and pipelines.
        All of the potential consequences of failure need to be considered and the severity of
        these consequences predicted to aid in developing a risk profile for the dam.
        Table 2-1 in the Dam Safety Guidelines (CDA, 2013) presents a classification scheme that
        can be used to provide guidance on the standard of care expected of dam owners and
        designers. It considers a segment of the consequences discussed above: population at
        risk, loss of life, environmental and cultural values, and infrastructure and economics.
        For ease of reference, Table 2-1 is reproduced here (labeled Table 3-1 in this document).
       The population at risk and potential loss of life are determined using standard
       approaches. However, little guidance is provided in CDA (2013) for assessment of
       “Environmental and cultural values.” Since the environmental and cultural conditions
       associated with each mining dam can vary, specialist knowledge must be applied in the
       fields of ecosystems, land, water quality, fisheries, and cultural values. The classification
       criteria and terminology such as “significant loss” and “critical habitat” should be
       defined and agreed upon early in the design or safety review process, with input from
       specialists and the regulatory authorities. Because of the difficulty in predicting the
       environmental and ecosystem effects from accidental releases, it is often necessary to be
       on the conservative side when applying dam classifications.
       The Dam Safety Guidelines (CDA, 2013) consider only the economic losses to third parties
       beyond the limits of the mining lease on which the mining dam is situated. In many
       cases, the failure of a mining dam can have no effect on a third party, if the failure and
       runout is wholly contained on the mine property. As noted above, the financial
       consequences to a mine owner can be much larger than the financial effects on third
       parties.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                18
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
          Hence, it is important to note that the classification scheme in Table 3-1 is one
          consideration for the owner in terms of establishing the risk profile for the mining dam.
          The owner must also consider the other consequences, as described above that the dam
          presents to their operation when establishing the risk profile and although this may not
          change the classification, the risk profile could have a bearing on the surveillance
          activities and design criteria.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                19
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
      of potential loss of life (to assist in decision-making if the appropriate analysis is carried out).
 Note 2. Implications for loss of life:
      Unspecified—The appropriate level of safety required at a dam where people are temporarily at risk depends on
      the number of people, the exposure time, the nature of their activity, and other conditions. A higher class could be
      appropriate, depending on the requirements. However, the design flood requirement, for example, might not be
      higher if the temporary population is not likely to be present during the flood season.
         The consequences of dam failure (and associated risks) and the classification can change
         if the dam is being raised, if there are substantial changes to the downstream
         environment including development, or if there are other regulatory drivers.
         Internal dams (dams that are contained within a larger facility and are not on the
         perimeter of the facility) can also be classified. If the consequences of failure of an
         internal dam can trigger the failure of a perimeter dam or vice versa (cascading failure
         scenario), the cascading failure scenario needs to be considered when setting the
         classification.
Operation and maintenance procedures and the appropriate levels of monitoring that are
necessary, can change during different phases of the dam or as the dam evolves during a
particular phase. Because of these changes, the OMS Manual must be considered a “living”
document and it should be revised or updated as required. In some cases, a review of the OMS
manual should be done as part of the dam safety inspections and as part of the Dam Safety
Reviews.
Section 3.6.2 of Dam Safety Guidelines (CDA, 2013) includes suggested frequencies for visual
inspections that include routine inspections done by the owner (weekly or monthly frequency),
engineering inspections done by a qualified professional engineer (annual or semi-annual), and
special inspections after unusual or extreme events. For dams in the Low consequence category,
the inspection frequency can be extended to once every two years, depending on the overall risk
that the dam poses. For dams in the Significant classification, the frequency could be from
annually to every other two years, depending on the risk. For dams in the High to Extreme
consequence category, the inspections should be semi-annually to annually depending on the
risk.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                20
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
Release of water that has been affected by mining operations can cause more damage than release
of a similar amount of fresh water. In some cases, the water supply downstream can be adversely
affected. These factors have to be considered in the emergency planning and development of
measures to minimize the impacts resulting from a dam failure. A risk assessment of various
scenarios is useful to guide the development of appropriate response and mitigative measures.
The following planning considerations are provided as examples that apply specifically to
mining dams:
      •   In addition to general access to the site (e.g. primary and secondary routes) to repair or
          contain damage, it may be necessary to access a specific area or segment of the dam. If
          access is not readily available for a potential failure scenario, then a decision should be
          made by the owner as to whether such access should be developed ahead of time or a
          plan developed to ensure that such access could be established in a timely manner.
      •   Regulatory approvals (requirements and procedures) may be required before
          implementing certain mitigative measures such as construction of a berm in natural
          water courses to contain tailings or other solids.
      •   There may be a need to provide an alternate water supply for the potentially impacted
          downstream population.
Dam Safety Reviews should be undertaken for mining dams in the Operation and Transition
Phases, consistent with Section 5 of the Dam Safety Guidelines (CDA 2013). It is noted that the
CDA is currently developing additional guidance on Dam Safety Reviews.
The suggested frequency of Reviews ranges from 5 to 10 years, depending on the consequences
of failure and changes in the dam or surroundings; any regulatory requirements would always
need to be met as a minimum, but more frequent Reviews may be warranted for some mining
dams depending on their risks. Low consequence dams may not need Dam Safety Reviews, but
the consequences of failure should be reviewed periodically for confirmation. Dam Safety
Reviews should also be undertaken when there is a substantive change in the operation of a
mining dam, if significant changes occur downstream, or if applicable regulations change.
On many mine sites, there may be several dams with different dam classifications that could have
varying frequencies for Dam Safety Reviews. Because of the dynamic nature of mining
developments, the Review could be undertaken for all of the structures on the site in accordance
with the most stringent frequency derived from the dam classifications.
Dam Safety Guidelines (CDA, 2013) state that it is the “owner’s responsibility to ensure that the
findings of the review engineer will not be influenced by his or her prior participation in the
design, construction, operation, maintenance or inspection of the dam under review,” and also
that “it is advisable that the same review engineer not carry out two consecutive safety reviews of
the same dam.”
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                21
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
While recognizing this principle of independent reviews, there may be cases when there is an
advantage to having the EOR significantly involved in a Dam Safety Review. Mining dams can
often evolve over time with a long and complex design, construction and operational history.
There can be frequent changes among the mining company personnel who are responsible for the
safety of the dams and the EOR provides continuity between personnel. In addition, ownership
changes can result in changes to staff responsible for dam safety.
Typically, a dam safety specialist who has not been involved in the previous designs will be
engaged as the “review engineer” but the EOR should be consulted and input obtained during
the Dam Safety Review.
In special cases, the EOR may lead the Dam Safety Review and be considered the “review
engineer,” with additional external reviewers who participate in an advisory capacity. This
approach can satisfy the need for the review findings to be independent of conflict of interest.
However, this approach should be limited in application. An example of an appropriate case
might be where an owner has never done a Dam Safety Review of a dam and the EOR is the
person most familiar with the location and content of key information. In this instance, it may be
most effective for the EOR to lead the Review and present the findings to external reviewers.
Thus, in the initial Dam Safety Review, the documentation would be gathered and compiled in a
form such that subsequent Reviews can be done effectively by a third party.
        Section 6 of Dam Safety Guidelines (CDA, 2013) outlines approaches to dam safety analysis
        and assessment to support decision-making related to dam safety. A risk-informed
        approach is encouraged because it includes traditional deterministic standards-based
        analysis among many considerations. Also, as noted above, the consequence
        classification does not address all of the potential risks presented by a dam. The risk-
        informed approach is continuing to develop and a standards-based approach may be
        appropriate for certain elements of dam design and assessment.
        The design of a mining dam must meet the requirements of the project as it is defined at
        the time of the design. Often, a mine will expand and result in an increase in the mining
        dam size. The design should take into consideration the possibility of such an increase in
        size. Also, the design must consider the possibility that there could be a premature
        suspension of mining activities, due to economic or environmental reasons, where there
        may not be an opportunity for operator intervention and the usual controls (such as
        operating water management structures) may not occur.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                22
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        As noted above, it is important that the design of dams consider the ultimate end point
        that is expected to be achieved for the dam (including plans for maintenance and
        inspection and the configuration of the ultimate facility). An assessment should then be
        done as to whether the dam should be constructed for the Closure – Active and/or
        Closure - Passive Care Phases prior to cessation of the operation, or if it is more
        advantageous to modify the dam during the Transition Phase in preparation for the
        Closure - Active Care and/or Closure - Passive Care Phases.
        For tailings facilities, the risk assessment approach should be used when assessing the
        tailings technologies and closure strategies that are considered for the facility.
3.5.2 Hydrotechnical
       Figure 3-1 shows a section through a generic mining dam and how the storage and
       conveyance of runoff is often managed (i.e., a pump system or flow decant to control the
       water level and an emergency spillway to prevent overtopping of the dam).
IDF
EDF
NOWL
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                23
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        The IDF is either stored or conveyed from the pond via a spillway or equivalent overflow
        structure. Water may be released from the pond via a low flow structure or reclaim
        pumping system. Even for those dams where the IDF can be temporarily stored, the
        installation of an emergency spillway should be considered as a precautionary measure.
        Runoff that is impounded is typically recycled or treated and released over time
        following a storm event to draw down the reservoir from a level at or below the
        Environmental Design Flood High Water Level (EDF level) to the Normal Operating
        Water Level (NOWL). In many cases, discharge from a pond can be subject to seasonal
        and environmental constraints, resulting in periods when water is meant to accumulate
        in the impoundment and these inflows must be managed between the LOWL and
        NOWL. The design of the dam must be based on an appropriately detailed water
        balance, which will change over the life cycle (see Section 2.2).
       Many factors can affect operational pond levels in addition to the factors of EDF and IDF
       (discussed below). These include: the minimum pond volume required to clarify
       supernatant that is reclaimed for milling; the need for a reserve volume to guard against
       a mill water supply interruption during the winter or dry periods; the minimum pond
       depth required to operate reclaim facilities; the minimum pond size to effectively control
       beach length when tailings dam fill is hydraulically placed; and the pond size necessary
       to control beach length to control dusting.
       The central element of a good water management plan is a water balance. This is an
       important tool in the design of a mining dam. Some of the items that a water balance
       needs to consider with respect to dam safety are the following:
       The Environmental Design Flood (EDF) is the most severe flood that is to be managed
       without release of untreated water to the environment. An EDF is necessary in situations
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                24
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        where contaminated water must be retained either with no discharge to the environment
        or with controlled discharge through a treatment system prior to discharge to the
        environment. Retention of water during the EDF requires storage capacity above the
        NOWL.
        The selection of return period and duration of the EDF must take into account factors
        such as the water quality that is being stored and could be released, regulatory
        requirements, frequency of overflow events, the rate and duration of overflows, the
        environmental sensitivity of the receiving environment, downstream flow in the receiver,
        downstream mixing characteristics, and public perception on the matter. The selection of
        an appropriate EDF is therefore site specific and should be derived through:
        1) Consultation with regulatory agencies.
        2) Consideration of environmental effects associated with the frequency, magnitude
            and duration of an infrequent release.
        3) Consideration of dilution that may be available from flood flows in the receiving water.
        4) Consideration of the time needed to draw down the EDF volume from the storage area.
        5) Consideration of the costs associated with varying degrees of environmental control.
        Typical EDF return periods range from 1 in 50 years to 1 in 200 years, but more stringent
        criteria may be required depending on the site conditions. The appropriate EDF duration
        is site specific and typically ranges from weeks to months depending on the assimilative
        capacity of the receiving stream and the capacity of the water treatment system to
        process the stored volume.
        As noted in Dam Safety Guidelines (CDA 2013), the IDF is the most severe inflow flood
        (peak, volume, shape, duration, timing) for which a dam and its associated facilities are
        designed. Table 3-2 below presents suggestions on target levels for the inflow design
        flood as excerpted from CDA (2013). These are considered applicable for the
        Construction, Operation, and Transition Phases.
        As noted in Section 3.1, the dam classification and the associated target levels shown in
        Table 3-2 should be considered when developing the design criteria. In addition, the
        mining dam owner will want to factor in other risks and may choose to adopt more
        stringent design criteria than suggested by the classification alone.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                25
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
Freeboard
        Freeboard guidelines as outlined in the Dam Safety Guidelines (CDA, 2013) apply to most
        mining dams. However, the following should be considered for mining dams:
            •    The suggested minimum freeboards in the Dam Safety Guidelines (CDA, 2013)
                 were developed to account for the typical nature of a pond on a river system
                 where the high water level generated during a flood event may not occur at the
                 same time as a high wind event that occurred during the storm that resulted in
                 the flood. For mining dams that contain ponds, there can be a condition where
                 the high water level does occur at a similar time as the storm event and high
                 wind event and this condition should be examined when developing the return
                 period for the design wind for the minimum freeboard calculation.
            •    The fetch of the pond contained by a mining dam can often be less than a
                 conventional dam and the water depth can be shallow as a result of tailings or
                 sludge deposition.
            •    As discussed below in Section 3.5.3, the freeboard guidelines can be superseded
                 by minimum beach length guidelines for upstream and centerline tailings dams,
                 if these other guidelines are more conservative.
        Table 6-1 of the Dam Safety Guidelines (CDA, 2013) provides suggestions on the target
        levels for earthquakes. As discussed above with respect to the IDF, these target levels
        may generally be applied for the Construction, Operation, and Transition Phases of a
        mining dam. Table 3-3 below shows these target levels.
        Similar to the discussion for the IDF and the owner’s risks, the owner may adopt criteria
        more stringent than these target levels suggested by the classification alone or those
        required by the regulator.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                26
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        The current state of practice with respect to seismic effects on dams comes largely from
        the conventional dam industry where deformations of the crest could result in potential
        for overtopping. For many mining dams, the crest deformations could be much larger
        and not result in a release of contents. Hence, criteria should be established for suitable
        deformations of a mining dam and the appropriate analyses undertaken to demonstrate
        the effect of an earthquake on the dam and determine if the deformation criteria is met.
        With respect to tailings stacks that do not have water ponded at the crest, but contain
        potentially liquefiable sediment, the liquefaction potential should be reviewed as part of
        each Dam Safety Review to determine if there have been changes in the seismic criteria or
        the conditions of the dam that may affect the liquefaction potential (i.e. lowering of the
        phreatic surface).
3.5.4 Geotechnical
3.5.4.1 Criteria
        Tables 3-4 and 3-5 show the target levels related to slope stability. These are based on the
        values provided in Tables 6-2 and 6-3 of Dam Safety Guidelines (CDA 2013). However, the
        Dam Safety Guidelines call for a factor of safety of 1.3 for the condition: “End of
        Construction Before Reservoir Filling.” For tailings dams that are constructed over time
        and the reservoir is filled and operated as the dams are constructed, this factor of safety
        may not apply. On the other hand, a factor of safety of 1.5 was intended for the loading
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                27
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        condition where the seepage was at steady state and the reservoir was at the NOWL.
        Steady state seepage may not be achieved in a tailings dam until near the completion of
        the dam raises and, if the pond geometry is adjusted after the dam reaches its final
        elevation, the seepage pattern may change again.
        Hence, the designer needs to consider the loading conditions and establish factors of
        safety that are appropriate for the mining dam in question. A factor of safety of 1.3 may
        be acceptable during construction of a dam where the consequences could be minor and
        measures are taken during construction to manage the risk such as detailed inspection,
        instrumentation, etc. But, the factor of safety of 1.3 should not simply be adopted because
        it is “End of construction.” A factor of safety of 1.5 has typically been adopted for tailings
        dams because of the potential consequences of failure.
        Therefore, when setting the design criteria for the dam, these target levels can be
        considered, but the risks associated with instability of the dam also need to be
        considered.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                28
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
       Tailings dams that are raised in the upstream direction typically rely on a tailings beach
       upstream of the dam crest to control the phreatic surface within the dam. This can also be
       applicable to centerline and modified centerline dams that require upstream beaches for
       stability. The minimum beach width is established by considering: the margin of dam
       stability (including under seismic conditions), angle of the beach slope, gradation of the
       tailings and expected infiltration response, performance of drains that may be
       incorporated within the dam, and the resulting rise in the phreatic surface within the
       dam due to pond level fluctuations.
       A key design issue is the rate of raising of the dam fill (perimeter and internally) as this
       can result in static liquefaction of the tailings and failure of the perimeter dam. The
       maximum allowable rate is dependent on a number of factors (permeability, gradation,
       density, location of the phreatic surface, etc.) and is unique for each structure.
       It is recommended that upstream constructed tailings dams not be built in high seismic
       areas.
       As noted in Section 2.1 and 2.2.5, the potential for flow of the impoundment contents
       beyond the perimeter containment is a determining factor on whether the containment
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                29
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        needs to be considered as a dam. An evaluation of the flow potential should consider the
        following:
             • Degree of saturation
             • Contractive vs. dilatant behaviour of tailings
             • Compaction and other densification methods
             • Removal of ponded surface water, drawdown, and desaturation
             • Comparison of flow slides between active and inactive tailings dam failures
             • Saturation-induced collapse behaviour of dry-stack materials.
       Methods may be undertaken to stabilize the impoundment contents and reduce the flow
       potential.
Other Considerations
       Some other unique aspects of mining dams with respect to geotechnical design are listed
       below.
            •   The design, construction, and operation of tailings dams often use the
                observational method due to the long construction period and opportunities to
                review actual conditions.
            •   Loading on a dam shell from an upstream tailings beach needs to be accounted
                for in stability assessments.
            •   Liquefaction of tailings upstream of the dam needs to be considered in stability
                assessments.
            •   Mine waste is often used in the structural portion of a mining dam and this
                requires special care with respect to the design of filters and transition zones to
                protect the seepage control elements of the dam.
            •   Geochemical processes (often acid rock drainage or metal leaching) can clog
                filters and drains through precipitate accumulation. While this can also occur
                with conventional dams, it is more prevalent in mining dams that contain
                materials with acid rock drainage generation potential. The rate of clogging and
                the time that the drains are required to operate may greatly exceed those typical
                of conventional water storage dams. Cementing of soil into a “hard pan” can
                affect the seepage conditions in a dam.
            •   Decant structures and/or pipes embedded in embankments in general are
                potential pathways for seepage. The deterioration of pipes through dams is a
                well known cause of several mining dam failures. Development of preferential
                seepage paths and arching zone(s) are also notable safety hazards. For decant
                pipes with intermittent discharge, frost action can also create seepage pathways
                around the pipes. Hence, these structures need to either be avoided or designed
                and constructed with a high level of care, including redundant protective
                measures.
            •   Mining dams are often located near other infrastructure such as open pits and
                underground workings. The consequences of failure of such mining dams
                require careful consideration. Also, the potential interaction of the mining
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                30
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
                 operations (i.e. blasting or large waste rock dumps) on the mining dams must be
                 assessed.
             •   Subsidence of ground beneath a mining dam can occur due to underground
                 workings that may not have been detected prior to the design and construction
                 of the dam.
             •   Piping can occur into underground workings with caving occurring upward into
                 the tailings.
             •   Design for thickened tailings discharge facilities.
             •   Geosynthetics are often considered for mining dams because of limited
                 construction materials, but these must be used judiciously when considering
                 structures that will have to last a long time.
             •   Design should be flexible to accommodate variability and availability of
                 construction materials throughout the life of a tailings dam.
             •   Instrumentation monitoring, recording between raises, damage to
                 instrumentation during construction or mine operations.
             •   The use of impervious membranes for lined ponds that also require measures to
                 prevent wildlife from getting trapped in the ponds and causing damage to the
                 liners.
             •   Vandalism, particularly recreational vehicles that can cause damage to closed site
                 dams.
For those mining dams that cannot be decommissioned and have to be maintained as functional
dams for a very long time, Dam Safety Guidelines (CDA, 2013) does not provide specific guidance.
This section provides such guidance for the Closure – Active and Closure – Passive Care Phases.
The dam classification scheme described above in Section 3.1 applies to mining dams in the
Closure – Active and Closure – Passive Care Phases. However, the designer should consider
measures to reduce the consequences of dam failure and thus the dam classification, such as the
following:
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                31
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
On the other hand, changes or potential changes in the downstream environment (i.e.
development, ecosystem establishment) could cause an increase in the consequences of failure.
The designer should consider the potential for these changes in the long term.
Section 3.1 provided information on the Engineer of Record (EOR) and records management.
Because of the extended time frame of closure, these items are very important and systems need
to be put in place to ensure that these items are adequately addressed.
Prior to entering the Closure – Active Care Phase, the OMS Manual should be updated to reflect
the conditions in this phase. The OMS Manual should include the maintenance and surveillance
requirements. These would reflect the consequence classification of the dam and the associated
risks.
Prior to entering the Closure – Passive Care Phase, the OMS Manual should be updated as well.
The following items would be considered:
    • Routine inspections may not normally be done as the site will typically not be staffed. If
         an owner wishes to utilize routine inspections to help manage the risks and reduce costs
         associated with capital improvements, then that could be an acceptable approach.
    • Instrumentation monitoring may not be conducted due to site access or resource
         limitations. Remote observation systems could be considered.
    • Engineering inspections may not have to be the same as for the Transition Phase and
         Closure - Active Care Phase.
Special inspections may be required after extreme events and the OMS Manual should prescribe
the conditions under which this inspection should be done.
A key objective of the design and closure measures that are implemented for the Closure –
Passive Care Phase is to reduce the effort associated with the operations, maintenance, and
surveillance activities to as low as reasonably practical.
For sites that require on-going water management and water treatment, site personnel are
typically present during the Closure – Active Care Phase. Other sites may only have intermittent
surveillance during this phase. The ability to respond to emergencies effectively during this
phase needs to be evaluated as part of the closure planning process.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                32
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
For sites in the Closure – Passive Care Phase, there are typically no staff on site and there is no
ability to respond in a short time frame to problems with the dams or emergencies. The
Emergency Preparedness and Response Manual for the Closure – Passive Care Phase still should
develop an approach for dealing with possible emergencies related to dam stability issues.
The Dam Safety Review process is an important means of managing risk associated with dams in
the Closure – Active and Closure - Passive Care Phases. By undertaking a Dam Safety Review at
regular intervals, the owner ensures that changes to the dam and surrounding environment are
considered, their effects on the safety of the dam defined, and the potential consequences of
failure re-evaluated.
The surveillance and inspection frequency should be re-assessed and the OMS Manual reviewed
with consideration to these evolving changes. This is also an effective means of managing risks
associated with climate change as it is not possible to make accurate predictions of climate change
in the long term. The Dam Safety Review should identify the need for updates to the OMS
Manual to reflect the changing environment, if appropriate.
The dam classification and risk profile of the dam (including the additional risks that are not
captured in the dam classification scheme) should be revisited as part of the Dam Safety Review
process to reflect changes in the downstream environment and land use. The design criteria
should be reviewed in the context of the classification as well as the state of practice at the time of
the Dam Safety Review. As part of the Dam Safety review the design life and design interval for
the structure should be considered.
If modifications to the design are required as a result of the Dam Safety Review, the dam would
return to the Transition Phase and then move through to the Closure – Active Care and possibly
the Closure - Passive Care Phase.
The frequency of future Dam Safety Reviews should be developed as part of the OMS Manual
that is prepared prior to entering the Closure – Active or the Closure – Passive Care Phases. This
frequency should then be reviewed during each Dam Safety Review and the dam specific
frequency established with the associated conditions. Risk assessment methods can be used to
assist with the Dam Safety Reviews and prescribing frequency of future dam safety inspections
(DSIs) and Dam Safety Reviews.
Section 3.0 presented the concept of the design interval. For the Closure – Active Care Phase, the
design interval could last for decades or hundreds of years, but as noted above, if the dams are
being monitored on a regular basis, there are ongoing DSIs, and there is an ability to effectively
respond to warning signs and emergencies, then the target levels and approaches described in
Section 3.5 would apply. For Closure - Passive Care Phase, the design interval could extend for
hundreds of years and there may not be regular monitoring or an opportunity to effectively
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                33
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
respond to warning signs and emergencies. There is an intermediate condition in the Closure –
Active Care Phase where the surveillance is intermittent and the ability to respond to
emergencies might be limited. This will have a bearing on setting the design criteria and
surveillance program and the guidance in Section 3.5 may not strictly apply.
The extended design interval needs to be considered when developing the criteria for dam safety.
A longer design interval (or exposure period) increases the likelihood of an event occurring. Since
design criteria are established to reduce the probability of failure, the design criteria for the
Closure – Passive Phase may need to be more stringent to account for the longer design interval
and the limited monitoring and opportunity to respond to warning signs and emergencies. For
failure modes that have a probability of failure associated with them, a design interval (or
exposure period) of perpetuity would result in a probability of unity.
Assuming that the other variables will not change over the life of a structure, then the design
criteria for flooding and seismic events can be made more stringent. The resulting suggested
target levels for the flood and earthquake hazards are shown in Tables 4-1 and 4-2. It is noted that
the ranges shown for the Significant and High consequence dams illustrate that the criteria
should be commensurate with the range of potential consequences for the particular dam. A risk
assessment may be necessary to justify the selection of criteria.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                34
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
It is important to note that the designer (EOR) and owner can increase beyond these target levels
when setting the criteria if they wish to further reduce the risk. The designer can also go lower if
they have done a comprehensive risk assessment to support such a decision and the regulator
concurs with the assessment.
Tables 4-1 and 4-2 could also be applicable for dams that are expected to remain in the Closure –
Active Care Phase for an extended period (many decades or centuries) if the owner is conducting
infrequent surveillance or would not have sufficient resources to respond to warning signs or
emergencies.
Risk assessment methods can be used to provide informed guidance on criteria development.
Items such as erosion of the downstream and upstream slopes; spillway sizing not only to pass
the IDF but to handle blockage due to fallen trees, ice, and beaver activity; access, etc. need to be
considered with respect to the Closure – Passive Care Phase when personnel are not on site on a
regular basis and there is reduced surveillance and inspection.
With respect to hydrotechnical matters, the guidance provided in Section 3.5 is considered
acceptable for Closure – Passive Care Phase as well, again assuming that other variables will not
change over the life of the structure. An item that warrants attention is diversion ditches that are
used to divert fresh water away from an impoundment to limit treatment requirements. For
closure, it is typical to assume that these diversion ditches are not functioning during the IDF.
With respect to factor of safety, the guidance provided in Section 3.5 is considered acceptable for
Closure – Passive Care Phase as well, again assuming that other variables will not change over
the life of the structure.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                35
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
Erosion protection on side slopes of the dams is an important consideration for closure, especially
for the Closure – Passive Care Phase, where significant erosion gullies could form without being
detected. A design flood event must be established to support the design of the erosion
protection system on the slopes (from vegetation to rockfill). The design flood event for this can
range from the 1 in 1,000 year event to the PMF depending on the consequences of the erosion
feature. Also, the effect of animal burrows should be considered.
Geosynthetics are often considered as design elements for the dams at closure and the use of
these materials needs to be carefully evaluated for dams that are being prepared for the Closure –
Passive Care Phase.
In addition to the extended design interval, additional factors should be considered when
developing design criteria for the Closure – Passive Care Phase, such as the following:
    •   The inherent limitations associated with estimating changes over extended time periods
        based on 20 to 50 years of data.
    •   The effect of climate change on extreme events.
    •   The effect of changes in the condition of the facility (i.e. vandalism, reduced maintenance,
        natural hazards such as fire and drought).
    •   The effect of potential changes in ownership of the facility or personnel and the degree of
        vigilance/inspection of the structure.
    •   The effect of changes in water table and water chemistry of the impounded fluid or
        materials that could alter the seepage conditions within the dam and foundation.
    •   The potential for future settlement and land developments in the area.
    •   Changes to filters over time that could reduce their effectiveness in the long term. In
        some jurisdictions, the designs have to demonstrate that the dam is stable assuming that
        filter is fully clogged, regardless of the mechanism that could result in such clogging.
The design criteria for the Closure – Passive Care Phase may, in fact, be the primary criteria that
are adopted for design during the Operation, Transition, or the Closure – Active Care Phases.
Studies can be done to determine which phase is the optimal phase for implementing the designs
required to meet the Closure – Passive Care Phase.
This sub-section focused on design criteria which are intended to address the probability part of
the risk equation. Section 4.1 discussed means of reducing the classification (the consequence part
of the risk equation). Tradeoff studies can be undertaken when designing for closure to
determine the optimal combination.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                36
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
When dealing with acid rock drainage (ARD) and metal leaching (ML), many mines have opted
to construct “wet covers” that create a pond over the ARD/ML material (typically tailings, but
also other process residues, etc.) that is contained by low permeability dams. In some cases, the
dam and facility is constructed to support an elevated water table (EWT) that can maintain acid
generating materials in a saturated state while not resulting in a free water pond. Such
structures are often also expected to exist in perpetuity, providing a wet cover over ARD/ML
tailings forever. These strategies have proven to be effective in controlling ARD/ML.
When comparing dry covers to wet covers, it is important to conduct a careful evaluation of both
options as they have direct ramifications on the design of the containment dams. The following
lists some of items that should be considered in this evaluation:
    •   The consequences of failure of a wet cover system can be more severe than for a dam
        containing a dry cover system. Not only will a dam break include the water forming the
        wet cover, but the tailings that are contained will be more mobile because they are
        saturated.
    •   The OMS requirements will be greater for a dam supporting a wet cover than a dry
        cover.
    •   A wet cover is more susceptible to variations in climate change.
    •   It is less likely that the dam could reach the Closure – Passive Care Phase and the dam
        may be in the Closure – Active Care Phase for perpetuity.
    •   The potential for creating a landform that is effectively a “walk away” closure solution is
        very difficult with a wet cover, moreso than a dry cover.
    •   The regional ground water system could be affected as a result of long term seepage from
        the wet cover and through the tailings.
    •   Long term geochemical reactions and their effect on the elements within the dam will be
        more prevalent for a wet cover system than a dry cover system, particularly filters.
The challenges associated with water covers are described in a State of the Art Report on Water
Cover Closure Design for Tailings Dams Bjelkevik (2005).
A tradeoff study should be undertaken to fully compare all that is required to maintain a wet
cover and the associated dam safety obligations (as outlined in this Bulletin and other guidance)
against other options that do not call for a wet cover. The study should look at other options as
well such as storage in mine workings.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                37
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
For a mining dam on a property owned by a mining company, the ownership and liability will
transfer with the property ownership, but it is recognized that provincial or territorial
governments may ultimately become liable for these dams as some mining corporations cease to
exist. This is addressed in part by financial assurance packages that a mining company must put
in place either prior to or during their operation. This is an important issue that is beyond the
scope of this Bulletin but needs to be recognized in the design of the mining dam and in
establishing criteria that are suitable to stakeholders including future owners, landowners, and
the provincial/territorial governments.
When a mining dam is located on land owned by the provincial or federal government (the
Crown), under a mining lease (or through surface rights or patents), then ultimately, when the
lease expires, the Crown will become the owner of the mining dam through the process of
Custodial Transfer in accordance with the lease terms. Financial assurance packages are still
required and the design also has to consider this end point.
In Alberta, there is a formal process for transferring disturbed lands back to the Crown (Richens
and Purdy, 2011). The Institutional Control Program (ICP) in Saskatchewan, is outlined as
follows (Saskatchewan 2009):
        “The ICP consists of those actions, mechanisms and arrangements implemented in order
        to maintain control or knowledge of a remediated site after project closure and custodial
        transfer to some form of responsible authority. This control may be active (e.g. by means
        of monitoring, surveillance, remedial work, fences, etc.) or passive (e.g. land use
        restrictions, markers, records, etc.). Activities undertaken by the post-transfer custodian
        (i.e. the province is the responsible authority) could range from the simple act of
        permanently recording the location of a remediated site all the way to conducting regular
        inspections that may or may not include active measurements and the collection of
        samples for analysis and potentially the eventual maintenance of certain aspects of the
        property.“
The Native Orphaned and Abandoned Mines Initiatives (NOAMI) produced the “Policy
Framework in Canada for Mine Closure and Management of Long Term Liabilities” (Cowan
Minerals Ltd., 2010). In assessing the role of perpetual care, long-term monitoring and
maintenance, the report stated the following with respect to mining dams:
        “We know that there are elements of sites closed out under acceptable technical
        standards and guidelines that now require long-term monitoring and maintenance in
        order to ensure the safeguards remain intact and are performing as intended in the
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                38
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
        closure process. These safeguards can range significantly depending on the complexity of
        the original mining operations.”
That document provides further guidance on issues to consider for custodial transfer, including
the following Policy Guidance:
    •   “Ensure all closed out site features that may present a future hazard and cost are
        identified in all the closure plan process.
    •   Develop a site land return process that focuses on these features/hazards to provide a
        degree of certainty of impacts, potential for occurrence, level of risk acceptance and
        method of costing. This should include worst case scenarios to assist in emergency
        response planning and costing.
    •   Establish or identify a jurisdictional body that coordinates agency/stakeholder inputs and
        has authority to negotiate final assurance requirements and develop appropriate
        inspection programs.
    •   Establish a recognized authority for receipt of assurance and tracking and consistent
        application of funds for monitoring, maintenance and emergency requirements. This
        should include funds dedicated to site specific features as well as funds established for
        unforeseen incidents.
    •   Ensure funds are held in dedicated accounts with appropriate investment growth
        potential.
    •   Establish a secure archiving/filing system to store mine site data for ready access.
    •   Ensure all land use restrictions are applied, recorded, enforced and appropriately
        identified in all land use planning systems such as GIS."
Morgenstern (2012) stated that these approaches are “untested on the complex issues associated
with reclamation of lands disturbed by oil sands mining.” This would also be true for non-oil
sands mining. Morgenstern further states that “Strategies based on perpetual care are attractive…
and should be assessed.” The guidance provided in this Bulletin with respect to Closure – Active
Care and Closure – Passive Care fits with this approach.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                39
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
7.0 References
Bjelkevik, Annika. 2005. Water Cover Closure Design for Tailings Dams, State of the Art Report.
     Lulea University of Technology, Department of Civil and Environmental Engineering. ISSN:
     1402-1528. http://epubl.ltu.se/1402-1528/2005/19/LTU-FR-0519-SE.pdf
Cowan Minerals Ltd. 2010. Policy framework in Canada for mine closure and management of
   long term liabilities, for NAOMI.
Environment Canada. 2009. Environmental Code of Practice for Metal Mines. Issued by the
    Mining Section, Environmental Stewardship Branch, document 1/MM/17.
ICOLD Bulletin 103. 1996. Tailings Dams and Environment – Review and Recommendations.
Commission Internationale des Grands Barrages. Paris.
ICOLD Bulletin 139. 2011. Improving Tailings Dam Safety: Critical Aspects of Management,
    Design, Operation, and Closure. International Commission on Large Dams.
ICOLD Bulletin 153. 2013. Sustainable Design and Post-Closure Performance of Tailings Dams.
    International Commission on Large Dams.
Morgenstern, N.R. 2012. Oil Sands Mine Closure – The End Game: An Update. University of Alberta,
    Edmonton, Alberta
Szymanski, M.B. 1999. Evaluation of Safety of Tailings Dams. BiTech Publishers. Vancouver.
Richens, T.C. and Purdy, B.G., 2011. Regulatory requirements for reclamation and closure
    planning at Alberta’s oil sands mines. Proceedings 6th Int. Conference on Mine Closure,
    2011, Vol. 2, p. 47-55, Australian Centre for Geomechanics.
This document has been provided for use by McGill University Libraries. No part of this
publication may be reproduced, copied, distributed or transmitted in any form or by any means
without prior written permission from CDA. Because revisions and commentary on this
publication may be issued at any time, CDA does not warrant that this edition is the most
current. Revisions and commentary are made available to CDA members at www.cda.ca.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                40
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                41
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
              APPENDIX A.
 COMPARISON TO MAC AND ICOLD GUIDELINES
MAC and ICOLD provide guidance with respect to the phases of a mining dam. This sub-section
compares the framework discussed in this Bulletin with the guidance from MAC and ICOLD
with a focus on closure.
Figure A.1 shows the “stages in the life cycle of a tailings facility” from MAC (1998). The stages
are site selection and design, construction, operation, and decommissioning and closure. As
noted above, we have adopted the term “phases of life” instead of “life cycle”. MAC does not
provide detailed guidance on “decommissioning and closure” and this Bulletin addresses this.
Figure A.1. Stages in the Life Cycle of Tailings Facility (from MAC 1998)
Figure A.2 shows the “phases of tailings management” from ICOLD (2011) which begins with
planning and ends with long term care.
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                42
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
ICOLD (2011) provides the following definitions associated with the terms provided in Figure
A.2:
        Closure is the shutting down and decommissioning of a mine and tailings dams when
        production has ceased including the transition of the mining area and dam into long-
        term stable structures. Normally, closure includes decommissioning, remediation
        (reclamation or rehabilitation) and after care at the site and the tailings dam.
        Remediation refers to measures required to secure the long-term stability and to ensure
        environmental safety of structures such as tailings dams and disturbed ground. It often
        includes measures to encapsulate tailings in order to restrict the potential for toxic
        materials entering the wider environment.
        After Care is the last phase of closure that is required to verify that the measures taken
        are performing according to the design and expectations. When verified, the Long Term
        Monitoring phase starts.
        Long term monitoring is the period of time for which closure is designed and
        commences after completion of the after care phase.
When developing the framework described in Section 2.2 in this Bulletin, we considered these
definitions and addressed them as follows:
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                43
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
    •   The term “Closure” as defined by ICOLD was modified as per the definition in Section
        2.2.4 as the ICOLD definition was focused on tailings dams and this Bulletin extends to
        other mining dams.
    •   The term “Decommissioning” was extended to include the removal of a dam (breach,
        partial removal, or full removal).
    •   “Remediation” is part of the Operation and Transition Phases described in Section 2.2.
    •   “After Care” is part of the Active Care Phase described in Section 2.2.
    •   “Long Term Monitoring” is part of the Passive Care Phase described in Section 2.2.
ICOLD (2013) provided further clarification to the terminology to be used for closure. In that
Bulletin, Closure is defined as the planned cessation of tailings disposal into the tailings dam and
the modification/engineering of the tailings dam with the objective of achieving long term
physical, chemical, ecological, and social stability and a sustainable, environmentally appropriate
after use.
ICOLD (2013) also states that Post closure is the period following cessation of operation of the
tailings into its final form. The post closure period is generally divided into active and passive
care periods. Active care is the period when intervention and monitoring is required to achieve a
final sustainable form concurrently with stabilization of the structures and environmental
elements. Passive care is the period following active care during which the performance of the
tailings dam is monitored to ensure its compliance with the closure objectives. This period has no
time limit, but can be defined as being necessary until the tailings dam, in the opinion of the
regulatory authorities, is considered to be physically , chemically, ecologically, and socially stable
and no longer poses a risk to life or the environment. This is an important point that is described
below in the sub-section entitled Landforms.
When developing the phases described in this Bulletin, we considered the ICOLD (2013)
definitions and addressed them as follows:
    •   The term “Closure” was focused on tailings dams and we modified it to include other
        mining dams, but retained the sustainability concept put forward by ICOLD (2013).
    •   The term “Post Closure” was not used as we adopted the term “Closure” to address the
        “Active and Passive Care”. The term “Post Closure” may be best used for the time when
        the dam could be considered a landform.
    •   The concept of “Active Care” was retained, but we established a Transition Phase
        between “Operations” and Active Care Phase.
    •   The concept of “Passive Care” was retained.
It is interesting to note that ICOLD (2013) allows for the possibility of a dam becoming a
landform through their statement “no longer poses a risk to life or the environment.” This would
be similar to the landform concept discussed in Section 2.4.
Figure A.3 provides a comparison between the guidance provided in this Bulletin, MAC and
ICOLD (2011, 2013).
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                44
TECHNICAL BULLETIN
Application of CDA Dam Safety Guidelines to Mining Dams
    This document has been provided for Chrystian Alexander Caceres Dominguez, Sr. of GEOHIDRAC
SAC. All rights reserved.
                                                45