Intake, Raw Water Pump Station, and Transmission Mains: 1.1 Scope
Intake, Raw Water Pump Station, and Transmission Mains: 1.1 Scope
1.0 Introduction
1.1 Scope
To meet regulatory requirements and expand the jointly owned water system serving the City of Parksville
and the Regional District of Nanaimo (RDN), the Englishman River Water Service (ERWS) is developing a new
river water supply coupled with Aquifer Storage and Recovery (ASR). This innovative approach meets the
ERWS’s mission for “An Environmentally Sensitive Use of Water to Improve Fish Habitat and Domestic Water
Supply.”
Work carried out previously by other consultants includes water quality monitoring, water treatment pilot
testing, and preparation of a conceptual design for the project. Pilot testing of the ASR is ongoing and
expected to be completed by the beginning of 2014.
The purpose of this Technical Memorandum (TM) is to confirm the design basis, present proposed design
alternatives, and recommend a design for the raw water intake, pump station, and transmission main to the
Englishman River Water Treatment Plant (WTP).
1.2 Existing System and Proposed Development
The Comparison of Intake and Water Treatment Plant Siting Options report prepared by Associated
Engineering in 2011 describes the past and proposed development of the existing Englishman River water
system.
Figure 1-1 shows the location of the existing drinking water infrastructure. In brief, drinking water is
currently derived from municipal wells and an intake in the Englishman River. Treatment is limited to
chlorination of the river water.
With the limited availability of water supply sources in the area, the Arrowsmith dam is a critical element of
the water supply system. The dam collects and stores water during the winter for release back to the
Englishman River during the summer for fisheries enhancement and drinking water use.
The proposed development of the ERWS is intended to address the City of Parksville’s and RDN’s need for
additional drinking water, and the Vancouver Island Health Authority’s (VIHA) requirement for additional
water treatment by December 16, 2016. This project will involve design and construction of:
• A surface water intake on the Englishman River to replace the existing intake and raw water pump
station
• A membrane filtration WTP
• Watermain upgrades and installation on new water supply lines
Development of ASR wells are also part of the overall project; the ASR design is currently being completed
by Associated Engineering under a separate contract.
ERWS_TM2C_INTAKEPS.DOCX 1
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
The ASR wells have an estimated potential capacity of 15 ML/d, and will allow treated water from the new
WTP to be pumped into an aquifer during the winter months and stored until the summer when water
demands are at their highest. As such, they will provide a third source of supply to supplement the river
intake, in addition to the existing groundwater wells which will remain in operation after the WTP has been
commissioned.
1.3 References
The following reports and documents were reviewed during the preparation of this TM:
1. Comparison of Intake and Water Treatment Plant Siting Options, Associated Engineering, May 2011
2. Site Development – Water Transmission and Distribution, Koers & Associates Engineering Ltd., May 2011
3. Arrowsmith Water Service Englishman River Water Intake, Treatment Facilities and Supply Mains,
Phase 1 – Conceptual Planning, Budgeting and Scheduling, Associated Engineering, Kerr Wood Leidal,
Koers, April 2011
4. Environmental Assessment of Alternative Water Intake Sites in Englishman River, LGL Ltd., May 2010
5. British Columbia Building Code, 2012
6. Flood Hazard Area Land Use Management Guidelines, Ministry of Environment, 2004
7. Freshwater Intake End-of-Pipe Fish Screen Guidelines, Department of Fisheries and Oceans, 1995
8. WorkSafeBC Occupational Health and Safety Regulation
2 ERWS_TM2C_INTAKEPS.DOCX
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
the future. The ultimate design flow of 48 ML/d is shown in this memorandum for information purposes
only.
Providing a cost-effective solution was identified as one of the critical success factors at the project
chartering meeting with ERWS. An effective phasing strategy will minimize costs by evaluating capital costs
in the first phase against potential savings in future phases. Table 2-1 shows the proposed sizing and phasing
of the intake, pump station, transmission mains, and WTP to ultimate build out.
TABLE 2-1
Proposed Sizing and Phasing of Infrastructure
Capacity
Initial Phase, 2016-2035 Ultimate Phase, 2036-2050
Raw Water Flow
Intake Screen 28.8 48
Raw Water Pump Station 28.8 48
Raw Water Supply Main to WTPa 48 48
a WTP waste flows are expected to be approximately 1%.
This phasing strategy will be practical to construct and matches community spending with needs in an
affordable manner. For instance, the raw water main from intake to WTP will be designed to carry the
ultimate design flow of 48 ML/d, which is greater than the maximum capacity of the intake pumps at
28.8 ML/d, as increasing capacity of the raw water main would be more costly and disruptive in the future.
2.1.2 Seismic Requirements
The intake and raw water pump station will be designed to the 2012 BC Building Code which designates
water treatment facilities as post-disaster structures.
2.1.3 Flood Protection Level
The flood protection level is based on the Ministry of Environment (MOE) Flood Hazard Area Land Use
Management Guidelines (2004). This guideline recommends a freeboard of 0.6 m over the 200 year peak
flood for public utilities; however, due to the “flashy” nature of the Englishman River and the potential for
debris, a freeboard of 1.0 m is recommended.
The 200 year peak flood level was updated as part of this project. Details of this analysis can be found in
TM2A Intake Hydrology and Hydraulics.
2.2 Intake
2.2.1 Location
The river reach upstream of the Island Highway (Highway 19) bridge has been identified as the most suitable
location for the proposed raw water intake. This is based on a thorough and systematic constraint mapping
and detailed site evaluation carried out as part of the Comparison of Intake and Water Treatment Plant
Siting Options study carried out by Associated Engineering in 2011. The constraint mapping to develop a
short-list of candidate sites was based on equal weighting of the following criteria:
• Land use compatibility
• Heritage/archeological concerns
• Ecological impacts
• Geotechnical considerations
• Water system considerations (i.e., pumping versus gravity feed)
These criteria were reviewed along a 10 km stretch of the Englishman River from the river mouth to the
confluence of the South Englishman River with the Englishman River mainstem. Through the constraint
mapping process and preliminary screening of the short listed sites based on known site conditions, three
ERWS_TM2C_INTAKEPS.DOCX 3
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
sites were selected for detailed site evaluation. This detailed evaluation included preliminary environmental,
geotechnical, and hydrological assessments as well as conceptual intake/WTP design and cost estimates. Of
the three short listed sites, the reach upstream of the Island Highway Bridge is considered to provide the
best compromise between limiting ecological impact, limiting contamination risk to municipal water supply
as a result of spills, and limiting both capital and on-going operating costs.
In order to select the final intake location within the identified river reach, the following major and minor
design criteria were developed for the purpose of evaluating the potential intake locations. These criteria
were reviewed with ERWS prior to the site meeting on August 13, 2013.
Major Criteria
• River Depth: A minimum water depth less than 0.75 m will likely require a weir to extract the ultimate
design flow of 48 ML/d. Installing a weir is less desirable because it increases cost and may affect
recreational activities on the river. River Crossing: A river crossing will increase costs.
• Land Ownership: Land owned by the City of Parksville or the RDN is preferred. Private land ownership
will potentially add costs and delays for land acquisition.
• Site Access: A site access road that connects the intake and pump station to the WTP is preferred.
• Flood Protection: The pump station must be above the 200 year flood plain elevation.
• Recreation Impacts: A site with fewer impacts to recreational activities along the river is preferred.
Minor Criteria
• Existing Water Licenses: A site without existing water licenses is preferred.
• Geotechnical: If rock excavation is required to construct the foundation of the intake and pump station
at either site, it will significantly increase the cost. It should be noted that at this stage, minimal
geotechnical work has been completed.
• Riparian Habitat: A site which requires less riparian habitat to be disturbed is preferable because of
lower costs of compensation and potentially less onerous permitting requirements.
2.2.2 Screen
• Initial Design Flow = 28.8 ML/d (per Table 2-1)
• Average Approach Velocity = 0.11 m/s
The approach velocity is based on the DFO Freshwater Intake End-of-Pipe Fish Screen Guideline (1995) for
subcarangiform fish (trout- or salmon-like swimming mode).
2.2.3 Minimum Downstream Conservation Flow
Historically, minimum conservation flows in the Englishman River have been based on recommendations
made by DFO and MoE in response to the original water license application for Arrowsmith Dam and a
proposed new intake on the Englishman River in 1992. Both DFO and MoE recommended a preferred
minimum flow of 1.13 m3/s be maintained through the summer from July to October with DFO
recommending an absolute minimum of 0.71 m3/s. MoE refined the preferred minimum flow stating that
1.13 m3/s should be maintained at or above a 20-year return period drought condition. These minimum
conservation flows have provided the basis for the current operating order for Arrowsmith Lake dam which
requires specific minimum flows to be maintained at the Englishman River near Parksville Water Survey of
Canada Gauge (WSC 08HB002).
Both of these downstream conservation flows requirements have been reviewed as part of a low flow
aquatic habitat assessment carried out by LGL Ltd., outlined in the report prepared in October 2014. The LGL
report recommended a series of revised minimum downstream conservation flows based on results of
habitat simulation modelling. The downstream conservation flows used in the assessment are outlined in
Table 2-2.
4 ERWS_TM2C_INTAKEPS.DOCX
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
TABLE 2-2
Recommended Downstream Conservation Flows Below Proposed Raw Water Intake
Scenario Downstream Conservation Flow
Dry Year
1.2 m3/s
(5-year Return Period to 20-year Return Period Drought)
Current conservation flow downstream of existing intake is 1.13 m3/s for 20-year return period drought with absolute minimum
of 0.71 m3/s. Arrowsmith Dam was designed to maintain minimum preferred flow of 1.13 m3/s up to 15-year return period
drought condition with minimum flow of 0.9 m3/s supported using syphon during periods of low lake levels.
ERWS_TM2C_INTAKEPS.DOCX 5
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
• Common Alignment: install the pipeline along same alignment as the access road, unless diverging will
reduce installation costs
• Tree Removal: minimize impact on existing forested area as much as practical
• Buffer Area: leave a treed section of land between the Island Highway and the pipe alignment
• Right-Of-Ways: minimize encroachment on the existing Ministry of Transportation (MOT) and Island
Corridor Foundation (ICF) rights-of-way (for the Island Highway #19 and the ICF Railway)
• Riparian Area: minimize detrimental impact on the Englishman River riparian area
2.4.2 Vertical Alignment
• Minimum Depth of Cover: must be sufficient to prevent frost and pipe damage from vehicle loading
• Maximum Grade: areas steeper than 10% require installation of a trench dam
2.4.3 Pipe Sizing
• Ultimate Design Flow = 48 ML/d (as per Table 2-1)
• Maximum Velocity = 2.0 m/s
2.4.4 Pipe Material
• Working Pressure = 690 kPa
• Seismic: joints must be fully restrained to provide for seismic reliability
• Material: must be suitable for use with potable water (as per AWWA pipe material standards)
2.5 Access Road
2.5.1 Horizontal Alignment
• Access: provide vehicle access to the intake pump station from the WTP
• Cut/Fill Balance: minimize the total volumes of cut and fill required for construction (to minimize capital
cost)
• Slope Stability: minimize detrimental impact on the existing banks of the Englishman River (slope
stability to be reviewed as part of the geotechnical report)
• Tree Removal: minimize impact on existing forested area as much as practical
• Buffer Area: leave a treed section of land between the Island Highway and the intake access road
2.5.2 Vertical Alignment
• Maximum grade = 8%
• Elevation: finished grade above the 200 year flood elevation including 1.0 m freeboard
• Vertical Clearance: minimum 5.0 m clearance from finished road grade to underside of railway and
highway bridges (as per Ministry of Transportation and Infrastructure typical design guidelines)
2.5.3 Cross Section
• Design Vehicle: The road must accommodate a “rubber tire” crane for removal and installation of the
pumps
• Road Structure: The road structure must support the design vehicle
• Road Surface: The road surface must have minimal maintenance requirements
• Road Drainage: The road cross section must be graded to shed water from its surface and prevent
pooling of runoff from the hillside
6 ERWS_TM2C_INTAKEPS.DOCX
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
TABLE 3-1
Intake Location Comparison Matrix
Criteria Site 2 Points Site 3 Points
River Depth ~0.9 m 1 ~0.4 m 0
River Crossing Required 0 Not required 1
Land Ownership Private / MOTI ROW 0 City Park 1
Site Access Roundabout access to WTP 0 Direct access to WTP 1
Flood Protection PS can be built above flood levels 0 PS can be built above flood levels 0
Recreation Impacts None 1 Weir may be required in future 0.5
Existing Water Licenses Yesa 0 No 0
Riparian Habitatb Remove some vegetation 0.5 Remove mature vegetation 0
Geotechnicalc Sandstone bedrock 0 Glacial till over conglomerate bedrock 0.5
Total 2.5 4.0
aExisting water license at Site 2 has a withdrawal rate of less than 1 ML/d. Therefore, it is not expected to significantly affect the
withdrawal rate for ERWS.
b Since vegetation must be removed from both sites, this criteria is not considered a major factor.
c This criteria will be promoted to the major category once more geotechnical information is available.
Based on this comparison and the final onsite review with ERWS and RDN staff, Site 3 is the preferred
location for the new intake.
3.1.2 Screen
The intake screens will be designed to protect fish and other aquatic life at the intake, as well as prevent
debris from entering the raw water supply. The ERWS has had ongoing maintenance issues with its existing
infiltration gallery due to sand and gravel clogging the intake; therefore, this style of intake was not
considered for the proposed intake structure.
The intake structure will be divided into two bays so one can be taken out of service for maintenance. There
will be two screens per bay for a total of four screen panels. Figure 3-2 shows a plan view of the intake
structure.
Based on the design parameters in Section 2.2.2, the proposed sizing and design of the intake screen is as
follows:
• Number of Screen Panels = 4
ERWS_TM2C_INTAKEPS.DOCX 7
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
8 ERWS_TM2C_INTAKEPS.DOCX
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
• The pump station would house equipment which could potentially be damaged in a flood, including:
− Electrical, instrumentation and controls equipment
− Air compressor for backwashing the intake screens
Figure 3-5 shows the preliminary pump station layout.
3.2.3 Pump Type
Submersible and vertical turbine pumps were considered for this project. Submersible pumps are quieter
than vertical turbine pumps given that they are located below the floor of the pump station. However,
submersible pumps typically have lower efficiencies than vertical turbine pumps which means they will have
a higher energy cost over the design life. Therefore, vertical turbine pumps are the preferred type and will
be used.
The type of pump drive depends on the requirements of the WTP and the minimum withdrawal rate
required. A Variable Frequency Drive (VFD) allows the raw water pumps to provide a fixed flow to the WTP
under varying head conditions. In addition, the withdrawal rate of the pumps can be lowered as required to
maintain required in-stream flow requirements. Therefore, the raw water pumps will be equipped with
VFDs.
3.2.4 Pump Sizing
Three pumps will be installed in the initial phase with an additional pump installed in the ultimate phase.
The proposed sizing including the total and firm capacity is shown in Table 3-2. Pump starting and ramp up
procedures will be controlled to avoid rapid changes in the withdrawal rate. The pumps will be started one
at a time at their low flow rate with flow gradually increased as needed to meet demand. A level sensor will
be installed at the intake structure to monitor the river level during pump startup and normal operation.
TABLE 3-2
Proposed Pump Installation Phasing
Initial Phase Ultimate Phase TDH
Year 2016-2035 2036-2050 m
Pump 1 9.5 ML/d 16 ML/d 55
Pump 2 9.5 ML/d 16 ML/d 55
Pump 3 19.3 ML/d 16 ML/d 55
Pump 4 16 ML/d 55
Total Capacity 28.8 ML/d 64 ML/d
Firm Capacitya 19 ML/d 48 ML/d
Raw Water Demand 24 ML/d 32 ML/d
a Firm capacity assumes the largest pump is out of service
ERWS_TM2C_INTAKEPS.DOCX 9
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
Esquimalt & Nanaimo Railway. The proposed transmission main alignment has received approval in principle
from MOTI but must receive formal approval from MOTI and ICF during the next stage of design.
3.3.2 Vertical Alignment
The proposed transmission main profile is shown on Figures 3-6 and 3-7. The profile was selected using the
following design rationale:
• The profile will rise continually from the raw water pump station to prevent sediment accumulation at
low points
• In the section along the river (Station 0+000 to about 0+080), the crown of the pipe will be below
natural grade to prevent damage to the pipe if the access road is damaged
• In the section between the MOTI and ICF ROWs, the main will be laid at approximately existing grade,
and fill will be placed on top to get the required cover, eliminating the need for extensive shoring of the
embankment fills during watermain installation
The steepest section of main will be less than 8%; therefore, trench dams should not be required.
The minimum depth of cover for municipalities in the south coast region ranges from 0.9 m to 1.2 m. Given
that the access road is subject to minimal vehicle traffic, a minimum depth of cover of 0.9 m for the
transmission main is proposed. This depth of cover will also be sufficient for frost protection.
The limited geotechnical information near the highway bridge fill and piers indicates that bedrock is within
1.0 m of the existing ground surface in some locations; therefore, rock blasting will likely be required to
install the transmission main. This requirement will be confirmed upon completion of the geotechnical
report for this project.
3.3.3 Pipe Sizing
Based on the design flow of 48 ML/d, an inside pipe diameter of 600 mm is proposed. This pipe size results
in a maximum velocity of less than 2.0 m/s in the transmission main.
3.3.4 Pipe Material
City of Parksville Bylaw No. 1261 “Subdivision Servicing Bylaw” permits the use of ductile iron or polyvinyl
chloride (PVC) pipe for watermains. However, the proposed pipe material for this application is 600 mm
diameter (nominal) carbon steel due to the improved repairability and reliability gained with steel pipe.
A working pressure of 690 kPa has been assumed for the pipe. The working pressure for the transmission
main will be confirmed once the pump sizing has been finalized. Standard schedule carbon steel pipe has a
sufficiently high pressure rating to suit the working pressure.
3.3.5 Valves
Buried isolation (line) valves will be required immediately downstream of the pump station and immediately
upstream of the water treatment plant. To minimize costs, the valves will be butterfly style. A 600 mm
diameter gate valve is significantly more expensive than a butterfly valve of the same size (typically on the
order of 5 times the cost). No additional valves are required on the transmission main.
10 ERWS_TM2C_INTAKEPS.DOCX
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
INTAKE, RAW WATER PUMP STATION, AND TRANSMISSION MAINS
proposed alignment has received approval in principle from MOTI but must receive formal approval from
MOTI and ICF during the next stage of design. The road will be gated at the rail crossing.
3.4.2 Vertical Alignment
The profile of the preliminary vertical alignment of the access road is shown on Figures 3-6 and 3-7. The
maximum grade is less than 6% which will allow the design vehicle (rubber tire crane) to travel between the
WTP and the pump station. The elevation gain between the intake and the WTP is approximately 13 m.
The vertical clearance between the proposed road surface elevation and the undersides of the highway and
railway is in excess of 5 m, and will not pose a constraint to the placement of the access road.
The estimated volume of fill required to construct the road (based on 1 m of freeboard above the 200 year
flood elevation) is approximately 2,100 m3.
3.4.3 Cross Section
The typical road cross section is shown on Figure 3-7. The proposed road width of 5 m is sufficient for one
way traffic for the design vehicle. The road crossfall will be sloped towards the downhill side such that
surface flow will be able to run downhill towards the river.
The proposed road structure will consist of a minimum 300 mm thickness of 75 mm minus crushed gravel,
capped with a minimum 100 mm thickness of 19 mm minus gravel. Some locations will require the roadway
to be over-excavated in order to provide this minimum gravel thickness. The road structure will be
confirmed upon completion of the geotechnical report.
In locations where pooling could occur (low points on the road profile), culverts will be installed to convey
runoff under the road and onto the downhill side of the slope. It is anticipated that two culverts
(approximately 10 to 15 m in length each) will be required. The cross section also shows a ditch on the inside
edge of the road which will prevent runoff from the hillside from flowing across the road. The ditch will cross
the road at one of the culvert locations.
ERWS_TM2C_INTAKEPS.DOCX 11
COPYRIGHT 2014 BY CH2M HILL CANADA LIMITED • ALL RIGHTS RESERVED • COMPANY CONFIDENTIAL
Figures
ERWS Intake Treatment and Supply
-
Mills Street
Shelly Road
-
d
oa
Plum R
m h
Stanford Avenue East er Ro
ad at
R
Legend
Contour
Rat
hO
nra
mp Railway
Roa
d
Tanglewood Place
Proposed Intake Sites
ad
Ro
ers
id e Treatment Plant Site
R iv
Greig Road
Resort Drive
Parrys Park Road
Blower Road
20
ort Way
- Res
ad
Despard Avenue
Ro
an
Tu
Arbutus
Road
Se
aw
ay
ay
D riv
lW
e
Martindale Road
ul
G
ng
rri
He
Fr
an
kl
in
s
-
G In Saturna Dr
ul du ive
-
lR st
oa ria
Ga
d lW
ay
b ri
Wain Road
ola
-
D ri
ve
Is
l
an
No
d
H
rth
ig
hw
we
ay
st
Ea
Ba
st
yR
oa
d
Fou
60 rnea
uW
ay
60
1
ass
yp
eB
v il l
ar ks
P 4
asvictoria.victoria.kerrwoodleidal.org\DATA\Victoria\Projects\0000-0999\0400-0499\468-010\430-GIS\Plan_overview.mxd Date Saved: 25/06/2013 3:51:12 PM
2
Evergreen Way © 2013 Kerr Wood Leidal Associates Ltd.
200 0 200
(m)
80
1:5,000
60
ad
Ro
e
Kay
40
Englishman River
Proposed Intake Sites
User: LChristensen
Copyright:© 2013 Esri, DeLorme, NAVTEQ, TomTom, Source: Esri, DigitalGlobe, GeoEye, i-cubed, USDA, USGS, AEX, Getmapping, Aerogrid, IGN, IGP, swisstopo, and the GIS User Community
Figure 3-1
Path: \
Appendix A
ERWS Water License
Appendix B
Intake Screen Sizing Calculations
PROJECT: Englishman River Intake BY: R.E. Gatton CHK'D BY: J. Cheng
SUBJECT: Slant Screen Sizing DATE: 9/19/2013
PROJECT NO.: 476148.03.35.10.70
Purpose
The purpose of this calculation sheet is to determine the geometry and number of bays needed for slant screens.
Calculation
Design Criteria
Approach Velocity 0.11 m/s DFO criteria for subcarangiform fish (salmon and trout)
3
Total Design Flow 0.56 m /s 48 ML/d (ultimate capacity)
Purpose
The purpose of this calculation sheet is to determine the diversion capacity of the screens as a funciton of river depth.
Calculation
Effective Invert 10 m
Effective Screen Length 5.20 m
Slope Factor 1.8
Approach Velocity 0.11 m/s
Purpose
The purpose of this calculation sheet is to determine the approach velocity at different pumping rates.
Calculation
Approach
Capacity Capacity Velocity
3
(ML/d) (m /s) (m/s)
28.8 0.33 0.10
24 0.28 0.08
18 0.21 0.06
12 0.14 0.04
6 0.07 0.02