Introduction To Construction Management One
Introduction To Construction Management One
Introduction to construction
1
PRESENTATION OUTLINE
1. Construction Project
7/28/2022
2. Phases of a Construction Project
3. Importance of Construction and Construction Industry
7/28/2022
A Project is defined as a temporary endeavor
undertaken to create a unique product/service/results.
7/28/2022
manpower and their duration can range
from a few weeks to more than five years.
7/28/2022
A start and finish
Complexity
7/28/2022
No practice/rehearsals
Uniqueness of people relationship
7/28/2022
A. Briefing stage
B. Designing stage
7/28/2022
are studied with regard to cost and benefits so as to
establish the economic viability/social utility of a
7/28/2022
• To carry out technical and non-technical investigation so that
alternative proposals may be given due consideration.
9
Feasibility report
• Technical analysis
7/28/2022
• Economic analysis
7/28/2022
would prove expensive.
• A realistic and detailed cost estimate of the project can
7/28/2022
– Soil investigation
7/28/2022
agreed mutually between the owner’s team and
the contractors.
7/28/2022
investigation of the potential of contractor’s financial,
necessary information.
Activities (Tendering stage)
• Negotiating contract price with qualified
contractor.
7/28/2022
• Reviewing documents submitted by
15
D. Construction stage
• The construction stage involves the execution
of construction work as per the design,
7/28/2022
drawing and within agreed limits of time, cost
and specified quality.
Construction Planning Activities
• Construction schedule
• Manpower schedule
16
• Material delivery schedule
• Plant and equipment schedule Instructor: Solomon Abebe
Control of site operations Activities
• Supply of materials and equipment
• Supervision for quality control
7/28/2022
• Co-ordination among sub-contractors
7/28/2022
maintenance and repair are considered.
7/28/2022
and have any defects rectifies.
Instructor: Solomon .A
• To prepare operating instructions and
maintenance manuals.
• To carry out tests for performance, such as
water tightness, strength etc. 19
3. IMPORTANCE OF CONSTRUCTION AND
CONSTRUCTION INDUSTRY
• Construction is an important part of real estate
7/28/2022
and infrastructure such as:
Instructor: Solomon.A
• Real estate
– Residential
– Industrial
– Corporate 20
– Commercial
– Urban infrastructure
– Ports
– Airports
– Power
7/28/2022
• The importance of construction can be gauged
Instructor: Solomon.A
from the fact that cost of construction of certain
infrastructure projects may be as high as 60 to
80% of the total project cost.
21
• Construction is recognized as the basic input for
socio-economic development of a country.
• Since construction industry is dependent on a
7/28/2022
number of industries, its growth in other
Instructor: Solomon.A
industries as well.
– Development of building materials industry
– Development of construction equipments
industry 22
•Construction products such as buildings,
bridges, roads, power plants have a long life
as compared to the products of other
7/28/2022
industries.
Instructor: Solomn.A
23
4. INDIAN CONSTRUCTION INDUSTRY
Factors in favour of Indian construction industry
• Availability of cheap labour
7/28/2022
• Availability of qualified professionals
Instructor: Solomon.A
• Large number of construction companies
• Actual shortage of housing
• Boost from the government
• Growth in industrial sector
24
INDIAN CONSTRUCTION INDUSTRY (Cont.)
Factors against the Indian construction industry
• Low productivity
7/28/2022
• Low ratio of skilled to unskilled workers
• High cost of finance
Instructor: Solomon.A
• Complicated tax structure
• Presence of small contractors who lack financial and
technology backup
• Negligible investment in R & D 25
7/28/2022
commercial and hospitality sectors
• Technology and solutions for smart sustainable
Instructor: Solomon.A
cities
• Technology for the promotion of low cost
housing
• Green building solutions 26
• Smart cities
• Training and Skill development of
construction sector workers
• Urban water supply, Sewage, Sewage
7/28/2022
treatment, Solid waste management
Instructor: Solomon.A
27
5. CONSTRUCTION MANAGEMENT
• Project Management is the art and science of
mobilising and managing people, materials,
equipment and money to complete the assigned
7/28/2022
project work on time, within budgeted costs and
Instructor: Solomon.A
specified technical performance standards.
• Construction Management may be defined as the
management in which group of people of different
categories works together, to execute the project
economically without affecting the quality in a well 28
7/28/2022
• Material management
Instructor: Solomon.A
• Equipment management
• Labour management
• Site layout
• Equipments and Materials plant location
• Labour relationships 29
7/28/2022
• Development of management and machinery
Instructor: Solomon.A
• Speed of Construction
• Quality Control of materials and workmanship
30
Objectives of Construction Management
• Completing the work within estimated budget.
• Completing the work within specified time.
• The Quality and workmanship should be better.
7/28/2022
• The work should be executed as per specification.
• Providing safe and satisfactory working conditions for all
personnel and workers.
• Taking sound decisions at the lowest practical management
level through delegation of authority.
• Motivating people to give their best within their capacities. 31
• Creating an organization that works as a team.
Instructor: Solomon.A
Phases / Functions of Construction Management
• Planning and Scheduling
• Organising
•
7/28/2022
Staffing
• Directing
•
Instructor: Solomon.A
Controlling
• Co-ordinating
• Communication
32
Planning - Planning involves formulation of a number
of alternative of realistic work plans for achieving
specified objectives and finally selecting a plan which is
best suited from the standpoint of available resources
7/28/2022
and constraints imposed upon the project.
• Planning is the administrative process which translates
Instructor: Solomon.A
the policy into a method of achieving the objectives.
• How a project will be carried out?
• What materials will be used?
• What equipment and machineries will be utilized? 33
• What men and staff will be employed?
Scheduling - Scheduling is the fitting of the final work plan to a
time scale.
It shows the duration and order of various construction activities.
‘When to do?’
7/28/2022
• Time plan
• Resources plan
Instructor: Solomon.A
• Plan for controlling project
• Schedule of design and drawing preparation
• Work quantities
• Progress of work planned
• Resource allocations 34
• Budget costs
Organising – Organising is concerned with division
of the total construction work into manageable sections
and systematically arranging various operations by
delegating specific tasks to individuals.
7/28/2022
Instructor: Solomon.A
Staffing – Organizing involve the division of the
project work into sections and staffing is the provision
of people to fill the positions so created.
• Staffing functions- Recruiting the right people,
35
Arranging staff training courses, Carrying out proper
staff assessment
Directing – The directing function is concerned with training
sub-ordinates to carry out assigned tasks, supervising their
work and guiding their efforts.
• The essence of directing lies in the ability to motivate
7/28/2022
people individually and as groups to utilize their creative
Instructor: Solomon.A
efforts in achieving specified objectives.
Controlling – Controlling is necessary for ensuring effective
and efficient working.
• It involves a constant review of the work plan to check on
actual achievements and to discover and rectify deviations 36
through appropriate corrective measures.
Co-ordinating – This is a process where the
framework of the organization is made to operate
smoothly with the flow of information, decisions
7/28/2022
and results in every direction.
Instructor: Solomon.A
37
7/28/2022
Instructor: Solomon,.A
6. Importance of Planning, Scheduling and
Controlling projects
38
Planning
• Planning aims at formulation of a time based plan of action
for co-ordinating various activities and resources to achieve
specified objectives.
7/28/2022
• Planning is the process of developing the project plan.
Instructor: Solomon.A
Benefits (Planning)
• Project plan clearly defines project’s scope of work.
• Project plan aids the management in performing its functions
efficiently and effectively.
• Project plan identifies critical activities. 39
• Project plan provides the yard-stick for measuring progress
and evaluating resources performance.
Benefits (Planning)…
• A project plan maintains continuity of work, specially
when project organization is temporary and its
staffing is transient in nature.
7/28/2022
• Project plans provide the basis of coordinating the
Instructor: Solomon.A
efforts of clients, consultants, architects, designers,
quantity surveyors, suppliers, contractors and the
project staff.
• Project plan creates healthy environment.
• It commits individuals to tasks and motivates them to 40
7/28/2022
• Schedule aids in the optimization of resources
employed.
7/28/2022
objectives.
Instructor:Solomon.A
Benefits (At each level of management for Controlling)
(a) Operational control at supervisory level
(b) Administrative control at managerial level
(c) Directional Control at General Manager (GM) /
42
Project Manager (PM) level
Benefits (At each level of management for
Controlling)…
(a) Operational control at supervisory level
• Minimizing unproductive man hours
7/28/2022
• Preventing wastage of materials
Instructor: Solomon.A
• Economizing plant and machinery utilization
• Reducing activity execution time
43
(b) Administrative control at managerial level
• Updating the work quantities status and determining
the balance scope of work
7/28/2022
• Analyzing project time status
• Evaluating production cost status and forecasting
Instructor: Solomon.A
future trends
• Calculating income status and forecasting cash
inflows
• Computing budget status and forecasting cash 44
inflows
(c) Directional Control at General Manager (GM) /
Project Manager (PM) level
• Analyzing project time – cost behaviour and making
decisions on time saving when required
7/28/2022
• Reviewing project cost and profitability, and making
Instructor: Solomon.A
profitability improvement decisions
• Auditing management’s performance
(d) Strategic control at corporate level
• Determining overall profitability
• Budgeting and allocating funds and resources 45
7/28/2022
• Industrial construction
Instructor: Solomon,A
• Special – purpose projects
46
Building construction
• Residential buildings
• Commercial buildings
7/28/2022
• Educational buildings
Instructor: Solomon.A
• Recreational buildings
• Hospitals and hotels
• Warehouse and marketing facilities
47
Infrastructure construction
• Highways and expressways
• Dams and canals
7/28/2022
• Airports
•
Instructor: Solomon.A
Railways
• Bridges
• Oil / gas pipelines
• Large water supply and sewerage networks
•
48
Docks and harbours
• Nuclear and thermal power plants
Industrial construction
• Construction of steel plants
• Petroleum refineries
7/28/2022
• Chemical and Fertilizer plants
•
Instructor: Solomon.A
Consumer goods factories
• Automobile and aircraft industry
49
Special – purpose projects
• Environmental works
• Emergencies
7/28/2022
• Remedial works
•
Instructor: Solomon.A
Installation and commissioning of equipment
Classification of projects based on completion time
• Large duration projects (over 10 years)
• Medium duration projects (3 to 10 years)
• Short duration projects (few months to 3 years) 50
7/28/2022
million)
Instructor: Solomon.A
• Medium value projects ($ 10 million to $ 100
million)
• Small value projects (less than $ 10 million)
51
Classification of projects based on plant and
equipment.
Light Construction
7/28/2022
• Residential buildings
Instructor: Solomon.A
• Educational buildings
• Recreational buildings
• Commercial buildings
• Schools, hotels
52
• Small bridges, water tanks
Classification of projects based on plant and
equipment …
Heavy Construction
7/28/2022
• Dams, barrages, tunnels
Instructor: Solomon.A
• Highways, railways, airports
• Harbours
• Multispan bridges with well / pile foundations
53
Resources for Construction Industry
• Man power
• Money
7/28/2022
• Materials
Instructor: Solomon.A
• Machinery
54
Resources for Construction Industry…
• Man power – Man power in the form of technical and
managerial personnel and work force in various trades is
essential to carry out project activities.
7/28/2022
• Money – Adequate funds should be available for smooth
Instructor: Solomon.A
implementation of the project.
• Materials – bricks, steel, stones, timber, aggregate,
scaffolding, cement, water supply and sanitary fittings, lime,
petrol, oil, lubricants
• Machinery – batching and mixing plants, Mixers, crushers, 55
Trucks, dumpers, tractors, Rollers, Powers, Cranes,
excavators, hoist, Pumps, generators
Stakeholders of a Construction Project
(Construction Team)
• Owner
7/28/2022
• Engineers / Architects
Instructor: Solomon.A
• Contractors
56
Owner – The owner in a building or engineering project may
be an individual, group of individuals, private or public
undertaking.
7/28/2022
Responsibilities of the owner
• The owner is supposed to provide necessary site on which
Instructor: Solomon.A
the proposed work is to be constructed.
• The owner should appoint an engineer, to look after the
technical requirements of the work.
• The owner should supply necessary plans and working
drawings through his architect to the contractor in time so 57
that the work is not unnecessarily delayed.
Responsibilities of the owner…
• The owner should respect the conditions of contract
concerning his powers and duties.
• The owner should provide necessary work front to the
7/28/2022
contractor so that work is not delayed.
Instructor: Solomon.A
• The owner should make necessary arrangement for the
funds required for the construction of the work so that
regular payments shall be made to the contractor.
• It is desirable that the owner should pass all the instructions
to the contractor through his engineer. 58
• The owner should supply materials and issue machinery, if
it is a part of the contract.
Responsibilities of the owner…
• The owner should make arrangements to record the
measurement of items in time before they are covered up in
the subsequent execution of work.
7/28/2022
• The owner should not interfere with the progress of the
Instructor: Solomon.A
work and should not pass such instructions which will lead
to the problems of extra items, liquidated damages, etc.
• The owner should not suspend the work temporarily unless
it appears to be in his interest to do so.
• To take over possession of the completed work timely from 59
the contractor.
Engineers and architects
• This includes structural, mechanical and electrical
engineers, architects, quantity surveyors, specialists
7/28/2022
such as structural consultants, safety and maintenance
planners, soil investigators etc.
Instructor: Solomon.A
Responsibility of engineer
• To organize and supervise the execution of work and
to see that they are suitably and economically carried
out with specified quality of materials. 60
Engineers and architects…
• It is the duty of the executive engineer to prepare
estimate of proposed works through his subordinates
7/28/2022
and submit the same to his superintending engineer.
• The engineer is responsible for explaining the plans
Instructor: Solomon.A
and provisions of the specifications.
• The engineer is responsible for giving all lines and
levels required in connection with the work.
• It is his duty to invite tenders for works valued within 61
7/28/2022
method of construction in detail to the contractor.
• It is duty of the engineer to prepare specifications for
Instructor: Solomon.A
the work and to see that these specifications are
accurate, proper and reasonable for the work.
• The assistant engineer is responsible for taking
detailed measurement of works during progress and to 62
enter the same in M.B. and prepare bills for payment.
Engineers and architects…
• To see that machinery likely to be used on works are
properly maintenance and safely house.
7/28/2022
• To keep tools and plants in working conditions and
arrange to protect surplus stock from deterioration.
Instructor: Solomon.A
• To prevent encroachment on government lands under
his division.
• The engineer is responsible for the acts of his
assistants or other agencies employed by him. 63
• It is also the duty of the engineer to assist the court of
Contractor
• The contractor may be an individual undertaking
small or big need the services of qualified engineers.
7/28/2022
Responsibilities of the contractor
• The contractor is responsible to provide all the
Instructor: Solomon.A
materials, labour, equipments, etc. required under the
provisions of the contract for the execution of the
work.
• The contractor should carry out the work as per plans 64
and specifications and as per directions given by the
engineer
Responsibilities of the contractor…
• The contractor should inform the supervising engineer
before taking up any new item and before covering up of
any work.
7/28/2022
• The contractor should appoint a qualified person on site
Instructor: Solomon.A
of the work to whom instructions and directions can be
imparted.
• The contractor is responsible for any damage to the
persons or adjoining properties during execution of the
work. 65
7/28/2022
subcontractors.
Instructor: Solomon.A
• The contractor should give all the required assistance
to the engineer for establishing the lines and levels of
the work.
• • The contractor is responsible for arranging for the
66
permit of the controlled materials and for paying fees
and royalties for the use of patented articles.
Responsibilities of the contractor…
• The contractor is responsible for the safety of all the
labourers and personnel working at the site and
should provide safety shoes, helmets etc. to the
7/28/2022
workmen.
Instructor: Solomon.A
• To handover the completed work in a sound
condition.
• The contractor should submit his claims for extra
items in due time.
67
Interaction between Owner, Engineer and Contractor
1. Co-relation between the Owner and an Engineer
• As the owner finances the project and employs an
7/28/2022
engineer who agrees to perform his professional duties
with reasonable efforts and skill.
Instructor: Solomon.A
• If an engineer makes an unfortunate mistake, in spite
of due skill, he is not liable for his mistake unless the
owner proves that he failed to perform his duty
carefully.
• It is responsibility of the engineer to plan things for the 68
owner economically.
Interaction between Owner, Engineer and Contractor
2. Co-relation between an Engineer and Contractor
• There is much co-relation between an engineer and a
7/28/2022
contractor as the latter executes the work in strict
supervision of the former.
Instructor: Solomon.A
• The contractor has to work as per the design and
drawing in consultation with the engineer to avoid
any dispute.
69
Causes of delay in construction project
• Unexpected site conditions
• Difficulties in availability of materials
7/28/2022
• Difficulties in availability of labours
• Weather conditions – heavy rain
Instructor: Solomon.A
• Delay in issue of construction drawings
• Lack of liaison between contractor and Engineer
• Delay in clarifying bills
•
70
Cash flow and financial constraints
• Dispute between contractor and owner/engineer
Engineer and Construction Economy
• To adopt such construction methods which would
result in the lowest practical cost of the project.
7/28/2022
• Using as simple design as possible.
• Making use of locally available materials.
Instructor: Solomon.A
• Encouraging the use of materials of commercial
sizes.
• Making use of cost saving equipments and adopting
proper construction methods. 71
7/28/2022
• Providing suitable checks on costs of labour,
materials, equipments, supervision charges, etc.
Instructor: Solomon.A
• Engaging supervisors who have sufficient judgement
and experience in construction.
• Providing necessary work front to the contractor to
avoid any delay in construction 72
Contractor and Construction Economy
• Pre bidding studies of the project on the following aspects
will effect economy.
– Topography of the area
7/28/2022
– Climate
Instructor: Solomon.A
– Sources of materials
– Geology
– Availability of labour
– Local services, power, fuel, water
– Access to the site 73
7/28/2022
• Maintaining the construction equipments in proper working
Instructor: Solomon.A
conditions.
• Maintaining an atmosphere of co-operation with the labour
force.
• Giving liberal incentives to the labour force for greater
output. 74
• Adopting reliable safety measures to reduce accidents.
Contractor and Construction Economy…
• Holding periodic meeting with key personnel and
concerned design engineers to discuss plans,
7/28/2022
procedures and results.
• To satisfy himself with a reasonable percentage of
Instructor: Solomon.A
profit.
• Appointing sub-contractors for the specialized
operations.
75
THANK YOU!!!