HSE Report: Suramadu Project

The daily HSE report from May 31, 2022 summarizes contractor activities on the 150kV Suramadu project in Surabaya-Bangkalan. It notes that 58 toolbox meetings and 2 job safety analyses were conducted, along with 12 permit to work approvals. A total of 30 workers from various contractors logged 240 safe manhours. There were no reported safety incidents. Weather was reported as sunny between 7am to 3pm and from 4pm to 5pm.

Uploaded by

Edwin Rajagukguk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
90 views2 pages

HSE Report: Suramadu Project

The daily HSE report from May 31, 2022 summarizes contractor activities on the 150kV Suramadu project in Surabaya-Bangkalan. It notes that 58 toolbox meetings and 2 job safety analyses were conducted, along with 12 permit to work approvals. A total of 30 workers from various contractors logged 240 safe manhours. There were no reported safety incidents. Weather was reported as sunny between 7am to 3pm and from 4pm to 5pm.

Uploaded by

Edwin Rajagukguk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

HSE DAILY

PROYEK : SKTT LOKASI : Surabaya - Bangkalan TANGGAL : 31 Mei 2022


150 kV Suramadu

CONTRACTOR ACTIVITIES
I. HSE ACTIVITIES
No Activities Today Before Total Remark
1 Orientation/Induction
2 Toolbox Meeting 58
3 Job Safety Analysis 2
4 Permit To Work 12
5 Risk Containment Audit
6 HSE Meeting 3
8 Health Check
9 Inspection
15 Other …………………….
II. PERSONAL PROTECTIVE EQUIPMENT
DIBERIKAN KE PEKERJA
No Kind of PPE Remark
Today Record
1 Safety Shoes √
2 Safety Helmet √
3 Safety Glases √
4 Gloves Catun √
5 Ear plug/Ear muff
6 Rompi Keselamatan √
7 Full Body Harnes Doublel
8 Breathing Apparatus
9 Wearpack
10 Masker √
11 Leather Gloves
12 Rubber Gloves
III. PERFORMANCE REPORT
3.1 Incident Report
No Type of Incident Today Before Total Remark
1 Near Miss -
2 First Aid Case -
3 Medical Treatment -
4 Lost Time Injurie -
5 Fatality -
6 Fire Accident -
7 Traffic Accidennt -
8 Propertiy Damage -
9 Environmental Damage -
3.2 Manhour & Safe Manhour
Today Before Total
No Company Remark
Worker Safe Manhour Safe Safe Manhour
Manhour
1 PLN Pusmanpro 5 40 2824 2864
2 PLN UPP 1 8 664 672

1|Page
HSE DAILY
PROYEK : SKTT LOKASI : Surabaya - Bangkalan TANGGAL : 31 Mei 2022
150 kV Suramadu

3 KSO PT. Sucaco – PT. DGS 22 176 10756 10932


4 PLN UPT 2 16 72 72
5 PLN Tim Audit - - 24 24
6 PLN UIT - - 16 16
7 PLN UIP - - 40 40
8 PU - - 72 72
Grand Total 30 240 14468 14692
3.3 Safe Vehicle Distance (In Kilometer)
No Company Today Before Total Remark
1 KSO (Engkel ) 150 3950 4100
2 PLN Pus (Xenia) 80 2000 2080
3 PLN UPP(Xenia) 70 1770 1840
4 PLN UPT (Mobil) - 76 76
5 PLN UIT (Motor) - 70 70
6 PLN Tim Audit - 80 80
7 PLN UIP - 30 30
8 PU (PPK Suramadu) 65 65
Grand Total 300 8041 8341
IV.
Time Sunny Cloudy Rainy Time Sunny Cloudy Rainy
07.00 – 08.00 15.00 – 16.00 √
08.00 – 09.00 √ 16.00 – 17.00 √
09.00 – 10.00 √ 17.00 – 18.00
10.00 – 11.00 √ 18.00 – 19.00
11.00 – 12.00 √ 19.00 – 20.00
12.00 – 13.00 √ 20.00 – 21.00
13.00 – 14.00 √ 21.00 – 22.00
14.00 – 15.00 √ 22.00 – 23.00

HSE KSO HSE PLN PUSMANPRO HSE PLN UPP

Nama Kartika Dewi Asrori Afandi Ady Suryo Nugroho

TANDA TANGAN

Tanggal
31 Mei 2022 31 Mei 2022 31 Mei 2022