INSTALLATION CHECKLIST- DISTRIBUTION
PANEL
Project Name Area :
Project No. Drawing No. :
Client Report No. :
Contractor Date :
Sr.
Check Points Acceptance Norms Check Date Signature Remarks
No.
1 Proper Identification of the Panels As per approved layout drawings
Check for any physical damage to the
2 No damage
Panel & its components
Verification of the make of the
All the components should be as
3 components
per approved BOQ
as per the approved make
As per approved drawings
4 Check fixing arrangement
/specification
5 Check for proper fixing of the Panel/DB Properly tighten and rigid
Panel should be aligned both
6 Alignment of the Panel/DB
horizontally & vertically
Ensure the extra gland holes are
covered with dummy caps for
7 Extra holes should be plugged
preventing inrush of foreign objects &
particles
8 Tightness of the gland Gland should be tightened properly
Earthing connection should be
9 Earthing of the Panel and Doors
provided on both sides
Tightness of cable/wire terminations
10 All the terminations should be tight
inside the Panel/DB
11 Provision of MCB Blanker (if required) Extra space should be plugged
Check the Panel/DB Door alignment & DB doors should be closing
12
proper closing properly
Panel should be clean
13 Cleaning of the Panel/DB
inside/outside
Contractor Client
Signature: Signature:
Name: Name:
Date: Date:
Site / Quality In charge Site / Quality In charge
Page 1 of 5
Installation Check List
ABB/L&T/T03-07/CL/034.1 PROJECT: Sub Contact T0307
Terminal 3 Electrical System
ITEM: CAT-6 UTP cable
Date:
Building Drawing No
Block System
Level Activity
Report no Others
AGENCIES
SL No CHECK PONT ACCEPTANCE NORM SUBCONTRACTOR REMARKS
CONTRACTOR
Execution QC
1 Acceptance of material Approved by Contractor/Employer
2 Ensure proper Storage of cable Moisture should not enter in to the cable
Storage area should have provision for
water draining
3 Type and size of the cable As per approved drawing/Cable Schedule
4 Verification of Proper laying, dressing of Bending angle of Cat-6 UTP Cable
Cat-6 UTP cable. should be greater than120 Degree.
Ensure no physical damage to the cable
during cable Laying
There should not any twist in the cable
5 Verify the gap between power cables laid As per approved drawing
in same level
6 Ensure the proper dressing of the cable As per approved drawing
with proper Cable Tie
7 Continuty of the Cable with SLT or LAN Continuity should be there
tester
8 Ensure the proper Tag marking of each Tag Marking should indicate origin and
and every cable purpose of the cable
Execution Sub contractor QA Sub contractor Contractor Employer
Name : Name : Name : Name :
Date: Date: Date:
Signature: Signature: Date:
Signature:
Signature:
Installation Check List
ABB/L&T/T03-07/CL/34.2 PROJECT: Sub Contact T0307
Terminal 3 Electrical System
ITEM: Optical Fibre cable
Date:
Building Drawing No
Block System
Level Activity
Report no Others
AGENCIES
SL No CHECK PONT ACCEPTANCE NORM SUBCONTRACTOR REMARKS
CONTRACTOR
Execution QC
1 Acceptance of material Approved by Contractor/Employer
2 Ensure proper Storage of cable Moisture should not enter in to the cable
Storage area should have provision for
water draining
3 Type and size of the cable As per approved drawing/Cable schedule
4 Verification of Proper laying and Bending angle of Optical Fiber Cable
dressing for OF Cable. should be greater than120 Degree.
Ensure no physical damage to the cable
during cable Laying
There should not any twist in the cable
5 Verify the gap between OF cables laid As per approved drawing
in same level
6 Checking whether the various noise As per approved drawing
class cables are laid in the different
trays -
7 Ensure the proper dressing of the cable As per approved drawing
with proper Cable Tie
8 Continuty of the Cable with Lazer Continuity should be there
tourch
9 Ensure the proper Tag marking of each Tag Marking should indicate origin and
and every cable purpose of the cable
Execution Sub contractor QA Sub contractor Contractor Employer
Name : Name : Name : Name :
Date: Date: Date:
Signature: Signature: Date:
Signature:
Signature:
Installation Check List
ABB/L&T/T03-07/CL/35.1 PROJECT: Sub Contact T0307 Terminal
ITEM: CAT-6 cable 3 Electrical System
termiation DATE
Building Drawing No
Block System
Level Activity
Report no Others
AGENCIES
SL No CHECK PONT ACCEPTANCE NORM SUBCONTRACTOR REMARKS
CONTRACTOR
Execution QC
Approved by
1 Acceptance of material
Contractor/Employer
2 Dressing of cable As per Approved drawing
3 Termination as per cable schedule Terminal no as per cable
schedule
size of cable as per cable
schedule
Ferrule as cable schedule
4 Damage of wire during stripping There shall be no damage
either on the wire or on the
5 Damage of insulation during stripping insulation
6 crimpling compactness
7 Termination Check tightness of screw with
screw Driver for screw
termination
Termination of Cable with
Impact tool
8 Continuity of the cable with SLT or Continuity should be there
LAN tester
Execution Sub contractor QA Sub contractor Contractor Employer
Name : Name : Name : Name :
Date: Date: Date: Date:
Signature: Signature:
Signature: Signature:
Installation Check List
ABB/L&T/T03-07/CL/35.2 PROJECT: Sub Contact T0307
ITEM:Optical Fibre Terminal 3 Electrical System
cable termiation DATE
Building Drawing No
Block System
Level Activity
Report no Others
AGENCIES
SL No CHECK PONT ACCEPTANCE NORM SUBCONTRACTOR REMARKS
CONTRACTOR
Execution QC
1 Acceptance of material Approved by Contractor/Employer
2 Dressing of cable As per approved drawing
3 Termination as per cable schedule Terminal no as per cable
schedule
size of cable as per cable
schedule
Ferrule as cable schedule
4 Damage of wire during stripping There shall be no damage either
on the wire or on the insulation
5 Damage of insulation during stripping
6 crimpling compactness
7 Termination Check tightness of screw with
screw Driver for screw fibre panel
termination.
Termination of OF cable with
Splicing machine or fiber tool kit
8 Continuity of the cable with Lazer tourch
Execution Sub contractor QA Sub contractor Contractor Employer
Name : Name : Name : Name :
Date: Date: Date:
Signature: Signature: Date:
Signature: Signature: