Scrum Open
Percentage: 93.3%
Duration: 00:12:42
Date started: Thu 15 Sep '22 16:01
Date finished: Thu 15 Sep '22 16:14
Feedback
Congratulations! Your score on the Open assessment demonstrates you know some
Scrum basics.
Scrum on,
Ken Schwaber
Continue here
Return to Scrum.org
all questions 28 correct 2 incorrect
https://www.classmarker.com/online-test/start/results/?quiz=3qg5fac7589c0416 1/4
15/09/2022 22:15 Scrum Open
Question 4 of 30
True or False: The Scrum Team must choose at least one high priority process improvement
item, identified during the Sprint Retrospective, and place it in the Sprint Backlog.
True
False
Feedback
An earlier version of the Scrum Guide prescribed the practice of placing one
improvement in the Sprint Backlog. This was removed in the 2020 update to the Scrum
Guide because it was felt to be too prescriptive. However, if this practice provides value
to you then you should adopt it. It is simply not prescribed anymore, but can still be
valuable.
https://www.classmarker.com/online-test/start/results/?quiz=3qg5fac7589c0416 2/4
15/09/2022 22:15 Scrum Open
Question 25 of 30
Which of the following are examples of a Scrum Team practicing Scrum poorly or not exhibiting
traits of a self-managing Scrum Team?
(choose the best three answers)
A. Stakeholders attend the Daily Scrum to check on the Scrum Team’s
progress.
B. The Developers are working within the boundaries of their
organizations functional description and nicely handing off work from
analyst to developer to tester to integration.
C. The Developers create their own Sprint Backlog, reflecting all work
that is required to meet the Definition of Done.
D. The Developers have all the skills they need to create a valuable,
useful Increment.
E. The Developers invite external stakeholders to the Sprint Planning to
ask them how to turn a Product Backlog item into an Increment via a
complete and detailed Sprint Backlog.
F. The Developers are collaboratively selecting their own work during the
Sprint.
You did not select all available correct options.
Feedback
The Daily Scrum is for the Developers. It should not be used by
external stakeholders to check progress.
During Sprint Planning the Scrum Team should be crafting the Sprint
Goal based on the set of Product Backlog items selected for the Sprint.
The Developers identify the necessary work to meet the Sprint Goal.
Scrum Team members do not have titles, and no sub-teams; such as
testing, architecture, or operations are recognized. Accountability
belongs with the Scrum Team as a whole, regardless of whether team
members have specialized skills.
https://www.classmarker.com/online-test/start/results/?quiz=3qg5fac7589c0416 3/4
15/09/2022 22:15 Scrum Open
https://www.classmarker.com/online-test/start/results/?quiz=3qg5fac7589c0416 4/4