0% found this document useful (0 votes)
65 views2 pages

M1515-MAI-MCL-MIR-0048 (Material Inspection Request)

Uploaded by

manoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
65 views2 pages

M1515-MAI-MCL-MIR-0048 (Material Inspection Request)

Uploaded by

manoj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Nudra Private Villas Project, Plot No.

A3 & A4

MATERIAL INSPECTION REQUEST

REFERENCE No.: M1515-MAI-MCL-MIR-0048 REV. 02 DATE: 29/11/2021


INSTALLATION OF STEEL STRUCTURE CANOPY WITH WPC
SUBJECT: PROJECT No. M1515
CLADDING
M1515-MCL-ALH-MSA-
Delivery Doc Ref: Maisam Material Submittal Ref:
0001

TO: Maisam FROM: McLaren Construction Ltd.


☒Architectural ☐Civil / Structural ☐MEP ☐External work ☐Others (Specify)__________

QUANTITY DELIVERY SPEC. INSPECTION


NO. MATERIAL DESCRIPTION UNIT
LOCATION SECTION RESULT
MAIN FRAME
1 No. 1 MOCK-UP AREA
RHS 200x100x3mm
SECONDARY FRAME
2 Nos. 2 MOCK-UP AREA
RHS 200x100x3mm
3 FASTNERS SS316 SELF SCREW Packs 2 MOCK-UP AREA
4 ALUMINIUM TUBE AA6063 Mtr. 30 MOCK-UP AREA
HILTI-RE 500 V4 + ANCHOR
5 Nos. 12 MOCK-UP AREA
BOLT M20 x 150mm Lg
6 WPC PANEL PLANK Lumps MOCK-UP AREA

FOR CONTRACTOR:
NAME: ________________DESIGNATION: ______________SIGNATURE: __________________ DATE: ________________

ENGINEER’S COMMENTS:

Test Required Y/N:


No. of Samples Required Y/N:
Engineer’s
Confirm compliance with approved transmittal: Y/N
Signature:
☐ A - Approved ☐B - Approved w/ Comment ☐C - Revise & Resubmit ☐D - Review not Required

QMS002 (UAE) 09/15 Rev A Page 1 of 2 Material Inspection Request


|
Nudra Private Villas Project, Plot No. A3 & A4
(Work may proceed) (Incorporate comments & Proceed) (Work may not proceed) (Work may Proceed)

Note: Inspection request should be submitted 24 hours prior for inspection

Received by Contractor (Please sign below: retain Original & Return Copy)

Name: Signature: Date:

QMS002 (UAE) 09/15 Rev A Page 2 of 2 Material Inspection Request


|