Engineering Assurance Network Rail 2 of 2
Engineering Assurance Network Rail 2 of 2
Supplementary Information
PowerPoint Presentation
• NR/L2/CIV/003/Awareness Briefing
• NR/L2/CIV/003/Technical Briefing
Word documents
• NR/L2/CIV/003/FormA
• NR/L2/CIV/003/FormB
• NR/L2/CIV/003/FormC
• NR/L2/CIV/003/FormD
• NR/L2/CIV/003/FormE
• NR/L2/CIV/003/FormF
• NR/L2/CIV/003/FormG
• NR/L2/CIV/003/FormH
• NR/L2/CIV/003/F1990
• NR/L2/CIV/003/F1991
• NR/L2/CIV/003/F1992
• NR/L2/CIV/003/F1993
• NR/L2/CIV/003/F1994
• NR/L2/CIV/003/F1997
If you have any questions, or need assistance, please contact IHS Support
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Information accessed via the links above is the property of the Copyright holder
Level 2
Business Process
Engineering and Architectural Assurance of
Building and Civil Engineering Works
Approvals
......................................................................................................
Steve Williams,
Technical Lead
Ian Brookes,
Standard and Control Document Owner
......................................................................................................
Kerry Marchant,
Standards and Controls Management Team
This document is the property of Network Rail. It shall not be reproduced in whole or part nor disclosed to a third
party without the written permission of Network Rail.
© Copyright 2021 Netwo rk Rail.
Published and Issued by Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN.
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
User information
This Network Rail document contains colour-coding according to the following
Red–Amber–Green classification.
Red requirements – no variations permitted
• Red requirements are to be complied with and achieved at all times.
• Red requirements are presented in a red box.
• Red requirements are monitored for compliance.
• Non-compliances will be investigated and corrective actions enforced.
Page 2 of 58
--`,``,,````````,,,,
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Compliance
This Network Rail standard/control document is mandatory and shall be complied
with by Network Rail Infrastructure Limited and its contractors if applicable from 4th
March 2022.
Where it is considered not reasonably practicable to comply with the requirements in
this standard/control document, permission to comply with a specified alternative
should be sought in accordance with the Network Rail standards and controls
process, or with the Railway Group Standards Code if applicable.
If this standard/control document contains requirements that are designed to
demonstrate compliance with legislation they shall be complied with irrespective of a
project’s Governance for Railway Investment Projects (GRIP) stage or Project
Acceleration in a Controlled Environment (PACE) phase. In all other circumstances,
projects that have formally completed GRIP Stage 3 (Option Selection) or PACE
strategic development & project selection phase may continue to comply with any
relevant Network Rail standards/control documents that were current when GRIP
Stage 3 or PACE phase 1 was completed.
NOTE 1: Legislation includes National Technical Specification Notices (NTSNs)
NOTE 2: The relationship of this standard/control document with legislation and/or
external standards is described in the purpose of this standard.
Disclaimer
In issuing this standard/control document for its stated purpose, Network Rail
Infrastructure Limited makes no warranties, expressed or implied, that compliance
with all or any standards/control documents it issues is sufficient on its own to
provide safety or compliance with legislation. Users are reminded of their own duties
under legislation.
Compliance with a Network Rail standard/control document does not, of itself, confer
immunity from legal obligations.
Where Network Rail Infrastructure Limited has granted permission to copy extracts
from Network Rail standards or control documents, Network Rail Infrastructure
Limited accepts no responsibility for, nor any liability in connection with, the use of
such extracts, or any claims arising there from.
This disclaimer applies to all forms of media in which extracts from Network Rail
standards and control documents might be reproduced.
Supply
Copies of standards/control documents are available electronically, within Network
Rail’s organisation. Hard copies of this document might be available to Network Rail
people on request to the relevant controlled publication distributor. Other
organisations can obtain copies of this standard/control document from an approved
distributor.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Issue record
Issue Date Comments
1 October 2001 Supersedes RT/CE/P/003
2 February 2004 Supersedes RT/CE/S/003 Issue 1
3 June 2011 Updated to reflect changes to the organisation and
streamlining of Technical Approval procedure.
4 June 2012 Editorial edits to eliminate typographical errors,
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Page 5 of 58
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Legislation
This standard/control document has been reviewed to confirm it complies with the
following legislation:
Equality Act 2010 (c.15)
CDM Construction (Design and Management) Regulations 2015
Department for Transport National Railways Security Programme, enforced under Sections 119
to 121 of the Railways Act 1993
Compliance with this standard/control document does not, on its own, provide
compliance with the legislation listed.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Contents
1 Purpose ........................................................................................................................ 9
2 Scope .......................................................................................................................... 10
2.1 Types of Assets ....................................................................................................... 10
2.2 Types of Works ........................................................................................................ 10
2.3 External Party Assets .............................................................................................. 10
2.4 Application ................................................................................................................ 11
2.5 Exclusions ................................................................................................................ 11
3 Roles and responsibilities ....................................................................................... 12
Table 1 – Roles .............................................................................................................. 13
Table 2 –RACI chart ...................................................................................................... 14
4 Definitions .................................................................................................................. 15
Table 3 – Terms ............................................................................................................. 19
Table 4 – Abbreviations ................................................................................................. 20
5 B&C Engineering and Architectural Assurance Business Process ................. 21
Figure 1 – Process flow diagram for permanent works. .............................................. 22
Figure 2 – Process flow diagram for temporary works. ............................................... 23
6 Remit ........................................................................................................................... 24
7 Requirements development .................................................................................... 24
7.1 Requirements documents ....................................................................................... 24
7.2 Contract Requirements – Technical (CR-T) ........................................................... 24
7.3 Risk Assessment ..................................................................................................... 25
8 Feasibility ................................................................................................................... 25
9 Option Selection ....................................................................................................... 26
10 Architectural and layout acceptance ................................................................... 27
11 Single option development to Approval in Principle (AiP) .............................. 28
11.1 Overview ................................................................................................................ 28
11.2 Approval in Principle (AiP) .................................................................................... 29
11.3 Consultation with Client/AM team ......................................................................... 29
11.4 External stakeholder agreement ........................................................................... 30
11.5 Certificate of Approval in Principle (AiP) .............................................................. 30
12 Detailed design and design check for permanent works ................................. 33
12.1 Detailed design ...................................................................................................... 33
12.2 Use of the Combined Certificate of Approval in Principle, Design and Design
Check (FormG) for Design Check Category I permanent works. ................................ 34
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
13.1 General................................................................................................................... 35
13.2 Temporary works operations. ............................................................................... 35
13.3 ASPRO controlled temporary works operations .................................................. 38
14 Use of the Certificate of Design and Check (FormH) for Design Check
Category 0 works ......................................................................................................... 39
15 Design Check and Design Check Category........................................................ 39
Table 5 – Design check categories ............................................................................... 41
16 Approved for Construction (AFC) design ........................................................... 42
16.1 Technical Approval of the design.......................................................................... 42
17 Specification and Inspection & Testing Plans (ITP’s) ....................................... 43
18 Verification for Entry into Service ........................................................................ 44
18.1 Preparation............................................................................................................. 44
18.2 Certificate of fitness to be taken into use ............................................................. 44
19 Complimentary assurance processes................................................................. 44
Table 6 – Engineering assurance processes ............................................................... 45
20 Records .................................................................................................................... 45
21 Timeframes .............................................................................................................. 46
Appendix A - Design Check Categories ................................................................... 47
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Table A-1 – Applicability of forms.................................................................................. 47
Figure A-1 – Skew bridge dimension parameters ........................................................ 51
Appendix B - Model forms for technical approval .................................................. 57
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
1 Purpose
This business process sets out:
a) the technical and architectural assurance of works to Building and Civil
Engineering infrastructure; and
b) Entry into (Operational) Service (EIS) requirements for such works.
The Assurance process is a method of consistently verifying that Building and Civil
Engineering infrastructure designs:
1) meet client, project and stakeholder requirements;
2) are suitable in terms of:
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
• safety;
• security;
• constructability;
• functionality;
• appearance and other architectural aspects;
• planning conditions & requirements;
• heritage requirements;
• spatial capacity;
• human factors / ergonomics;
• wayfinding and navigation;
• accessibility;
• maintainability;
• sustainability;
• specification;
• cost;
• decommissioning;
• demolition.
Quality design, checking, execution and assurance is critical to controlling business
and safety risk throughout the asset lifecycle.
The processes described in this document support the Engineering Management
processes detailed in NR/L2/RSE/02009. They also support the Project Acceleration
in a Controlled Environment requirements set out in NR/L2/INI/P3M/201, where
PACE applies.
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
2 Scope
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
f) building services;
g) civil and building type elements or components of other assets.
NOTE 2: The types of assets listed might include architectural aspects.
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
2.4 Application
This business process applies to Network Rail and non-Network Rail personnel
involved in the remitting, design, checking, design assurance, construction assurance
and taking into use of Buildings and Civils infrastructure.
2.5 Exclusions
This business process does not apply to:
a) consents or approvals from bodies outside Network Rail including:
1) regulatory and statutory authorities;
2) planning, listed building and conservation authorities;
3) environmental regulators;
4) land and property owners or leaseholders;
5) statutory undertakers and other public services and utilities owners.
b) obtaining approvals for the New Roads and Street Works Act;
c) obtaining approval from other Network Rail engineering disciplines for the
equipment carried by Equipment Support Structures or for the performance of
that equipment;
NOTE: For Example, signal sighting and reduced clearances.
d) assessments of structures.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Role Responsibilities
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Table 1 – Roles
workshops etc.
Sponsor
Checker
PM
Remit Acceptance A R C C C I I I I
Requirements Production Ref er to NR/L3/INI/P3M/221 PACE Manage Scope, where
documents
Acceptance PACE applies.
Contract Requirements
– Technical (CR-T) / Production I A R R I I I I
Technical Work Scope
Production I I C C A R
Feasibility Study
Acceptance C C A,R R R I I
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
CRE (Construction)
overall accountability to make sure that a task
or action is completed.
C – Consulted people have an input into the
CRE (Design)
task or action, this can be providing
information, reviewing documents or attending
PE (B&C)
workshops etc.
Sponsor
Checker
I – Informed people are those who receive
CEM
DPE
the output of a task or process.
AM
PM
* Denotes option for delegation
Production C I C C A R
Option Selection
Acceptance C C A,R C R I I
Single Option Production I C C A R
Development to
Approval in Principle Acceptance A R C R R I I
Production I C C A R I C
Detailed Design Design Check I I I A C R I
Acceptance I,C 1
I I A R I I I I
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
4 Definitions
The terms used in this document are described in Table 3 and the abbreviations
used in this document are described in Table 4.
Term Definition
Approval in Principle (for Forms part of single option development. Approval signifies
permanent works) that the Asset Manager (AM) is satisfied that the design
solution identified is the preferred option for achieving the
Project Requirements. The AM might require
supplementary endorsement from other stakeholders to
support the Approval.
Approved for Construction As defined in NR/L2/RSE/02009
(AFC design)
Building and Civil
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Term Definition
Design Check Statement A document, which describes the proposed methodology
for undertaking a checking to Design Check Category III
works (See clause 15)
Designer ‘Designer’ means any person (including a Client, contractor
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
or other person referred to in the CDM Regulations) who, in
the course or furtherance of a business:
• prepares or modifies a design or specifies a standard
design
• arranges for (or instructs) any person under their control
to do so.
Diversity Impact The process Network Rail adopts to assess and consult on
Assessment the effects that a project has on different groups in a
community.
NOTE: It is carried out under the Equality Act (2010).
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Term Definition
External Party An organisation, other than Network Rail, that is an:
infrastructure owner
• developer
• user or occupier of Network Rail’s infrastructure.
NOTE: The term includes highway authorities, passenger transport
executives, public or private developers and train operating companies.
Hidden Critical Element A structural part of an asset that cannot be observed from
at least one side throughout its extent and which is not
protected by a material that can preserve its condition.
Remit / Technical work A form of agreement and specification for works, which
scope creates and defines obligations between a project and a
design/construction organisation or team, where PACE
does not apply.
Renewal Major works that result in permanent changes to the asset.
For geotechnical assets examples of renewal works include
full regrading, the installation of major retaining structures
or other major support measures. Refer to Network Rail’s
Cost & Volume Handbook for more information on this
Work Activity.
Repair Work Planned work that requires reinstatement of the
components of an asset, but which does not result in a
permanent change to the general form of that asset or a
permanent reduction in the standard of safety.
NOTE 1: e.g. structure gauge not reduced.
The term includes:
a) like-for-like repairs and replacement of components;
b) repair and replacement of components in similar or
generally accepted equivalent materials provided that
such substitution does not adversely affect the integrity
or performance of the asset or operations;
c) ‘good housekeeping’ activities such as cleaning,
painting, pointing, removal of harmful vegetation from
assets and clearing mud and silt from watercourses.
NOTE 2: Refer to Network Rail’s Cost & Volume Handbook for more
information on this Work Activity.
Replacement Works that involve the replacement of an asset (or part of
one) where there is no change to the functionality of that
asset.
NOTE: Refer to Network Rail’s Cost & Volume Handbook for more
information on this Work Activity.
Page 17 of 58
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Term Definition
Requirements documents As defined in NR/L2/P3M/221 for PACE projects, or for the
purposes of this standard, the Remit or the Technical
Workscope or the Works Order for non-PACE projects
Section Manager Person responsible for delivery of works undertaken by an
Infrastructure Maintenance Team.
Sponsor’s Instruction The formal document from the Sponsor that describes the
objectives for each stage of a Project and details the
services to be provided by the Project Manager.
Taken into Use The state of new, altered or renewed infrastructure or
temporary works (whether complete or not) when fit for (as
applicable):
a) the safe passage of trains;
b) occupation by users;
c) use of or passage by members of the public;
d) installation of plant or equipment.
Technical Acceptance (of As defined in NR/L2/RSE/02009
Engineering Deliverables)
Temporary conditions Those parts of the works that allow or enable construction
of, protect, support or provide access to, the permanent
works, which may or may not remain in place at the
completion of the works. This includes states of the
permanent works which are temporary and temporary
stages or phases of works put into operational use prior to
completion of the works.
NOTE: Examples of temporary conditions include interim signalling
solutions, part-built structures, early striking of concrete, un-propped
excavations and masonry at near full height but without head restraints.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Term Definition
Temporary works An engineered solution that is used to support or protect
either an existing structure or the permanent works during
construction, or to support an item of plant or equipment, or
the vertical sides or side-slopes of an excavation during
construction operations on site or to provide access. It is
used to control stability, strength, deflection, fatigue,
geotechnical effects and hydraulic effects within defined
limits.
NOTE: Temporary works includes, but is not limited to:
a) supporting or protecting either an existing structure or the
permanent works during construction, modification or demolition;
b) provision of stability to the permanent structure during
construction, pre-weakening or demolition (e.g. propping, shoring,
façade retention);
c) securing a site, or providing access to a site or workplace on site
or segregation of pedestrians and vehicles (e.g. hoarding, haul
roads, fencing, stairs);
d) supporting or restraining plant, materials or equipment, including
stability of water-borne craft;
e) provision of earthworks or slopes to an excavation or supports to
the side or roof of an excavation or supports or diversions to
watercourse during construction operations;
f) providing a safe platform for work activity on land or water (e.g.
jetty, scaffolding, edge protection or towers);
g) providing measures to control noise, dust, debris, fume, air quality,
groundwater or any site discharges during construction or
demolition (e.g. screens, bunds, de-watering, demolition debris);
h) providing protection or support to services;
i) facilitating testing (e.g. pressure testing pipes, pile testing, pre-
demolition floor load capacity testing);
j) Providing measures to confirm the temporary condition of
permanent works is stable and safe during construction or
deconstruction
Table 3 – Terms
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
Abbreviation Description
AFC Approved for Construction
AiP Approval in Principle
AM Asset Manager (per asset discipline)
B&C Building and Civil Engineering (disciplines)
BREEAM Building Research Establishment Environmental
Assessment Method
CDM Construction (Design and Management) Regulations
CEEQUAL Civil Engineering Environmental Quality Assessment
and Award Scheme
CEM Contractor’s Engineering Manager
CM Construction Manager
CRE Contractor’s Responsible Engineer
CR-T Contract Requirements – Technical
DIA Diversity Impact Assessment
DRA Designer’s Risk Assessment
DPE Designated Project Engineer
EIS Entry into (Operational) Service
IDC Interdisciplinary Check
IDR Interdisciplinary Review
LRVR Local Risk & Vulnerability Register
NR Network Rail
PACE Project Acceleration in a Controlled Environment
PE Project Engineer
PM Project Manager
RACI Responsible, Accountable, Consulted and Informed
TVRA Threat and Vulnerability Risk Assessment
TWf Temporary Works forum
Table 4 – Abbreviations
--`,``,,````````,,,,`
Ref: NR/L2/CIV/003
Issue: 7
Date: 04 December 2021
Compliance date: 04 March 2022
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Engineering and Architectural Assurance of Building and Civil Engineering Works; Permanent Works
Feasibility and optioneering Design Construct, test, Hand back & close out
Remit and Requirements (Development and project selection) (Project design) commission (Delivery) (Project close)
Start
Remit
[6.0]
[7.0] End
Processes Specified in
Approved for
Inspection
construction
and Testing
design
[17]
[16]
Forms specified in NR/L2/
Engineering Assurance
Process Form
KEY Process
pre-defined
Engineering and Architectural Assurance of Building and Civil Engineering Works; Temporary Works
Feasibility and Optioneering Design Construct, test and commission Hand back and close out
(Development and project selection) (Project design) (Project delivery) (Project close)
Remit and Requirements
Start
Remit
[6.0]
End
FORM C FORM E
Certificate of Design Certificate of
and Check for fitness to be taken
L2/CIV/003
FORM H
Certificate of design
and check for
Category 0 works
Process Form
KEY Process
pre-defined
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
6 Remit
The remit shall set out the objectives and other critical success criteria for the project.
The remit may take different formats depending on the scope of works and delivery
approach, examples include the following:
1) A client remit is a PACE product and should be utilised for renewal and
enhancement projects;
2) A Works Order might perform the role of the remit for works instructed to the
Works Delivery organisation;
3) A contractually binding agreement between Network Rail and an External
Party which captures the project scope, respective rights, obligations and
should form the basis of the remit for External Party works as set out in
NR/L2/CIV/095 and NR/L2/CIV/096.
7 Requirements development
requirements for projects or programmes that impact how the public access station facilities. The DIA
should be continuously reviewed and updated if necessary, throughout the project’s development.
NOTE 2: See standard NR/L2/ENV/015 - Environmental and Social Minimum Requirements – Design
and Construction – for environmental and sustainable development requirements. This standard
manages environmental and social risks and opportunities during the design and/or construction
phases of a project.
The Designated Project Engineer is responsible for aligning the requirements of the
CR-T with those specified in the requirements documents, workscope, remit or works
order, depending on whether PACE is used or not.
NOTE: Where the Contract does not require CR-T, an equivalent should be provided to capture
technical requirements.
8 Feasibility
Where required by the Client/Sponsor, a feasibility study (or studies) shall be
undertaken.
The purpose of the feasibility study is to:
a) define the outputs required to meet the business objectives;
b) identify project constraints and risks;
c) identify likely options that could be delivered by the project to achieve the
outputs.
The scope of a feasibility study should reflect the size and complexity of a project,
and can include the following considerations:
a) planning and consent requirements;
b) environmental and social constraints, impacts and opportunities;
c) security consents, requirements, constraints and impacts;
d) stakeholder requirements;
e) other legal / statutory approvals;
f) determining scope of works;
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
t) Employers Information Requirements and other BIM related requirements
u) diversity and inclusion requirements. (e.g. under the Equality Act (2010))
v) requirements for BREEAM or CEEQUAL accreditation
NOTE 1: Examples where a feasibility study might not be required include emergency works or works
where the appropriate design solution is self-evident.
NOTE 2: Feasibility is typically undertaken in the PACE Strategic development and project selection
Phase
NOTE 3: The scope and size of the study and associated report is typically be dependent upon the
scale and complexity of the proposed scheme and range of options considered.
NOTE 4: The output from the feasibility study should be presented in a clear and structured report to
facilitate understanding by the client, sponsor, project team and stakeholders.
NOTE 5: Designers may make use of emerging industry tools to help undertake feasibility work
efficiently.
9 Option Selection
Where required by the Client or Sponsor, an optioneering appraisal / study shall be
undertaken.
The purpose of the optioneering appraisal / study is to:
a) define the project and infrastructure constraints in greater detail;
b) develop the evaluation criteria for feasible options;
c) develop feasible options that deliver the required outputs;
d) evaluate feasible options and select an appropriate option(s) for development;
e) recommend option(s) to progress during project development and design.
In order to provide greater certainty of the scope for option selection, an improved
understanding of the site conditions and project scope and constraints would typically
be required. The following optioneering related activities are commonly required:
a) surveys (topographical surveys, condition surveys, environmental surveys);
b) environmental desk study;
c) geotechnical desk study;
d) ground investigation;
e) ground investigation report;
f) records searches; (asset records, utility records)
g) station pedestrian capacity assessment;
h) stakeholder liaison;
i) Provision and acceptance of Form D where appropriate; refer clause 10.
j) sustainability (including lifecycle costing) and environmental assessment; e.g.
requirements of NR/L2/ENVV/015 and other ENV series standards.
k) Diversity Impact Assessment.
NOTE 1: E.g. to meet the Equality Act (2010).
Issues to be assessed as part of the optioneering study include those listed in clause
8.
The project Sponsor shall select a single option from the optioneering study for
subsequent development to enable the project to proceed.
NOTE 2: It might be necessary to select more than one option for development (for example where
critical programme constraints dictate that design development should progress in advance of
agreement of key project or stakeholder requirements).
The option selection process generally includes:
a) identifying the options and the criteria for the option evaluation;
b) providing impartial scoring (qualitative or quantitative) for the options and
applying weighting criteria;
c) viewing and analysing the results;
NOTE 3: With confirmation of sensitivity and robustness of the scoring.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
11.1 Overview
The chosen single option shall be developed. Single option development shall
comprise the production and endorsement of the Certificate of Approval in Principle
(NR/L2/CIV/003/FormA).
The Approval in Principle form shall set out the basis upon which the Detailed Design
of the works or a specific part of them is to be developed.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
NOTE: Where applicable to the works, the submission should also include the Architectural and
Layout Acceptance (NR/L2/CIV/003/FormD) and/or the Road/Highway Authority Agreement to bridge
works (NR/L2/CIV/003/FormF ).
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
b) emergency works;
c) temporary works;
NOTE 1: For temporary works refer to NR/L3/CIV/020 for specific requirements relating to Approval in
Principle of temporary bridges, as in some circumstances AM approval for Temporary bridges is
needed.
d) those schemes where the Design only requires a Category 0 Design Check ,
where FormH applies.
NOTE 2: Examples of Design Check Category 0 works are included in Appendix A.
NOTE 3: Approval in Principle is to obtain and record Network Rail and key stakeholder approval of
the proposed single option.
Approval in Principle shall be achieved by the signed completion of
NR/L2/CIV/003/FormA.
NOTE 4: NR/L2/CIV/003/FormA should contain sufficient information to enable the design proposal to
be approved in principle (AiP). This should include proposals for asset design life and other
parameters from F1990 to F1997, noting most parameters in these forms are not required at AiP.
The CRE (B&C) shall enable PE (B&C) to provide signed acceptance of
NR/L2/CIV/003/FORM A prior to the start of the Detailed Design stage, by providing
the Form A in good time.
NOTE 5: The PE (B&C) might by exception permit the Detailed Design to commence prior to
acceptance of the NR/L2/CIV/003/FormA (for low complexity design for example).
separate copies of NR/L2/CIV/003/FormA for (for example), (a) structural works, (b) architectural &
layout design and (c) the provision of Building Services.
NR/L2/RSE/02009 section 15 sets out the requirements for undertaking
Interdisciplinary Coordination, Interdisciplinary Checks and Interdisciplinary Reviews
prior to the technical acceptance of engineering Deliverables, including the FormA.
Approval of NR/L2/CIV/003/FormA consists of signed approval by the PE (B&C) and
signed confirmation by the relevant AM(s).
Revised or additional route requirements identified on the approved
NR/L2/CIV/003/FormA shall be agreed with the Sponsor and included in the
requirements documents..
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
b) schedules;
c) performance;
d) materials;
e) workmanship specifications, including performance testing requirements not
specified by product standards; and
f) Designer’s Risk Assessment.
g) IDR certificate
The Detailed Design of Buildings and Civils infrastructure shall be integrated with
other parts of the Design.
NOTE 1: This includes Building Services.
Reference to the Technical Design Requirements Forms (NR/L2/CIV003/F1990 to
F1997) and the selected options for applying the suite of Structural Eurocodes shall
be provided with the FormB, except for the design life to be agreed at AiP.
The criteria in Forms F1990 to 1997 shall be agreed with the DPE/PE (B&C) early
after AiP and before detailed design, to inform the detailed design, prior to
submission of the FormB.
NOTE 2: The design working life (dwl) from Form 1990 and other criteria from F1990 to F1997 are
agreed at FormA. The other parameters in F1990 to F1997 need to be agreed between the CEM/CRE
and DPE/PE(B&C) to inform the detailed design, with the agreed criteria recorded on the Form B. A
mechanism for recording the criteria will be agreed between the CEM and DPE via correspondence.
NOTE 3: AM signature to FormB part 6, AM acceptance, is optional and only necessary when there
has been significant change from the AiP submission which affects the future asset, such as changes
to foundation types, introduction of new assets or significant changes to maintenance requirements.
NR/L2/RSE/02009 section 15 sets out the requirements for undertaking
Interdisciplinary Coordination, Interdisciplinary Checks and Interdisciplinary Reviews
prior to the technical acceptance of engineering Deliverables, including the FormB.
The technical assurance of the detailed design of works to Building and Civil
Engineering infrastructure shall be documented and accepted within
NR/L2/CIV/003/FormB, Certificate of Design and Check for permanent works. This
form shall be submitted by the CRE and confirm that the Design has been:
a) carried out in accordance with NR/L2/CIV/003/FormA;
b) checked in accordance with the agreed Design Check Category.
In addition, the CRE shall confirm the matters that have been reviewed in the Design
by completing the Design Checklist in NR/L2/CIV/003.
There is no need to complete NR/L2/CIV/003/FormB for a permanent works design
submission if the AM and/or PE (B&C) has accepted in writing the selection of
Design Check Category 0.
In such cases the simplified NR/L2/CIV/003/FormH shall be used; see clause 14.
Design Check Category 0 shall not be adopted for Designs that vary from the
requirements of Network Rail standards or Railway Group Standards.
list below;
NOTE: The following assurance standards are as listed in NR/L2/RSE/02009 clause 15.6:
a) NR/L2/SIG/30035;
b) NR/L2/TRK/2500;
c) NR/L2/ELP/27311;
d) NR/L2/TEL/30022;
e) NR/L2/ERG/24020;
f) System Integration deliverables for, System Safety, Interoperability, System
security, Performance, Reliability, Operational readiness and maintenance
readiness.
4) unless otherwise agreed with the DPE, in consultation with the PE
(B&C), works are not over the operational railway;
5) unless otherwise agreed with the DPE, in consultation with the PE
(B&C), works are not under the operational railway (as Track Support
Zone defined under NR/L2/CIV/177);
6) unless otherwise agreed with the DPE, in consultation with the PE
(B&C), works are not situated within the structure envelope (as defined
under NR/L2/TRK/2049);
7) there is no requirement for design integration with other projects or
programmes.
In such cases no part of Combined Design Submission Form NR/L2/CIV/003/FormG
shall be omitted.
13.1 General
The Permanent Works Designer shall confirm temporary works requirements as part
of the permanent works design at both Approval in Principle and as Detailed Design
and Check develops.
The Temporary Works Designer shall account for the temporary works requirements
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Page 36 of 58
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
In such cases the simplified FormH shall be used; see clause 14.
Design Check Category 0 shall not be adopted for Designs that vary from the
requirements of Network Rail standards or Railway Group Standards. Approval of
NR/L2/CIV/003/FormC consists of signed acceptance by the PE (B&C)
A single copy of NR/L2/CIV/003/FormC might be submitted where a Design is used
repetitively for a generic group of temporary works designs
The submission of a temporary works design that is split into parts shall be integrated
through:
NOTE 4: E.g. due to the Contractor’s delivery strategy.
a) the appointment of a lead Designer and lead Checker; and
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
In-accordance with the Asset Protection Engineering Management Plan produced in
compliance with NR/L2/CIV/094, the highest Design Check Category III shall be
applied when working on Outside-Party or Third-Party projects.
NOTE: This is due to the risk of construction alongside and/or on the railway, which is undertaken by
external contractors.
The DPE shall, in circumstances where the temporary works proposed are deemed
by the DPE as low risk, undertake an evaluation when determining if there should be
any reduction in the Design Check Category from category III. This evaluation shall
include the following assessment:
a) If the works are low risk and adequate controls can be put in place by the
contractor with adherence to appropriate Task Briefing documentation;
b) If the DPE has sufficient confidence in the Contractor’s management/supply ;
c) If the Contractor also works directly for NR and the design would otherwise be
controlled under a reduced category;
d) That the Design Check Category shall not be less than that stated in Appendix
A of this standard, upgraded as necessary in accordance with 13.1.
14 Use of the Certificate of Design and Check (FormH) for Design Check
Category 0 works
For Design Check Category 0 permanent works or temporary works a simplified
certificate of design and check form, NR/L2/CIV/003/FormH, shall be used, provided
that the following criteria are met:
NOTE 1: The NR/L2/CIV/003/FormH replaces “schematics” designs and allows corporate governance
of simple designs under the cover of one simple form.
NOTE 2: Also see clause 13.2 for situations where FormH for cat 0 temporary works is not required.
a) agreed with the DPE in advance,
b) the design is Design Check Category 0 only,
c) the design shall not affect other disciplines such that design deliverables are
required for Track, CCS, E&P and Telecoms as per the list below;
NOTE 3: The following assurance standards are as listed in NR/L2/RSE/02009 clause 15.6:
a. NR/L2/SIG/30035;
b. NR/L2/TRK/2500;
c. NR/L2/ELP/27311;
d. NR/L2/TEL/30022;
e. NR/L2/ERG/24020;
f. System Integration deliverables for, System Safety, Interoperability, System security,
Performance, Reliability, Operational readiness and maintenance readiness.
d) unless otherwise agreed with the DPE, in consultation with PE (B&C), works
are not over the operational railway;
e) unless otherwise agreed with the DPE, in consultation with PE (B&C), works
are not under the operational railway (as Track Support Zone defined under
NR/L2/CIV/177);
f) unless otherwise agreed with the DPE, in consultation with PE (B&C), DPE
and PE (B&C), works are not situated within the structure envelope (as
defined under NR/L2/TRK/2049);
g) There are no requirements for a NR/L2/CIV/003/FormD or
NR/L2/CIV/003/FormF;
h) there is no requirement for design integration with other projects or
programmes.
Page 39 of 58
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
NOTE 1: The Design Check Category is recorded in NR/L2/CIV/003/FormA for permanent works and
FormC for temporary works. Examples of Design Check Categories for different types of Works are
given in Appendix A.
The method of checking should be as shown in Table 5, except in the following cases
where a more onerous level of check category should be selected:
a) the Design is for a new generic Standard Designs and Details where the next
level of check shall be selected (e.g., Category I Design is checked as a
Category II design) including:
1) Standard Designs and Details for incorporating into NR/L3/CIV/151/F010
or equivalent index; or
2) Design of new ranges of overhead line or signalling structures; or
b) the Design is delivered by an organisation contracted by Network Rail to
deliver both Design and Construction and the Design organisation and
Construction organisations are not separate legal entities; or
c) the work is being carried out by an External Party and the DPE assesses that
the Designer’s competence to perform their duties in close proximity to a
railway environment under the agreed Engineering Management Plan
represents an increased risk to safety or operations compared to use of an
industry approved supplier working for Network Rail; or
d) Network Rail is carrying out work for an External Party and the Network Rail
Sponsor requires greater confidence that future liabilities would not arise due
to errors in the design; or
e) The permanent works and temporary works should be reviewed by the
designers for each. In the case of complex works with multiple interfaces
between the permanent works and temporary works, e.g. crane loadings on
existing structures or SPMT moves where moving can affect integrity of the
transported structure, confirmation should be given by the PE B&C and the
CRE B&C to enhancing the Design Check Category.
Except where permitted in Table 5, the Design Check shall be carried out by the
Checker without reference to the Design calculations.
Design Type of designs Method of checking
Check
Category
0 Designs for which calculations are not The Design may be checked in the
required and the Design can be same Design team but by staff
checked by inspection. other than the Designer(s).
Designs shall meet the requirements of The Design may be checked by
Network Rail standards and Railway inspection/review.
Group Standards. The Checker shall assess the
Designs for which, although simple validity of the Designer’s
calculations can be required, the assumptions.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
I Standard or simple Designs using The Design may be checked in the
simple methods of analysis and where same Design team but by staff
all aspects of Design are in accordance other than the Designer(s).
with relevant standards. The Checker may ref er to the
Assemblies of elements or components Design calculations and the
which have themselves been designed assumptions upon which the
and checked/accepted. calculations are based.
The Checker shall assess the
validity of the Designer’s
assumptions.
II Designs not in Categories 0, I or III. The Design may be checked in the
same organisation as that which
prepared the Design.
Checking shall be undertaken in a
group or team that has not been
concerned with the development of
the Design.
The Design Check shall be carried
out without reference to design
calculations.
III Complex or unusual Designs or Designs The Design shall be checked by an
which involve significant departures organisation independent of the
from current standards, novel methods Design organisation (that is, by an
of analysis or considerable exercise of organisation which is a separate
engineering judgement legal entity).
Extent of Cat III works shall be The Design Check methodology
determined and agreed prior to design and analysis shall be independently
submission. derived against a common set of
design criteria
proposed methodology for completing the Design Check prior to undertaking the
detained design.
The Design Check statement shall:
a) describe the method of analysis to be used;
NOTE 2: This includes the use of computer-based methods.
b) define the programme for the Design Check;
NOTE 3: This includes interfaces with the Designer.
c) state how compliance with the requirements of the Design Check shall be
achieved.
Where novel analytical or calculation methods have been adopted for the design, the
Checker (all categories) shall employ established alternative methods for completing
the Design Check.
Category III Checkers should use an independently derived methodology. Different
analysis software should be deployed where the method of analysis used is the same
as that for the design.
The PE (B&C) shall be advised where this is not feasible and agree how the validity
of the design shall be substantiated to an equivalent level of confidence.
The AFC design shall be endorsed by the CEM prior to issue, having closed out all
comments on the Detailed Design submission.
The AFC Design shall be issued to the PM, DPE and CM prior to execution of any
works which may affect Network Rail Managed Infrastructure.
The CEM shall provide documented evidence, in a format agreed with the DPE, to
confirm that the AFC Design accounts for, and has closed out, all comments on the
Detailed Design.
NOTE 2: Where works are phased the CEM and DPE should agree which AFC packages are
required and in which order.
No construction or fabrication activity shall commence before AFC design is in place
for the individual works, unless as stated in NR/L2/RSE/02009 clause 15.8.
Significant alterations to the Design shall require resubmission.
a) the changes shall be designed and checked; and
b) interdisciplinary coordination, checks and reviews shall be carried out, and
c) a revised version of appropriate NR/L2/CIV/003/Form shall be issued with the
revised Design to Network Rail for acceptance.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
NOTE 3: The designer should specify any special requirements for specialist engineering supervision
for verification purposes, e.g. Geotechnical engineering supervision to verify ground conditions meet
with designed parameters and DIR/GDR findings in cases of variable ground.
ITPs shall be produced by the contractor to describe the sequence, method and
acceptance criteria for product inspections and their associated records, based on
the designers specification.
The designer shall approve the contractors ITP to confirm that the designers
specification criteria have been achieved.
Confirmation of approval of ITP's shall be provided by the designer to the B&C PE /
DPE no later than 28 calendar days prior to the inspection activity commencing.
18.1 Preparation
Unless agreed with the Network Rail Project Manager, for multi-disciplinary projects
the planning activities set out in NR/L2/INI/CP0075 shall be followed.
NOTE: The development of an Entry into Service (EIS) strategy and EIS file and deferred items list
(all as defined in NR/L2/INI/CP0075) should also be checked by the project team for single-disciplinary
projects of a large or complex nature.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
18.2 Certificate of fitness to be taken into use
The CRE (Construction Phase) shall sign NR/L2/CIV/003/FormE before any part of
the permanent or temporary works for a project may be taken into use.
The CRE (Construction Phase) shall sign NR/L2/CIV/003/FormE before taking any
working platform into use, in accordance with NR/L2/CIV/0063.
NR/L2/CIV/003/FormE shall be shared with the person responsible for the provision
of access within 3 metres of the track to certify that the works are Fit to be Taken into
Use when:
a) the Work is carried out during periods when normal train operations are
suspended; or
b) other means of maintaining the safety of the operational railway are utilised.
NOTE: This applies whether the permanent works are completed or not.
Copies of the completed NR/L2/CIV/003/FormE shall be issued to the PE (B&C),
DPE and the Network Rail Project Manager not more than 3 working days after
completion of the form.
NR/L2/RSE/02009
(This document)
NR/L2/OHS/0047
NR/L2//P3M/201
NR/L2/INI/0300
NR/L2/CIV/003
Engineering assurance process
Peer reviews ✓
Interdisciplinary checks (IDCs) ✓
Interdisciplinary reviews (IDRs) ✓
Design Reviews ✓
Acceptance reviews ✓
Design Checks ✓
Technical Acceptance ✓ ✓
Phase gate reviews ✓
Phase gate reviews to iELCP process ✓
20 Records
The records specifically mandated by this standard shall be retained for the life of the
asset.
The designers and contractors for all works covered by this standard shall comply
with the requirements of NR/L2/OHS/0047 regarding the provision of CDM 2015
compliant Health and Safety files on all projects.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Records of the engineering assurance carried out as part of external party works
shall be managed in accordance with Asset Protection procedures with details of any
new or altered railway infrastructure obtained, stored and maintained on completion
of the works.
In all other cases, as-built drawings or records of the installed works shall be
produced for acceptance by the DPE. These shall be accompanied by the completed
and checked calculations to be incorporated into the H&S file. As-built drawings or
records shall include details of identified Hidden Critical Elements
NOTE 2: Records should be stored and maintained in accordance with Network Rail Information
Management Standards. Refer to NR/L2/INF/02018 and NR/L2/INF/02202.
Project specific requirements for records might be included in the contract, CR-T
and/or Engineering Management Plan.
21 Timeframes
Timeframes shall be as defined within the CR-T, Project Requirements and other
requirements issued as part of the project.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
NOTE 3: + FormG and Form H should only be used when the requirements in clauses 12.2, 13 or 14
are met in full.
A.3.1 Category 0
1) Emergency works that are determined without Design calculations;
2) Surface car parks (unless extensive);
3) Drainage works that do not require hydraulic design;
4) Earth-retaining structures with a retained height not exceeding 600 mm in
locations where their failure would not obstruct the passage of trains or affect
an External Party;
5) Fencing, palisade fencing and safe cess walkways unless elevated;
6) Painting;
7) Waterproofing of bridge decks;
8) Brickwork re-pointing;
9) The superstructure of modular platforms (for supporting lineside equipment)
that are to be installed according to the manufacturer’s recommendations
(foundations are categorised separately).
A.3.2 Category I
1) Bespoke designs of the superstructure of modular platforms (for supporting
lineside equipment) supported on spread footings on natural undisturbed
ground;
2) Platforms supported on spread footings on natural undisturbed ground;
3) Emergency works determined with Design calculations;
4) Structures with a span of 5.0m or less which can be built without requiring a
possession. This excludes bridges that carry road or rail traffic;
5) Signalling:
a. Superstructures: straight post, signal post, OLE mesh, bespoke elevated
structure (LOC platform, SPT walkway), speed sign post, ground position light
signal, level crossing elements, gallows structure for banners;
b. Foundations: foundations for the above superstructures, REB and URX;
c. Earth-retaining structures with a retained height not exceeding 1m that do
not meet the criteria set out for category 0.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
6) Telecoms:
a. Superstructures: brackets supporting telecom display units, gallows
structure for OFF Indicator or for NTI;
b. Foundations: spread foundations to the above superstructures, DOO
camera column or DOO monitor stacked housing.
7) Electrification:
a. Spread concrete foundations (bases) supporting DNO, auxiliary
transformer, mobile generator, PSP, points heating cubicle, points heating
transformer, points heating terminal box, functional supply point,
substructure of lighting columns < 25m high
8) Lighting columns <25m high;
9) Bridge superstructure whose Design is based closely on one previously
certificated with Design Check category II or III (that is, one with no more than
minor modifications);
10) Single span simply supported reinforced concrete slab or deck-type bridge
superstructures with a span not exceeding 15m and a skew not exceeding 20º
where simple manual methods of distribution are used;
10) Footbridges of conventional construction with a span not exceeding 20m ;
11) Portal equipment support structures of conventional construction with a span
not exceeding 20m;
12) Substructure and superstructure of lighting columns ≥ 25m high;
13) Culverts;
14) Reinforced concrete boxes with spans not exceeding 6m;
15) Gravity earth-retaining walls with a retained height not exceeding 5m;
16) Soil stabilisation works involving toe weighting, sheet piling or bored piles;
17) Station platforms on level or near-level ground or in cuttings;
18) Single-storey buildings and platform canopies of conventional construction;
19) Bespoke buildings of two storeys or less with one plan dimension of 6.0m or
less and which are supported on spread footings;
20) Drainage works that require hydraulic design;
21) Undertrack crossings.
NOTE 1: Refer to NR/L3/CIV/044 for further guidance on DCC for UTX.
NOTE 2: Category I works normally require AM endorsement at Form A. DPE to gain written
confirmation from AM if AM does not wish to endorse the Form A, with the Form A annotated
accordingly.
A.3.3 Category II
1) Works not in Design Check Category 0, I or III.
2) Existing, modified, new or proposed Critical National Infrastructure (CNI)
assets, NRSP security Category A & B stations or works that the Network Rail
Chief Security Officer and Nominated Security Contact, their deputies or
competent security role holders in region and route security teams consider to
be in Design Check Category II
NOTE: Security requirements for Network Rail CNI assets are defined in the Network Rail
Security Assurance Framework - if you are unsure if an asset is or will become CNI, consult
with the Region security team or Group Security in the Technical Authority.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
6) New tunnels;
7) Substantial works in existing tunnels or tunnel shafts (other than conventional
lining works - such as the replacement of a brick ring or the spraying of
concrete);
8) New and altered structures with non-standard loading conditions;
9) Where the Design involves assessment of the aerodynamic effects of trains
travelling at speeds greater than 125mph;
10)Works which include structural features or characteristics that have not
previously been used and which would be subject to railway live loading.
11)Use of glass as a structural material.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
12)Stations, buildings or building façade solutions which do not have a clear and
robust evidence of previous use;
13)Other works that the Network Technical Head, AM or Project Engineer (B&C)
consider to be in Design Check Category III.
Lead Skew span
Sq
ua
Skew° re
sp
a n
A.4.1 Overview
These examples are aligned with Temporary Works Forum guidance document
TWf20 4:02 ‘Clients’ guide to temporary works’.
A.4.2 Category 0
1) Shallow trenches, pits and excavated batters, not exceeding 1.2m depth with
no significant overburden or groundwater. Where subject to railway or road
vehicular live loading these should not exceed about 600mm in the direction of
traffic;
2) Low-rise formwork at ground/excavation level, max 2.4m double sided, 0.9m
single sided;
3) Non-design scaffolds to TG20:21;
4) Site hoarding and fencing less than 2m high unless on a platform;
5) Other low risk items generally less than 1.2m high or 1.2m deep;
A.4.3 Category I
1) Use of standard components to catalogue design;
2) Pits and trenches to CIRIA 97 Trenching Practice;
3) Excavated slopes not exceeding 30deg incline or 2m height in free draining
soil;
4) Designed scaffolds and loading platforms to TG20:13 tables;
5) Double sided formwork with access platforms at ground/excavation level;
6) Single sided formwork to 2.4m;
7) Routine formworks/falseworks at not more than 6m height, slabs not
exceeding 500mm thick, beams not exceeding 1m width, 1.5m depth;
8) Mobile crane outrigger foundations in good ground. Crane rated capacity to
50T;
9) Piling gates, simple and medium designs;
10)Permanent falsework (such as metal decking);
11)Site hoarding and fencing greater than 2m high;
12)Concrete pumps outriggers with good ground conditions and access;
13)Proprietary previously-designed road vehicle bridge or footbridge
superstructure systems used at the rated loading and used in accordance with
the manufacturer’s recommendations;
14)Single-level propped soil-retaining structures;
15)Cantilever soil-retaining structures with a retained height not exceeding 3m;
16)Reinforced soil structures with a retained height not exceeding 3m;
17)Temporary level crossings;
18)Temporary pedestrian edge protection for public use;
19)Tube-and-fitting scaffolding supported on the ground, not more than 6m high
and not spanning more than 3m.
20)Hoardings on a Platform below 2m high.
A.4.4 Category II
1) Departures from catalogue of design for standard components;
2) Formwork and falsework for heavy suspended slabs and beams;
3) Formwork and falsework that is at a height greater than 6m;
--`,``,,````````,,,,```,``-`-`
competent security role holders in region and route security teams consider to
be in Design Check Category II.
Note: Security requirements for Network Rail CNI assets are defined in the Network
Rail Security Assurance Framework - if you are unsure if an asset is or will become
CNI, consult with the Region security team or Group Security in the Technical
Authority.
34)SPMT working platform designs
NOTE: SPMT working platform designs should be risk assessed between the DPE
and CRE/TWC depending on several factors including utilisation factors, ground
investigation findings and complexity. For instance, if utilisation factors are very high
and ground conditions very poor or operations are complex there may be added
value in seeking a fully independent Category III check to de-risk possible programme
or cost implications of failure.
• Where poor ground or other features such as potentially unstable cuttings/embankments exist,
there is a risk that additional measures need to control the risk of unintended events from
occurring;
• Assessing of the quality of ground conditions would need to take sufficient account of the
effects of changes in weather.
A.6.1 Category 0
Like-for-like building renewals whose design/arrangements are based on National
Building Regulations (for example) (so that they do not require a detailed Design)
and which do not affect the kinetic envelope or clearances to trains.
A.6.2 Category I
Where the Design is undertaken to The Chartered Institute of Building Services
Engineers Guides or a similar national building specification approved by the
Professional Head.
A.6.3 Category II
Works not in Design Check Category 0, I or III.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
• safety; d) earthworks;
e) drainage;
• security;
f) building services;
• constructability;
g) civil and building type elements or components of other
• functionality; assets.
• appearance and other architectural aspects; NOTE 2: The types of assets listed might include architectural
• planning conditions & requirements; aspects.
Application
This business process applies to Network Rail and non -Network
Rail personnel involved in the remitting, design, checking, design
assurance, construction assurance and taking into use of
Buildings and Civils infrastructure.
Exclusions
This business process does not apply to:
a) consents or approvals from bodies outside Network Rail
including:
1) regulatory and statutory authorities;
2) planning, listed building and conservation
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
authorities;
3) environmental regulators;
4) land and property owners or leaseholders;
5) statutory undertakers and other public services and
utilities owners.
b) obtaining approvals for the New Roads and Street
Works Act;
c) obtaining approval from other Network Rail engineering
disciplines for the equipment carried by Equipment
Support Structures or for the performance of that
equipment;
NOTE: For Example, signal sighting and reduced clearances.
d) assessments of structures.
e) obtaining the Acceptance of the engineering deliverable
of the project to achieve Approved for Construction
status as covered within NR/L2/RSE/02009.
Overview of changes
• Permanent works submissions reduced from three forms (Forms F001/F002/F003 to two forms (Forms A/B);
• Temporary works submissions reduced from two forms (Forms F002/3 to one form (FormC);
• Design Check Category (DCC) I Permanent works submissions in simple circumstances further reduced to one form
(FormG);
• Design Check Category 0 Permanent works and temporary works submissions now covered by one very simple form
(FormH) instead of “schematics”;
• Renamed and improved other extant Forms.
Copyright Network Rail
Provided by S&P Global under license with Network Rail Licensee=Public Transport Authority WA/5992775001, User=Narayanaswamy, Venkatesa
No reproduction or networking permitted without license from S&P Global Not for Resale, 07/28/2022 18:51:38 MDT
V6.0
OFFICIAL
• Simplified Design Check Category from I(a) and I(b) to I only;
• Updates to other DCC and associated text;
• Updates to references, updated standards and guidance;
• Changes from Security Team and Environment and Sustainability teams made to add value, e.g., reduction of DCC from
III to II for security design ;
• Updates to allow flexibility with different Requirements documents and different project management methodologies such
as PACE.
• Updates to align with NR/L2/RSE/02009 Engineering Management for Projects
• Several changes made to enhance design and assurance robustness and efficiency, regarding permanent works,
temporary works, specifications and inspection & test plans;
• Reference to new standard NR/L3/CIV/0063, Piling, Drilling, Crane, MEWP and SMPT operations adj acent to the Railway;
• Reference to new guidance NR/GN/CIV/003, Guidance on Engineering and Architectural Assurance of Building and Civil
Engineering Works;
• Reference to updated standard NR/L2/ENV/015, Environment and Social Minimum Requirements for Projects- Design
and Construction.
Accounting for extensive feedback on the previous version, the standard has been comprehensively rewritten to improve efficiency,
simplify process, add flexibility and reduce the number of forms used on a particular project.
It therefore aligns with the principles of PACE and SPEED, without diluting the need to both robustly and safely design, execute and
assure works of building and civil engineering on the Railway.
It also closes out formal Standards Challenges on the previous issue, together with resolving temporary variations pending
standard change.
It also aligns with forms nomenclature in other discipline engineering assurance standards
Affected documents:
Reference Impact
NR/L2/CIV/003 ISSUE 6 Superseded
NR/L2/CIV/003/F001 ISSUE 3 Withdrawn
NR/L2/CIV/003/F001-002 ISSUE 1 Withdrawn
NR/L2/CIV/003/F002 ISSUE 4 Withdrawn
NR/L2/CIV/003/F003 ISSUE 4 Withdrawn
NR/L2/CIV/003/F004 ISSUE 2 Withdrawn
NR/L2/CIV/003/F005 ISSUE 3 Withdrawn
NR/L2/CIV/003/F006 ISSUE 2 Withdrawn
NR/L2/CIV/003/F1990 ISSUE 3 Superseded
NR/L2/CIV/003/F1991 ISSUE 2 Superseded
NR/L2/CIV/003/F1992 ISSUE 2 Superseded
NR/L2/CIV/003/F1993 ISSUE 2 Superseded
NR/L2/CIV/003/F1994 ISSUE 2 Superseded
NR/L2/CIV/003/F1997 ISSUE 2 Superseded
NR/L2/CIV/003/FORMA ISSUE 1 New
NR/L2/CIV/003/FORMB ISSUE 1 New
NR/L2/CIV/003/FORMC ISSUE 1 New
NR/L2/CIV/003/FORMD ISSUE 1 New
NR/L2/CIV/003/FORME ISSUE 1 New
NR/L2/CIV/003/FORMF ISSUE 1 New
NR/L2/CIV/003/FORMG ISSUE 1 New
NR/L2/CIV/003/FORMH ISSUE 1 New
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
Briefing requirements:
Copyright Network Rail
Will Briefing Management System be used to deliver the briefing
Provided by S&P Global under license with Network Rail
Not forto posts listed below? No
Licensee=Public Transport Authority WA/5992775001, User=Narayanaswamy, Venkatesa
No reproduction or networking permitted without license from S&P Global Resale, 07/28/2022 18:51:38 MDT
V6.0
OFFICIAL
Technical briefings are given to those who have specific responsibilities within this standard/control document.
Awareness briefings are given to those who might be affected by the content but have no specific responsibilities within the standard/control
document.
Details of the briefing arrangements are included in the associated briefing programme.
All posts identified for briefing must be as described in OrgPlus.
Roles are directly briefed and do not cascade briefings.
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
A Director Engineering & Asset Management, Southern Southern Region N
A Director Engineering & Asset Management, Wales & Western Wales & Western Region N
A Director Engineering & Asset Management, NW&C North West & Central N
Region
A Director Engineering & Asset Management, Scotland Scotland N
Briefing Role
(A-Awareness/ Function
T-Technical)
T Project Engineering (B&C) All roles All
--`,``,,````````,,,,```,``-`-`,,`,,`,`,,`---
A Asset Management (B&C) All
A Commercial All
A Sponsorship All
NOTE: Contractors are responsible for arranging and undertaking their own Technical and Awareness Briefings in accordance with thei r own processes
and procedures.