AT NORTH CAMPUS, ASHOKA UNIVERSITY, RAI, SONIPAT, HARYANA
S.No DESCRIPTION UOM QUANTITY
Providing, driving with hydraulic piling rigs with
power units and installing driven cast-in-situ
reinforced cement concrete piles of grade M-25
of specified diameter and length below the pile
cap, to carry safe working load not less than
1 specified, excluding the cost of steel
reinforcement but including the cost of shoe and
the length of pile to be embedded in the pile cap
etc. all complete. (Length of pile for payment shall
be measured from top of shoe to the bottom of
pile cap)
a 500 mm dia piles metre 1440.00
b 550 mm dia piles metre R.O
c 750 mm dia piles metre R.O
d 1000 mm dia piles metre R.O
Providing, driving with DMC Tripod Rig and
installing cast- In-situ reinforced cement concrete
piles of grade M-25 of specified diameter and
length below the pile cap, to carry safe working
2 load not less than specified, excluding the cost of
steel reinforcement but including the cost of shoe
and the length of pile to be embedded in the pile
cap etc. all complete. (Length of pile for payment
shall be measured from top of shoe to the bottom
of pile cap)
a 500 mm dia piles metre 1440.00
b 550 mm dia piles metre R.O
c 750 mm dia piles metre R.O
d 1000 mm dia piles metre R.O
Carrying out routine load test on selected piles by
Engineer-in-charge to one and half times the
working load on the above piles in accordance
3 with IS 2911 (Part-III) 1980 or latest including all No.'s 1
necessary arrangements such as platform
kentledge, jacks, measuring devises, etc. all
complete as per specifications .
Dismantling / Breaking top portion of concrete
piles up to pile cut off level and removing
rubbish/spoil up to a lead of 500m with all lifts,
4 cleaning top portion of pile cleaning Cum 14
reinforcement exposed due to breaking of pile
top, bending pile reinforcement into pile cap as
per drawing and instruction of engineer.
5 Providing and making spot welding of pile Nos. 300
reinforcement at top & bottom by 10mm dia ring
Steel reinforcement for R.C.C. work including
6 straightening, cutting, bending, placing in position
and binding all complete upto plinth level.
Thermo-Mechanically Treated bars of grade Fe- kg 50000
500D or more.
# Classification - Public
NOTE
1 The bentonite slurry or equivalent material shall be used for the stabalising of the soil during the piling operation
2 PVC tanks to be used for storing the bentonite slurry for boring of piles. No temporary tanks will be permitted to be made in the groun
3 Disposal of used bentonite shall be in scope of the piling agency outside the project premises.
4 Reinforcement steel shall be provided for fabrication of pile cages. Fabrication and placing in position of cages shall be in scope of pilin
5 Concrete shall be provided to the piling agency. Pouring of concrete shall be in scope of piling agency.
6 The cost of mobalising & demobalising of equipment is deemed to be included in the rates quoted
GST will be paid extra
7 Payment Terms
(A) 20% advance on mobilization of equipment hydraulic/TMR on site
(B) 50% on completion of pile drilling, lowering of cage & laying RCC
( C) 10% on completion of routine load test pile
(D) 10% on cut of pile head as per BOQ specifications
(E ) 10% completion of site work & submission of test report
8 Electricity/water will be provided on chargeble basis
9 Muck removal & disposal within distance of 50m as directed by project manager, in scope of piling agency.
10 TMR system is acceptable for piling work.
11
Spot welding of verticle reinforcement with the master ring in scope ofpiling agency.
12
Soil report attached.
13 Item
chargeDescription
to one andashalf
pertimes
BOQ the working load on the above piles Query raised by bidder/s
in accordance with IS 2911 (Part-III) 1980 or latest including all a) Design load of Pile
necessary arrangements such as platform kentledge, jacks,
b) Type of test on Routine pile
(i) Vertical
(ii) Pull out
(iii) Lateral
And the method by which the
test/s are to be conducted at the
location.
# Classification - Public
Column5 Column6
Contact Us- 9814043774
Email us- [email protected]
RATE AMOUNT
2100 3,024,000
2350
3450
4150
1800 2,592,000
2000
2450
3050
174000.00 174,000
5100.00 71,400
500 150,000
7.20 360,000
# Classification - Public
6,371,400
e piling operation
l be permitted to be made in the ground.
sition of cages shall be in scope of piling agency.
gency.
ing agency.
Response
a) Safe load is 58Tons so
testing shall be done for
b) VerticalTons.
58X1.5=87 type of test on
routine pile shall be done.
Testing shall be done by Kentledge
method.