0% found this document useful (0 votes)
73 views2 pages

MPM 332 01 33

This document provides instructions for preventive maintenance of a Koomey pump. It lists safety notes for lockout/tagout and permits. The job plan instruction includes inspecting the motor, bearings, temperatures, fan, boxes, grounding, taking amp readings on phases, and testing operation. Checks and measurements are also specified, including acceptable lower and upper limits for megger testing and amp readings on each phase.

Uploaded by

Mousa Petrol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
73 views2 pages

MPM 332 01 33

This document provides instructions for preventive maintenance of a Koomey pump. It lists safety notes for lockout/tagout and permits. The job plan instruction includes inspecting the motor, bearings, temperatures, fan, boxes, grounding, taking amp readings on phases, and testing operation. Checks and measurements are also specified, including acceptable lower and upper limits for megger testing and amp readings on each phase.

Uploaded by

Mousa Petrol
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

GDI PREVENTIVE MAINTENANCE INSTRUCTION Date: 15/04/10 Rev: 0

Maximo Ref. MPM-332-01-33 SFI Code 332-01


Equip.
Koomey Pump
Description
Manufacturer Shanghai Shenkai Equip. Location Various

Model FKQ1280-6

MAINTENANCE SPECIFICATIONS

Frequency 3 Monthly Estimated Duration 1 Hours

Criticality 5 Area Authority Chief Electrician

Class Structure 2509 Failure Code DSBP

Craft Chief Electrician No. of Craft 1

SAFETY NOTES

• Complete required Permit-To-Work (PTW).


• Lockout / Tag-out Permit required
• Review / Complete Job-Safety-Analysis (JSA).
• Inform Area authority if work is carried out on critical equipment for ongoing
operation.
• Do not wear jewellery when working around rotating machinery.
• Wear all proper safety equipment.

JOB PLAN INSTRUCTION

1. Inspect the exterior of the AC motor, including the cables for damage.
2. Check for excessive bearing noise or vibration.
3. Check for excessive motor or bearing temperatures.
4. Check cooling fan and fan cover.
5. Verify motor is clean with no excessive paint.
6. Check and verify that junction and starter boxes are properly sealed.
7. Check that the AC motor is correctly earthed.
8. Megger pump motor and record.
9. Take Amp Reading on motor phase A and record.
10. Take Amp Reading on motor phase B and record.

11. Take Amp Reading on motor phase C and record.


Check and verify the operation of the indication lights and starter buttons. Test the operation of
12.
emergency shutdown button.
13. Visually inspect starter for signs of overheating.

1
GDI PREVENTIVE MAINTENANCE INSTRUCTION Date: 15/04/10 Rev: 0

Maximo Ref. MPM-332-01-33 SFI Code 332-01


Equip.
Koomey Pump
Description
Manufacturer Shanghai Shenkai Equip. Location Various

Model FKQ1280-6

CHECKS AND MEASUREMENTS

MAXIMO ALLOWABLE UPPER/LOWER LIMITS


Recorded Lower
Description Unit Lower Value Upper Value Upper Value
Readings Value
Alarm Action Alarm
Action

Megger pump motor MΩ 8 10 99999 9999

Motor phase A Amp 31.2 33.6 52.8 48

Motor phase B Amp 31.2 33.6 52.8 48

Motor phase C Amp 31.2 33.6 52.8 48