Pert and CPM PDF
Pert and CPM PDF
INTRODUCTION
to
discussed various activities pertaining
n the previous chapters, we have of
from scratch; that is, setting up
the operations in the hotel business right
s u c c e s s . During
the c o u r s e of
it an operational
d
new property
to making facility
terms such as project planning,
o u r discussions, we often came a c r o s s focus
So far, the
activities, etc. being used in various contexts.
designing, and every aspect
was on the various activities o r tasks
that went into each
for those
of planning a hotel facility as also the kind
of resources required
within
these tasks is their accomplishment
acivities. An important aspect of o r finances
at hand. This is
the desired time frame and within the budget
and scrupulous
because apart from good planning, what
is required is careful
the success of the business activity
implementation of those plans to ensure
undertaken. various
lhe process of planning and executing a project by synchronizing
within the desired timelines
constituent activities to achieve its accomplishment
have defined
and available resources is called project management. Experts
the UK Association of
management in various ways. According to
project monitoring, and
'it is a process of planning, organizing,
roject Management, achieve
a project and the
motivation involved to
controlling of all aspects of
cost and performance
the project objectives safely and within the agreed time,
the hospitality and service industry, you
criteria. As a future manager of such as planning a n e w
hotell
are likely to come across scores of projects,
even a research
an old property, or
restaurant/bar, or may be renovating
It therefore, necessary to not only
project, during the course of your career. is,
have an idea of the contours of planning but
also a good grasp of the tools or
instruments that aid in efficient project management.
activities involved
Planninga new project requires of various
identification
in the project and the sequence in which these activities have to be performed.
within the scheduled time, thus
A well planned project leads to completion
cost. In this chapter, we shall focus
on
avoiding unnecessary delays and extra and models
of project management, particularly on
the tools
various aspects
that are widely used to ensure the completion of projects within the specified
time and within the limitation of all resources.
is a
group of tasks aimed towards the achievement of an
objective withinin
stipulated time and cost. Thus, the first step in project management Woull
be determination of the constituent activities and their interrelationshine
estimation of the resources required, and a realistic projection of the tim
ips,
me
needed to accomplish these activities. This detailed analysis of the project has
to be followed up with execution of the activities under complete monitorine
and control to meet the time lines and avoid cost escalation of the projects,
Network Analysis
An mportant aspect of project management is cost control and time manage.
ment. The project managers would always aim to accomplish activities in the
shortest possible time without compromising on the quality of work and the
costs involved. A technique helping them achieve this is network analysis,
It is a technique for sequencing problems interested in minimizing the total
time required to complete the project, as well as minimizing the overall project
costs. It is particularly suitable for projects which are not routine or repetitive,
and which are conducted only once or a few times. For example, construction
of building, dams, research and development, marketing of new products,
building a ship, construction of factories, missile production, etc.
Modern management uses two forms of network analysis or techniques in
most scheduling projects as sequencing models:
involved
PERT activity cannot be specified accurately because of uncertainties
the activity times
while carrying out the activity. PERT network is used when
are probabilistic; hence three time
estimations are considered: optimistic time,
system-oriented planning
and control de
2. PERT/CPM are
control of time, which are
are in evices.
addition
emphasize upon the
ad
They
to the usual control devices.
3. PERT/Cost is very useful in project management. It is
an
instrument of cost control.
Basic Steps
The basic steps for drawing a network diagram are the following:
A
6 A
6
Right
Wrong
Figure 7.1
Writing the Network
(c) While writing the network, ensure that activities do not cross ea
other. Also, arcs or loops as in Figure 7.3 should not
join activities.
1
Wrong
Figure 7.3 Crossing of Activities Not Allowed
el Facility Planning
(d) While writing a network, looping should be avoided. This is to say that
the network arrows should move in one direction, that is start from the
Right
2
Wrong
When two activities start at the same event and end at the same
(e)
event, they should be shown by dummy activity as in
means of
C
3 C
Dummy
D
Right
Wrong
Figure 7.5 Depiction of Dummy Activity
( When the event is written at the tail end of an arrow, it is known as tail
event. If event is written on the head side of the arrow, it is known as
head event. A tail event may have any number of arrows (activities
emerging from it. This is to say that an event may be a tail event to
any number of activities. Similarly, a head event may be a head event
for any number of activities. This means that several activities may
conclude at one event. This is shown in Figure 7.6.
Project Management 227
F C
G
D,E
H
3
F,G
I
1
H,I
D1
2
A2 A2
B3 B3
C4 CA
Figure 7.2(a) Figure 7.2(b)
We show these along with the names of the three activities in the networ
diagram. Activity D needs A as its
preceding activity, which means that D ca
be started only when A Make a small circle at the end of the arro
gets over.
for activity A to
represent event 2, which marks the completion of activity A
Then draw an arrow from node 2 to
Table 7.2 shows that the represent activity D Figure 7.2(b)].
B gets completed in event 3.
predecessor for activities E and F is B. Activit
Therefore, draw two arrows from node 3 t-
represent activities E and F |Figure 7.2(c)].
Project Management 229
D1
D1
A2
A2 E2
E2
1 B3
1 B3
3
C4 FS G7
Figure 7.2(c)
Figure 7.2(d)
Activity G can be started at event 4
ends at node 4
as its required predecessor is C, which
Activity H |Figure7.2(d).
Join arrows D and E to end
requires both D and E to be over before it starts. Therefore,
at a common node 5. From this new event 5, draw
an arrow to
both F and
represent activity H
[Figure 7.2(e)]. Similarly, activity I requires
G
to end before
it starts.
node 6. From this newTherefore, join arrows and G to end
at a common F
event 6, draw an arrow to
activity I |Figure 7.2(0.J. represent
ActivityJ requires both H and I to be over before its start.
arrows H and I to end at a common node 7. From this
Therefore, join
an arrow to new event 7, draw
represent activities H and I. From event 7, draw an arrow to
represent activityJ. Activity J ends at node 8, which becomes the last
the project |Figure7.2(g)). node of
D1
2 5 D1
5
H2 H2
A2
E2 A2
E2
B3 B3
F5
G7 13
G7
4 6