Doc. No.
: TM-ROA-01
Logo Risk and Opportunity Assessment Rev. No.: 00
(Process : Manufacturing) Date : 01/06/17
Team : M/s Rajesh Kumar………………….. Next due Date for review : 01/06/18
Risk Index Risk Mitigation / Resp. & Target Action Results
S. ACTIVITY/ Risk
EVENT RISK ( R) OPPORTUNITY EXISTING COTROL S O = Recommended Action Completion
No. OPERATION Priority Risk Index
SxO (s) date Action Taken S O
SxO
Related to QMS Activity
If BOM is not available, material planning would
All models approved BOM are
1 BOM not be accurate Can create problem in 2 2 4 #2
available in Empro
Organization performance
If sales plan is not available, results in shortage
1 month firm plan & 2 month forecast
2 Sales Plan of material Can create problem in QMS 3 1 3 #2
from Sales every month
performance
Planning would be accurate & time
3 MRP System Manual Planning
would be reduced
Material Planning
Non - OEM BOM frequent Resulting in shortage of material Can create Regular meetings with Sales &
4 3 3 9 #2
changes problem in QMS performance Purchase
If planning is changed, results in non- availability
Regular meetings with Sales &
5 Frequent Changes in plan of material & delay in production Can create 2 3 6 #2
Purchase
problem in Organization performance
Mismatch in physical & If mismatched, dispatch schedule will be delayed A class monthly inventory & quaterly
6 3 3 9 #2
system stock Can create problem in QMS performance invontory for all parts
if Sales forecast is changed, palnning would not
Regular meetings with Sales &
7 Sales forecast / plan be correct Can create problem in Organization 2 3 6 #2
Purchase
performance
Changes in customer Sudden change in volume by customer can
8 2 month inventory stock maintained 3 3 9 #2
demand create problem in QMS performance
Timely achievement of plan would be delayed
9 Availability of manpower Multiskilled manpower available 2 2 4 #2
Can create problem in Organization performance
Production Planning
Timely achievement of plan would be delayed
10 Availability of material Daily shortage meeting with Purchase 3 3 9 #2
Can create problem in QMS performance
Incomplete information would delay in planning
11 Information from Sales FO format available 3 2 6 #2
Can create problem in QMS performance
Delay in quality clearance would lead to stock
Quality clearance in
12 update in Empro will result in Loss or degradation Daily Pending GRIN reports 3 3 9 #2
empro
of secondary function
Production plan not achieced due non availability
13 Material Shortage of material Can create problem in QMS Daily shortage meeting with Purchase 3 3 9 #2
performance
Non-availability of manpower delay in delivery Multi skilled manpower
14 Manpower shortage 3 3 9 #2
Can create problem in QMS performance Provision of over time
Contigency plan for tools
Breakdown of tools & machines, delay in delivery
AMC contract
15 Breakdown will result in Loss or degradation of secondary 3 3 9 #2
Critical spares part list
function
Autonomous Maintenance Checklist
if skilled manpower is not available, chances of
16 Skilled manpower OJT's 4 2 8 #2
creating NG product is more, Key driver to IPC
Can provide tool to all station to
17 Tool availabiity Budget Planning
improve productivity
change in plan will take more time to produce Multi skilled manpower
18 Change in plan 3 2 6 #2
number Can create problem in QMS performance Provision of over time
If material not issue from store on prior day ,
Material not issues from Regular follow up of PPC person with
19 production will stop Can create problem in QMS 3 2 6 #2
store on time Store
performance
Production Planning
Sub Assy material if sub assembly is not ready, delay in production
20 Production Planning Daily advance planning meeting 2 2 4 #2
readiness can create problem in Organization performance
if BOM is not as per requirement, wrong material
22 BOM mismatching will issue from store & leads to delay in BOM sign-off b/w Sales & Customer 4 2 8 #2
production, Key driver to IPC
if part number change in BOM frequently lead to
23 Frequent part no change ECR/ECN 3 2 6 #2
delay Can create problem in QMS performance
more time consumed to repir & production plan
24 Rework/ Repair Incoming Inspection 2 2 4 #2
will suffer will result in Annoyance
If space is not available change over time
Space for keeping Semi
29 incraeses Can create problem in Organization Space defined for semi FG product 2 2 4 #2
FG products
performance
If packaging planning not done, FG material will
30 Aligment with packaging stock on assy line Can create problem in QMS Daily morning meeting 3 2 6 #2
performance
Every 6 month maintenance plan to be
To be included in
Assembly trolley introduced which smoothens the Mr. Ramesh
31 Annual Preventive Maintenance Plan preventive maintenance
movement mechanism which helps in increase of Immediate
plan
productivity
If preventive manitenance is not done, chances of
36 Preventive Maintenance Preventive Maintenance Plan 2 2 4 2
NG product will result in Annoyance
If validation is not done in NABL approved lab,
37 NABL Approved Lab then chances of wrong results will result in 3 approved NABL labs available 2 2 4 2
Annoyance
Process validation
If calibrated instruments are not available,
39 Calibrated Instruments chances of wrong results will result in Loss or Calibration Plan 3 2 6 2
degradation of secondary function
If history card is not available, loss in traceability
42 History Card Production Recording register 3 3 9 2
Can create problem in QMS performance
If parts identification is not done, results in higher
43 Parts Identification warranty Can create problem in QMS Warranty format 3 3 9 2
performance
If persons are absent then objective would not be
47 Absenteesm fulfilled Can create problem in Organization Prior information 5 1 5 2
performance
On Job. Training
Poor understanding Can create problem in
48 Work Instruction Prior information 2 2 4 2
Organization performance
results in making of NG product will result in
51 Set up Approval Checksheets 3 3 9 2
Loss or degradation of secondary function
If instruments is not available, difficult to check
Availability of
53 parametrs Can create problem in QMS Master list of instruments 3 3 9 2
Instruements
performance
if calibrated instruments are not available, results
54 Inprocess Calibrated Instruments in wrong results will result in loss or degradation Master list of instruments 3 2 6 2
Inspection of secondary function
Rejection Tag
If control os not available, chances of mixing up
Rejection Bin
55 Control of NG parts with OK parts will result in Loss or degradation of 5 2 10 2
Rejection storage Area
secondary function
If identification is not there, status of parts would
56 Identification be missing will result in loss or degradation of Rejection tag 3 2 6 2
secondary function
If PDI is not done, chances of NG product to
57 PDI customer will result in Loss or degradation of PDI Checksheet 3 2 6 2
secondary function
Final Inspection
Final Inspection
Product status will not be known / Chances of
Unit identification sticker with brand
59 Identification mixing up will result in Loss or degradation of 3 2 6 2
name pasted inside the unit
secondary function
if packing material is not available, delay in
Availability of packing
61 dispatch Can create problem in QMS Bulk stock 3 2 6 2
material
performance
Ispace is not available then time consumption
62 Space for packing would be more & also chances of mixing up can Area defined for packaging 2 2 4 2
create problem in Organization performance
Packing list is not there, then chances of
63 Packing List shortage of material Can create problem in Approved packing list 2 2 4 2
Dispatch Organization performance
Prior dispatch packing
Clear understanding of packing Mr. Shubham
64 Customer Approval Customer approved packing standard standard to be made &
standards Immediate
approved by customer
Status of packed part would not be known Can
65 Identification Unit serial no manually mention 3 2 6 2
create problem in QMS performance
Incorrect Packing will result in Loss or
66 Method of packing Packing Standard available & WI 3 2 6 2
degradation of secondary function
Delay in shipment Can create problem in QMS
67 Mode of transport Daily morning meeting with logistics 3 2 6 2
performance
Delay in dispatch if not verified Can create
68 Transport verification Security Checklist 3 2 6 2
problem in QMS performance
Dispatch
Short supply results in extra freight cost Can Regular shortage meeting with
69 Short Supply 3 3 9 2
create problem in QMS performance purchase
Invoice / Packing List / Delay in shipment Can create problem in QMS
70 Daily morning meeting with logistics 3 2 6 2
PDI performance
Objective would not be fulfilled Can create
74 Kaizen & Continual Employee Engagement Monthly Meeting 3 2 6 2
problem in QMS performance
Improvement
process (CIP) KAIZEN / CIP would not get implemented can
77 Management Support Available 3 2 6 2
crate problem in QMS performance
Average
Risk Index
Severity (S) Rank Occurrence (O) Rank
=SXO
Risk----Effect of uncertainty
Almost certain (Very Note 1: An effect is a deviation from the
Key driver for Customer & QMS performance 5 5 25 expected — positive or negative.
high)
Note 2: Uncertainty is the state, even
Key driver to Interested Parties 4 Likely (High) 4 16 partial, of efficiency of information related
to, understanding or knowledge of, an
Can create problem in Organization event, its consequence, or likelihood.
3 Possible (Moderate) 3 9
performance
Can create problem in Functional /
2 Unlikely (Low) 2 4 Risks and opportunities ----
Departmental / Process performance
Potential adverse effects (threats) and
Negligible effect 1 Rare (Very Low) 1 1 potential beneficial effects (opportunities)
Action Criteria :
i) Risk Priority # 1: Either Severity (S) = 5 or Risk Index SXO > 16, Risk Priority #2: if Risk Index SXO ≤ 16;
ii) Action shall be taken on those Risks which have been identififed as Risk Priority #1
F:TM:06, Rev. No. 00, Eff. Date : 01/07/17