Unit of Standard Productivity
Activity
Measure Rate
Preliminaries
Jobsite Management
Temporary Facilities
Temporary Utilities
Weather and Environmental Control
Quality Control
Jobsite Safety
Tools and Equipment
Mobile Crane Operation hr 12.17 MH/hr
Tower Crane Jack-Up hr 12.191 MH/hr
Tower Crane Operation hr 12.191 MH/hr
Boom Truck Operation hr 11.665 MH/hr
CONCRETE WORKS
Concrete Forming and Accessories
Fabriation/ Installation/ Hauling/ Stripping/ m² 2.947 MH/m²
Housekeeping of Formworks
Fabrication of Formworks System m² 0.442 MH/m²
Hauling from Fabrication Area to Installation Area m² 0.295 MH/m²
(Vertical, Horizontal)
Installation of Formworks System m² 1.032 MH/m²
Rectification Works (Formworks) m² 9.108 MH/m²
Housekeeping (Formworks) m² 0.295 MH/m²
m² 0.737 MH/m²
Stripping and Dismantling of Fowmworks System
CONCRETE REINFORCING STEEL
kg 0.013 MH/kg
Fabrication of Rebars (Measuring, Cutting, Bending)
Hauling of Rebars form Fabrication Area to kg 0.004 MH/kg
Installation Area
Installation of Rebars (Laying, Tying, Splicing) kg 0.018 MH/kg
Rectification Wors (Rebar Works) hr 9.108 MH/hr
Housekeeping (Rebar Works) kg 0.004 MH/kg
Drilling of Concrete (For rebar Installation) kg 0.004 MH/kg
Fabrication of Shear Bar kg 0.004 MH/kg
CAST IN PLACE
Concrete Placing through Pumpcrete or Direct m³ 1.368 MH/m³
pouring
Rectifiation Works (Concrete Placing) hr 9.108 MH/hr
F/I of Wheel Stop no 4.705 MH/no
PRECAST CONCRETE
Precast Panel Installation m² 2.874 MH/m²
Sealant Application for Precast Walls lm 0.411 MH/lm
Unloading of Precast Panels m² 0.411 MH/m²
Repair of Precast Wall m² 0.205 MH/m²
Fabrication of Precast Embedment Plate m² 0.205 MH/m²
MASONRY WORKS
CONCRETE HOLLOW BLOCK
CHB Laying m² 1.895 MH/m²
Installation of Zocalo lm 1.368 MH/lm
Curb and Gutter Installation lm 1.368 MH/lm
Installation of Wheelstop lm 1.368 MH/lm
Open Canal Installation lm 1.368 MH/lm
METALS
Installation of Metal Handrails lm 7.621 MH/lm
Installation of Guard Rail lm 3.537 MH/lm
Installation of Caged Ladder lm 31.263 MH/lm
Installation of Stair Nosing lm 4.095 MH/lm
Installation og Trench Grating lm 27.368 MH/lm
Installation of Railings at Parking lm 28.421 MH/lm
Installation of Steel Bollards pc 19.368 MH/pc
Installation of Ladder Rungs no 7.576 MH/no
Installation of Manhole Cover no 39.947 MH/no
WATERPROOFING
Installation of Bentonite Pad m² 1.916 MH/m²
Installationg of Insulation m² 12.632 MH/m²
Installation of Styrophor Deck Insulation m² 3.495 MH/m²
Doors & Windows
Installation of Metal Doors set 31.674 MH/set
Installation of Door Hardwares pc 1.158 MH/pc
FINISHES
GENERAL FINISHES
Hauling of Architectural Materials hr 8.881 MH/hr
FLOOR FINISHES
Trowelling or Rough Finish m² 0.474 MH/m²
Installation of Waffle type Concrete Tiles m² 2.316 MH/m²
m² 2.316 MH/m²
Installation of Homogeneous Ceramic Floor Tiles
Installation of Granite Stone m² 2.316 MH/m²
Installation of Vinyl Floor Tiles m² 0.663 MH/m²
Straight to Finish m² 0.474 MH/m²
Concrete Topping m² 1.158 MH/m²
Epoxy Floor Coating Application m² 0.853 MH/m²
Chemical Resistant Epoxy Coating Application m² 2.211 MH/m²
pu Coating Application m² 3.579 MH/m²
WALL FINISHES m² MH/m²
Plastering Works m² 1.895 MH/m²
Plain Cement Plastering m² 1.895 MH/m²
Rubbed Concrete Finish to Concrete Wall m² 0.684 MH/m²
m² 2.526 MH/m²
Installation of Homegeneous Ceramic Wall Tiles
Installation of Drywall Partition m² 7.895 MH/m²
Baseboard Installation m² 2.526 MH/m²
Concrete Underslab Smooth Rubbed Finish m² 0.684 MH/m²
CELING FINISHES m² MH/m²
Rubbed Concreting m² 0.579 MH/m²
Installation of Gypsum Board Ceiling m² 3.158 MH/m²
Installation of MR Gypsum Board Ceiling m² 2.368 MH/m²
Installation of Drop Ceiling m² 2.368 MH/m²
Installation of Cove Lights Ceiling m² 2.368 MH/m²
PAINTING WORKS m² MH/m²
Ceiling Paint Application m² 0.663 MH/m²
Interior Wall Paint Application m² 0.663 MH/m²
Exterior Wall Paint Application m² 1.295 MH/m²
Painting of Stair Railings lm 0.484 MH/lm
Painting of Islands lm 1.105 MH/lm
Painting of Parking Slot Nos lm 0.521 MH/lm
Painting of Parking Lines lm 0.474 MH/lm
Painting of Pedestrian Markings lm 1.105 MH/lm
Painting of Structural Steel m² 1.295 MH/m²
Painting of Metal Doors m² 1.295 MH/m²
Painting of Wheel Stop lm 0.611 MH/lm
SPECIALTY WORKS
Installation of Toilet Accessories pc 4.737 MH/pc
Installation of Facial Mirror pc 4.737 MH/pc
Installation of Lavatory Countertop pc 4.737 MH/pc
0.853 134 114.302 mh
57.151
86
Activity Unit Unit Price
Rebar Works
Form Works
Concrete Works