PULLOVER HOODIES PRODUCTION PROCESS OF TEXTILE INDUSTRIES
TEXTILE INDUSTRY
Project Start Date 5/1/2021 (Saturday) Display Week 1 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Project Lead MAAZ ALI Order Quantity 6000 PCS 26 Apr 2021 3 May 2021 10 May 2021 17 May 2021 24 May 2021 31 May 2021 7 Jun 2021 14 Jun 2021
26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
WORK
WBS TASK JOB # START END DAYS % DONE M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
DAYS
1 [PULLOVER HOODIE] - -
1.1 YARN KNITTING LS-001 Sat 5/01/21 Mon 5/10/21 10 90% 6
1.2 KNITTED FABRIC DYEING LS-001 Mon 5/10/21 Tue 5/18/21 9 100% 7
1.3 CUTTING LS-001 Tue 5/18/21 Tue 5/25/21 8 80% 6
1.4 STITCHING LS-001 Thu 5/20/21 Tue 5/25/21 6 100% 4
1.4.1 BUTTON PRESSING LS-001 Fri 5/21/21 Fri 5/28/21 8 80% 6
1.4.2 CROPPING LS-001 Mon 5/24/21 Tue 6/01/21 9 100% 7
1.5 CHECKING LS-001 Wed 5/26/21 Wed 6/02/21 8 100% 6
1.6 PRESS LS-001 Mon 5/31/21 Sun 6/06/21 7 80% 5
1.7 PACKING LS-001 Fri 6/04/21 Tue 6/08/21 5 80% 3
KEY POINTS
TASK COMPLETED
PREPAID MAAZ ALI TASK INCOMPLETED
BY