1. All projects registered in the Project Portfolio Management (PPM) system must update their project status information monthly. The project manager is responsible for preparing the status and the agency coordinator posts it by the first of each month. 2. When registering a project, required fields include the name, dates, type, state, phase, objectives, funding and description. For monthly status updates, fields like accomplishments, next steps, budget status and issues must be reported on. 3. Status fields use a color code (green, yellow, red) to indicate whether the project is on track, slightly off track, or needs urgent attention. Comments are required to explain yellow or red statuses. The date status is

Uploaded by

Kamila Aburwais
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
847 views3 pages

Best Monthly Management Report Template

1. All projects registered in the Project Portfolio Management (PPM) system must update their project status information monthly. The project manager is responsible for preparing the status and the agency coordinator posts it by the first of each month. 2. When registering a project, required fields include the name, dates, type, state, phase, objectives, funding and description. For monthly status updates, fields like accomplishments, next steps, budget status and issues must be reported on. 3. Status fields use a color code (green, yellow, red) to indicate whether the project is on track, slightly off track, or needs urgent attention. Comments are required to explain yellow or red statuses. The date status is

Uploaded by

Kamila Aburwais
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Project Portfolio Management (PPM)

Monthly Status Reporting Procedure


All projects registered in PPM must update project status information monthly. Additionally, project managers and
agency coordinators should review all project information to ensure accuracy. A change that may impact the accuracy
of project information includes, but is not limited to the following:
Integrated change control
Change in project phase or project state
Progressive elaboration of project deliverables (for example: after the Project Charter is complete, funding
sources may be different than when the project was proposed)

Who updates project status?


The Project Manager is responsible to prepare status information.
The Agency Coordinator is responsible for posting project status information on PPM by end of the day, the
first calendar day of the month.

Required Fields – Completed when Registering a Project


Name
Proposed Start Date
Proposed Finish Date
Project Class
Project Type
Project State
Project Phase
Primary Project Driver
Primary Project Outcome
Primary Funding Source
Brief Project Description
Activity
Project Requestor

Monthly Reporting – Fields Required for Status Updating


Accomplishments
Next Steps
Overall Status
Budget Status
Scope Status
Schedule Status
Risk Status
Issue Status
Control Status
Date Status Updated
Accomplishments
1. Updates are recorded for the project activities within the last month only.
2. How to write your project activities
a. Use verb, object/subject of important high-level activities
b. Use past tense verbs because these are past accomplishments.
c. Do not submit a “journal” of everything you and your team did (such as “conducted team meeting,
“worked on project schedule.” There is a spacing constraint. If the data is too long, you risk not being
able to read all your project activities listed in the status report.
d. In general, try not to use pronouns or personal names.
Example: If referring to something you accomplished, it should be written in the past tense as in the
following: “the project manager has/did/planned or, the Business Analyst recommended,” etc.
1. Format of the Accomplishments section
a. Start with reporting period dates
b. List each activity (line) starting with a bullet.
c. In the Accomplishments section you will always show the past 30 days of project activities.
d. Delete all other report periods

Next Steps
1. Next Steps report future project activities forecasted to occur during the one month period.
2. How to write your future projects activities:
a. Use verb, object/subject of important high-level activities
b. In general, do not use pronouns or personal names. Example: If referring to something you will
accomplish, it should be written as “the project manager plans to…
3. Use verb, object/subject of important high-level activities
4. Format of the Next Steps section
1. Start with report period dates
2. List the future activities starting with a bullet.
3. Delete all other time periods

Project Health Scale


The following recorded fields require a color scale:
Overall Status
Budget Status
Schedule Status
Scope Status
Risk Status
Issue Status
Control Status
Mark each field with the appropriate color that reflects the project status below:
Green - Project and tasks are on track per plan.
Yellow - Project not quite to plan. Task or Project is behind schedule or over budget or scope is creeping /
changing. I have a plan to fix the issue. Project change request may be in process. Minor issue.
Red - I am off plan. I need help from management. I am not sure how to proceed. This is a serious issue with
the task or plan. There is a problem which affects the critical path. This is a judgment call (raising your hand).
Comments
Any time you report Red or Yellow status, in the above seven status fields you must state why the status is at risk in
the Comments section. Consider including the following:
List any current major issues
List any major risks (with mitigation strategy if known)
Always review your comments area and delete those comments that do not apply to the current reporting
period.

Date Status Updated


Change this date each reporting time period the information is updated.
This date verifies that the information given in this report has been updated by the project manager in the
current reporting period.

Monthly Reporting – Review and update fields as needed


Although information in other PPM fields may change, the following fields typically need to be updated throughout the
lifecycle of every project:
Total Cost Planned
Approved Finish Date
Project Phase
Project State