Itp Survillance Equipments
Itp Survillance Equipments
: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
1 General
1.3 Check for safety of the work area. Ashghal Prior to start Compliance to MEP
Safety the activity project requirement Coordinator, H H S S N/A Start cards
regulations SE, HSE, QC
Legend: R- Review
S- Surveillance inspection
W- Witness, raising of Inspection Request is not mandatory which shall be at the discretion of consultant/ Ashghal
H- Hold Point, raising of Inspection Request is mandatory
Page 1 of 6
Project name: CONSTRUCTION OF SATELLITE MONITORING CENTER - WADI AL MARKHIYA Doc. no.: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
Legend: R- Review
S- Surveillance inspection
W- Witness, raising of Inspection Request is not mandatory which shall be at the discretion of consultant/ Ashghal
H- Hold Point, raising of Inspection Request is mandatory
Page 2 of 6
Project name: CONSTRUCTION OF SATELLITE MONITORING CENTER - WADI AL MARKHIYA Doc. no.: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
Page 3 of 6
Project name: CONSTRUCTION OF SATELLITE MONITORING CENTER - WADI AL MARKHIYA Doc. no.: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
Legend: R- Review
S- Surveillance inspection
W- Witness, raising of Inspection Request is not mandatory which shall be at the discretion of consultant/ Ashghal
H- Hold Point, raising of Inspection Request is mandatory
Page 4 of 6
Project name: CONSTRUCTION OF SATELLITE MONITORING CENTER - WADI AL MARKHIYA Doc. no.: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
Prepared by (QA/QC Eng.) XXXXXX Reviewed by (QA/QC Eng.): XXXXX Approved by (PM): XXXXXXX
Legend: R- Review
S- Surveillance inspection
W- Witness, raising of Inspection Request is not mandatory which shall be at the discretion of consultant/ Ashghal
H- Hold Point, raising of Inspection Request is mandatory
Page 5 of 6
Project name: CONSTRUCTION OF SATELLITE MONITORING CENTER - WADI AL MARKHIYA Doc. no.: xxxxxxxxxxxxx
Project Number: BP 2020 C 018 S Rev.: XXXXXXX
Date :13-12-2022
Inspection and Test Plan for Installation of Surveillance Equipment’s.
* Inspection & Test code
(R, S, W, H)
Control Records to
Third Party
Sl. Acceptance Responsible
Consultant
Contractor
Description of Activity Procedure/ Spec. / Frequency be
Sub-cont.
no Criteria person
Ashghal
codes/ standard generated
Legend: R- Review
S- Surveillance inspection
W- Witness, raising of Inspection Request is not mandatory which shall be at the discretion of consultant/ Ashghal
H- Hold Point, raising of Inspection Request is mandatory
Page 6 of 6