Assignment (Network Diagram)

1. The document describes a network of activities with dependencies. 2. Activity G follows F but precedes H. Activity M follows H but precedes L. 3. The final activities are J and L, which terminate at the same time, restricting the start of earlier activities K and M.

Uploaded by

michael david
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
84 views2 pages

Assignment (Network Diagram)

1. The document describes a network of activities with dependencies. 2. Activity G follows F but precedes H. Activity M follows H but precedes L. 3. The final activities are J and L, which terminate at the same time, restricting the start of earlier activities K and M.

Uploaded by

michael david
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

completion of A

c. E may also begin only after


d. F follows activity ofB.
E and F a r e completed.
e. G be started until both
cannot
H allow J to start.
on both G and
f. Completion restrained by a notice
of comple
further
start of J is
g. The
tion of D. as
s a m e (completion)
and culminates in the
h. K follows D
event J.

network:
Praw the following
HH
a. G follows F but precede
follows D but precede J
b. G
c. M follows H
but precede L
L
d. K follows A but precede
Draw the network diagram of the following informations. e. F follows A
time
f. A and D start at the same
A-is the first job of the project terminate at the same time.
g. J and L
O and N are the two final jobs for project completion
K-Precedes 0 construct a network diagram.
N-follows L and M 4From the following data,
J- restricts the start of K and M
C and B depends on the completion of A Precedes
Activity
D follows B and may go on in parallel with C and E
E follows C a

- restricts the start of J and L b d,e


H and G also restrict K and M
F must precede G and may go in parallel with H d
E and D restrict H and I 9
C-must precede F. end
end
2Draw the Network Diagram ofthe following
informations:
Using the following informations, perform the following:
a. At the start of the project, each of 3 separate activities A,
B and C may or may not begin and progress concurrently. a. Network diagrama
b. D may begin until A is completed. b. Determine which activities are on the critical path
107
106
C. Compute the length of the critical path

Activity Estimated time (days)

1-2 5
2-3 3
24
3-6 10
6-7
4-5
4-7 6
5-7 10